Louis Koerner, Jr. v. Vigilant Insurance Company , 910 F.3d 221 ( 2018 )


Menu:
  •      Case: 18-30019    Document: 00514751695     Page: 1   Date Filed: 12/07/2018
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT United States Court of Appeals
    Fifth Circuit
    FILED
    December 7, 2018
    No. 18-30019
    Lyle W. Cayce
    Clerk
    LOUIS R. KOERNER, JR., Individually and as Assignee of Jean McCurdy
    Meade,
    Plaintiff - Appellant
    v.
    CMR CONSTRUCTION & ROOFING, L.L.C.,
    Defendant - Appellee
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    Before JONES, CLEMENT, and SOUTHWICK, Circuit Judges.
    EDITH BROWN CLEMENT, Circuit Judge:
    This case is about a roof. A perpetually leaky roof that Louis Koerner
    could never seem to get CMR Construction & Roofing LLC to fix. Koerner
    challenges the district court’s decision setting aside CMR’s default, its grant of
    summary judgment in CMR’s favor, and its denial of his Rule 59(e) motions for
    reconsideration. These three challenges call upon this court to answer a myriad
    of sub-issues. But in the end, we find no error and affirm.
    I.
    In the aftermath of Hurricane Katrina, in late 2005 and early 2006, CMR
    sold a Slate 2.0 roof to Koerner and installed it. CMR periodically returned to
    Case: 18-30019     Document: 00514751695      Page: 2   Date Filed: 12/07/2018
    No. 18-30019
    perform warranty and repair work in 2006, 2007, 2011, and early 2012. And
    despite CMR’s contention that its workmanship was not to blame, it paid a
    contractor to conduct additional repairs in November 2012.
    In April 2016, Koerner sued his insurer, Vigilant Insurance Company, in
    state court alleging that his home required several repairs. The case was
    removed to federal court. Thereafter, Vigilant denied Koerner’s claim for roof
    repairs by citing the faulty-workmanship exclusion to his policy, which
    implicated CMR. Koerner moved to join CMR as a defendant, and the district
    court granted the motion.
    Koerner served CMR with a complaint and summons; however, the cover
    sheet misnamed CMR. When CMR failed to respond to the complaint, Koerner
    was granted an entry of default and a partial default judgment against CMR
    for nearly $500,000. Finally roused to action, CMR successfully moved to set
    aside the default, claiming that (1) it did not willfully ignore the complaint, (2)
    Koerner would suffer no harm or prejudice if the default were set aside, and
    (3) it had meritorious defenses. After several months of discovery, CMR filed a
    motion for summary judgment, which was granted. That same day, the district
    court entered final judgment dismissing all of Koerner’s claims.
    Koerner timely filed two motions under Rule 59(e), one to amend the
    district court’s interlocutory ruling setting aside the entry of default and
    partial default judgment, and another to amend the summary-judgment order.
    Koerner’s motions introduced new evidence to impeach CMR’s denial of
    willfully failing to respond to the initial complaint and to contest the summary-
    judgment order. On November 15, 2017, the district court summarily denied
    Koerner’s motion to amend the entry of default and partial default judgment.
    And on January 4, 2018, the court denied the motion to amend the summary-
    judgment order. This appeal followed.
    2
    Case: 18-30019      Document: 00514751695     Page: 3   Date Filed: 12/07/2018
    No. 18-30019
    II.
    Koerner first challenges the district court’s decision to set aside the entry
    of default and vacate the partial default judgment.
    Under Rule 55(c), a district court “may set aside an entry of default for
    good cause.” Fed. R. Civ. Pro. 55(c). To decide if good cause exists, courts
    consider three non-exclusive factors: “whether the default was willful, whether
    setting it aside would prejudice the adversary, and whether a meritorious
    defense is presented.” Lacy v. Sitel Corp., 
    227 F.3d 290
    , 292 (5th Cir. 2000)
    (internal quotation mark omitted). “A finding of willful default ends the
    inquiry, for ‘when the court finds an intentional failure of responsive pleadings
    there need be no other finding.’” 
    Id.
     (quoting In re Dierschke, 
    975 F.2d. 181
    ,
    184 (5th Cir. 1992)).
    Defaults are “generally disfavored.” Mason & Hanger-Silas Mason Co. v.
    Metal Trades Council of Amarillo, Tex. & Vicinity, AFL-CIO, 
    726 F.2d 166
    , 168
    (5th Cir. 1984). “Unless it appears that no injustice results from the default,
    relief should be granted.” In re OCA, Inc., 
    551 F.3d 359
    , 370–71 (5th Cir. 2008).
    We review a district court’s decision to set aside an entry of default or a default
    judgment for an abuse of discretion. Lacy, 
    227 F.3d at
    291–92. Determining
    whether a defendant willfully defaulted is a factual finding that we review for
    clear error. Wooten v. McDonald Transit Associates, Inc., 
    788 F.3d 490
    , 495
    (5th Cir. 2015).
    The district court dutifully applied these good-cause factors. Koerner
    challenges only the analysis of the willfulness factor, so we too will evaluate
    only that factor.
    The district court held that “CMR was not intentionally failing to
    respond to litigation or trying to be uncooperative or obstructionist.” The court
    based this holding on an affidavit from CMR’s President, Steven Soulé.
    According to Soulé, he believed that it was too late for Koerner to sue CMR
    3
    Case: 18-30019     Document: 00514751695     Page: 4   Date Filed: 12/07/2018
    No. 18-30019
    because the allegations dated from 2005 and 2006. He also believed that CMR
    was not actually involved in the lawsuit because the only defendant named in
    the caption was Vigilant and because the cover sheet sent to CMR by its
    registered agent was incorrectly addressed to “CMR Construction & Roofing of
    Texas, LLC” instead of “CMR Construction & Roofing, LLC.” Upon confirming
    that the cover sheet misnamed CMR, the district court held, “[a]lthough Soul[é]
    certainly acted unwisely in failing to contact an attorney upon receiving the
    summons for this litigation, under the circumstances Soul[é]’s negligence is
    insufficient to warrant a finding of willfulness.”
    Koerner objects to the characterization of CMR’s conduct as negligent.
    Specifically, Koerner argues that Soulé was dishonest in his affidavit and that
    CMR had sufficient notice of the lawsuit to infer that its failure to respond was
    intentional, notwithstanding the cover sheet. Koerner grounds this claim in a
