Shaw Constructors v. ICF Kaiser Engineers ( 2005 )


Menu:
  •                                                      United States Court of Appeals
    Fifth Circuit
    F I L E D
    REVISED JANUARY 24, 2005
    December 30, 2004
    UNITED STATES COURT OF APPEALS
    For the Fifth Circuit            Charles R. Fulbruge III
    Clerk
    No. 02-30183
    SHAW CONSTRUCTORS, INC.,
    Plaintiff-Appellant, Cross-Appellee,
    VERSUS
    ICF KAISER ENGINEERS, INC., ET AL.,
    Defendants,
    PCS NITROGEN FERTILIZER, L.P.
    Defendant-Appellee, Cross-Appellant
    Appeal from the United States District Court
    For the Middle District of Louisiana
    Before HIGGINBOTHAM, GARZA and DENNIS, Circuit Judges.
    DENNIS, Circuit Judge:
    This is an action based on the Louisiana Private Works Act
    that requires the interpretation and application of the Louisiana
    Civil Code articles in the chapters on Third Party Beneficiary and
    1
    Dissolution of Contracts.
    A subcontractor performed its part of the work in constructing
    a $38 million Nitric Acid Facility for the owner of an industrial
    plant.   In   the   subcontract   with   the    general    contractor,   the
    subcontractor “agrees to and does waive” its right to file claims
    or liens against the owner’s property. When the general contractor
    materially breached its primary obligation to pay the subcontractor
    the $5.3 million balance due for work on the owner’s facility, the
    subcontractor filed claims and privileges or liens against the
    owner’s property and brought suit against the owner under the
    Louisiana Private Works Act (“LPWA”).1         The owner filed a counter-
    claim, as third party beneficiary of the subcontract’s lien waiver
    provision,    seeking   the   enforcement      of   that   provision,    the
    cancellation of the claims and liens filed, and the award of
    damages and attorneys’ fees.         Applying Louisiana law in this
    diversity jurisdiction suit, we reverse the magistrate judge’s
    holding that the subcontractor may not raise against the owner-
    third party beneficiary’s demand the defenses it could have raised
    against the general contractor. Instead, we enter summary judgment
    sustaining the subcontractor’s right to regard the subcontract as
    dissolved and the parties restored to their pre-contract positions
    1
    La. R.S. § 9:4801, et seq. The subcontractor also brought suit
    against the general contractor, but these parties entered into a
    “Compromise Agreement,” described more fully herein, reserving
    the subcontractor’s rights against the owner.
    2
    when it became evident that the general contractor would not
    perform and had materially breached the subcontract.2          Because
    dissolution and restoration operate retroactively to have effect as
    of the day the subcontract was entered into, and because the
    subcontractor did not explicitly waive its right to dissolution,
    the dissolved lien waiver provision of the rescinded subcontract
    could not be invoked to preempt or bar the exercise of the
    subcontractor’s right to file claims and liens under the LPWA and
    seek to enforce them against the owner and its property.
    I.
    On September 17, 1997, PCS Nitrogen Fertilizer, L.P. (“PCS”),
    owner of an industrial plant near Geismar, Louisiana, entered into
    a $38 million contract (“Prime Contract”) with general contractor
    ICF Kaiser Engineering, Inc. (“Kaiser”) for design and construction
    of a structure named the “1265 STPD NITRIC ACID FACILITY.”          The
    facility was built at the PCS plant straddling the boundary line
    between Iberville and Ascension Parishes.
    Under the Prime Contract, PCS authorized Kaiser to subcontract
    portions of the work but specified that Kaiser would be responsible
    for the   actions   of   subcontractors.   The   Prime   Contract   also
    provided that Kaiser would pay and discharge any lien that may be
    filed, and indemnify, defend, and hold PCS harmless from liens on
    2
    Id. arts. 2013, 2016, & 2018.
    3
    its property.3       In addition, the Prime Contract provided that
    Kaiser     would   reimburse   PCS   whatever   costs   PCS   incurred   in
    discharging any liens. Although the LPWA authorized PCS to protect
    itself against personal liability and privileges on its property
    under the Act by filing a notice of the contract and having Kaiser
    file a bond to protect subcontractors,4 PCS chose not to do so.
    In January 1998, Kaiser subcontracted a portion of its work to
    Shaw Constructors, Inc. (“Shaw”).5          The subcontract states that
    Shaw agrees to provide labor, equipment, materials, and other
    construction services for the 1265 STPD NITRIC ACID FACILITY
    project and “agrees to and does waive its right to file any
    mechanic’s lien or claims of any sort or kind against [PCS’s]
    premises or any part thereof.”6           In exchange, Kaiser obligated
    3
    The common law term “lien” and civil law term “privilege”
    will be used interchangeably throughout this opinion because the
    parties spoke of the terms as equivalent and as the differences
    between the terms are not relevant to our analysis.
    4
    La. R.S. § 9:4802(C).
    5
    PCS was not a party to the subcontract, and there was no
    privity between PCS and Shaw. However, the subcontract between
    Kaiser and Shaw referred to the Prime Contract between PCS and
    Kaiser, referred to PCS as “owner,” and stated that
    “Subcontractor hereby agrees to and does waive its right to file
    any mechanic’s lien or claims of any sort or kind against owner’s
    premises or any part thereof.”
    6
    The full text of the lien waiver clause provides:
    Subcontractor hereby agrees to and does waive its right
    to file any mechanic’s lien or claims of any sort or
    kind against owner’s premises or any part thereof.
    Subcontractor further agrees to obtain a written waiver
    4
    itself in the subcontract to make payments to Shaw, based on its
    monthly progress, within 45 days after receiving each of Shaw’s
    invoices.
    As Shaw’s work progressed, Kaiser failed to make timely
    payments, and Shaw contemplated stopping work. Instead, on January
    12, 1999, Shaw agreed to continue work in exchange for Kaiser
    making specifically scheduled payments and obtaining a payment bond
    for the remainder of the work on the project.
    Nevertheless, Kaiser still failed to perform its obligation
    under the subcontract to pay for Shaw’s work.   Instead, on January
    26, 1999, Kaiser notified Shaw that it could or would not make any
    further payment under the subcontract. Shaw, which essentially had
    completed its work, wound up its portion of the project on February
    1, 1999.    At the time of Kaiser’s complete, material breach of the
    subcontract, it had failed to pay Shaw over $5.2 million for Shaw’s
    construction work on the PCS nitric acid facility.   On January 27,
    1999, Shaw filed and recorded statements of claim and privilege
    asserting its rights under the LPWA against PCS and its property
    of the right to file any mechanic’s liens or claims of
    any sort or kind against Owner’s premises or any part
    thereof from any and all subcontractors, suppliers and
    materialmen at the time any subcontracts or purchase
    orders are issued in connection with the work. In
    accordance with Article 25E of Exhibit “C”, General
    Conditions for Subcontract, a “Release and Waiver of
    Lien” in the form of Appendix 1-A shall be executed by
    Subcontractor prior to release of each payment
    hereunder.
    5
    for Shaw’s uncompensated work on the PCS facility.
    On February 23, 1999, Shaw filed suit against PCS and Kaiser
    in state court in Iberville Parish.                    PCS and Kaiser removed the
    case to federal court.         On April 8, 1999, Shaw and Kaiser entered
    into an agreement (“Compromise Agreement”) that: (1) Kaiser would
    pay off $5,238,217.90 owed to Shaw for work on the PCS facility in
    20 monthly installments; (2) a default judgment would be entered to
    that effect; (3) Shaw’s liens on PCS’s property would not be
    cancelled     unless    Kaiser    filed       a   bond    or    other     security    in
    conformity    with     the   requirements         of    the   LPWA   or   furnished    a
    $5,300,000 letter of credit; and (4) Shaw would not dismiss its
    claims and lawsuit against PCS unless Kaiser furnished replacement
    security or Kaiser’s monthly installment payment obligations to
    Shaw were satisfied.         Pursuant to the Compromise Agreement, Kaiser
    confessed to the allegations in Shaw’s petition in its Answer and
    Confession     of    Judgment,      admitting           its    default     under     the
    subcontract, its debt to Shaw, and the validity of Shaw’s claim and
    privilege against PCS. PCS did not participate in the negotiations
    and agreements between Shaw and Kaiser, and Shaw reserved all of
    its rights against PCS.           After a default judgment was entered,
    Kaiser made installment payments to Shaw totaling $3,201,133.21,
    but   never   provided       replacement      security.         Thereafter,    Kaiser
    defaulted on the remaining amount, leaving an unpaid principal
    balance of $2,037,084.77 due Shaw.                On June 9, 2000, Kaiser filed
    6
    a petition in bankruptcy.        On October 20, 2000 PCS demanded that,
    within ten days thereof, Shaw cancel the claim, privilege or lien
    and dismiss this lawsuit against PCS with prejudice, and on October
    26, 2000 Shaw refused.
    After the foregoing events, Shaw moved for partial summary
    judgment on liability only to the effect that, under the LPWA, PCS
    was personally liable and its nitric acid facility was subject to
    a privilege for Shaw’s uncompensated work on the project.                 PCS
    moved for partial summary judgment dismissing Shaw’s demands and
    cancelling Shaw’s statements of claim and privilege filed on PCS’s
    property.        The   parties   consented   to   adjudication   before    a
    magistrate judge. On August 3, 2001, the magistrate judge ruled in
    favor of PCS on both of the cross-motions for summary judgment,
    dismissing Shaw’s claims and ordering Shaw’s lien removed from the
    public records.        Thereafter, Shaw and PCS filed a second set of
    motions    for   summary   judgment   concerning    attorneys’   fees   and
    damages.    On December 21, 2001, the magistrate granted summary
    judgment in favor of PCS and awarded it $61,614.68 in attorneys’
    fees and damages under La. R.S. § 9:4833 of the LPWA. Both Shaw and
    PCS appealed.
    Shaw argues that the magistrate judge erred by holding that
    PCS was a third party beneficiary of the subcontract and therefore
    able to demand specific enforcement of Shaw’s obligation to comply
    with the lien waiver provision.       Alternatively, Shaw charges that,
    7
    if PCS was a third party beneficiary, under Louisiana Civil Code
    article 1982 Shaw had the right to raise against PCS, as third
    party beneficiary, defenses based on the contract that it could
    have raised against Kaiser, had Kaiser made the same demand against
    Shaw.   Specifically, Shaw contends that, when Kaiser materially
    breached the subcontract, Shaw had the right to refuse to perform
    its file-no-lien obligation, to employ all rights and defenses
    against PCS that it may have raised against Kaiser, and to enforce
    its claim and privilege or lien against PCS and its property under
    the LPWA.
    PCS argues that the magistrate judge correctly ruled that Shaw
    could not raise against PCS the defenses it could have raised
    against Kaiser, and that, in any event, Kaiser’s material breach of
    the subcontract had no effect upon the lien waiver provision of the
    subcontract. PCS contends that the magistrate judge correctly held
    that it may as third party beneficiary enforce the lien waiver
    provision against Shaw, that Shaw’s claim and privilege or lien
    therefore were filed in violation of the lien waiver provision,
    that Shaw’s claim and privilege or lien were improperly filed under
    the LPWA for the same reason and others, that Shaw therefore cannot
    hold PCS personally liable or enforce a lien or privilege against
    PCS’s property under the LPWA, that Shaw did not have reasonable
    cause to refuse to cancel its lien upon PCS’s demand, and that Shaw
    should be taxed with attorney’s fees and damages pursuant to the
    8
    LPWA.
    Both Shaw and PCS appealed.
    We review rulings on motions for summary judgment de novo,
    applying the same standards prescribed for use by the district
    court.7     Cross-motions must be considered separately, as each
    movant bears the burden of establishing that no genuine issue of
    material fact exists and that it is entitled to judgment as a
    matter of law.8      If there is no genuine issue and one of the
    parties is entitled to prevail as a matter of law, the court may
    render summary judgment.9      Louisiana substantive law applies to
    7
    See Walker v. Thompson, 
    214 F.3d 615
    , 624 (5th Cir. 2000).
    8
    10A CHARLES ALAN WRIGHT, ARTHUR R. MILLER & MARY KAY KANE, FEDERAL
    PRACTICE AND PROCEDURE §2720 (3d ed. 1998)(“The court must rule on
    each party’s motion [for summary judgment] on an individual and
    separate basis, determining for each side, whether a judgment may
    be entered in accordance with the Rule 56 standard.”)
    9
    10A CHARLES ALAN WRIGHT, ARTHUR R. MILLER & MARY KAY KANE, FEDERAL
    PRACTICE AND PROCEDURE §2720 (3d ed. 1998)(“But if there is no
    genuine issue and one or the other party is entitled to prevail
    as a matter of law, the court will render judgment.”) Vela v.
    City of Houston, 
    276 F.3d 659
    , 671 (5th Cir. 2001)(In situations
    involving cross-motions for summary judgment and upon finding no
    genuine issues of material fact, this court regularly reverses
    grants of summary judgment and enters judgment for the opposite
    party.). See also Owsley v. San Antonio Independent School Dist.,
    
