Apache Corporation v. W & T Offshore, Incorporated , 930 F.3d 647 ( 2019 )


Menu:
  •      Case: 17-20599   Document: 00515035583        Page: 1   Date Filed: 07/16/2019
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    No. 17-20599                        Fifth Circuit
    FILED
    July 16, 2019
    APACHE DEEPWATER, L.L.C.,                                        Lyle W. Cayce
    Clerk
    Plaintiff - Appellee
    v.
    W&T OFFSHORE, INCORPORATED,
    Defendant - Appellant
    Appeal from the United States District Court
    for the Southern District of Texas
    Before HIGGINBOTHAM, GRAVES, and WILLETT, Circuit Judges.
    PATRICK E. HIGGINBOTHAM, Circuit Judge:
    This dispute arises from a successful plugging and abandonment
    operation of three offshore oil and gas wells in the Mississippi Canyon area of
    the Gulf of Mexico. Apache Deepwater, LLC performed the operation and seeks
    payment from its non-operator partner, W&T Offshore, Inc. A jury awarded
    $43.2 million to Apache for W&T’s breach of the Joint Operating Agreement.
    W&T challenges the district court’s application of the Louisiana Civil Code and
    interpretation of the contract. Alternatively, W&T contends that it is entitled
    to an offset in damages because of Apache’s bad faith. Finding no error, we
    affirm.
    Case: 17-20599     Document: 00515035583     Page: 2   Date Filed: 07/16/2019
    No. 17-20599
    I.
    In May 1999, Apache and W&T’s predecessors entered into a Joint
    Operating Agreement (“JOA”) that governed the operation of three offshore
    deepwater oil and gas wells (the “Wells”) in the Mississippi Canyon area of the
    Gulf of Mexico. This dispute arises from operator Apache’s plugging and
    abandonment (“P&A”) of the Wells.
    In 2012, Apache attempted to P&A the Wells with an intervention vessel
    called Uncle John with the consent of W&T, but that operation was
    unsuccessful. Following that failure, Apache contracted to use a different
    intervention vessel, the Helix-534 (“Helix”). An internal figure by Apache
    estimated that the cost to P&A the Wells with the Helix was approximately
    $56,350,000. In June 2014, W&T contacted Apache to set up a status
    conference in July discussing the P&A operation, confirming that W&T knew
    “that the Helix 534 is contracted for the project.” At that meeting, W&T learned
    that Apache proposed using two drilling rigs for the project instead of the Helix,
    the Ocean Onyx (“Onyx”) and Ensco-8505 (“Ensco”).
    W&T and Apache offered to the jury competing explanations for the
    switch from the Helix to the Onyx and Ensco drilling rigs. By W&T’s telling,
    Apache’s decision to use the Onyx and Ensco was a simple matter of cost: W&T
    contends that Apache entered into a contract for the two drilling rigs for the
    purpose of drilling new deepwater wells, but abandoned that project in 2014
    and was left with exorbitant stacking costs for the idle rigs (approximately
    $1,000,000 per day). W&T asserts that Apache’s decision to use the rigs instead
    of the Helix was an attempt to recoup on the costs of contracting for the unused
    rigs because Apache had been unsuccessful in unloading the rigs onto another
    operator. Prior to the July meeting, Apache prepared estimates for the use of
    the rigs which totaled between $81 and $104 million. W&T points to an
    internal presentation in which Apache was weighing the costs of using the
    2
    Case: 17-20599      Document: 00515035583        Page: 3    Date Filed: 07/16/2019
    No. 17-20599
    Helix against the rigs and determining that with the stacking costs Apache
    was paying for the idle rigs, the use of the rigs would be cheaper because the
    cost would be split with W&T. Apache cancelled the Helix contract. W&T
    claims that although Apache purported to rely on written evaluations
    explaining the technical reasons the rigs were necessary (including that the
    Helix no longer complied with government regulations), Apache refused to
    provide those analyses to W&T.