    series of communications between himself and Soulé in February 2016. These
    consisted primarily of one-way demands by Koerner via email, phone, and text
    in which Koerner told Soulé there was a lawsuit pending against CMR and
    that CMR would be in default if it failed to respond. Given these repeated
    contacts, he insists that CMR’s “supposedly good faith error” does not justify
    setting aside the entry of default and partial default judgment.
    While we agree that Koerner’s proffered evidence could support a
    willfulness inference, Soulé’s affidavit, if believed, supports the contrary
    inference. Given the record as a whole, we cannot say the district court clearly
    erred when it chose to credit Soulé’s affidavit over Koerner’s evidence.
    Consequently, the district court did not abuse its discretion in setting aside the
    entry of default and partial default judgment.
    III.
    Koerner next challenges the district court’s summary denial of his Rule
    59(e) motion to reconsider the order setting aside the entry of default and
    4
    Case: 18-30019     Document: 00514751695     Page: 5   Date Filed: 12/07/2018
    No. 18-30019
    partial default judgment. That motion contained additional evidence
    impeaching Soulé’s affidavit—the only evidence supporting the non-willfulness
    finding.
    “Reconsideration of a judgment after its entry is an extraordinary
    remedy that should be used sparingly.” Templet v. HydroChem Inc., 
    367 F.3d 473
    , 479 (5th Cir. 2004). “There is no requirement that reasons be stated for
    the denial of a motion for reconsideration under Rule 59(e),” especially if
    “valid—indeed compelling—reasons for denying the motion are obvious and
    apparent on the face of the record.” Briddle v. Scott, 
    63 F.3d 364
    , 381 (5th Cir.
    1995).
    Koerner was not entitled to this extraordinary relief, and there is an
    obvious reason on the face of the record why this is so. To be granted, a Rule
    59(e) motion ‘“must clearly establish either a manifest error of law or fact or
    must present newly discovered evidence’ that was not available before the
    judgment issued.” Molina v. Equistar Chemicals LP, 261 F. App’x 729, 733 (5th
    Cir. 2008) (quoting Schiller v. Physicians Res. Grp. Inc., 
    342 F.3d 563
    , 567 (5th
    Cir. 2003)). The district court set aside the default in May 2017. The evidence
    that Koerner attached to his Rule 59(e) motion came to light after Soulé’s
    deposition on August 25, 2017. The court entered final judgment on October
    18, 2017. Thus, because the evidence came to light before final judgment was
    entered, relief under Rule 59(e) was improper.
    Koerner should have instead filed a Rule 54(b) motion while the case was
    still open. Under that rule, district courts can amend interlocutory orders for
    any reason they deem sufficient before final judgment is entered. Austin v.
    Kroger Tex., L.P., 
    864 F.3d 326
    , 336–337 (5th Cir. 2017) (describing the
    differences between Rule 59(e) and Rule 54(b)). But in the interest of finality,
    Rule 59(e) sets a much higher threshold for relief once judgment is entered. 
    Id.
    5
    Case: 18-30019        Document: 00514751695           Page: 6     Date Filed: 12/07/2018
    No. 18-30019
    Koerner actually admits that he could have filed a Rule 54(b) motion, but
    he says that he did not do so because they are disfavored for having the
    potential to interfere with the underlying case’s progress. He cites no cases for
    this perplexing proposition. We fail to see how sitting on potentially dispositive
    evidence until the district court completes more work and enters final
    judgment on a summary-judgment motion is preferable to correcting error as
    soon as possible.
    Koerner made a poor tactical decision by waiting until after final
    judgment to bring the new evidence forward. But the fact remains: the
    evidence was available before final judgment was entered, so he is not entitled
    to the extraordinary relief that Rule 59(e) provides.
    IV.
    Finally, Koerner argues that the district court erred in granting
    summary judgment on (1) the fraud claim stemming from the 2006 purchase
    of his roof, (2) the claims related to the 2011 repairs, and (3) the negligence,
    fraud, and detrimental-reliance claims surrounding the 2012 repairs. After
    reviewing the district court’s grants of summary judgment de novo, we find no
    error in any of the district court’s conclusions. 1
    The question at summary judgment is whether “the record, taken as a
    whole, could . . . lead a rational trier-of-fact to find for the non-moving party.”
    Kariuki v. Tarango, 
    709 F.3d 495
    , 501 (5th Cir. 2013) (defining a genuine
    dispute of material fact). “Credibility determinations have no place in
    1     Koerner also faults the district court for failing to give him adequate notice of the
    grounds upon which it granted summary judgment. We need not address this argument
    because after reviewing all the evidence submitted on appeal, we do not believe that there is
    any dispute of material fact on any of Koerner’s claims. See Ross v. Univ. of Tex. at San
    Antonio, 
    139 F.3d 521
    , 527 (5th Cir. 1998) (“[F]ailure to provide notice may be harmless error
    . . . . if all of the nonmovant’s additional evidence is reviewed by the appellate court and none
    of the evidence presents a genuine issue of material fact.” (internal citation and quotation
    mark omitted)).
    6
    Case: 18-30019     Document: 00514751695     Page: 7   Date Filed: 12/07/2018
    No. 18-30019
    summary judgment proceedings” because “non-movants’ summary judgment
    evidence must be taken as true.” Richardson v. Oldham, 
    12 F.3d 1373
    , 1379
    (5th Cir. 1994). All facts and inferences must be viewed in the light most
    favorable to the non-movant. Love v. Nat’l Med. Enters., 
    230 F.3d 765
    , 770 (5th
    Cir. 2000). However, “[s]elf-serving allegations are not the type of significant
    probative evidence required to defeat summary judgment,” and “a vague or
    conclusory affidavit [without more] is insufficient to create a genuine issue of
    material fact in the face of conflicting probative evidence.” Kariuki, 709 F.3d
    at 505 (internal quotation marks omitted). Therefore, “[w]hen opposing parties
    tell two different stories, one of which is blatantly contradicted by the record,
    so that no reasonable jury could believe it, a court should not adopt that version
    of the facts for purposes of . . . summary judgment.” Scott v. Harris,
    
