Chevron USA, Inc. v. Aker Maritime, Inc. , 689 F.3d 497 ( 2012 )


Menu:
  •      Case: 11-30369   Document: 00511939414   Page: 1   Date Filed: 07/31/2012
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    July 31, 2012
    No. 11-30369                    Lyle W. Cayce
    Clerk
    CHEVRON USA, INCORPORATED,
    Plaintiff
    v.
    AKER MARITIME INCORPORATED; TECHNIP OFFSHORE
    ENGINEERING, INCORPORATED; TECHNIP OFFSHORE MOORINGS,
    INCORPORATED; TECHNIP OFFSHORE INCORPORATED,
    Defendants-Appellees
    v.
    OCEANEERING INTERNATIONAL INCORPORATED,
    Defendant-Appellant
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    Before JONES, Chief Judge, PRADO, and SOUTHWICK, Circuit Judges.
    LESLIE H. SOUTHWICK, Circuit Judge:
    Following a jury trial, Chevron USA, Inc. was awarded damages from
    Aker Maritime, Inc. and its subsidiaries, and from Oceaneering International,
    Inc.    That judgment was affirmed in an earlier appeal and is not subject to
    further challenge. A bench trial was held on remand to consider remaining
    contractual claims. The district court ordered Oceaneering to pay indemnity
    Case: 11-30369      Document: 00511939414         Page: 2     Date Filed: 07/31/2012
    No. 11-30369
    and attorneys’ fees to Aker. In this appeal, Oceaneering seeks to reverse those
    awards. We AFFIRM.
    FACTUAL AND PROCEDURAL BACKGROUND
    In 2001, there was a significant and costly failure of insignificant-sized
    and inexpensive bolts used on an oil production and drilling facility that sits in
    2600 feet of water, 150 miles south of New Orleans in the Gulf of Mexico. All the
    bolts in the riser system securing the Genesis Spar facility to the Gulf’s floor
    had to be replaced when defects in them were found. Chevron, the operator and
    part owner of the facility, brought suit to allocate responsibility among several
    companies involved in the procurement and installation of the bolts.
    This is the second appeal of a final judgment in the district court. We
    excerpt from our earlier opinion those facts that are most important for
    understanding the remaining issues:
    Chevron hired Aker Maritime, Inc. (“Aker”) in 1998 to provide
    design and engineering services for the initial construction of the
    riser system. Stability problems plagued the riser system after its
    completion, leading to a crack in the spar’s hull in 2000.
    Oceaneering International, Inc. (“Oceaneering”) repaired the hull at
    Chevron’s request, and Chevron put Aker in charge of designing a
    permanent fix. Large bolts called carriage bolts hold the riser
    system together, and Aker ordered the bolts from Lone Star,
    according to testimony a “well-known” bolt manufacturer that also
    distributed others’ bolts. Aker initially requested eight-inch Grade
    5 carriage bolts, which Chevron had approved. When Lone Star
    responded that it had no Grade 5 bolts, Aker placed an order for
    2,092 Grade 2 carriage bolts, costing a total of $878.64. Instead of
    shipping Grade 2 bolts, Lone Star shipped Grade A bolts1
    manufactured by Oriental Fastener Co. (“Oriental”). At the time,
    1
    Grade A and Grade 2 bolts are similar, but the standards are different in several
    respects. The most important difference in this case is that Grade 2 bolts require heating to
    a specific temperature [to] keep them from breaking, whereas Grade A certification allows the
    manufacturer to determine what level of heat treatment is appropriate. At the time, Oriental
    routinely did not heat-treat its bolts at all. [Footnote in original.]
    2
    Case: 11-30369     Document: 00511939414    Page: 3   Date Filed: 07/31/2012
    No. 11-30369
    Lone Star routinely substituted Grade A bolts for Grade 2 bolts,
    then a widespread practice in the fastener industry.
    Lone Star shipped the bolts to Oceaneering, which was in
    charge of assembling the risers. The bolts were marked “OF,”
    indicating the manufacturer, and arrived in shipping boxes bearing
    the Lone Star mark. They also arrived with a packing slip noting
    that they were either “manufactured or distributed” by Lone Star.
    Oceaneering accepted the bolts, failing to notice the substitution.