    187 F.3d 521
    , 527 (5th Cir. 1999)(reversing and rendering
    judgment for the adverse party on cross motions for summary
    judgment.); Ehrlicher v. State Farm Ins. Co. 
    171 F.3d 212
    ,(5th
    Cir,. 1999)(reversing and rendering judgment for the adverse
    party on cross motions for summary judgment.); Gilley v.
    Protective Life Ins. Co. 
    17 F.3d 775
    , (5th Cir. 1994)(reversing
    and rendering judgment for the adverse party on cross motions for
    summary judgment.)
    9
    this diversity jurisdiction case.10
    II.
    The magistrate judge correctly interpreted the subcontract
    between Kaiser and Shaw as stipulating a benefit for PCS as a third
    party beneficiary, but it incorrectly concluded that Shaw could not
    raise against PCS the defenses on the contract that it could have
    raised against Kaiser.
    As the magistrate judge, in concluding that PCS was a third
    party beneficiary of the Kaiser-Shaw subcontract’s lien waiver
    provision, stated:
    Shaw expressly agreed to waive its right to file any
    liens or claims of any sort against the owner’s premises.
    The subcontract clearly identifies PCS as the owner....
    The preamble of the subcontract... stated that the
    subcontract was made pursuant to the contract between PCS
    and Kaiser....    Because of Kaiser’s agreement in the
    prime contract, the subcontract lien waiver provision
    benefitted both Kaiser and PCS. This arrangement does
    not render the benefit which Shaw unequivocally conferred
    upon PCS by agreeing to the condition any less apparent
    or direct.11
    Nor do we see any error in the magistrate judge’s conclusion that
    PCS adequately manifested its intention to avail itself of the
    benefit before any attempt was made by Kaiser and Shaw to revoke
    10
    Erie R.R. Co. v. Tompkins, 
    304 U.S. 64
     (1938).
    11
    Aug. 3, 2001 Magistrate Judge Opinion, at 13-15 (citing
    Merco Mfg., Inc. v. J.P. Michael Const. Co., 
    372 F.Supp. 967
    , 974
    (W.D.La. 1974)(footnote omitted)).
    10
    the stipulation.12
    The magistrate judge erred, however, in concluding that Shaw
    could not raise against PCS the defenses based on the subcontract
    that it had against Kaiser.      Louisiana Civil Code Article 1981
    provides, in pertinent part, that “[t]he stipulation gives the
    third party beneficiary the right to demand performance from the
    promisor.”13    That right is qualified, however, by Louisiana Civil
    Code Article 1982, which states that “[t]he promisor may raise
    against the beneficiary such defenses based on the contract as he
    may have raised against the stipulator.”14     Thus, in the present
    12
    See La. Civil Code arts. 1978-1979. PCS filed an
    affidavit by its senior counsel that he had informed Kaiser as
    early as February 26, 1999 and on numerous other occasions that
    Kaiser should take no action which would waive or limit PCS’s
    third party beneficiary rights. Shaw offered no evidence to
    refute these expressions by PCS that implied its intention to
    avail itself of the benefit. The events that Shaw contends
    revoked the stipulation occurred after February 1999. “Once the
    third party has manifested his intention to avail himself of the
    benefit, the parties may not dissolve the contract by mutual
    consent without the beneficiary’s agreement.” 
    Id.
     art. 1978.
    “Under this Article, the beneficiary’s intention to accept the
    benefit may be made known in any manner, even implied.” 
    Id.
     art.
    1978 rev. cmt. b. “The stipulation may be revoked only by the
    stipulator and only before the third party has manifested his
    intention of availing himself of the benefit.” 
    Id.
     art. 1979.
    13
    