    550 U.S. 372
    , 380 (2007). With this familiar standard in mind, we turn to
    Koerner’s claims.
    A.
    Koerner maintains that in 2006 CMR fraudulently induced him to
    purchase a roof made of Slate 2.0. His only evidence: his two declarations made
    under penalty of perjury. In those declarations, he states that Eric Hunter, a
    CMR representative, told him that Slate 2.0 had all the same attributes as
    traditional slate but was better in every meaningful way. This representation,
    Koerner claims, was false. Slate 2.0 actually differs from traditional slate in
    that it consists of decorative slate facade over a synthetic membrane. Had he
    known that it was the membrane—not the slate itself, as in traditional slate—
    that provides most of the protection against the elements, Koerner claims that
    he would not have purchased the roof from CMR.
    To establish fraud involving a contract under Louisiana law, a plaintiff
    must prove three elements: “(1) a misrepresentation, suppression, or omission
    of true information; (2) the intent to obtain an unjust advantage or to cause
    7
    Case: 18-30019     Document: 00514751695      Page: 8    Date Filed: 12/07/2018
    No. 18-30019
    damage or inconvenience to another; and (3) the error induced by a fraudulent
    act must relate to a circumstance substantially influencing the victim’s consent
    to (a cause of) the contract.” Shelton v. Standard/700 Associates, 
    798 So. 2d 60
    , 64 (La. 2001). Additionally, a contractual fraud claim will not lie if “the
    party against whom the fraud was directed could have ascertained the truth
    without difficulty, inconvenience, or special skill.” La. Civ. Code Ann. art. 1954;
    see also Cashman Equip. v. Acadian Shipyard, Inc., 66 F. App’x 524 (5th Cir.
    2003) (per curiam).
    Koerner’s claim does not survive summary judgment for two reasons.
    First, Koerner puts forth no competent evidence of fraudulent intent. He
    simply asserts in his declaration that Hunter “knew,” but concealed, the
    differences between Slate 2.0 and traditional slate. But this is a topic about
    which Koerner could have no possible personal knowledge. His speculative
    opinion as to what Hunter knew and did not know cannot defeat a summary-
    judgment motion. And without any other evidence that Hunter intentionally
    misled Koerner, he cannot prove his fraud claim.
    Second and more importantly, Koerner could have easily ascertained the
    truth about Slate 2.0’s qualities. Slate 2.0 differs from traditional slate in two
    ways. First, the Slate 2.0 tiles sit flush against each other—as opposed to being
    partially overlaid as in traditional slate. And second, because of this, Slate 2.0
    relies more on the synthetic membrane to keep out the elements—whereas
    traditional slate uses felt and relies primarily on the actual slate for protection.
    Koerner was aware of both differences. He admitted in his declaration that he
    knew CMR was going to use a synthetic membrane. He also knew, based on
    his own research, that Slate 2.0 is designed so that the individual tiles do not
    overlay on each other. Koerner could have easily put these facts together to
    figure out that what he was purchasing was different than a traditional slate
    8
    Case: 18-30019         Document: 00514751695   Page: 9   Date Filed: 12/07/2018
    No. 18-30019
    roof and that the Slate 2.0 tiles do less work in keeping out the elements than
    traditional slate tiles.
    Summary judgment was proper on this claim.
    B.
    Turning to the 2011 repairs, Koerner argues that the district court erred
    in dismissing Koerner’s claims as perempted. We disagree.
    The district court held that under Louisiana Revised Statute § 9.2772(A),
    any claims arising from repairs done to Koerner’s roof are subject to a five-year
    peremptive period. Since Koerner first asserted claims against CMR on
    November 14, 2016, the district court held that “any claims arising from
    ‘improvement[s]’ that Koerner ‘occupied’” prior to November 14, 2011, would
    fall outside the required five-year window and be perempted. Koerner does not
    challenge these premises; he argues only that the 2011 repairs should not have
    fallen within this five-year period because the 2011 and 2012 repairs were part
    of the same project. There is no dispute that if the 2011 and 2012 repairs are
    considered one project, then the 2011 repairs should not have been perempted.
    But the only evidence in support of this proposition is one conclusory
    assertion in Koerner’s declaration that “based on [his] understanding,” the
    2011 repairs were part of a larger remedial project that was not completed
    until November 2012. But this subjective belief is belied by other more concrete
    evidence in the record. For example, CMR’s job report documented the 2011
    job as closed on November 10, 2011. It then separately agreed to do work three
    months later, in February 2012. After reviewing the record as a whole, we
    agree with the district court that the 2011 claims are perempted.
    C.
    As to the 2012 repairs, Koerner alleges three claims: negligence, fraud,
    and detrimental reliance. Summary judgment was appropriate on all of them.
    9
    Case: 18-30019    Document: 00514751695        Page: 10   Date Filed: 12/07/2018
    No. 18-30019
    i.
    Koerner asserts a negligence claim against CMR for the repairs done in
    November 2012. There is only one problem—CMR did not perform the repairs;
    a different roofer named Brian Velasquez did. As in the district court, Koerner
    argues that CMR can be held liable for Velasquez’s work because he was CMR’s
    independent contractor. But under Louisiana law, Koerner must point to a
    valid contract between Velasquez and CMR before he can successfully argue
    that they had a principal/independent-contractor relationship. See Bourquard
    v. L.O. Ausauma Enter., Inc., 
    52 So. 3d 248
    , 253 (La. Ct. App. 2010). This, he
    cannot do.
    The summary-judgment evidence shows that Koerner entered into a
    contract with Velasquez—not CMR—to repair his roof in November 2012. It is
    true that CMR was involved with the repairs in many ways: it agreed to
    reimburse Koerner for Velasquez’s work, set the scope of the work it would
    reimburse, had some supervisory power over Velasquez, and later assured
    Koerner that Velasquez’s work was complete and done well. None of this,
    however, is evidence of a contract between CMR and Velasquez. At best, it is
    evidence of an independent agreement between Koerner and CMR to pay for,
    supervise, and inspect Velasquez’s work. But the transitive property does not
    apply in contract law. The fact that Koerner had a contract with Velasquez and
    a contract with CMR does not mean that Velasquez and CMR had a contract
    with each other. And without a contractual relationship, CMR cannot be held
    responsible for Velasquez’s alleged negligence.
    ii.
    Koerner claims that CMR fraudulently represented to him that the work