    Apache rejects W&T’s economic explanation and argues that the Helix
    was not a safe option after the Deepwater Horizon spill and the government
    regulators would not have approved the Helix for the P&A operations. Apache
    put on evidence that it had discussed the risks of using the Helix with W&T,
    and demonstrated that technical difficulties posed by the Wells would make
    the “open water” operations of the Helix environmentally risky, that the Wells
    were “high risk,” and that the drilling rigs were able to conduct the P&A
    operations with safeguards mitigating the risk of oil spills. Apache also claimed
    that the federal Bureau of Safety and Environmental Enforcement (“BSEE”)
    advised Apache that it was no longer approving the type of open-water
    operations that Helix would need to perform to complete the P&A task. In
    Apache’s version, W&T began “actively resisting” the P&A plan using the rigs
    because the Helix operation would be far cheaper for W&T and W&T was
    disregarding the environmental risk. 1 Apache argued to the jury that W&T
    ignored the fact that Helix would have had operational issues that would have
    1 Apache points to an internal e-mail from W&T’s vice president Cliff Williams in
    which he wrote: “I’d like to determine options should we not agree with operators plan and
    believe we can perform well abandonments cheaper. Can we non-consent and take over
    abandonment operations with Apache obligated to pay their share of estimated abandonment
    costs?”
    3
    Case: 17-20599       Document: 00515035583         Page: 4     Date Filed: 07/16/2019
    No. 17-20599
    increased the costs of the operation past the initial estimates and that the use
    of the rigs was “reasonably necessary.”
    Amid their dispute over the appropriate intervention vessel, Apache
    sought W&T’s approval for use of the rigs through an Authorizations for
    Expenditure (“AFE”), but W&T decided not to approve the use of the rigs, 2 and
    rejected two other requests for AFEs. Apache decided to use the rigs for the
    P&A and the work was successfully completed in February 2015 for a total cost
    of $139,900,000. Apache billed W&T for its contractual 49% share, or
    $68,570,000. W&T decided to pay $24,860,640, which represented 49% of the
    estimate for use of the Helix, contending that “Apache’s insistence on using a
    drilling rig unnecessarily and unreasonably increased the costs of this work,”
    and determining that it was not obligated to pay the full billed amount because
    it had not approved the AFEs.
    Apache sued for breach of contract in Texas state court in December 2014
    and the case was removed by W&T in January 2015. Prior to trial, W&T moved
    for summary judgment on Apache’s breach of contract claim, arguing that the
    JOA was unambiguous in requiring the operator (Apache) to obtain an
    approved AFE before expending over $200,000. The parties’ argument turned
    on the reading of two provisions in the JOA: § 6.2 governing authorizations for
    expenditures and § 18.4 governing abandonment operations required by the
    government:
    6.2. Authorization for Expenditure: The Operator shall not
    make any single expenditure or undertake any activity or
    2 In its response, W&T stated: “We believe Apache, as a prudent operator, has an
    obligation to conduct the operation in a cost effective and safe manner in compliance with all
    governmental regulations. We do not understand why Apache continues to advocate the use
    of the Ensco 8505 rig when it is clear that an intervention vessel could safely perform the
    abandonment work at a much lower cost. . . . We do not believe W&T should be obligated to
    pay the additional charges arising from the use of the Ensco rig when other less expensive
    options are available.”
    4
    Case: 17-20599     Document: 00515035583       Page: 5      Date Filed: 07/16/2019
    No. 17-20599
    operation costing Two Hundred Thousand Dollars ($200,000) or
    more, unless an AFE has either (1) been included in a proposal for
    an activity or operation and is approved by the Participating
    Parties through their Election to participate in the activity or
    operation, or (2) received the approval of the Parties as a General
    Matter. When executed by a party, an AFE grants the Operator
    the authority to commit or expend funds on the activity or
    operation in accordance with this Agreement for the account of the
    Participating Parties. . . .
    18.4.    Abandonment         Operations      Requirement       by
    Governmental Authority: The Operator shall conduct the
    abandonment and removal of any well, Production System or
    Facilities required by a governmental authority, and the Costs,
    risks and net proceeds will be shared by the Participating Parties
    in such well, Production System or Facilities according to their
    Participating Interest Share.
    The district court denied W&T’s motion for summary judgment and
    determined that the interaction of the provisions in the JOA was ambiguous,
    creating an issue of fact as to the “parties’ intent on the applicability of § 6.2 to
    a government-mandated plugging and abandonment operation governed by
    § 18.4.” The case proceeded to trial and the jury made five findings:
    (1) Did W&T fail to comply with the Contract by failing to pay its
    proportionate share of the costs to plug and abandon the MC 674 wells?
    Yes.
    (2) What sum of money, if any, would compensate Apache for W&T’s
    failure to pay its proportionate share of costs to plug and abandon the
    MC 674 wells? $43,214,515.83.
