Doug Kellermann v. Avaya, Incorporated ( 2013 )


Menu:
  •      Case: 12-51249       Document: 00512282179         Page: 1     Date Filed: 06/20/2013
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    June 20, 2013
    No. 12-51249                          Lyle W. Cayce
    Summary Calendar                             Clerk
    DOUG KELLERMANN,
    Plaintiff-Appellant
    v.
    AVAYA, INC.,
    Defendant-Appellee
    Appeal from the United States District Court
    for the Western District of Texas
    USDC No. 1:11-CV-359
    Before KING, CLEMENT, and HIGGINSON, Circuit Judges.
    PER CURIAM:*
    Doug Kellermann filed suit against Avaya, Inc., alleging that Avaya
    breached the terms of its commission policy by manipulating its revenue
    recognition procedure, increasing Kellermann’s target quota, and reducing his
    commission payment. Avaya moved for summary judgment on the basis that
    Kellermann could not prevail on his breach of contract claim because the policy
    at issue expressly authorized Avaya to adjust sales quotas and incentive
    *
    Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR.
    R. 47.5.4.
    Case: 12-51249        Document: 00512282179        Page: 2       Date Filed: 06/20/2013
    No. 12-51249
    payments at its discretion. The district court granted Avaya’s motion, and
    Kellermann now appeals. For the reasons that follow, we AFFIRM the district
    court’s judgment.
    I. FACTUAL AND PROCEDURAL BACKGROUND
    Doug Kellermann worked for Avaya, Inc., as a global account manager.
    His compensation was governed by Avaya’s “Global Sales Compensation
    Policies” (“Policies”) and included a base salary and certain incentive payments.
    Incentive payments were based on the attainment of certain quotas, or monetary
    sales goals, that were established by the company for each salesperson during
    each plan period. Plan periods were either twelve months (from October 1
    through September 30) or six months in length (October 1 through March 31,
    and April 1 through September 30).1 A given sale was credited toward a
    salesperson’s quota after revenue from that sale was recognized by Avaya, and
    incentive payments based on quota attainment were calculated and paid on a
    monthly or quarterly basis.
    To receive incentive payments, a salesperson was required to have a
    signed, up-to-date condition sheet on file. Effective October 1, 2009, Avaya
    developed its condition sheet for the first half of fiscal year 2010 (the “October
    condition sheet”), which Kellermann accepted on December 3, 2009. The October
    condition sheet included a section stating that the undersigned employee
    acknowledged the applicability of the Policies to the employee’s compensation
    plan. At all times relevant to this action, the Policies included the following
    notice, in bold lettering, on the cover page:
    AVAYA INC. (“AVAYA”) HAS THE RIGHT TO AMEND, CHANGE,
    OR CANCEL THE SALES COMPENSATION POLICIES SOLELY
    AT ITS DISCRETION AND WITHOUT PRIOR NOTICE, EXCEPT
    IN COUNTRIES WHERE IT IS A VIOLATION OF APPLICABLE
    LAW.
    1
    Kellermann alleges that six-month periods were atypical.
    2
    Case: 12-51249      Document: 00512282179      Page: 3    Date Filed: 06/20/2013
    No. 12-51249
    Elsewhere, the Policies included the following provision:
    Quota adjustments may be necessary after the start of the plan year
    (e.g., error correction, redefinition of quota, assignments, crediting
    changes, etc.). Sales management (with the appropriate approvals)
    has the discretion to change quota, should there be an error in quota
    setting, assignments, crediting, or to ensure credit to those
    associates involved in a sale.
    Finally, the Policies contained a similar provision near the end of the document,
    which stated:
    Avaya reserves the right to: (1) amend, change, or cancel the Sales
    Compensation Plan or Policies or any elements of the Plan solely at
    its discretion; and (2) revise assigned territories, revenue quotas,
    reduce, modify, or withhold compensation based on individual/team
    performance or Avaya determination of special circumstances, with
    or without prior notice, and either retroactively or prospectively,
    except in countries where it is a violation of applicable law.