    Id.
     art. 1981.
    14
    
    Id.
     art. 1982. Louisiana Civil Code Article 1982 is
    similar to the prevailing rule in other jurisdictions. See
    RESTATEMENT (SECOND) OF CONTRACTS § 309(2) (1981)(“If a contract
    [creating the promisor’s duty to the intended beneficiary] ceases
    to be binding in whole or in part because of... present or
    prospective failure of performance, the right of any beneficiary
    is to that extent discharged or modified.”); Id. cmt.b. (“Thus a
    11
    case, Shaw, the promisor, had the right to raise against PCS, the
    beneficiary, any defense based on the subcontract that Shaw could
    have raised against Kaiser, the stipulator or promisee.15
    The magistrate judge concluded that interpreting Article 1982
    to allow Shaw to raise against PCS any defense based on the
    contract that Shaw could have raised against Kaiser, “would negate
    the right of PCS under articles 1978 and 1981 to accept and demand
    failure of the promisee to perform a return promise ordinarily
    discharges the promisor’s duty to a beneficiary to the same
    extent that it discharges his duty to the promisee.”); 13 RICHARD
    A. LORD, WILLISTON ON CONTRACTS § 37:55 (4th ed. 2000) (collecting
    authorities, e.g., Nauru Phosphate Royalties, Inc. v. Drago Daic
    Interests, Inc.,
    138 F.3d 160
    , 166 (5th Cir. 1998)).
    15
    Article 1982 was adopted in 1984 to “express[] a
    conclusion reached by the Louisiana jurisprudence.” La. Civ.
    Code art. 1982 rev. cmt. (citing Union Bank of Louisiana v.
    Bowman, 
    9 La. Ann. 195
     (1845); Tiernan v. Martin, 
    2 Rob. 523
    (1842)); see also J. Denson Smith, Third Party Beneficiaries in
    Louisiana: The Stipulation Pour Autrui, 11 TUL. L. REV. 18, 57
    (1936-37)(“[T]he promisor may oppose the suit of the beneficiary
    any defenses arising from the contract which are available to him
    as against the promisee such as that the contract was ineffective
    because ... there was a failure of consideration, or of a
    condition upon which performance of the promise was made to
    depend.” (citing Bowman, 9 La. Ann. at 195, Brandon v. Hughes, 
    22 La. Ann. 360
     (1980); Janney v. Ober, 
    28 La. Ann. 281
     (1876);
    Tennent v. Caffrey, 
    129 So. 128
     (1930))); 2 MARCEL PLANIOL, TREATISE
    ON THE CIVIL LAW, No. 1264(5) (La. State L. Inst. Transl. 1959)
    (“Failure by the Stipulator to Execute his Obligations. If the
    stipulator has not carried out his own obligations to the
    promisor, the latter is discharged from his obligation to the
    third person.... [I]t is in conformity to the apparent will of
    the parties to presume that the promisor is not obligated to the
    third person except in consideration of the obligations towards
    him.”).
    12
    performance of the stipulation pour autri.”16            We cannot agree.
    Article 1982 only subjects the beneficiary’s demand for performance
    from the promisor to the same contractual defenses which would
    apply if the stipulator demanded performance under the contract.
    Article 1982 would have no application to a case in which the
    promisor   has   no   defense   based    on   the   contract   against   the
    stipulator or promisee.     Thus, Article 1982 does not “negate” or
    nullify the third party beneficiary’s right to avail himself of the
    benefit and demand performance from the promisor under Articles
    1978 and 1981.   In sum, when we interpret Article 1982 in reference
    to the other code articles on the same subject,17 as we think the
    Louisiana Supreme Court would, we conclude that the beneficiary’s
    16
    The magistrate judge’s reasoning seems to be based on the
    incorrect assumption that the beneficiary’s right must be
    considered as either an absolute right or a nullity. The court’s
    full statement provides:
    Article 1981 grants both the stipulator and the third
    party beneficiary the right to demand performance.
    Under the second part of the article, if Kaiser
    demanded performance it would be doing so not for
    itself but for PCS. By exercising its equal right
    under article 1981 to claim the benefit of the
    stipulation, PCS cannot be exercising greater or better
    rights than Kaiser. Interpreting article 1982 as
    suggested by Shaw in the context of this case, would
    negate the right of PCS under articles 1978 and 1981 to
    accept and demand performance of the stipulation pour
    autri.
    Aug. 3, 2001 Magistrate Judge Opinion, at 19 (footnote omitted).
    17
    See La. Civ. Code art. 13 (“Laws on the same subject
    matter must be interpreted in reference to each other.”)
    13
    right is not absolute or independent.          Inherently, it is a right
    derived solely from the third party beneficiary contract between
    the promisor and the stipulator or promisee. Unsurprisingly, then,
    the Code provides in Article 1982 that the beneficiary’s right is
    amenable to the same defenses based on that contract that the
    promisor may use against the stipulator or promisee.
    In comparison, this contextual interpretation of Article 1982
    is consistent with the prevailing general rule recognized by other
    American jurisdictions.18 “As with any contract, the promisor’s and
    promisee’s     substantive     purpose    in   entering   a   third   party
    beneficiary contract is the performance of the mutual promises. If
    the promisee fails to perform, the promisor has not received the
    agreed consideration.    Under these circumstances, it is manifestly
    unjust to allow a mere donee to enforce the promise.          Even creditor
    beneficiaries are not entitled to any greater right than their
    debtor possessed.”19 This reading of Article 1982 is also in accord
    with Marcel Planiol’s treatise on the civil law, which states that
    “[i]f the stipulator has not carried out his own obligations to the
    promisor, the latter is discharged from his obligation to the third
    18
    See supra note 12.
    19
    13 LORD, WILLISTON ON CONTRACTS, supra note 12, § 37:56.
    (internal footnotes omitted).
    14
    person.”20   Planiol maintained this view, despite disagreement from
    “[c]ertain authors” at the time, because “it is in conformity to
    the apparent will of the parties to presume that the promisor is
    not obligated to the third person except in consideration of the
    obligations towards him.”21
    For these reasons, we conclude that the Louisiana high court
    would follow the plain words of Article 1982 and allow Shaw to
    raise against PCS such defenses based on the subcontract as it may
    have raised against Kaiser. Accordingly, we turn to an examination
    of the Civil Code rights and defenses that Shaw argues it could
    have raised against Kaiser had Kaiser demanded that Shaw perform
    its obligation arising from the subcontract’s waiver of right to
    file liens provision.
    III.
    Shaw’s most relevant argument is that it was entitled, because
    of Kaiser’s material breach of the commutative subcontract between
    them, to rescind the contract and invoke a non-breaching party’s
    right under La. C.C. art. 2022 to refuse to perform its own
    obligations   under   the    contract.       Consequently,   Shaw    further
    20
    2 PLANIOL, TREATISE ON THE CIVIL LAW, supra note 13, No.
    1264(5); see also Smith, supra note 13, at 57 (citing Bowman, 9
    La. Ann. at 195, Brandon v. Hughes, 
    22 La. Ann. 360
     (1980);
    Janney v. Ober, 
    28 La. Ann. 281
     (1876); Tennent v. Caffrey, 
    129 So. 128
     (1930)).
    21
    2 PLANIOL, TREATISE   ON THE   CIVIL LAW, supra note 13, No.
    1264(5).
    15
    contends, it was entitled to refuse to perform its obligation not
    to file liens even as to PCS, the third party beneficiary, because
    Civil Code article provides that “[t]he promisor [Shaw] may raise
    against the beneficiary [PCS] such defenses based on the contract
    as he may have raised against the stipulator [Kaiser].”        For the
    reasons now assigned, we conclude that Shaw’s arguments have merit.
    A.
    The subcontract between Kaiser and Shaw was a commutative
    contract making “the performance of the obligation of each party
    ... correlative to the performance of the other,”22 as well as a
    bilateral or synallagmatic contract in which “the parties obligate
    themselves reciprocally, so that the obligation of each party is
    correlative to the obligation of the other.”23
    22
    La. Civ. Code art. 1911and rev. cmt.(b)&(c); see Morris v.
    Homco International, Inc., 
    853 F.2d 337
    , 342 (5th Cir. 1988);
    SAÚL LITVINOFF, 5 CIV. L. TREATISE § 15.12 (2d ed. 2001); ALAIN A.
    LEVASSEUR, PRECIS IN CONVENTIONAL OBLIGATIONS: A CIVIL CODE ANALYSIS 24
    (Michie, 1980)(“A contract is commutative when a party considers
    that what he gives or does is the equivalent of what it will
    receive from the other party.”)
    23
    La. Civ. Code art. 1908 and rev. cmt.(b)(citing 1 SAÚL
    LITVINOFF, OBLIGATIONS 396-400 (1969) ; see Morris, 
    853 F.2d at 342
    ;
    cf.., Stockstill v. Byrd, 
    132 La. 404
    , 407, 
    61 So. 446
    , 447
    (1913)(“The courts at the present day incline strongly against
    the construction of promises as independent; and, in the absence
    of clear language to the contrary, promises which form the
    consideration for each other will be held to be concurrent or
    dependent, and not independent, so that a failure of one party to
    perform will discharge the other, [and] so that one cannot
    maintain an action against the other without showing the
    performance or tender of performance on his part.”); Accord: 15
    LORD, WILLISTON ON CONTRACTS, supra note 14, § 44:5 (“The modern rule
    16
    “Either party to a commutative contract may refuse to perform
    his obligation if the other has failed to perform or does not offer
    to perform his own at the same time, if the performances are due
    simultaneously.”24          Therefore, when Kaiser failed to perform its
    obligation under the subcontract of making payments for work done
    by Shaw, Shaw had the right to refuse to perform its obligation
    adopts a presumption that mutual promises in a contract are
    dependent and are to be so regarded, whenever possible.”); §44:11
    (“Under the modern view, promises in a contract are generally
    presumed to be dependent unless a contrary intent is
    shown.”)(also quoting RESTATEMENT (Second) of Contracts § 232);
    Foley Lumber Industries, Inc. v. Buckeye Cellulose Corp., 
    286 F.2d 697
    , *700 (5th Cir. 1961)(“Although many nice distinctions
    are to be found in the books upon the question, whether the
    covenants or promises of the respective parties to the contract,
    are to be considered independent or dependent; yet it is evident,
    the inclination of courts has strongly favored the latter
    construction, as being obviously the most just.” (quoting Bank of
    Columbia v. Hagner, 1828, 
    1 Pet. 455
    , 465, 
    26 U.S. 455
    )).
    24
    La. Civ. Code art. 2022 and rev. cmt.(b)(citing 2 SAÚL
    LITVINOFF, OBLIGATIONS 426-434, 501-506 (1975)). The Second
    Restatement of Contracts expresses a similar principle in the
    introduction to Chapter 10 on Performance and Nonperformance:
    The most important and complex of the rules stated
    in this Chapter apply to the most significant type of
    contract, that in which the parties have exchanged
    promises in the expectation that there will be a
    subsequent exchange of performances....
    When a party fails to receive the performance that
    he expects,....[i]t is, therefore generally fairer to
    give the injured party, to the extent that it is
    possible, the right to suspend his own performance and
    ultimately to refuse it and, if the other party’s
    nonperformance is not justified, to claim damages for
    total breach of contract.
    RESTATEMENT (SECOND)   OF   CONTRACTS ch. 10 intro. note, at 193-94.
    17
    under the subcontract.25
    More important, when it became evident that Kaiser would not
    perform its subcontract obligation, Shaw had the right to consider
    the subcontract and all of its provisions dissolved26 and the
    25
    Article 2022 gives “general formulation to the exceptio
    non adimpleti contractus (defense of nonperformance).” La. Civ.
    Code art. 2022 rev. cmt. b. As Planiol explained, the “exception
    non adimpleti contractus...is interposed when one of the parties
    is claiming of the other the performance of his engagement,
    without himself offering what he owes; such party is nonsuited by
    the filing of the above mentioned exception.” 2 PLANIOL, TREATISE ON
    THE CIVIL LAW, supra note 13, No. 949(2). “[W]hen two persons
    obligate themselves the one to the other, each one of them gives
    only but conditional consent to the act; one obligates himself
    because the other also obligates himself towards him. The
    reciprocity of the obligations necessarily implies performance
    and this concept leads, on the one hand, to a ‘give and take’
    system of performance or to the exceptio non adempleti
    contractus..., and on the other hand, to the right to demand the
    resolution when it was too late to oppose the said exception
    because the obligation was already performed.” Id. No. 1309.
    26
    La. Civ. Code art. 2016 (“[W]hen it is evident that the
    obligor will not perform, the obligee may regard the contract as
    dissolved without any notice to the obligor.”); id. rev. cmt.
    (“Louisiana courts have established that a putting in default is
    not necessary when the obligor has communicated an intention not
    to perform, or in a situation where time is of the essence
    (citing Allen v. Steers, 
    2 So. 199
     (1887); Abels v. Glover, 15
    La. Ann.247(1860); Kinsell & Locke, Inc. V. Kohlman, 
    126 So. 257
    (La. App. Orl. 1930))); 
    id.
     art. 2013 (“When the obligor fails to
    perform, the obligee has a right to the judicial dissolution of
    the contract or, according to the circumstances, to regard the
    contract as dissolved.”).
    Planiol explained some of the principles underlying the
    right of resolution or dissolution as follows:
    Art. 1184 in establishing the action of resolution,
    indicates in the following terms the circumstances
    which gives rise to it: “in case one of the contracting
    parties does not comply with his engagements.” The law
    is not precise as to the nature of the cause which
    18
    parties   restored    to   the   situation    that   existed   before   the
    subcontract     was   made.27     Thus,      the   “dissolution   operates
    prevents him from complying.... The text makes no
    distinction, and the jurisprudence therefore concludes,
    as do the majority of the authors, that there is an
    action in resolution, whatever is the cause for which
    the adverse party fails to comply with his
    engagements.”
    2 PLANIOL, TREATISE ON THE CIVIL LAW, supra note 13, No. 1313
    (citations omitted).
    The action in resolution established by Art. 1184 is
    given only to the party who is ready to perform his
    engagement or who has already performed it. The other
    party has no right to the resolutions of the
    contract.... It is natural, therefore, that the party
    at fault should suffer the resolution by the will of
    the other, without being able to demand it himself.
    Id. No. 1314 (citations omitted).
    The party entitled to the action of resolution is not
    limited to this means only; he has the choice of
    resolving the contract or of demanding its performance
    if he prefers it, provided that the fault of the debtor
    has not rendered such performance impossible.
    Id. No. 1315.
    The resolution of the contract is not sufficient in
    itself to completely satisfy the plaintiff. His
    recovering or keeping the object of his obligation
    often does not give him the contemplated profits he
    would have obtained upon the effective performance of
    the contract. To compensate him for the damage
    suffered by this loss of profits, he is entitled to
    damages to be fixed by the judge.
    Id. No. 1317.
    27
    La. Civ. Code art. 2018 (“Upon dissolution of a contract,
    the parties shall be restored to the situation that existed
    before the contract was made.”); see Sliman v. McBee, 
    311 So. 2d 19
    retroactively,”28 “has a retrospective effect to the day that the
    engagement was contracted,”29 and “the parties are restored to the
    situation in which they would be if the contract had not been
    entered into.”30
    Moreover, under the Louisiana Supreme Court’s decisions, in
    order for a party to waive his right to dissolve a commutative
    contract upon the other party’s material breach, the non-breaching
    party must express therein his intent to relinquish that right in
    words that make specific reference to the action to dissolve.           In
    the leading case of Sliman v. McBee,31 Mrs. Sliman sold immovable
    248, 252 (La. 1975)(“The effect [of dissolution] is to place all
    parties in the same position they occupied prior to the sale.”);
    Louis Werner Saw Mill Co. v. White, 
    17 So. 2d 264
    , 268 (La.
    1944)(“The effect of the dissolution is to place matters in the
    same state as though the obligation had not existed.”); U.S. v.
    Maniscalco, 
    523 F.Supp. 1338
    , 1342(E.D.La. 1981)(“The effect of
    the resolutory condition is codified in Article 2130 which states
    that obligations are "extinguished" by the effect of the
    dissolving condition.”).
    28
    2 A.N. YIANNOPOULOS, LA. CIVIL LAW TREATISE: PROPERTY § 233, at
    469 (4th ed. 2001).
    29
    Liquidators of Prudential Sav. & Homestead Soc. v.
    Langermann, 
    100 So. 55
    , 61 (La. 1924); McKenzie v. Bacon, 
    5 So. 640
     (La. 1889).
    30
    Hood v. Southern Prod. Co., 
    19 So. 2d 336
    , 341 (La.
    1944)(dictum); Sliman v. McBee, 
    311 So. 2d 248
    , 252 (La.
    1975)(“[T]he seller may sue for dissolution of the sale and
    return of the property. The effect is to place all parties in
    the same position they occupied prior to the sale.” (citations
    omitted)).
    31
    
