AEP Texas North Co. v. Texas Industrial Energy Consumers ( 2007 )


Menu:
  •                                                    United States Court of Appeals
    Fifth Circuit
    F I L E D
    REVISED JANUARY 16, 2007                       December 21, 2006
    IN THE UNITED STATES COURT OF APPEALS Charles R. Fulbruge III
    FOR THE FIFTH CIRCUIT                Clerk
    No. 05-51755
    AEP TEXAS NORTH CO.,
    Plaintiff-Appellee,
    versus
    TEXAS INDUSTRIAL ENERGY CONSUMERS,
    Intervenor-Defendant,
    versus
    CITIES OF ABILENE, BALLINGER, CISCO, SAN ANGELO and
    VERNON, TEXAS,
    Intervenor-Defendants-Appellants,
    versus
    THE PUBLIC UTILITY COMMISSION OF TEXAS, ET AL,
    Defendants,
    PAUL HUDSON, CHAIRMAN OF THE PUBLIC UTILITY
    COMMISSION OF TEXAS; JULIE PARSLEY, COMMISSIONER
    OF THE PUBLIC UTILITY COMMISSION OF TEXAS; and
    BARRY T. SMITHERMAN, COMMISSIONER OF THE PUBLIC
    UTILITY COMMISSION OF TEXAS,
    Defendants-Appellants.
    Appeals from the United States District Court for
    the Western District of Texas
    (USDC No. 1:04-CV-1069)
    _________________________________________________________
    Before REAVLEY, STEWART, and CLEMENT, Circuit Judges.
    REAVLEY, Circuit Judge:
    The issue before us is whether a state regulatory agency may set retail rates
    based on its own determination that a utility has not complied with a Federal Energy
    Regulatory Commission (“FERC”) tariff. We hold that pursuant to the filed rate
    doctrine, federal law preempts state regulators from making a final determination as
    to whether a FERC tariff has been violated and from imposing a remedy for an
    alleged violation. We therefore affirm.
    I.
    A. The Merger
    Appellee Texas North Company (“TNC”) provides retail electric service
    solely in Texas. In 1999, TNC's parent, the Central and South West Company,
    merged with the American Electric Power Company (“AEP”). TNC is now one of
    nine public utilities owned by AEP.
    Before the merger, AEP submitted a merger plan, termed the System
    2
    Integration Agreement (the “SIA”), for approval to FERC. FERC approved the
    plan. The SIA is the tariff, or rate schedule, currently filed with FERC.
    When the AEP system has an excess of generating capacity, an affiliate of the
    utilities, called the AEP Service Corporation (“AEPSC”) sells the excess power at
    wholesale. The SIA requires that AEPSC determine the profits from such sales,
    called Trading and Marketing Realizations (“TMRs”), “on an hourly basis." The
    SIA defines TMRs as "the difference between i) the revenues collected from
    Trading and Marketing Activities and ii) the Out-of-Pocket Cost of such Trading
    and Marketing Activities and any transmission cost related to such activities."
    The SIA then mandates that from sales made by all, AEPSC will distribute
    the TMRs between two zones in the AEP system, according to a specific formula.
    The distribution occurs in two stages. First, the SIA provides that all TMRs up to a
    certain amount (equaling the amount of TMRs that were recorded in a Base Year,
    the twelve month period preceding the merger) will be allocated between the former
    Central and South West company (now called AEP West) and the former AEP
    company (now called AEP East) as they were in the Base Year. This first allocation
    favors AEP East. Second, all remaining TMRs are allocated between AEP East and
    AEP West in proportion to generating capacity. This allocation favors AEP West.
    Therefore, TNC is favored in the second stage of the allocation process.
    3
    B. The Commission’s Review
    Immediately before Texas moved to a deregulated electricity market in 2002,
    the Texas Legislature mandated that the successors of the former public utilities
    seek a final reconciliation of their regulated fuel expenses and revenues before the
    Public Utility Commission of Texas (the “Commissioners”). According to Texas
    law, after costs and revenues are reconciled, the utilities must refund any
    over-recovery to the utility's retail ratepayers. 16 Tex. Admin. Code Ann. §
    25.236(e) (2002). TNC filed a petition for a final reconciliation in June 2002.
    In the first proceeding related to this appeal, the Commissioners found that
    the TMR allocations were correctly calculated pursuant to the SIA. On rehearing,
    however, the Commissioners disagreed with AEPSC's calculation of TMRs in the
    Base Year. AEPSC credited the AEP East companies with the values of "open"
    transactions that had not yet been completed, as well as the profits from completed
    sales. The Commissioners determined that including the "open" transactions (a
    method of accounting known as "mark-to-market") in the Base Year calculations
    was not consistent with the SIA, which defined TMRs as the difference between
    revenues collected and out-of-pocket costs.
    The Commissioners then proceeded to rectify the alleged error in
    calculations. The parties in the reconciliation proceeding stipulated that the
    4
    mark-to-market accounting resulted in $7.9 million less in revenues for TNC. The
    Commissioners ordered that TNC reduce its retail rates as if it had received this
    revenue. However, AEPSC did not change its method of calculating TMRs.
    Because of the lower retail rates, TNC was forced to absorb the difference between
    the actual allocation of revenues and the lower retail rates. TNC filed a motion for
    rehearing, which was overruled.
    TNC filed this action in federal court, challenging the order on preemption
    grounds. The district court granted TNC's motion for summary judgment, finding
    that the Commissioners' ruling violated the Federal Power Act and the Supremacy
    Clause of the U.S. Constitution.
    II.
    A.
    The Federal Power Act (“FPA”) gives FERC exclusive jurisdiction to
    regulate the transmission and wholesale sale of electric energy in interstate
    commerce.1 The filed rate doctrine, which governs this case, derives from that
    jurisdictional grant. "The filed rate doctrine requires ‘that interstate power rates
    filed with FERC or fixed by FERC must be given binding effect by state utility
    1
    16 U.S.C. § 824(b)(1).
    5
    commissions determining intrastate rates.'"2 The FPA and the Supremacy Clause,
    U.S. Const. art. VI, § 2, preempt any state action modifying or overruling a filed
    rate.3 Pursuant to the doctrine, the Supreme Court has determined that federal law
    preempts states from second-guessing FERC's allocations of electric power4 and
    from conducting prudence inquiries into FERC's cost allocations, even when FERC
    has not conducted such an inquiry.5 In addition, states are prohibited from “trapping
    costs” by setting retail sales at a level that would prevent a utility “from recovering
    the costs of paying the FERC-approved rate.”6
    In Entergy, the most recent Supreme Court case dealing with the filed rate
    doctrine, the Court considered “whether a FERC tariff that delegates discretion to
    the regulated entity to determine [a] precise cost allocation. . . preempts a [state
    commission’s] order that adjudges those costs imprudent.”7 The Entergy
    2
    Entergy Louisiana, Inc., v. Louisiana Pub. Serv. Comm'n, 
    539 U.S. 39
    , 47, 
    123 S. Ct. 2050
    , 2056 (2003) ("Entergy") (quoting Nantahala Power & Light Co. v. Thornburg, 
    476 U.S. 953
    , 962, 
    106 S. Ct. 2349
    , 2354 (1986)).
    3
    