    scope it was proposing for the November 2012 repairs would fix all of his roof’s
    problems, when it knew the work would not. In support, Koerner relies on an
    email from Gary Klocke, a CMR superintendent, to his colleagues after
    10
    Case: 18-30019      Document: 00514751695      Page: 11      Date Filed: 12/07/2018
    No. 18-30019
    inspecting Koerner’s roof saying, “I did not disclose or offer any info on my
    findings [to Koerner] and simply left [Koerner] assured we are working on
    correcting his leak issue, after all he is a lawyer and I know they are sneaky
    :).”
    To prove fraud, Koerner must prove that “(1) a misrepresentation of
    material fact, (2) made with the intent to deceive, (3) caus[ed] justifiable
    reliance with resultant injury.” Becnel v. Grodner, 
    982 So. 2d 891
    , 894 (La. Ct.
    App. 2008). Fraud can be predicated on a promise made with no intention of
    performing, but a “failure to perform as promised or nonperformance of an
    agreement to do something at a future time” does not evince fraud. Taylor v.
    Dowling Gosslee & Assocs., 
    22 So. 3d 246
    , 255 (La. Ct. App. 2009). Koerner
    argues that when all inferences are drawn in his favor, Klocke’s email shows
    an intention not to fix all the roof’s problems even though CMR told Koerner
    that it would.
    We think otherwise. The email states that Klocke did not want to tell
    Koerner about all of his particular findings; it does not say that Klocke did not
    intend to fix the other problems in addition to the leak. He just did not want to
    tell Koerner about them because he thought Koerner was a sneaky lawyer.
    Moreover, the entire email makes clear that the other problems Klocke found
    all relate to the mentioned leak. No reasonable jury could read Klocke’s email
    and infer an intent not to fix the identified problems. They could infer, at most,
    an intent not to tell Koerner about all of the leak’s nitty-gritty details. Without
    any other evidence of fraudulent intent, Koerner cannot prevail on this claim.
    iii.
    Koerner’s      detrimental-reliance      claim   centers    around     a   single
    representation: CMR assured him that the work done by Velasquez, a third-
    party contractor, was complete and would fix all of his roof’s problems. The key
    11
    Case: 18-30019     Document: 00514751695      Page: 12    Date Filed: 12/07/2018
    No. 18-30019
    question, then, is whether this type of representation can support Koerner’s
    claim.
    Detrimental-reliance claims are based on Louisiana Civil Code Article
    1967, which states that “[a] party may be obligated by a promise when he knew
    or should have known that the promise would induce the other party to rely on
    it to his detriment and the other party was reasonable in so relying.” (emphasis
    added).
    The statute’s focus is on one type of representation—a promise. Despite
    that focus, Koerner argues that the promise requirement is no longer on sure
    footing. He cites a single 2018 case for the proposition that a simple assertion
    can give rise to a detrimental-reliance claim. In Feingerts v. D’Anna, a lawyer
    told his client that he could sell his property without consent. A Louisiana
    appellate court held that this could support a detrimental-reliance claim,
    reasoning that “whether or not that assertion is labeled a promise or a legal
    opinion is inconsequential.” 
    237 So. 3d 21
    , 26 (La. Ct. App. 2018).
    Feingerts is not convincing. It is out of step with Article 1967’s plain text.
    When interpreting a Louisiana statute, “the words . . . must be given their
    generally prevailing meaning.” La. Civ. Code Ann. art. 11. And when “a law is
    clear and unambiguous . . . the law shall be applied as written and no further
    interpretation may be made in search of the intent of the legislature.” La. Civ.
    Code. Ann. art 9. The Feingerts court did not follow these principles. It did not
    even attempt to determine what Article 1967 meant by narrowing its reach to
    only “promises.”
    But in Wooley v. Lucksinger, another Louisiana court did just that—it
    attempted to determine the general prevailing meaning of a “promise” because
    that is the word the statute uses. 
    961 So. 2d 1228
    , 1238–39 (La. Ct. App. 2007).
    The court looked at Black’s Law Dictionary, Merriam–Webster’s Collegiate
    Dictionary, and Louisiana’s civil jury instructions. All of them were
    12
    Case: 18-30019       Document: 00514751695    Page: 13   Date Filed: 12/07/2018
    No. 18-30019
    substantially similar: a promise is a declaration that a person will or will not
    do something in the future. 
    Id. at 1239
    . Applying this definition, the court
    found that no promise had been made, so the plaintiff could not prove a
    detrimental-reliance claim. Id.; see also Saba v. Emerson, 
    2016 WL 6427697
    ,
    at *13 (La. Ct. App. 2016) (rejecting a detrimental-reliance claim by finding no
    promise in an inspector’s construction report that the plaintiffs relied upon to
    reduce their house’s value); Jones v. Herlin, 
    2013 WL 5270547
    , at *5 (W.D. La.
    Sept. 17, 2013) (relying on Wooley’s definition of promise).
    In an unpublished case, this court too has held that the first step in
    proving a Louisiana detrimental-reliance claim is showing that the defendant
    made a promise. In Roxco Ltd. v. Harris Specialty Chemical, Inc., we noted
    that we had sometimes, in the past, described the first element in a
    detrimental-reliance claim in terms of mere “representations.” 85 F. App’x 375,
    378 (5th Cir. 2004) (per curiam). But we decided that this description was too
    general and not consistent with the statute—which, “by its language, requires
    the representations to be promises.” 
    Id.
     We distinguished the old cases by
    holding that in those cases there was no question that the representation
    “related to promises or contracts.” 
    Id.
    Since Roxco, the Louisiana Supreme Court has been less than precise
    when listing out the detrimental-reliance elements. It has described the
    elements as “(1) a representation by conduct or word; (2) justifiable reliance;
    and (3) a change in position to one’s detriment because of the reliance.” Suire
    v. Lafayette City-Par. Consol. Gov’t, 
    907 So. 2d 37
    , 59 (La. 2005). But while
    using this broader language, the court used narrower promissory language
    later in the opinion:
    [T]he basis of detrimental reliance is the idea that a
    person should not harm another person by making
    promises that he will not keep. Thus, the focus of
    analysis of a detrimental reliance claim is not whether
    13
    Case: 18-30019    Document: 00514751695      Page: 14    Date Filed: 12/07/2018
    No. 18-30019
    the parties intended to perform, but, instead, whether
    a representation was made in such a manner that the
    promisor should have expected the promisee to rely
    upon it, and whether the promisee so relies to his
    detriment.
    