    The first bolt failure occurred on July 9, 2001, when a bolt
    head popped off one of the first bolts used in the risers. Jack Couch,
    the project manager for Oceaneering, contacted Aker’s Mike
    Harville and told Harville that he thought the bolts were a “serious
    weak link.” Couch took a picture of the failed bolt and sent it to
    Harville. Harville told Oceaneering that it had applied too much
    torque to the bolt, as Oceaneering was applying torque to Grade 2
    bolts that it believed to be Grade 5 bolts. Oceaneering continued
    assembly of the riser system using the torque appropriate for Grade
    2 bolts, apparently without incident. In August 2001, however,
    Aker took over riser assembly, and Oceaneering sent the parts,
    including the bolts, to Aker. Like Oceaneering’s employees, Aker’s
    employees failed to detect that the bolts were Grade A bolts.
    Chevron USA, Inc. v. Aker Mar., Inc., 
    604 F.3d 888
    , 890-91 (5th Cir. 2010) (two
    footnotes omitted).
    After the riser system was installed, it was discovered during a July 2002
    underwater inspection that the heads of several bolts had broken off. Further
    investigation resulted in a decision to replace all the bolts.
    In July 2003, Chevron sued Aker, Oceaneering, and other companies no
    longer in the suit. After a jury trial, Chevron’s total damages were found to be
    almost $3 million. All defendants were found to be negligent, and fault was
    apportioned among them. Aker was held to be 35% at fault, the company Aker
    contacted to supply the bolts also 35%, and the manufacturer of the bolts 20%.
    Oceaneering and the Aker subsidiary that assembled the risers after taking
    over from Oceaneering were each found to be 5% at fault. The district court
    3
    Case: 11-30369    Document: 00511939414   Page: 4   Date Filed: 07/31/2012
    No. 11-30369
    dismissed Aker’s indemnity claim against Oceaneering, concluding it was
    “trumped” by the jury verdict.
    On appeal, we affirmed the damages award. We also vacated the award
    of attorneys’ fees, and reversed and remanded the dismissal of Aker’s indemnity
    claims. After our remand order, Aker and Chevron reached a settlement for all
    claims against Aker “irrespective of their nature.” On remand, the court found
    Oceaneering liable to indemnify Aker for nearly the full settlement amount and
    for attorneys’ fees.
    There are two contracts that control the issues raised on appeal. One is
    a Contract for Genesis Riser Systems Support Services, entered by Chevron and
    Aker in December 1998, which we will call the “Support Contract.” The
    contract specifically dealt with the Genesis Spar project. The other is the
    Master Service Order and Agreement, entered between Chevron and
    Oceaneering in June 1991, which we will call the “Master Agreement.” It is a
    general agreement that predates the Genesis Spar project.
    DISCUSSION
    On this appeal, Oceaneering argues that neither indemnity nor attorneys’
    fees are appropriate because the relevant contracts do not support the awards.
    We will discuss the indemnity issues first.
    I.      Indemnity
    Whether Aker is entitled to indemnity turns on questions of contract
    interpretation. Those questions are legal ones to be reviewed de novo. E.g., Wal-
    Mart Stores, Inc. v. Qore, Inc., 
    647 F.3d 237
    , 242 (5th Cir. 2011). The contract
    and record are reviewed “under the same standards that guided the district
    court.” 
    Id.
     In this diversity suit, we apply the contract interpretation rules of
    4
    Case: 11-30369       Document: 00511939414       Page: 5    Date Filed: 07/31/2012
    No. 11-30369
    the relevant state, which is Louisiana. See Citigroup Inc. v. Fed. Ins. Co., 
    649 F.3d 367
    , 371 (5th Cir. 2011). In Louisiana, words and phrases in a contract are
    construed using generally prevailing meaning.                La. Civ. Code art. 2047;
    Cadwallader v. Allstate Ins. Co., 
    848 So. 2d 577
    , 580 (La. 2003).