    Entergy, 539 U.S. at 47
    , 123 S. Ct. at 2056.
    4
    
    Nantahala, 467 U.S. at 955
    , 106 S. Ct. at 2351.
    5
    Mississippi Power & Light Co. v. Moore, 
    487 U.S. 354
    , 357, 
    108 S. Ct. 2428
    , 2431
    (1988).
    6
    
    Nantahala, 467 U.S. at 970
    , 106 S. Ct. at 2358–59.
    7
    
    Entergy, 539 U.S. at 42
    , 123 S. Ct. at 2053.
    6
    Corporation owned five different public utilities, which could use each other's
    excess capacity. The costs of keeping excess capacity available were shared among
    the utilities according to a provision in a system agreement, filed with FERC, that
    Entergy's operating committee administered. The provision at issue was an
    automatic adjustment clause, which under § 205(f) of the FPA allows for increases
    or decreases in a utility's paid costs without prior hearings.8 In determining costs,
    the operating committee designated certain generating units (called Extended
    Reserve Shutdown, or ERS, units) as "available" when those units were actually
    shut down, but could be activated in emergencies.9 This designation caused Entergy
    Louisiana, Inc., a utility with ERS units, to pay a higher percentage of costs. The
    Louisiana Public Service Commission found that although it was preempted from
    determining whether the system agreement was violated, it could determine that
    Entergy’s expenditures were imprudent because Entergy paid more for possessing
    ERS units.10 Thus, the Louisiana Commission did not allow Entergy to increase
    8
    
    Id. at 42–43,
    123 S. Ct. at 2053–54.
    9
    
    Id. at 43,
    123 S. Ct. at 2054.
    10
    The Louisiana Public Service Commission looked only at the time period after August
    5, 1997, as FERC had already found that categorizing the ERS units as "available" was reasonable
    prior to August 5, 1997. 
    Id. at 44,
    123 S. Ct. at 2054.
    7
    retail rates to cover those costs.11
    The Supreme Court reversed, holding that the Commission’s prudence inquiry
    was preempted even though the proper classification of ERS units was not pursuant
    to a specific mandate from FERC, but instead was within the discretion of the
    operating committee.12 The Court found that the Commission’s order impermissibly
    “trapped costs” by failing to allow Entergy to recoup the costs of paying for the
    ERS units.13
    B.
    Here, we also consider a tariff which designates an agent to perform an
    allocation (although Entergy involved an allocation of costs, rather than revenues).
    Appellants argue that the instant case can be distinguished from Entergy because in
    this case, AEPSC’s interpretation of the formula violated the language of the filed
    tariff, an issue which was not before the Court in Entergy.14 They contend that the
    Commissioners’ order correctly interpreted the tariff, and therefore fulfilled the
    11
    