    Id.
     (emphasis added) (internal quotation marks omitted). Importantly, in Suire
    there was no dispute that the representation at issue was the city’s promise to
    pay for damages to a particular property. 
    Id.
    Post-Suire, this court has described the first element inconsistently. We
    have sometimes described the first element as a representation but described
    the remaining elements in terms of promises. See In re Ark-La-Tex Timber Co.,
    Inc., 
    482 F.3d 319
    , 334 (5th Cir. 2007) (listing the elements as “(1) a
    representation by conduct or word; (2) made in such a manner that the
    promisor should have expected the promisee to rely upon it; (3) justifiable
    reliance by the promisee; and (4) a change in position to the promisee’s
    detriment because of the reliance” (citing Suire, 
    907 So. 2d at 59
    )); see also
    Water Craft Mgmt., L.L.C. v. Mercury Marine, 426 F. App’x 232, 237 (5th Cir.
    2011) (per curiam). We have sometimes ignored altogether Suire’s formulation
    of the first element as a representation, relying instead directly on the statute’s
    promissory language. See Condrey v. SunTrust Bank of Ga., 
    429 F.3d 556
    , 565
    (5th Cir. 2005). And we have sometimes repeated verbatim all the elements as
    Suire listed them. See New Orleans City v. Ambac Assur. Corp., 
    815 F.3d 196
    ,
    203 (5th Cir. 2016); Audler v. CBC Innovis Inc., 
    519 F.3d 239
    , 254 (5th Cir.
    2008). But when doing so, we have continued to emphasize in other parts of
    the opinions that the representations are normally promises. See Ambac Assur.
    Corp., 815 F.3d at 203 (“Under Louisiana law, courts have found reliance on
    promises made outside of an unambiguous, fully-integrated agreement to be
    unreasonable as a matter of law.” (internal quotation marks omitted)); Audler,
    