    The relevant indemnity clause is found in Master Agreement Paragraph
    6(b), which was executed by Chevron and Oceaneering:
    CONTRACTOR [Oceaneering] shall be liable to and hold
    INDEMNITEES harmless for any loss of or damage to the property
    of COMPANY [Chevron] (its joint venturers and partners and
    affiliates) arising out of, connected with, incident to directly or
    indirectly2 or resulting from or related to CONTRACTOR’S
    performance of this Agreement, including but not limited to,
    CONTRACTOR’S use of equipment provided by COMPANY (its
    joint venturers and partners and affiliates) or others, regardless of
    the passive, concurrent or active negligence of, and regardless of
    whether liability without fault (including, but not limited to, claims
    for unseaworthiness of any vessel) is imposed or sought to be
    imposed on, INDEMNITEES.
    As      previously    mentioned,     this   contract    predates   Oceaneering’s
    involvement on the Genesis Spar. As a master agreement, it appears intended
    to apply to a variety of projects on which Chevron may at different times engage
    Oceaneering. By its own terms, the indemnity applies to damage “arising out
    of, connected with, incident to or resulting from or related to [Oceaneering’s]
    performance of this Agreement.” The work Oceaneering was to perform was
    described as “underwater services including diving, remote operated vehicles
    (ROVs), survey and related services.”
    The Master Agreement defines “Indemnitees,” its importance suggested
    by the fact it is the first term in the agreement.
    CHEVRON U.S.A., INC. and all of its affiliated or parent or
    subsidiary companies or corporations, all of its co-owners or joint
    2
    The three words with a strike-through were eliminated by agreement.
    5
    Case: 11-30369        Document: 00511939414           Page: 6     Date Filed: 07/31/2012
    No. 11-30369
    venturers, and all of the aforesaid entities’ agents, officers,
    employees, representatives or insurers.
    We will later quote the language in the Support Contract that makes Aker the
    agent of Chevron for certain purposes.
    Oceaneering insists that this claim falls outside the scope of the indemnity
    clause. Even if Aker were an agent, which it disputes, Oceaneering’s basic point
    is that Aker’s acts as an agent are not related in any way to Oceaneering’s
    performance of the agreement.              Oceaneering also argues that the Master
    Agreement limits the amount of indemnity, that the Chevron-Aker Support
    Contract limits Aker’s ability to recover from Oceaneering, and that Aker was
    not a third-party beneficiary of the Master Agreement.
    The task at hand is contract interpretation.                        When construing
    indemnification contracts, we will not ignore broad, straightforward language
    that unequivocally states an agreement to indemnify. Perkins v. Rubicon, Inc.,
    
    563 So. 2d 258
    , 259 (La. 1990). This contract unambiguously indemnifies agents
    of Chevron, using extremely broad language and going so far as to indemnify
    them regardless of their own negligence.3 Independent contractors, on the other
    hand, are not listed in this “indemnitees” definition. Thus, whether Aker was
    an agent is crucial to determining Oceaneering’s indemnification obligation.
    A.      Was Aker an Agent of Chevron?
    An agency relationship is determined by looking to “the facts surrounding
    the two parties.” Smason v. Celtic Life Ins. Co., 
    615 So. 2d 1079
    , 1085 (La. Ct.
    App. 1993). The subjective belief of third parties does not determine the
    existence of an agency relationship. 
    Id.
     “Under Louisiana law, an agency
    3
    In 2010, the Louisiana legislature passed a bill that will void, as against public policy,
    some indemnity clauses that seek to shift liability for an indemnitee’s negligence, but this only
    applies to contracts entered into after January 1, 2011. La. Rev. Stat. § 9:2780.1(F).
    6
    Case: 11-30369    Document: 00511939414    Page: 7     Date Filed: 07/31/2012
    No. 11-30369
    relationship cannot be presumed, it must be clearly established.” Matter of
    Oxford Mgmt., Inc., 
    4 F.3d 1329
    , 1336 (5th Cir. 1993).
    An agency may be created by written agreement. Busby v. Walker, 
    84 So. 2d 304
    , 307 (La. Ct. App. 1995). This agency is defined in Support Contract
    Paragraph 1:
    (c) CONTRACTOR [Aker] agrees to perform all SERVICES
    hereunder as an independent CONTRACTOR having full control of
    the manner and means of the performance of SERVICES, and not
    as an employee of COMPANY [Chevron]. . . .