    Id. at 45,
    123 S. Ct. at 2055.
    12
    
    Id. at 49–50,
    123 S. Ct. at 2057 (“We see no reason to create an exception to the filed
    rate doctrine for tariffs of this type that would substantially limit FERC’s flexibility in approving
    cost allocation arrangements.”).
    13
    
    Entergy, 539 U.S. at 49
    , 123 S. Ct. at 2056.
    14
    
    Id. at 50–51,
    123 S. Ct. at 2058.
    8
    state’s obligation to implement the filed rate.
    Although Appellants argue the Commissioners’ order implemented the filed
    rate, the entire SIA, not simply the formula in question, is filed with FERC. “[T]he
    filed rate doctrine is not limited to ‘rates’ per se.”15 The states are bound to
    implement a FERC-approved agreement, and the agreement authorizes only AEPSC
    to implement the formula.16
    Furthermore, FERC, not the state, is the appropriate arbiter of any disputes
    involving a tariff’s interpretation.17 Congress has given FERC exclusive jurisdiction
    to determine whether wholesale rates are just and reasonable.18 Additionally, it is
    FERC’s duty under the FPA to make an assessment of the broad public interests
    15
    Nantahala Power & Light Co. v. Thornburg, 
    467 U.S. 953
    , 966, 
    106 S. Ct. 2349
    , 2357
    (1986). See also 
    Entergy, 539 U.S. at 50
    , 123 S. Ct. at 2056 (“It matters. . . only whether the
    FERC tariff dictates how and by whom [the] classification should be made.”).
    16
    See Mississippi Power & Light Co. v. Moore, 
    487 U.S. 354
    , 374, 
    108 S. Ct. 2428
    , 2440
    (1988) (“States may not regulate in areas where FERC has properly exercised its jurisdiction . . .
    to insure that agreements affecting wholesale rates are reasonable.”).
    17
    See 
    id. at 2442–43
    (1988) (Scalia, J., concurring) (“[W]hether one characterizes the
    questions as related to prudence, interpretation [of the basic system agreements], or cost
    allocation, they are clearly matters most appropriately resolved by the Commission as part of its
    overriding authority to evaluate and implement all applicable wholesale rate schedules.”) (quoting
    AEP Generating Co., 36 FERC ¶ 61, 226 (1986)).
    18
    16 U.S.C. §§ 824d, 824e. See also Mississippi 
    Power, 487 U.S. at 377
    , 108 S. Ct. at
    2442 (Scalia, J., concurring) (“It is common ground that if FERC has jurisdiction over a subject,
    the States cannot have jurisdiction over the same subject.”).
    9
    involved in determining interstate rates.19 If each state could enforce its own
    findings as to the meaning of a filed tariff, in opposition to the conclusions of a
    FERC-approved agent, the conflicting interpretations would undermine FERC’s
    ability to ensure that a filed rate is uniform across different states, and intrude upon
    its exclusive jurisdiction over interstate power transactions.20 Therefore, it is within
    FERC’s jurisdiction, not the states’, to make a final determination as to whether the
    tariff has been violated. If a state disputes a utility’s interpretation of a tariff, FERC
    is the proper forum for resolving the disagreement.21
    Finally, the FPA gives FERC exclusive jurisdiction to remedy tariff
    violations by providing refunds.22 If states could remedy perceived violations by
    setting retail rates based on their own calculations, states could potentially “trap”
    costs by prohibiting the utility from passing on the price of FERC-mandated rates to
    consumers.23 Thus, the filed rate doctrine requires that the states use AEPSC’s
    19
    See 16 U.S.C. § 824(a).
    20
    See Appalachian Power Co. v. Public Service Comm’n of West Virginia, 
    812 F.2d 898
    ,
    905 (4th Cir. 1987).
    21
    Cf. Mississippi 
    Power, 487 U.S. at 375
    , 108 S. Ct. at 2241 (finding that the “only
    appropriate forum” for determining the reasonableness of filed rates and agreements “is before the
    Commission or a court reviewing the Commission’s order.”).
    22
    See 16 U.S.C. § 824e.
    23
    See Mississippi 
    Power, 487 U.S. at 372
    , 108 S. Ct. at 2439. Appellants claim that in
    this case, no costs were “trapped” because the formula at issue involved the allocation of revenue,
    10
    calculations to set retail rates until FERC resolves any dispute over the tariff’s
    interpretation.
    III.
    We find that the Commission’s actions were preempted by the Supremacy
    Clause and the Federal Power Act.
    AFFIRMED.
    not costs. Nonetheless, the result was the same: the utility lost money.
    11