    (3) Was Apache required to obtain W&T’s approval under Section 6.2 of
    the Contract before Apache plugged and abandoned the MC 674 wells as
    required      under     Section      18.4     of    the       Contract?      No.
    5
    Case: 17-20599      Document: 00515035583        Page: 6    Date Filed: 07/16/2019
    No. 17-20599
    (4) Did Apache act in bad faith, thereby causing W&T to not comply with
    the contract? Yes.
    (5) By what amount, if any, should the amount you found in response to
    Jury Question No. 2 be offset? $17,000,000.
    Following trial, the court entered its order and final judgment, determining
    that the jury’s “bad faith” finding in Question 4 did not preclude Apache’s
    recovery for breach of contract under Louisiana law and holding that W&T was
    not entitled to an offset under Louisiana law. The district court also denied
    W&T’s motion for a new trial or remittitur and renewed motion for judgment
    as a matter of law. This appeal followed.
    II.
    This court reviews the denial of a Rule 50(b) renewed motion for
    judgment as a matter of law de novo, “but our standard of review with respect
    to a jury verdict is especially deferential.” 3 A party is only entitled to judgment
    as a matter of law on an issue where no reasonable jury would have had a
    legally sufficient evidentiary basis to find otherwise. 4 In evaluating the
    evidence, this court “credit[s] the non-moving party’s evidence and disregard[s]
    all evidence favorable to the moving party that the jury is not required to
    believe.” 5 This court also has jurisdiction “to hear an appeal of the district
    court’s legal conclusions in denying summary judgment, but only if it is
    sufficiently preserved in a Rule 50 motion.” 6
    “A district court’s resolution of a motion for new trial is reviewed for
    abuse of discretion, and ‘[t]he district court abuses its discretion by denying a
    3  Olibas v. Barclay, 
    838 F.3d 442
    , 448 (5th Cir. 2016) (quoting Evans v. Ford Motor
    Co., 
    484 F.3d 329
    , 334 (5th Cir. 2007)) (internal quotation marks omitted).
    4 FED. R. CIV. P. 50(a)(1).
    5 Janvey v. Romero, 
    817 F.3d 184
    , 187 (5th Cir. 2016) (quoting Abraham v. Alpha Chi
    Omega, 
    708 F.3d 614
    , 620 (5th Cir. 2013)) (internal quotation marks omitted).
    6 Feld Motor Sports, Inc. v. Traxxas, L.P., 
    861 F.3d 591
    , 596 (5th Cir. 2017).
    6
    Case: 17-20599        Document: 00515035583          Page: 7     Date Filed: 07/16/2019
    No. 17-20599
    new trial only when there is an “absolute absence of evidence to support the
    jury's verdict.”’” 7 “A motion for a new trial or to amend a judgment cannot be
    used to raise arguments which could, and should, have been made before the
    judgment issued.” 8 “To the extent that a Rule 59(e) ruling was a
    reconsideration of a question of law, . . . the standard of review is de novo.” 9
    III.
    W&T contends that the plain language of Louisiana Civil Code Article
    2003 dictates that the jury’s bad faith finding bars Apache’s recovery for breach
    of contract. Article 2003 states that
    An obligee may not recover damages when his own bad faith has
    caused the obligor’s failure to perform or when, at the time of the
    contract, he has concealed from the obligor facts that he knew or
    should have known would cause a failure.
    If the obligee’s negligence contributes to the obligor’s failure to
    perform, the damages are reduced in proportion to that
    negligence. 10
    In answering the fourth question on the verdict form, the jury found that
    “Apache act[ed] in bad faith thereby causing W&T to not comply with the
    contract.”
    The district court denied W&T’s motion for judgment as a matter of law,
    concluding that it was bound by the Louisiana Supreme Court’s decision in
    7  McCaig v. Wells Fargo Bank (Tex.), N.A., 
    788 F.3d 463
    , 472 (5th Cir. 2015) (quoting
    Wellogix, Inc. v. Accenture, L.L.P., 
    716 F.3d 867
    , 881 (5th Cir. 2013)).
    8 Garriot v. NCsoft Corp., 
    661 F.3d 243
    , 248 (5th Cir. 2011) (citation omitted) (internal
    quotation marks omitted).