    The dispute currently at issue arose in connection with Kellermann’s
    involvement in Avaya’s successful effort to obtain a client’s Internet
    Protocol/Automated Call Distributor (“IP/ACD”) business. Kellermann was
    instrumental in securing the IP/ACD project, which was scheduled to be
    implemented in four phases. According to Kellermann, everyone within Avaya
    expected revenue for the first phase of the project (“IP/ACD I”) to be recognized
    during the last quarter of fiscal year 2009. Nevertheless, although IP/ACD I
    revenue allegedly was received during fiscal year 2009, and although IP/ACD I
    was fully installed and operational prior to October 1, 2009, Avaya did not
    recognize the related revenue until the first quarter of fiscal year 2010.2 As a
    result, Kellermann did not meet his sales quota for fiscal year 2009, and he did
    not receive a commission for IP/ACD I in fiscal year 2009.
    2
    Avaya maintains that it recognized revenue as soon as reasonably practicable,
    consistent with accepted accounting practices, and notwithstanding any potential
    compensation ramifications of doing so.
    3
    Case: 12-51249    Document: 00512282179     Page: 4   Date Filed: 06/20/2013
    No. 12-51249
    On October 1, 2009, Avaya’s salespersons began working under the sales
    quotas set forth in the October condition sheet. According to Kellermann, his
    quota was raised to include recognition of IP/ACD I revenue that he previously
    had anticipated would be recognized in fiscal year 2009. However, because
    Avaya’s sales team initially did not anticipate that phase two of the project
    (“IP/ACD II”) would begin until after March 31, 2010, Kellermann’s quota in the
    October condition sheet did not include any IP/ACD II revenue.
    Kellermann was paid his commission on IP/ACD I in January 2010. That
    same month, Avaya’s client indicated that it wished to accelerate by several
    months completion of IP/ACD II. As that phase of the project was moving
    forward, on March 1, 2010, Avaya approved for Kellermann a new condition
    sheet for the period October 1, 2009 through March 31, 2010. Included therein
    was an increased sales quota. According to Avaya’s sales operations manager,
    the company decided to issue new condition sheets to its sales personnel as a
    result of its December 2009 acquisition of Nortel Network’s enterprise solutions
    business.   As part of that acquisition, Avaya’s salespersons, including
    Kellermann, were expected to sell legacy Nortel products as well as Avaya’s
    products and services. The new condition sheets reflected those additional sales
    responsibilities, and in Kellermann’s case, also increased his quota to account
    for the earlier-than-anticipated revenue from the IP/ACD project.
    Kellermann rejected the new condition sheet on March 7, 2010, and
    submitted a letter of resignation the same day. IP/ACD II became operational
    in late March 2010, though Avaya allegedly already had recognized the revenue
    from that phase of the project earlier that month.         Thus, according to
    Kellermann, in contrast to the company’s approach with respect to IP/ACD I,
    Avaya recognized IP/ACD II revenue prior to the phase’s operational date.
    Because Kellermann had rejected the new condition sheet, Avaya’s
    position was that the October condition sheet remained in effect. Under its
    4
    Case: 12-51249       Document: 00512282179         Page: 5    Date Filed: 06/20/2013
    No. 12-51249
    terms, Kellermann had acknowledged—by the condition sheet’s incorporation of
    the Policies—the potential that Avaya could apply a “Large Sale Adjustment” to
    his quota. As set forth in the Policies, a Large Sale Adjustment permitted Avaya
    to (1) increase a salesperson’s quota by 85% of a large sale’s revenue and give
    credit to the salesperson for 100% of the large sale, or (2) leave the quota
    unchanged, but give the salesperson credit for only 15% of the large sale.3 Avaya
    contends that, because acceleration of the IP/ACD project caused estimates
    regarding the timing of the project’s revenue stream to be inaccurate,
    Kellermann achieved a disproportionately high quota achievement, resulting
    from an artificially low quota. To compensate for the inaccurate estimates,
    Avaya applied the Large Sale Adjustment to Kellermann’s sales, but did so only
    in connection with revenue received from the second phase of the IP/ACD
    project. Consequently, Kellermann was credited with only 15% of the IP/ACD
    II sales.