    (d) Notwithstanding paragraph (c) of this article 1, CONTRACTOR
    [Aker] may procure equipment, materials, and SERVICES for
    COMPANY [Chevron] as Agent for COMPANY. When
    CONTRACTOR provides such SERVICES as Agent for COMPANY,
    the following provisions of this Article 1 shall govern:
    (i) All purchases of materials, equipment and SERVICES
    including the applicable purchase order and/or contract terms
    therefor shall be subject to COMPANY approval. COMPANY
    will be responsible for providing to CONTRACTOR full
    information as to COMPANY’s requirements for the
    procurement SERVICES to be performed hereunder. In
    performing such procurement SERVICES, CONTRACTOR
    will endeavor to obtain reasonable guarantees and warranties
    favorable to COMPANY from service contractors and from the
    manufacturers of all plant, equipment and other
    manufactured items to be procured hereunder for COMPANY,
    and CONTRACTOR will cooperate with COMPANY in its
    enforcement of such warranties and guarantees obtained.
    (ii) CONTRACTOR’s liability to COMPANY as a result of any
    claims that result from or are in any way connected with the
    acts or omissions of any service CONTRACTOR or
    manufacturer pursuant to any contract entered into by
    CONTRACTOR as Agent for COMPANY shall be limited
    solely to COMPANY’S recoveries from such service
    CONTRACTOR or manufacturer.
    7
    Case: 11-30369    Document: 00511939414      Page: 8    Date Filed: 07/31/2012
    No. 11-30369
    This language establishes that Aker was Chevron’s agent in its capacity
    as a procurer of “equipment, materials, and services” for Chevron. Oceaneering
    maintains Paragraph 1(c) controls, arguing the exception in Paragraph 1(d) does
    not apply because damages were not caused by Aker acting as an agent to
    procure materials. Instead, damages were caused by Aker’s actions as an
    independent contractor. We examine next the scope of the agency.
    B.    What was the Scope of the Agency?
    Contracts are construed using their ordinary and prevailing meaning. See
    La. Civ. Code art. 2047. The Support Contract explicitly creates an agency
    relationship when Aker is “procur[ing] equipment, materials, and services” for
    Chevron. Oceaneering maintains this language means Aker is only an agent
    when dealing with the supplier. Aker was thus not Chevron’s agent with respect
    to Oceaneering because Aker never “procured” anything from Oceaneering.
    “Procurement” means an “act of getting or obtaining something.” Black’s
    Law Dictionary 1327 (9th ed. 2009). The plain language of the term extends
    beyond Aker’s mere ordering and includes the receipt of the bolts. Receipt and
    acceptance of faulty and improper bolts is at the heart of this action. The agency
    began with Aker’s initial ordering of the bolts and continued through the
    obtaining of possession. Because Chevron required the bolts to be delivered
    directly to Oceaneering, procurement continued at least until that delivery.
    The agency provision also refers to purchase orders and contracts between
    Aker and a supplier. There were no such written agreements between Aker and
    the distributer. We disagree with Oceaneering that the Support Contract
    requires purchase orders or contracts as prerequisites to establishing an agency
    relationship. When such documentation exists, though, the Support Contract
    makes their terms subject to Chevron’s approval.
    Oceaneering further contends that, at a minimum, it should not be
    obligated to indemnify Aker for the full amount of its liability because Aker’s role
    8
    Case: 11-30369    Document: 00511939414       Page: 9    Date Filed: 07/31/2012
    No. 11-30369
    as agent-procurer was only partially the source of its 35% liability to Chevron.
    Oceaneering maintains that Chevron made claims against Aker for failures in
    quality control, inspection, and engineering services, and it was in this capacity
    that Aker settled its claims with Chevron. Therefore, Oceaneering maintains
    the district court erred in holding it liable for all of Aker’s 35% liability.
    The contention that Aker’s responsibility should be divided in this way is
    being raised for the first time on appeal. Arguments not raised in district court
    will not be considered absent “extraordinary circumstances.” N. Alamo Water
    Supply Corp. v. City of San Juan, Tex., 
    90 F.3d 910
    , 916 (5th Cir. 1996).
    “Extraordinary circumstances exist when the issue involved is a pure question
    of law and a miscarriage of justice would result from our failure to consider it.”