    311 So. 2d 248
     (1975).
    20
    property to the McBees, her daughter and son-in-law.32   In the act
    of sale, Mrs. Sliman waived her vendor’s privilege stating that “no
    lien shall exist on the lots here sold securing payment” of the
    notes given by the McBees as part of the purchase price.33      The
    McBees defaulted and Mrs. Sliman brought suit for dissolution of
    the sale for nonpayment.34    The trial and appeals courts both
    decided against Mrs. Sliman, the latter holding that she had waived
    not only her vendor’s lien but also her right to dissolution of the
    sale for nonpayment.35     The Louisiana Supreme Court reversed,
    holding that (1) a “dissolving, or resolutory, condition is implied
    in all commutative contracts and takes effect upon the failure of
    either party to comply with his engagement and the demand for
    dissolution by the aggrieved party;”36 (2) the right of dissolution
    is an independent, substantive remedy in no way dependent upon the
    existence of a security device such as a mortgage or a privilege;37
    32
    
    Id. at 249
    .
    33
    
    Id. at 250
    .
    34
    
    Id. at 251
    .
    35
    
    Id. at 250-51
    .
    36
    
    Id.
     at 252 (citing and quoting La. Civ. Code art. 2045
    (1870): “The dissolving condition is that which, when
    accomplished, operates the revocation of the obligation, placing
    matters in the same state as though the obligation had not
    existed.”)
    37
    
    Id.
     The right to dissolution arises from the contract
    itself. La. Civ. Code art. 2013 comment (b).
    21
    (3) in order to waive the separate and independent right of
    dissolution the non-breaching party must “express her intent to
    relinquish that right in words that make specific reference to the
    action to dissolve as distinguished from the action to enforce the
    contract;”38 (4) the language in the act of sale does not constitute
    a waiver by Mrs. Sliman of her right to rescind the sale upon the
    McBees’ default in payment of the purchase price.39   “The fact that
    the vendor has lost, or not preserved, his vendor’s lien, or
    mortgage, presents no sort of obstacle to the exercise of this
    right of resolution.”40
    The already strong right to dissolution was preserved and
    strengthened by the 1984 revision of Title III of Book III of the
    Louisiana Civil Code of 1879, “Of Obligations.”         Article 2013
    “reproduces the substance of C.C. Arts. 2046 and 2047 (1870)and
    also provides that, according to the circumstances, the obligee has
    a right to regard the contract as dissolved, a right recognized by
    the Louisiana jurisprudence in numerous decisions.”41    Further,
    38
    
    Id.
    39
    
    Id. at 253
    .
    40
    
    Id.
     at 253 n.8 (quoting Stevenson v. Brown, 
    32 La. Ann. 461
    , 463 (1880)).
    41
    La. Civ. Code art. 2013 rev. cmt. a (citations omitted).
    Article 2013 (1984) provides:
    When the obligor fails to perform, the obligee has a
    right to the judicial dissolution or the contract or,
    according to the circumstances, to regard the contract
    as dissolved. In either case, the obligee may recover
    22
    Under this Article, either party to a contract may seek
    dissolution upon the other’s failure to perform. [T]his
    remedy is [no longer] predicated upon a resolutory
    condition implied in every commutative contract. This
    Article abandons both that rationale and that limitation,
    in accordance with modern doctrine. Nevertheless, under
    this Article a party’s right to dissolution because of
    the other party’s failure to perform arises from the
    contract itself, and to that extent it can be said to be
    implied in it, although not in the form of a resolutory
    condition.42
    Louisiana Civil Code Article 2018, in part, provides that:
    “Upon dissolution of a contract, the parties shall be restored to
    the situation that existed before the contract was made.”43 “It
    expresses a principle that is implied in C.C. Arts. 1901, 1903,
    2045, and 2046 (1870).”44
    Thus, we conclude, as we think the Louisiana Supreme Court
    would, that the subcontract provision by which Shaw “agrees to and
    does waive its right to file any mechanic’s lien or claims” against
    PCS’s property, does not constitute a waiver by Shaw of its
    dissolution rights because it does not express Shaw’s intent to
    relinquish the right to dissolution “in words that make specific
    damages.
    In an action involving judicial dissolution, the
    obligor who failed to perform may be granted, according
    to the circumstances, an additional time to perform.
    42
    