    In August 2010, Kellermann filed suit, claiming that Avaya breached its
    contract with him by manipulating its recognition of IP/ACD revenue and by
    applying the Large Sale Adjustment to IP/ACD II revenue. Following discovery,
    Avaya moved for summary judgment, which the district court granted after
    holding that Kellermann could not establish a breach of contract because Avaya
    simply had exercised its discretionary contractual right to amend, change, or
    cancel its sales compensation policies. Kellermann now appeals, contending that
    the court erred in granting summary judgment in Avaya’s favor.
    3
    According to the Policies, a quota could be reviewed in anticipation of a potential
    Large Sale Adjustment for the following, non-exclusive, reasons: “deal margin, profitability,
    structure, and validation/correction against original quota.” Sales were permitted to be
    reviewed when a particular sale exceeded a salesperson’s annual quota by 25% and was not
    included in the original quota allocation, or when the quota otherwise was inaccurate. Avaya
    expressly “reserve[d] the right to apply the Large Sale Adjustment Policy to any sales
    associates tied to the sale.”
    5
    Case: 12-51249     Document: 00512282179      Page: 6   Date Filed: 06/20/2013
    No. 12-51249
    II. STANDARD OF REVIEW
    We review a lower court’s grant of summary judgment de novo. First Am.
    Bank v. First Am. Transp. Title Ins. Co., 
    585 F.3d 833
    , 836–37 (5th Cir. 2009).
    Although we view the evidence and any inferences therefrom in the light most
    favorable to the nonmoving party, Eason v. Thaler, 
    73 F.3d 1322
    , 1325 (5th Cir.
    1996), summary judgment is appropriate where the record demonstrates that
    “there is no genuine dispute as to any material fact and the movant is entitled
    to judgment as a matter of law,” FED. R. CIV. P. 56(a), (c)(1). “A factual dispute
    is ‘genuine’ if a reasonable trier of fact could return a verdict for the nonmoving
    party.” James v. Tex. Collin Cnty., 
    535 F.3d 365
    , 373 (5th Cir. 2008). “Where the
    non-moving party fails to establish ‘the existence of an element essential to that
    party’s case, and on which that party will bear the burden of proof at trial,’ no
    genuine issue of material fact can exist.” Nichols v. Enterasys Networks, Inc.,
    
    495 F.3d 185
    , 188 (5th Cir. 2007) (quoting Celotex Corp. v. Catrett, 
    477 U.S. 317
    ,
    322–23 (1986)).
    III. DISCUSSION
    Kellermann argues that summary judgment was improper because various
    factual issues remain open. In particular, he maintains that the following fact
    questions precluded summary judgment: (1) whether Avaya intentionally
    delayed revenue recognition in fiscal year 2009; (2) whether Avaya intentionally
    accelerated revenue recognition in fiscal year 2010; (3) whether Avaya made this
    acceleration to implicate the Large Deal Adjustment (which otherwise would
    have been inapplicable); (4) whether Avaya refused to pay a commission it knew
    had been earned by Kellermann; and (5) what damages were sustained by
    Kellermann.     Avaya responds that its actions merely were the result of
    adjustments necessitated by unanticipated changes in revenue timing related
    to the IP/ACD project. In any event, Avaya contends that its rationale is
    immaterial because, by incorporating the Policies, the October condition sheet
    6
    Case: 12-51249     Document: 00512282179      Page: 7   Date Filed: 06/20/2013
    No. 12-51249
    reserved for Avaya unfettered discretion to alter or cancel its compensation
    policies.
    A. Applicable Law
    Under Texas law, “[t]he elements of a breach of contract claim are: (1) the
    existence of a valid contract between plaintiff and defendant; (2) the plaintiff’s
    performance or tender of performance; (3) the defendant’s breach of the contract;
    and (4) the plaintiff’s damage as a result of the breach.” In re Staley, 
    320 S.W.3d 490
    , 499 (Tex. App.—Dallas 2010, no pet.). “Whether a party has breached a
    contract is a question of law for the court, not a question of fact for the jury.”
    Meek v. Bishop Peterson & Sharp, P.C., 
    919 S.W.2d 805
    , 808 (Tex.