    
    Id.
     This litigation began over eight years ago. It has gone through two appeals,
    multiple proceedings in district court, and a settlement between Aker and
    Chevron. The jury found Aker liable for general negligence. Oceaneering did
    not propose instructions or a verdict form allowing the verdict to divide Aker’s
    fault into subcategories. It did not request a new trial, raise these issues in the
    district court on remand, or challenge Aker’s settlement with Chevron.
    In fact, the parties in the district court addressed a different subdividing
    of liability. Jurors assigned an additional 5% liability to an Aker subsidiary that
    had assembled the risers after Oceaneering stopped doing so. The district court
    deducted the amount attributed to Aker’s subsidiary from the total settlement.
    Oceaneering did not argue that any further partial reduction was justified.
    These arguments are waived.
    In summary, then, Aker’s arranging for the purchase and delivery of the
    bolts to Oceaneering was in the capacity of Chevron’s agent under the Support
    Contract. Some of the bolts were then used by Oceaneering in the initial efforts
    to assemble part of the riser system. The district court considered that work to
    be part of Oceaneering’s performance under the Master Agreement:
    9
    Case: 11-30369    Document: 00511939414      Page: 10   Date Filed: 07/31/2012
    No. 11-30369
    As Chevron’s receiving contractor, Oceaneering failed to detect that
    Lone Star [the distributor of the bolts] made an unauthorized
    substitution, which gave rise to Chevron’s claims against Aker.
    Hence, this scenario falls within the language of the indemnity
    clause, making Oceaneering liable to Aker.
    The court noted that this indemnity is quite broad, making Oceaneering’s
    relatively minor and brief performance of work under its Master Agreement with
    Chevron the source of a duty to indemnify Aker, who as Chevron’s agent was
    found by jurors to be much more at fault than Oceaneering. Such inequities,
    often unpredictable when contracts are written, do not then become a basis to
    prevent the contracts from being enforced.
    C.    Limitations on liability
    Oceaneering further maintains that even if Aker is entitled to indemnity,
    the Master Agreement limits its indemnity obligation to the applicable insurance
    coverage. In the district court there was no determination as to what insurance
    was applicable nor was Oceaneering’s insurer a party. As such, Oceaneering
    contends judgment against it was in error. But, again, Oceaneering failed to
    raise these contentions at any point prior to this appeal and they are waived.
    D.    Other arguments
    Oceaneering raises other arguments. One is that the Support Contract’s
    Paragraph 1(d) prohibits Aker from seeking indemnity. It maintains that only
    Chevron can pursue an indemnity action against it arising out of Aker’s role as
    agent. Oceaneering bases this argument on Support Contract Paragraph 1(d)
    subsections (i) and (ii). Paragraph 1(d)(i) states that Aker will obtain reasonable
    warranties and “will cooperate with [Chevron] in its enforcement of such
    guarantees or warranties obtained.” Chevron initiated this litigation and Aker
    cross-claimed. Support Contract Paragraph 1(d)(i) does not prohibit Aker from
    cross-claiming in litigation Chevron commences.
    10
    Case: 11-30369   Document: 00511939414     Page: 11   Date Filed: 07/31/2012
    No. 11-30369
    Subsection 1(d)(ii) does not offer any additional support. It limits Aker’s
    liability to Chevron’s recovery against the manufacturer. Oceaneering argues
    that the Support Contract’s limitation of Aker’s liability to Chevron
    demonstrates that Aker was not granted the right to sue a manufacturer it deals
    with as an agent. Although Subsection 1(d)(ii) may make bringing a suit
    unnecessary, it does not demonstrate that Aker is prohibited from pursuing a
    suit for indemnification against Oceaneering.
    Oceaneering is not a third-party beneficiary of the Support Contract. A
    contracting party may stipulate a benefit to a third person, but the intent of the
    parties to stipulate such a benefit must be clear. La. Civ. Code art. 1978; Doucet
    v. Nat’l Maint. Corp., 
    822 So. 2d 60
    , 66 (La. Ct. App. 2002). No clear intent
    exists and, thus, Oceaneering cannot rely on the Support Contract’s terms.