    Id.
     rev. cmt. b (citations omitted)(emphasis added).
    43
    
    Id.
     art. 2018.
    44
    La. Civ. Code art. 2018 rev. cmt. a.
    23
    reference to the action to dissolve.”45                      Further, that waiver
    provision     is    simply   too    vague,       indefinite,       and    uncertain    to
    indicate that the parties’ intended for it to supersede all of
    Shaw’s     rights   against    Kaiser       regardless       of   Kaiser’s      material
    failure of     performance.          For    these      reasons,     Shaw’s     right    of
    dissolution upon Kaiser’s material breach was not affected by
    Shaw’s agreement to waive the right to file liens and claims
    against PCS.
    Accordingly,       when       Kaiser        materially       defaulted      on    its
    obligation     of   performance,      Shaw       had   the    right      to   regard   the
    subcontract as having been dissolved. Upon its dissolution,                            the
    parties were restored to the situation that existed before the
    contract was made.46         Therefore, when PCS filed its counterclaim
    seeking, as third party beneficiary standing in Kaiser’s shoes, to
    enforce the erstwhile lien waiver provision, it was not entitled to
    do so. That provision had been dissolved as part of the dissolved
    subcontract; and Shaw was free of any obligation created by the
    parties’ agreement to the waiver provision because Shaw had been
    restored to the situation that existed before the subcontract.
    Consequently, after the dissolution and restoration Shaw had a
    right under the LPWA to file a claim and a privilege against PCS’s
    property and to seek recovery from PCS personally for uncompensated
    45
    Sliman v. McBee, 311 So.2d at 252.
    46
    La. Civ. Code art. 2018 (1984).
    24
    work on PCS’s nitric acid facility; when Shaw took these actions
    the subcontract and Shaw’s obligations under it had been dissolved
    ab initio.   Therefore, the dissolved lien waiver provision and any
    obligation created by it could not have any effect upon Shaw’s
    ability to exercise its rights under the LPWA against PCS and its
    property.
    In other words, PCS, whose right as a third party beneficiary
    can rise no higher than the right of Kaiser, its stipulator-
    promisee, is not entitled to enforce the lien waiver provision as
    if that obligation were separate and independent from the other
    obligations arising from the subcontract.      PCS is amenable to
    Shaw’s defense and right of dissolution just as Kaiser would have
    been if it had sought to enforce the lien waiver provision.
    B.
    PCS argues that, despite Kaiser’s material breach giving rise
    to Shaw’s rights and defenses, the magistrate judge’s ruling was
    correct and the lien waiver provision may still be enforced by PCS
    against Shaw because “‘[A] mechanic’s lien can be obtained only if
    there is a breach of contract and if ... a breach of contract
    nullifies a written waiver of lien, then there would be no way to
    effectively waive the right to a mechanic’s lien.’”47   PCS relies
    47
    PCS Original Brief, at 28 (citing and quoting Jankoviak v.
    Butcher, 
    159 N.E.2d 377
    , 378 (Ill. App. 2d Dist. 1959)).
    25
    principally upon this rationale, which it quotes from the Illinois
    Court of Appeal’s opinion in Jankoviak v. Butcher,48 a 1959 decision
    applying the Illinois mechanics’ lien statute to uphold a home
    builder’s lien waiver in its contract after an owner refused to pay
    the home builder.
    PCS’s argument is not relevant, however, because it is based
    on Illinois rather than Louisiana law.                   In    this       diversity
    jurisdiction case, we must apply Louisiana law, and in resolving
    any issues of interpretation or application, we must decide as we
    think the Supreme Court of Louisiana would.                     For several reasons,
    we believe that the Louisiana high court would refuse to borrow and
    apply      the     Illinois       court’s     interpretation         of   the   Illinois
    mechanics’ lien statute here as urged by PCS.
    To borrow the rule of decision from an Illinois case would
    require a drastic departure from the civil law methodology followed
    by the Louisiana Supreme Court.                    In Louisiana, “[t]he sources of
    law are legislation and custom.”49                  These authoritative or primary
    sources of law are to be “contrasted with persuasive or secondary
    sources       of    law,     such    as     [Louisiana    and    other      civil   law]
    jurisprudence, doctrine, conventional usages, and equity, that may
    guide     the      court    in    reaching     a    decision    in    the   absence   of
    48
    Jankoviak, 
    159 N.E.2d at 377-78
    .
    49
    La. Civ. Code art. 1.
    26
    legislation and custom.”50        “It is axiomatic that in Louisiana,
    courts must begin every legal analysis by examining primary sources
    of law: the State’s Constitution, codes, and statutes.”51           “[O]ur
    ultimate ‘Erie guess’ requires that we employ the appropriate
    Louisiana methodology to decide this issue the way that we believe
    the Supreme Court of Louisiana would decide it.”52 We are convinced
    that the Louisiana high court would not depart from its usual civil
    law   methods    of   examining   first   the   primary   sources   of   law
    applicable to the present case, the Louisiana Civil Code and the
    LPWA.      Therefore, we do not believe that the Louisiana high court
    would, in a case under the Civil Code or the LPWA, borrow and apply
    a rule of decision from an Illinois court’s interpretation of the
    Illinois mechanics’ lien law.       In addition, it is likely that no
    state supreme court would consider applying case law based on any
    50
    
    Id.
     rev. cmt. b. (citing A.N. YIANNOPOULOS, LOUISIANA CIVIL LAW
    SYSTEM §§ 31, 32 (1977).
    51
    Prytania Park Hotel, Ltd. v. General Star Indem. Co., 
    179 F.3d 169
    , 174 (5th Cir. 1999); see also Smith v. Southern
    Holding, Inc., 
    839 So. 2d 5
     (La. 2003); Cole-Miers Post 3619
    V.F.W. of DeRidder v. State, Dept. Of Rev. & Taxation, Office of
    Alcoholic Beverage Control, 
    765 So. 2d 312
     (La. 2000); Albert
    Tate, Jr., Techniques of Judicial Interpretation in Louisiana, 22
    LA. L. REV. 727, 727-728 (1962)(“[T]he primary basis of law for a
    civilian is legislation, and not (as in the common law) a great
    body of tradition in the form of prior decisions of the
    courts.... The Louisiana judge must, as stated, find primarily in
    legislative enactments the legal principles to be applied in
    deciding the case before him.”).
    52
    Lake Charles Diesel, Inc. v. General Motors Corp., 
    328 F.3d 192
    , 197 (5th Cir. 2003).
    27
    other     jurisdiction’s   mechanics’    lien   statute   because   of   the
    notorious diversity of such laws among the states.53
    In fact, the Illinois mechanic’s lien statute is crucially
    different from the LPWA. The 1959 Jankoviak decision is inapposite
    Illinois jurisprudence because it was based on two features of the
    Illinois mechanics’ lien statute that differ crucially from the
    LPWA.     First, the Illinois court noted that the Illinois statute
    53
    See, e.g., UNIFORM CONSTRUCTION LIEN ACT prefatory note, 7
    U.L.A. 2 (2002)(“All states presently have mechanics’ lien laws.
    Those laws present an extraordinarily varied approach, in
    substance, and in language, to the issues involved in mechanics’
    lien legislation. In fact, variation among the states may be
    greater in this area than in any other statutory area.”); 53 AM.
    JUR. 2D Mechanics’ Liens § 7(“The mechanic's lien laws of the
    various states are notorious for the extent to which they vary
    from each other in their application and operation. The
    diversity in the mechanic's lien laws of the various states
    diminishes, and may often nullify, the value of a decision from
    one state as a precedent in another, and courts often reject the
    asserted authority of a decision from another jurisdiction, or
    regard it as being of little or no value”(footnotes omitted));
    Ethan Glass, Old Statutes Never Die ... Nor Do They Fade Away: A
    Proposal for Modernizing Mechanics’ Lien Law By Federal Action,
    27 OHIO N.U. L. REV. 67 (2000)(“State statutes create many
    different rules regarding what property can be impaired by a
    mechanics' lien, who is entitled to claim a mechanics' lien, how
    a mechanics' lien may be created, and what the result is of the
    creation of a mechanics' lien. The ongoing theme to remember is
    that there are fifty-two jurisdictions with fifty-two different
    laws.”).
    The variety in state lien laws is particularly evident with
    respect to the effect of lien waiver clauses on lien rights. See
    8 LORD, WILLISTON ON CONTRACTS, supra note 12, § 19:58 (“There is a
    conflict in the cases as to the effect of a contractor’s waiver
    in a building contract of his right, or that of subcontractors or
    materialman, to file mechanics’ liens, with perhaps a majority of
    states refusing to permit such waivers, except upon or following
    payment.”(footnote omitted)).
    28
    provided that “[i]f the legal effect of any contract between the
    owner and contractor is that no lien or claim may be filed or
    maintained by anyone, such provision shall be binding.”54                   Second,
    that court’s decision was also based on the Illinois statutory
    requirement that a mechanic’s lien could be obtained only if there
    was first a breach of contract.55
    The LPWA does not make the breach of a contract indispensable
    to obtaining a lien, as the Illinois mechanics’ lien law does.
    Under     the   LPWA,   as   soon     as   the   work   has   been    substantially
    completed       or   abandoned   or    the      owner   has   filed   a   notice   of
    termination, a subcontractor may file and obtain a lien, regardless
    of whether there has been a breach of contract.56                 Thus, under the
    54
    Jankoviak, 
    159 N.E.2d at 378
    .
    55
    