    App.—Houston [14th Dist.] 1996, writ denied). “The court determines what
    conduct is required by the parties, and, insofar as a dispute exists concerning the
    failure of a party to perform the contract, the court submits the disputed fact
    questions to the jury.” Id. In other words, “[w]hile the factual determination of
    what actions were taken is for the fact finder, whether those actions constitute
    a breach of contract is a question of law for the court.” In re Cano Petrol., Inc.,
    
    277 S.W.3d 470
    , 473 (Tex. App.—Amarillo 2009, orig. proceeding).
    B. Analysis
    In applying these principles to the case sub judice, we find controlling our
    holding in Nichols, 
    495 F.3d 185
    . As here, the plaintiff in Nichols filed suit
    against his former employer for failing to pay certain outstanding commissions
    allegedly due under a compensation plan that provided for a base salary plus a
    commission incentive. Id. at 186–87. The dispute arose after the employer
    presented the employee with a new goal sheet and sales plan for fiscal year 2001
    that reflected a lower commission rate, a higher quota, and different customer
    assignments than had been provided for in the employee’s fiscal year 2000 plan.
    Id. at 187. The employee refused to sign the new goal sheet and, for various
    reasons, claimed that the terms of the fiscal year 2000 goal sheet and sales plan
    7
    Case: 12-51249     Document: 00512282179     Page: 8   Date Filed: 06/20/2013
    No. 12-51249
    still applied into fiscal year 2001. Id. The employer moved in district court for
    summary judgment, which the court granted after concluding that, regardless
    of which year’s goal sheet and sales plan applied, the employer’s compensation
    plan unambiguously gave management the right and discretion to adjust the
    employee’s compensation. Id. at 188.
    On appeal, we likewise observed that, even assuming the fiscal year 2000
    goal sheet and sales plan applied, the employer’s compensation plan allowed the
    employer “to establish or adjust quotas and geographic/account assignments at
    any time,” to “review any sales substantially in excess of annual quota or
    objective,” and “to make final and binding decisions regarding the amount of
    compensation earned and paid to any [p]lan [p]articipant.” Id. at 187. Thus, the
    employee’s contract “include[d] the very terms giving [the employer] discretion
    to adjust [the employee’s] commission, assignments, and final compensation.”
    Id. at 189. We therefore affirmed the district court’s judgment, concluding that
    the employee could not show that the employer breached the terms of the fiscal
    year 2000 compensation plan, because the employer merely had “exercis[ed]
    rights clearly reserved to it by the [p]lan’s language.” Id. at 191.
    In subsequently applying Nichols, we explained that the case stands for
    the proposition “that where an employer exercises rights reserved in the
    contract[,] there can be no breach of contract.” Hennings, Jr. v. CDI Corp., 451
    F. App’x 359, 367 (5th Cir. 2011) (unpublished) (per curiam) (citing Nichols, 495
    F.3d at 188 (“plaintiff cannot prove employer breached contract when employer
    exercising rights reserved in contract’s plain language”)). Accordingly, the
    holding in Nichols clearly governs the outcome here. Under the Policies, Avaya
    reserved—at its sole discretion, and without having to provide prior notice—the
    right to amend, change, or even cancel its sales compensation policies or any
    elements thereof; to revise revenue quotas; and to reduce, modify, or withhold
    incentive compensation. In other words, regardless of when it recognized
    8
    Case: 12-51249     Document: 00512282179      Page: 9    Date Filed: 06/20/2013
    No. 12-51249
    revenue for any particular sale, Avaya reserved for itself sole discretion to adjust
    Kellermann’s incentive pay.      Kellermann agreed to these terms when he
    accepted the October condition sheet. As a result, Kellermann was unable to
    establish a breach of contract, as Avaya simply exercised rights reserved to it in
    the plain language of the Policies. See Nichols, 495 F.3d at 191. Because
    Kellermann failed to establish the existence of this element of his breach of
    contract claim, no genuine issue of material fact existed, and summary judgment
    in Avaya’s favor therefore was proper. See Celotex Corp., 477 U.S. at 322–23.
    IV. CONCLUSION
    Accordingly, we AFFIRM the district court’s judgment.
    9