    Oceaneering argues that neither is Aker a third-party beneficiary of the
    Master Agreement.          Unlike the Support Contract, the Master Agreement
    manifests a clear intention to indemnify agents of Chevron. The fact that Aker
    was not named as an agent is irrelevant. Oceaneering agreed to indemnify all
    agents of Chevron. Who those agents would be in the future under different
    projects would not be known at the time of the 1991 Master Agreement.
    II.      Attorneys’ fees
    Oceaneering argues the award relied on an incorrect version of the
    contract, the court failed to consider certain required factors under our caselaw,
    and the fees should have been segregated.
    Our court reviews an attorneys’-fees award for an abuse of discretion. In
    re High Sulfur Content Gasoline Prods. Liab. Litig., 
    517 F.3d 220
    , 227 (5th Cir.
    2008).     To constitute an abuse of discretion, the district court must have
    erroneously applied the law or made a clearly erroneous assessment of the
    evidence. 
    Id.
     “A fee award is governed by the same law that serves as the rule
    11
    Case: 11-30369    Document: 00511939414     Page: 12   Date Filed: 07/31/2012
    No. 11-30369
    of decision for substantive issues in the case.” Mathis v. Exxon Corp., 
    302 F.3d 448
    , 461 (5th Cir. 2002). That means Louisiana law applies.
    Oceaneering contends the district court abused its discretion by relying on
    the wrong version of the Master Agreement when determining attorneys’ fees,
    failing to analyze the Johnson factors, and failing to segregate Aker’s fees.
    Regarding the contention that the court applied the wrong version of the
    Master Agreement, Oceaneering specifically maintains that the court relied on
    the “directly or indirectly” language in Master Agreement Paragraph 6(b) that
    was struck from the contract. But, as Aker points out, the court relied upon
    “directly or indirectly” as it is employed in Master Agreement Paragraph 6(c),
    not 6(b). This provision was not struck from the contract. Thus, the court did
    not rely on an incorrect version of the contract.
    The contention that the court did not analyze the Johnson factors similarly
    fails. In Louisiana, the amount of an attorneys’-fees award is governed by Rule
    1.5 of the Rules of Professional Conduct. State Dep’t of Transp. & Dev. v.
    Williamson, 
    597 So. 2d 439
    , 442 n.9 (La. 1992). The factors therein are very
    similar to those used in the federal “lodestar” method as set out in Johnson v.
    Georgia Highway Express, Inc., 
    488 F.2d 714
     (5th Cir. 1974), abrogated on other
    grounds by Blanchard v. Bergeron, 
    489 U.S. 87
     (1989). The Johnson factors
    include the difficulty of the matter, the requisite skill to perform the legal
    service, the amount involved, the results obtained, and the ability of the
    attorneys. Id. at 717-19. In its opinion, the court stated: “In conclusion, the
    complexity of this matter, counsel’s expertise, the amount of money involved,
    and the results obtained all require this Court to award Aker the full amount of
    attorneys’ fees and costs claimed, without any downward adjustment.” Chevron
    USA, Inc. v. Aker Mar., Inc., No. 2:03-CV-2027, 
    2011 WL 999253
    , at *4 (E.D. La.
    Mar. 17, 2011). Other statements in the same analysis show the court also
    considered the time and labor required as well as the customary fee. Id. at *3-4.
    12
    Case: 11-30369    Document: 00511939414       Page: 13   Date Filed: 07/31/2012
    No. 11-30369
    Because the court applied factors essentially identical to those required by
    Louisiana law, it did not abuse its discretion.
    Finally, Oceaneering contends that the district court erred in failing to
    segregate Aker’s fees. The relevant provision of the Master Agreement reads:
    CONTRACTOR shall promptly pay (I) to any INDEMNITEE all
    costs and attorneys’ fees incurred by such INDEMNITEE resulting
    directly or indirectly from any and all loss, damage, injury, liability
    and claims for which CONTRACTOR is obligated to indemnify such
    INDEMNITEE pursuant to the Paragraph 6 . . . .
    This shows that “directly or indirectly” was not struck from Master Agreement
    Paragraph 6(c). This clause is broad. It does not require segregation because
    the entire litigation is at least indirectly related to Oceaneering’s actions that
    resulted in the obligation to indemnify Aker.
    AFFIRMED.
    13