    Id.
     The Illinois statute may have been anomalous and
    contrary to a basic principle of contract law. “[I]t is essential
    to waiver that the right allegedly waived exist at the time of
    the waiver; a party may not waive any right it does not yet have.
    After a contract has been made, on the other hand, the right to
    performance under the contract may generally be waived either
    before or after the time when performance is due.” 13 LORD,
    WILLISTON ON CONTRACTS, supra note 12, § 39.10 (footnotes omitted);
    see also 31 C.J.S. Estoppel § 75 (“[A] waiver implies and
    requires the existence of the right in question at the time of
    the alleged waiver; there can be no waiver of a right before it
    exists, before a person is in a position to assert it, or after
    it has been lost.”); 28 AM. JUR. 2D Estoppel § 201 (“To constitute
    a waiver, the right or privilege claimed to have been waived must
    generally have been in existence at the time of the purported
    waiver. So, a person cannot waive a right before he or she is in
    a position to assert it.”).
    56
    La. R.S. § 9:4822(C).
    29
    LPWA, the subcontractor is not forced by law to wait until the
    general contractor actually defaults before filing a claim or
    privilege, as he would have to do under the Illinois statute.
    Moreover, unlike the Illinois statute, the LPWA does not declare
    that a contract between the owner and the contractor prohibiting
    the future filing of liens or claims by anyone “shall be binding.”
    In sum, the LPWA is more favorable to a subcontractor than the
    Illinois mechanics’ lien statute, because the LPWA does not limit
    his access to Civil Code and LPWA rights and remedies in case the
    general contractor breaches the contract, and the LPWA does not
    make breach of contract a sine qua non to the subcontractor’s right
    to file a claim or lien against the owner’s property.
    For these reasons, we are not persuaded by PCS’s argument
    based on the Illinois case and statute.
    C.
    PCS does not advance any other argument or authority for the
    proposition that it, as a third-party beneficiary, may require that
    the Kaiser-Shaw subcontract’s lien waiver provision be enforced
    despite Shaw’s rights of dissolution and restoration evoked by
    Kaiser’s material breach of that contract.57 Our own research leads
    57
    PCS cites a number of Louisiana cases cursorily mentioning
    or using waiver without defining it or discussing its nature,
    conditions or scope. Hero & Co. v. Farnsworth & Chambers Co., 
    107 So. 2d 650
     (La. 1958); Wardlaw Bros. Garage, Inc. v. Thomas, 
    140 So. 108
     (La. App. 2d Cir. 1932); Babineaux v. Grisaffi, 
    180 So. 2d 888
     (La. App. 3d Cir. 1965); Bank of Jena v. Rowlen, 
    370 So. 30
    only to additional reasons to doubt that the Louisiana Supreme
    Court would affirm that litigation position.
    The Kaiser-Shaw subcontract, after stating that Shaw “agrees
    to and does waive” its right to file claims and liens against PCS’s
    property, does not expressly state what legal effects the parties
    intended for the provision to have.        The term “waiver” does not
    appear to have any fixed meaning or connotation in Louisiana law to
    which it can be assumed that the parties must have referred.           The
    Louisiana   Civil   Code,   which   regulates   nominate   contracts   and
    juridical acts in detail, does not provide definition or regulation
    for a contract or act of waiver.58        The LPWA does not define or
    2d 146 (La. App. 3d Cir. 1979); Executive Office Centers, Inc. v.
    Cournoyer, 
    433 So. 2d 324
     (La. App. 4th Cir. 1983).   See also
    Union Texas Petroleum v. PLT Eng’g, 
    895 F.2d 1043
    , 1053 n.16 (5th
    Cir. 1990); Toomer v. Price, 
    122 So. 856
    , 856-58 (La. 1929).
    However, these cases do not address or support PCS’s position
    that, as third party beneficiary, it may assert greater or better
    rights against Shaw than Kaiser, its stipulator-promisee, after
    Kaiser’s material breach of the subcontract of which the third
    party stipulation was a part. And, while these cases may support
    a conclusion that Louisiana courts will enforce “lien waivers”
    executed in exchange for contemporaneous payment or alternate
    security, they are not support for enforcement of a waiver where
    there has been a failure of cause or consideration or material
    breach of a commutative contract. As Shaw correctly points out,
    they are distinguishable factually, contractually, and on other
    grounds. Shaw’s 2d brief, pp. 11-13.
    58
    The Civil Code in several articles provides for the
    “renunciation” of certain accrued or existing rights. See La.
    Civ. Code art. 626 (usufruct); 
    id.
     arts. 737 & 771-772 (predial
    servitudes); 
    id.
     arts. 963-966 (successions); 
    id.
     art. 1780
    (obligations with a term); 
    id.
     art. 1802 (solidary obligations);
    id. 2348 (matrimonial regimes); id. art. 2978 (sequestration);
    id. art. 3029 (mandate); id. arts. 3449-3451 (prescription). The
    31
    regulate waiver either.59
    We have found but three cases in which the Louisiana Supreme
    Court comprehensively defined “waiver.”        In two insurance coverage
    cases,    involving   whether   an   insurer   had    waived   a   coverage
    exclusion, and whether an insurer had waived a condition precedent
    of sound health, the state high court stated that “[w]aiver occurs
    when there is an existing right, a knowledge of its existence and
    an actual intention to relinquish it or conduct so inconsistent
    with the intent to enforce the right as to induce a reasonable
    belief that it has been relinquished.”60             In a third case the
    Louisiana Supreme Court, in deciding whether homeowners had waived
    their rights to sue the builder for noncompliance with building
    plans and specifications, defined waiver in similar but more
    Code does not, however, provide a general definition of
    “renunciation” applicable to other rights.
    59
    La. R.S. § 9:4801, et seq.
    60
    Steptore v. Masco Constr. Co., Inc., 
    643 So. 2d 1213
    , 1216
    (La. 1994) (emphasis added)(citing Tate v. Charles Aguillard Ins.
    & Real Estate, Inc., 
    508 So. 2d 1371
     (La.1987); Ledoux v. Old
    Republic Life Ins. Co., 
    233 So. 2d 731
     (La.App. 3d Cir. 1970);
    Peavey Co. v. M/V ANPA, 
    971 F.2d 1168
     (5th Cir.1992)). In Tate
    v. Charles Aguillard Insurance & Real Estate, Inc., the court
    stated: “Of course, reliable proof of such a knowing and
    voluntary waiver is necessary and the burden of producing it, as
    in the proof of obligations generally, falls on the party who
    demands performance.” 508 So. 2d at 1375 (citing La. Civ. Code
    art. 1831; id. art. 2232 (1870)); see also BLACK’S LAW DICTIONARY
    1574 (7th ed. 1999)(“The party alleged to have waived a right
    must have had both knowledge of the existing right and the
    intention of forgoing it.”).
    32
    comprehensive terms: “Though there are various definitions of the
    term ‘waiver’, it can be comprehensively defined as a voluntary and
    intentional relinquishment or abandonment of a known existing legal
    right, advantage, benefit, claim, or privilege, which except for
    such waiver the party would have enjoyed.”61                  If these waiver
    definitions apply here, Shaw would not have been able, when the
    Kaiser-Shaw subcontract was formed, to waive a right to file claims
    and liens against PCS’s property.                 Shaw had no known existing
    legal right to file a claim or lien against PCS at the inception of
    the subcontract under which it had not yet performed any work.                We
    are not called upon to make an Erie guess as to whether the
    Louisiana Supreme Court would apply those definitions of waiver
    here.     But   their   existence    in     the    court’s   jurisprudence    is
    consistent with our undiminished Erie duty to follow and apply the
    Louisiana Supreme Court’s rule against finding that a party has
    waived    the   right     of   dissolution    of    a   contract,   unless   she
    “express[es] her intent to relinquish that right in words that make
    specific reference to the action to dissolve[.]”62
    In sum, we have not discovered any basis in Louisiana law for
    concluding that a third party beneficiary, such as PCS, has a right
    to demand performance from the promisor, like Shaw, even though the
    61
    Breaux v. Laird, 
    88 So. 2d 33
    , 38 (La. 1956)(emphasis
    added).
    62
    Supra, n. 34.
    33
    contracting party through which the beneficiary claims,                   Kaiser,
    the   stipulator-promisee          here,        has   materially   breached      the
    underlying contract and caused its dissolution.                PCS’s reliance on
    inapposite Illinois authority indicates that it also was unable to
    find Louisiana law to support its position.                Consequently, in the
    absence of clear language in the subcontract to the contrary, we
    conclude that Shaw did not relinquish, but may enforce, its right
    to dissolution, and restoration. Consequently, PCS may not enforce
    the dissolved lien waiver provision against Shaw.                   Accordingly,
    unless we      find   merit   in   PCS’s        alternative   argument,   Shaw    is
    entitled to enforce its claim and lien, holding PCS liable under
    the LPWA.
    IV.
    A.
    Alternatively, PCS urges us to affirm the summary judgment in
    its favor on a ground that the magistrate judge did not reach,
    viz., that the statement of claim and privilege filed by Shaw did
    not reasonably identify the immovable with respect to which its
    work was performed.
    The LPWA provides that a statement of a claim or privilege
    must reasonably identify the immovable with respect to which the
    work was performed and its owner.63 “The purpose of a statement of
    claim or privilege is to give notice to the owner (and contractor)
    63
    La. R.S. 9:4822.G.(3)
    34
    of the existence of the claim and to give notice to persons who may
    deal with the owner that a privilege is claimed on the property.”64
    “Technical defects in the notice should not defeat the claim as
    long as the notice is adequate to serve the purposes intended,”65
    The filing of a statement of a claim or privilege is accomplished
    when it is filed for registry with the recorder of mortgages of the
    parish in which the work is to be performed.66    Each filing made
    with the recorder of mortgages which contains a reference to
    immovable property shall contain a description of the property
    sufficient to clearly and permanently identify the property.      A
    description which includes the lot and/or square and/or subdivision
    or township and range meets the requirement of the Act.67   Naming
    the street or mailing address without more is not sufficient.68
    On February 17, 1999 Shaw filed with the recorder of mortgages
    in Ascension and Iberville Parishes an amended and supplemental
    statement of claim and privilege in the amount of $5,350,000
    (modifying its original statement of claim and privilege for
    64
    Id., cmt. (g)(citing Mercantile Nat. Bank of Dallas v. J.
    Thos. Driscoll, Inc., 
    195 So. 497
     (La. 1940); See Hibernia
    National Bank v. Belleville Historic Development, L.L.C., 
    815 So.2d 301
    ,*306 (La. App. 4th Cir. 2002).
    65
    