    519 F.3d at 254
     (holding that “the focus of analysis of a detrimental reliance
    14
    Case: 18-30019    Document: 00514751695      Page: 15   Date Filed: 12/07/2018
    No. 18-30019
    claim is . . . whether a representation was made in such a manner that the
    promisor should have expected the promisee to rely upon it” (internal quotation
    mark omitted)).
    We now resolve any ambiguity in our prior cases and make the following
    Erie guess. See Howe ex rel. Howe v. Scottsdale Ins. Co., 
    204 F.3d 624
    ,628 (5th
    Cir. 2000) (“The role of this court is not to create or modify state law, rather
    only predict it.” (internal quotation marks omitted)). We hold that under
    Article 1967 the existence of a promise is a necessary element of a detrimental-
    reliance claim. We also adopt Wooley’s definition of promise—an assurance to
    do or not do something in the future. This result is faithful to the clear
    statutory text and the fact that Louisiana does not favor recovery under a
    detrimental-reliance theory. See Allbritton v. Lincoln Health Sys., Inc., 
    51 So. 3d 91
    , 95 (La. Ct. App. 2010). Under this construction, Koerner’s claim fails.
    CMR did not promise to do or not do anything; it simply assured Koerner that
    the roof work was done well.
    V.
    For the foregoing reasons, We AFFIRM the district court on all grounds.
    15
    