    9 Hoffman v. L&M Arts, 
    838 F.3d 568
    , 581 (5th Cir. 2016) (internal quotation marks,
    citations, and alterations omitted). The parties dispute whether the district court’s denial of
    W&T’s Rule 59 motion involved a pure question of law, with W&T arguing that it did and
    Apache suggesting that W&T’s motion merely criticized the evidence presented at trial. The
    Rule 59 motion and district court’s ruling is discussed below in Section III.
    
    10 La. Civ
    . Code art. 2003.
    7
    Case: 17-20599      Document: 00515035583        Page: 8     Date Filed: 07/16/2019
    No. 17-20599
    Lamar Contractors, Inc. v. Kacco, Inc. 11 The district court determined that,
    under Lamar, Article 2003’s bad faith damages bar is only implicated where
    the obligor has established that the obligee failed to perform a contractual
    obligation that caused the obligor’s failure to perform. In other words, to avoid
    liability pursuant to Article 2003’s bad faith bar, W&T would have to show that
    Apache failed in its performance of the contract and that failure caused W&T’s
    breach. Because the jury did not find that Apache had breached any obligation
    under the contract, 12 the district court reasoned that it was required to set
    aside the jury’s finding on Question 4—that Apache’s bad faith caused W&T’s
    failure to perform—meaning Apache was not barred from recovery under
    Article 2003.
    W&T disputes the district court’s reading of and reliance on Lamar,
    arguing that (1) Lamar is not binding on this court because it is not
    jurisprudence constante and this court must instead follow the plain language
    of Article 2003, which contains no language limiting Article 2003’s application
    to situations where the obligee has breached; (2) Lamar’s holding is limited to
    Article 2003’s negligence clause; and (3) application of Lamar is contrary to
    public policy.
    In diversity cases where this court must apply Louisiana substantive
    law, 13 “we look to the final decisions of the Louisiana Supreme Court.” 14 In the
    absence of a final decision by the state’s supreme court, we make an Erie guess,
    which requires us to “employ Louisiana’s civilian methodology, whereby we
    11 
    189 So. 3d 394
     (La. 2016).
    12 The district court noted that the jury considered and rejected that Apache had
    breached. For example, had the jury answered Question 3 in the affirmative, that would have
    amounted to a finding that Apache had breached an obligation under the contract. Question
    3 asked whether Apache was required to obtain W&T’s approval under § 6.2 before
    completing the P&A as required by § 18.4, which the jury answered in the negative.
    13 Erie R.R. Co. v. Tompkins, 
    304 U.S. 64
    , 78 (1938).
    14 In re Katrina Canal Breaches Litig., 
    495 F.3d 191
    , 206 (5th Cir. 2007).
    8
    Case: 17-20599       Document: 00515035583          Page: 9     Date Filed: 07/16/2019
    No. 17-20599
    first examine primary sources of law: the constitution, codes, and statutes.” 15
    Even caselaw rising to the level of jurisprudence constante is “secondary law in
    Louisiana” 16 and, accordingly, we are not strictly bound by the decisions of
    Louisiana’s intermediate appellate courts. 17 So, it is only when the Louisiana
    Supreme Court has not made a determinative decision that this court must
    make an Erie guess, employing Louisiana’s civilian methodology. 18
    The parties dispute whether Lamar speaks definitively on the issue of
    whether Article 2003 bars recovery of damages only when the obligee has been
    found in breach. In Lamar, the Louisiana Supreme Court considered a trial
    court’s decision to reduce breach of contract damages awarded to a general
    contractor, Lamar, after finding that Lamar had contributed to the
    subcontractor’s failure to perform. 19 The obligation imposed by Article 2003 is
    “correlative to the general duty imposed by [Article] 1983, which requires
    ‘contracts must be performed in good faith.’” 20 However, the court warned that
    the duty of good faith is not to be considered in isolation, and that it is
    circumscribed by the obligations imposed by the contract. 21 The court noted
    that “[a]lthough we have not had occasion to consider [Article] 2003 since its
    15 Id. at 206 (quoting Am Int’l Specialty Lines Ins. Co. v. Canal Indem. Co., 
    352 F.3d 254
    , 260 (5th Cir. 2003)).
    16 Prytania Park Hotel, Ltd. v. Gen. Star Indem. Co., 
    179 F.3d 169
     (5th Cir. 1999).