    Id.
    66
    La. R.S. 9:4831.A.
    67
    La. R.S. 9:4831.C.
    68
    
    Id.
    35
    $1,389,707.04    filed    January   27,   1999)69   for    labor,       equipment,
    materials and other engineering and construction services supplied
    to Kaiser to improve the immovable property of PCS.                    To describe
    PCS’s tract of land upon which its plant is located, it appears
    that Shaw used the surveyor’s legal property description contained
    in the deed by which PCS acquired title to the tract.                    The tract
    evidently borders on the Mississippi River at the boundary line
    between    Ascension    and   Iberville    Parishes,      so    that    the   tract
    includes land contiguously located in each parish. In other words,
    the   line   between    the   parishes    runs   through       PCS’s    tract   and
    intersects its river-front boundary at some point not precisely
    disclosed in this record. The surveyor’s legal description does not
    attempt to specify which part of the tract lies in each parish but
    simply begins by stating that the land is located east of the
    Mississippi     River    in    Ascension     and    Iberville          Parishes.70
    69
    Shaw’s original statement of claim and privilege filed
    January 27, 1999 in both parishes was essentially the same as the
    amended and supplemental statement, except for lesser amount of
    $1,389,707.04. The same surveyor’s legal property description was
    attached as in Exhibit A of the amended and supplemental
    statement. Both statements were filed timely and are essentially
    the same in other respects. Therefore, we will discuss in detail
    only the amended and supplemental statement of February 17, 1999.
    70
    The property description begins:
    Legal Description
    South Tract
    A TRACT OF LAND LOCATED IN SECTIONS 74, 75, &T95-R/E
    SECTIONS 38, 39, & 40, T95-R2E, SOUTHEASTERN DISTRICT,
    EAST OF MISSISSIPPI RIVER, ASCENSION & IBERVILLE
    PARISH, LOUISIANA
    36
    Apparently, the same deed of acquisition using the same surveyor’s
    legal description            was    recorded       by   PCS   in   both    Ascension    and
    Iberville Parishes. In any event, it is undisputed that Shaw’s
    statement of claim and privilege uses the only legal description
    pertaining to PCS’s property that is recorded in Ascension and
    Iberville Parishes.           Also, it is undisputed that PCS has not made
    available       to    Shaw    any     other    legal      property        description    to
    substitute for the legal property description recorded in the two
    parishes.
    It is evident from the property description that the PCS tract
    upon        which    the   construction        was      performed     is     bounded    by
    identifiable railroad, electric utility, state highway rights of
    way, and by identifiable tracts owned by a number of other named
    industries, as well as the Mississippi River.71                       It is undisputed
    71
    More specifically, Shaw’s amended and supplemental
    statement of claim provides, in pertinent part, as follows:
    ICF Kaiser Engineers, Inc...entered into a contract with the
    Owners of certain property believed to be PCS Nitrogen
    Fertilizer,L.P....whose address is Louisiana Highway 3115
    and 30, Post Office Box307, Geismar, La 70734 to provide
    labor, equipment, materials and other construction services
    for the construction of a project called “1265 STPD NITRIC
    ACID FACILITY.”
    ...Pursuant to [the Kaiser-Shaw] subcontract, SHAW supplied
    labor, equipment, materials and other
    engineering/construction services to...Kaiser...to improve
    the immovable property described...below.
    The subject immovable property, upon which the work was
    performed, is owned by...PCS Nitrogen Fertilizer,
    L.P....which immovable property is further described on
    37
    that the 1265 STPD Nitric Acid Facility was erected at the PCS
    plant     located   within    the   described   PCS   tract   near   Geismar,
    Louisiana;72 that the prime PCS-Kaiser contract provides that PCS
    will pay Kaiser $38,890,000 for the construction of the 1265 Nitric
    Acid Facility;73 and that Shaw was not paid $5,350,000 for the
    labor, equipment, materials and other engineering/construction
    services that it alone had contributed to the project.
    The Louisiana courts have not added any legal gloss to the
    LPWA’s requirement that a statement of a claim or privilege shall
    “reasonably identify” the property with respect to which the work
    was performed, for the purpose of notifying the owner, contractor,
    and persons dealing with the owner that a privilege is claimed on
    the property, and should be upheld despite technical defects if the
    notice is adequate to serve the purposes intended.74 They have
    Exhibit A attached hereto and made a part hereof.
    Exhibit A consists of a surveyor’s lengthy metes and bounds
    property description, entitled and commencing as follows:
    Legal Description
    South Tract
    A TRACT OF LAND LOCATED IN SECTIONS 74, 75, &T95-R/E
    SECTIONS 38, 39, & 40, T95-R2E, SOUTHEASTERN DISTRICT,
    EAST OF MISSISSIPPI RIVER, ASCENSION & IBERVILLE
    PARISH, LOUISIANA
    72
    See PCS Br. at 9.
    73
    2 R. at 302.
    74
    See, e.g., Hibernia Nat. Bank v. Belleville Historic
    Development, L.L.C., 
    815 So.2d 301
    , 305-306 (La.App. 4th Cir.
    38
    simply applied the unvarnished statutory standards and terms to
    each varying factual situation to determine whether the worksite
    was reasonably identified so as to provide adequate notice of the
    claim and privilege to the owner, contractor and persons dealing
    with the owner.75
    Applying the pertinent LPWA provisions, as we think the
    Louisiana Supreme Court would, we conclude that reasonable minds
    must find that Shaw preserved its claim and privilege by, inter
    alia, “reasonably identify[ing] the immovable with respect to which
    the work was performed...and the owner thereof.”76                     The legal
    description      identifies PCS’s industrial tract on the Mississippi
    River     with   certainty   according       to   surveys   by   a    registered
    professional land surveyor with references including state plane
    coordinates,      certain    section        corners,   metes,        bounds   and
    identifiable landmarks.       PCS does not dispute the fact that the
    1265 Nitric Acid Facility was constructed at PCS’s plant located
    2002)(“[S]trict construction cannot be so interpreted as to
    permit purely technical objections to defeat the real intent of
    the statute, which is to protect materialmen, laborers and
    subcontractors who engage in construction projects.”)(citing
    Bernard Lumber Company, Inc. V. Lake Forest Construction Co. Inc.
    
    572 So.2d 178
     (La. App. 1 Cir. 1990); Authement's Ornamental Iron
    Works v. Reisfeld, 
    376 So.2d 1061
     (La. App. 4th Cir.1979); Morgan
    v. Audubon Const. Corp., 
    485 So.2d 529
     (La. App. 5 Cir. 1986))
    Norris Rader, Inc. v. Swilley, 
    625 So.2d 1125
     (La. App. 3 Cir.
    1993).
    75
    
    Id.
    76
    La. R.S.9:4822.G.(3).
    39
    within PSC’s industrial river-front tract. It is also evident from
    the   foregoing           that   the   1265   STPD    Nitric    Acid    Facility     is   a
    substantial construction or edifice with a distinctive name located
    in PCS’s plant on the clearly and certainly described river-front
    industrial tract. Consequently, we conclude that by furnishing the
    surveyor’s legal property description---which                          described PCS’s
    industrial tract on the Mississippi River, wherein PCS’s plant was
    located, in which the distinctly named, substantial 1265 STP Nitric
    Acid Facility was built—–Shaw reasonably identified the property
    with respect to which the work was performed and the owner thereof.
    Thus, Shaw’s statement of claim and privilege fulfills its purpose
    of “giv[ing] notice to the owner (and contractor) of the existence
    of the claim and [gives] persons who may deal with the owner that
    a privilege is claimed on the property.”77 Because the “notice is
    adequate to serve the purposes intended” any “[t]echnical defects
    78
    in the notice should not defeat the claim.”
    PCS argues that Shaw did not reasonably identify the property
    where the work was done because the property description of PCS’s
    river-front industrial tract was “too broad” to pin-point the site
    of    the     1265    STPD       Nitric   Acid     Facility.    But    the   surveyor’s
    description          of    PCS’s    unsubdivided      industrial       tract   was    the
    77
    
    Id.
     Cmt. (G).
    78
    
    Id.
    40
    starting, not the ending, point.       Additionally, because of the
    magnitude of the construction, the fact that the structure or
    building was called by its specific, distinctive name, and the
    undisputed fact that it was designed and built as an improvement to
    PCS’s plant within the certainly described tract, there was a
    reasonable identification of the place where the work was done so
    as to give notice of the claim to persons who may deal with the
    owner that a privilege is claimed on the property.   Because it was
    adequate to serve this purpose, its technical defects, if any, do
    not defeat the claim.
    The cases upon which PCS relies are inapposite.   In re Lurgi-
    Knost, Inc., was a federal court decision predating the 1981 LPWA
    revision holding that a lien affidavit, stating that materials
    “were actually used in the construction of additions at the plant
    site [of] Enjay Chemical Co., Baton Rouge, Louisiana[,]” was too
    general to be effective because there was no legal description of
    the plant site, and “there is nothing in the affidavit to even
    vaguely indicate which building or structure and which lot or
    parcel of ground may be involved.”79 Shaw’s affidavit, in contrast,
    specifies far more than the owner’s plant in or near a certain
    city; it also provides a surveyor’s detailed legal description of
    the parcel containing the owner’s plant, and, in particular, names
    79
    