Document Info

Docket Number: 18-30019

Citation Numbers: 910 F.3d 221

Judges: Jones, Clement, Southwick

Filed Date: 12/7/2018

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (20)

Bourquard v. L.O. Ausauma Enterprises, Inc. , 2010 La.App. 4 Cir. 0323 ( 2010 )

Taylor v. Dowling Gosslee & Associates, Inc. , 2009 La. App. LEXIS 1728 ( 2009 )

Templet v. Hydrochem Inc. , 367 F.3d 473 ( 2004 )

Mason & Hanger--Silas Mason Company, Inc. v. Metal Trades ... , 726 F.2d 166 ( 1984 )

Bobby D. Lacy v. Sitel Corporation , 227 F.3d 290 ( 2000 )

Scott v. Harris , 127 S. Ct. 1769 ( 2007 )

Condrey v. Suntrust Bank of GA , 429 F.3d 556 ( 2005 )

Richardson v. Oldham , 12 F.3d 1373 ( 1994 )

in-the-matter-of-marvin-a-dierschke-dba-marvin-dierschke-farms-and , 975 F.2d 181 ( 1992 )

Love v. National Medical Enterprises , 230 F.3d 765 ( 2000 )

Becnel v. Grodner , 982 So. 2d 891 ( 2008 )

Shelton v. Standard/700 Associates , 798 So. 2d 60 ( 2001 )

Suire v. Lafayette City-Parish Government , 907 So. 2d 37 ( 2005 )

Wooley v. Lucksinger , 961 So. 2d 1228 ( 2007 )

Howe v. Scottsdale Insurance Co. , 204 F.3d 624 ( 2000 )

Audler v. CBC Innovis Inc. , 519 F.3d 239 ( 2008 )

Beitel v. OCA, Inc. , 551 F.3d 359 ( 2008 )

Briddle v. Scott , 63 F.3d 364 ( 1995 )

James A. Ross v. University of Texas at San Antonio Board ... , 139 F.3d 521 ( 1998 )

Allbritton v. Lincoln Health System, Inc. , 2010 La. App. LEXIS 1390 ( 2010 )

View All Authorities »