    380 F.Supp. 400
    , 403 (M.D.La. 1974).
    41
    specifically the $38 million 1265 STPD Nitric Acid Facility edifice
    built at the plant with Shaw’s labor, materials and services.
    Among other reasons, the lien in Samedan Oil Corp. V. Ultra
    Fabricators, Inc., was invalid because the “steel structures”
    fabricated        were not identified and there was “no block number or
    specific legal description” of the owner’s property.80       As we have
    explained, Shaw’s claim and privilege does name the particular
    structure upon which the work was done and describes its location
    with reference to a specific legal description that includes
    specific sections, townships and ranges, among other identifiers.
    Finally, Boes Iron Works v. Spartan Building Corp., is the most
    inapposite because it held a lien to be invalid on account of its
    identification of the property only by its municipal address.81
    Shaw, of course, did not place its reliance on a municipal address
    but used the multiple factors already described.
    B.
    Applying Section 4833 of the LPWA,82 the magistrate judge ruled
    that Shaw, without reasonable cause, failed to cancel its claims
    and privileges in response to PCS’s written request and assessed
    80
    
    737 So.2d 846
    , (La. App. 3d Cir. 1999).
    81
    
    648 So.2d 24
     (La. App.4th Cir. 1994).
    82
    La. R.S. 9:4833.
    42
    damages and attorneys fees against Shaw. After reviewing the
    record, however, we conclude that Shaw acted with reasonable cause
    and should not be taxed damages and attorneys fees.
    The LPWA provides that, if a statement of claim or privilege is
    improperly filed, an owner may require the filing party to give
    written authorization for the recorder of mortgages to cancel the
    statement of claim or privilege from the records.83             If the person
    who filed the statement of claim or privilege fails, without
    reasonable cause, to comply with the request within ten days, he
    shall be liable for damages suffered by the owner as a consequence
    and    for       reasonable      attorney’s   fees   incurred   in   obtaining
    cancellation.84
    Shaw filed its claim and privilege on January 27, 1999 in
    Ascension and Iberville Parishes and its amended and supplemental
    claim and privilege in both parishes on February 27, 1999. On
    October 20, 2000 PCS’s attorney sent Shaw’s attorneys a letter
    demanding that Shaw cancel its claims and liens in both Ascension
    and Iberville parishes and dismiss this action with prejudice
    within 10 days. Shaw’s attorney responded on October 26, 2000 that
    Shaw would not cancel its filings or dismiss this suit under the
    LPWA because, inter alia, Kaiser had materially breached the
    83
    La. R.S. 9:4833.A.
    84
    La. R.S. 9:4833.B.
    43
    subcontract giving Shaw the right under Civil Code article 1982 to
    raise against PCS all defenses it could raise against Kaiser.
    In parts II & III of this opinion we conclude that, because
    Kaiser materially breached the Kaiser-Shaw subcontract, Shaw had a
    right under Civil Code articles 2013 et seq. to consider the
    subcontract dissolved and to be restored to its position before
    entering the subcontract; and Shaw had a right under Civil Code
    article 1982 to use these rights in defense against PCS.                        Thus,
    because Shaw was no longer obliged by the dissolved subcontract to
    refrain from filing liens or claims against PCS’s property, Shaw
    had the right to file the statements of claim and privilege against
    PCS’s property upon which Shaw’s work was performed. Consequently,
    Shaw’s   claim   and   privilege      were   properly      filed,    and       it   had
    reasonable   cause     to   refuse    to   cancel   them    from    the    mortgage
    records.
    The magistrate judge also decided, however, that Shaw should
    be   assessed    damages     and     attorney’s     fees    because       it    acted
    unreasonably in failing to cancel its claim and lien in Iberville
    Parish because it knew that none of its work had been performed on
    PCS’s property in the parish.              But there is no support in the
    record or basis in law for the magistrate judge’s decision in this
    respect either.      Because the Ascension-Iberville line runs through
    PCS’s industrial tract and plant, Shaw did not know whether its
    44
    work had been performed in one or both of these parishes.85                Thus,
    when PCS filed a written request that Shaw cancel its claims and
    privileges in both parishes and dismiss its lawsuit on October 20,
    2000, Shaw had reasonable cause to refuse to comply.
    PCS   did   not    send    Shaw    any    other   written   request    for
    cancellation of a claim or privilege.              Therefore, Shaw was not
    called upon to consider making any response to a written request
    for cancellation       other   than    PCS’s   October   20,   2000   in   globo
    request.   Consequently, Shaw was never without reasonable cause to
    refrain from cancelling any of its claims or privileges.
    PCS’s January 4, 2001 amendment of its counterclaim to allege
    that Shaw had refused to cancel its liens in both parishes and to
    85
    The magistrate judge apparently concluded that PCS owned
    property on both sides of the river and that the nitric acid
    facility’s location with respect to the river would have made
    clear to Shaw in which parish the work was done. R. at 0683.
    However, the legal description of the property establishes that
    the whole of the property in question is east of the river. The
    surveyor’s description included in Shaw’s statement of claim and
    privilege begins
    Legal Description
    South Tract
    A TRACT OF LAND LOCATED IN SECTIONS 74, 75, &T95-R/E
    SECTIONS 38, 39, & 40, T95-R2E, SOUTHEASTERN DISTRICT,
    EAST OF MISSISSIPPI RIVER, ASCENSION & IBERVILLE
    PARISH, LOUISIANA
    (emphasis added) and the description of the north tract begins
    similarly. The parish line runs essentially perpendicular to the
    river, therefore the position of the nitric acid facility
    relative to the river would not, in and of itself, make clear in
    which parish the work was done.
    45
    pray for damages and attorney’s fees cannot be considered as such
    a request because it related only to Shaw’s rightful refusal to
    comply with PCS’s October 20, 2000 request.              Nor can we so consider
    PCS’s subsequent filing of an affidavit by Robert D. Brinker, its
    Lead Process Supervisor, dated February 15, 2001 that “[t]he 1265
    STPD Nitric Acid Facility is located [o]n a tract of land 160 feet
    x   180 feet,      located   exclusively       in   Ascension       Parish.”      That
    instrument did not request Shaw to do anything.                       Moreover, Mr.
    Brinker’s affidavit did not furnish Shaw with satisfactory proof
    that   none   of    its   work   had   taken    place    in   Iberville        Parish.
    According     to   his    affidavit    Mr.     Brinker   is     a    “Lead     Process
    Supervisor,” not an attorney or a surveyor, and does not show that
    he is qualified to determine the position of the parish line with
    respect to PCS’s plant or the 1265 STPD Nitric Acid Facility.
    Furthermore, the affidavit does not give any factual basis for such
    a determination by Mr. Brinker, does not show that Mr. Brinker’s
    opinion as to the location of the parish line with respect to
    Shaw’s work has a reliable basis, and does not contain a suitable
    legal description by which anyone could determine the location of
    the 160 feet x 180 feet tract conclusorily referred to by Mr.
    Brinker.
    Conclusion
    For the reasons assigned, we reverse the judgment of the
    46
    magistrate judge and instead render judgment in favor of Shaw and
    against PCS, on the issue of liability only, for the recognition of
    the validity of Shaw’s claim and privilege under the LPWA against
    PCS personally, and against its property upon which Shaw’s work was
    performed, for the amounts to be determined in further proceedings
    consistent with this opinion, and for the assessment of all costs
    of these proceedings against PCS.
    Magistrate Judge’s Judgments REVERSED; Judgment RENDERED, on the
    issue of liability, recognizing Shaw’s right to enforce its claim
    and privilege against PCS personally and against PCS’s property
    upon which Shaw’s work was performed, for amounts to be determined
    in further proceedings, and the assessment of all costs of these
    proceedings   against   PCS.    REMANDED   for   further   proceedings
    consistent with this opinion.
    47
    

Document Info

Docket Number: 02-30183

Filed Date: 1/24/2005

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (34)

Mercantile Nat. Bank v. J. Thos. Driscoll, Inc. , 194 La. 935 ( 1940 )

Louis Werner Saw Mill Co. v. White , 205 La. 242 ( 1944 )

J.B.N. Morris, Cross-Appellant v. Homco International, Inc.,... , 853 F.2d 337 ( 1988 )

Hero & Company v. Farnsworth & Chambers Co. , 236 La. 306 ( 1958 )

COLE-MIERS POST 3619 VFW v. State, Department of Revenue & ... , 765 So. 2d 312 ( 2000 )

Hood v. Southern Production Co. , 206 La. 642 ( 1944 )

Foley Lumber Industries, Inc. v. Buckeye Cellulose ... , 286 F.2d 697 ( 1961 )

Ehrlicher v. St Farm Ins Co , 171 F.3d 212 ( 1999 )

Executive Office Centers, Inc. v. Cournoyer , 433 So. 2d 324 ( 1983 )

Jankoviak v. Butcher , 22 Ill. App. 2d 126 ( 1959 )

Tennent v. Caffery , 170 La. 680 ( 1930 )

Erie Railroad v. Tompkins , 58 S. Ct. 817 ( 1938 )

union-texas-petroleum-corporation-v-plt-engineering-inc-state-service , 895 F.2d 1043 ( 1990 )

United States v. Maniscalco , 523 F. Supp. 1338 ( 1981 )

Owsley v. San Antonio Independent School District , 187 F.3d 521 ( 1999 )

Norris Rader, Inc. v. Swilley , 1993 La. App. LEXIS 3267 ( 1993 )

Bernard Lumber Co. v. Lake Forest Const. , 572 So. 2d 178 ( 1990 )

Steptore v. Masco Const. Co., Inc. , 643 So. 2d 1213 ( 1994 )

Lake Charles Diesel, Inc. v. General Motors Corp. , 328 F.3d 192 ( 2003 )

juan-e-vela-phillip-e-daley-tiera-angelle-leger-richard-wayne-medeiros , 276 F.3d 659 ( 2001 )

View All Authorities »