    17 In re Katrina, 495 F.3d at 206 (“Thus, although we will not disregard the decisions
    of Louisiana’s intermediate courts unless we are convinced that the Louisiana Supreme
    Court would decide otherwise, we are not strictly bound by them.”) (citing Am Int’l Specialty
    Lines, 352 F.3d at 261).
    18 Boyett v. Redland Ins. Co., 
    741 F.3d 604
    , 607 (5th Cir. 2014); see also Moore v. State
    Farm Fire & Cas. Co., 
    556 F.3d 264
    , 269–70 (5th Cir. 2009) (“To determine Louisiana law,
    we look to the final decisions of the Louisiana Supreme Court. In the absence of a final
    decision by the Louisiana Supreme Court, we must make an Erie guess . . . . When faced with
    unsettled questions of Louisiana law we adhere to Louisiana’s civilian decision-making
    process.”).
    19 Lamar, 189 So. 3d at 395–97.
    20 Id. (citing La. Civ. Code art. 1983) (internal alteration omitted).
    21 Id. at 398.
    9
    Case: 17-20599         Document: 00515035583           Page: 10     Date Filed: 07/16/2019
    No. 17-20599
    enactment in 1985, jurisprudence interpreting the predecessor article . . .
    emphasized that the obligor must establish that the obligee breached the
    contract, thereby making it more difficult for the obligor to perform its
    obligation.” 22 It concluded: “[A]n obligor cannot establish an obligee has
    contributed to the obligor’s failure to perform unless the obligor can prove the
    obligee itself failed to perform duties owed under the contract. Stated in other
    words, Kacco must demonstrate that Lamar failed to perform its obligations
    under the contract, which in turn contributed to Kacco’s breach of the
    contract.” 23 The question of the obligee’s bad faith does not become relevant
    until there is a determination that the obligee failed to perform a contractual
    obligation that in turn caused the obligor’s failure to perform. 24 For Article
    2003 to apply as a damages bar, there must be an antecedent determination of
    breach.
    While W&T urges that the Louisiana Supreme Court’s reading was
    limited to the second sentence of Article 2003—the negligence prong—the
    Lamar court drew no such limitation. 25 The reasoning of Lamar did not depend
    on the relationship between bad faith and negligence. W&T offers no principled
    reason why the Louisiana Supreme Court would have chosen not to recognize
    a requirement of breach had the obligee in that case acted in bad faith, rather
    than negligently. Indeed, we find no distinction in Lamar. Because Lamar is
    controlling here, the district court correctly concluded that the good-faith
    inquiry in Article 2003 is limited to situations where the obligee has
    22 Id. (referring to its decisions in Board of Levee Com’rs of Orleans Levee Dist. v. Hulse,
    
    120 So. 589
    , 590 (La. 1929) and Favrot v. Favrot, 
    68 So. 3d 1099
    , 1109 (La. Ct. App. 2011)).
    23 Id.
    24 Id. at 399 (summarizing the intermediate appellate court’s conclusion in Favrot that
    “the question of a party’s good or bad faith does not become relevant until there has been a
    determination that the party failed to perform an obligation under the contract”).
    25 Id.
    10
    Case: 17-20599         Document: 00515035583           Page: 11      Date Filed: 07/16/2019
    No. 17-20599
    breached. 26 The jury did not find that Apache breached so Article 2003 does
    not bar Apache’s entitlement to damages as a matter of law.
    IV.
    W&T also contends that the case never should have gone before a jury
    because W&T did not breach the contract as a matter of law. Section 6.2 of the
    JOA provides that the operator “shall not make any single expenditure or
    undertake any activity or operation costing Two Hundred Thousand Dollars
    ($200,000 or more), unless an AFE [is approved].” W&T reads that provision
    in conjunction with Exhibit C, governing accounting, which provides that
    “[a]cceptable reasons for non-payment or short payment . . . are as follows: . . .
    when an AFE is not approved.” Together, W&T argues, those provisions
    unambiguously resolve the issue of whether W&T breached. Because W&T as
    the non-operator decided not to approve any AFE, it contends that it was
    entitled to short the payment (and pay its share of the Helix P&A estimate)
    without being found in breach of the JOA. W&T emphasizes that Section 6.2
    does not contain an explicit exception for government-mandated operations
    undertaken pursuant to Section 18.4 and suggests that AFE approval was
    required even for operations performed under that Section. W&T points out
    that the parties understood how to make an exception to Section 6.2 and did so
    in a separate instance, exempting the operator from obtaining AFE approval
    in the event of a safety-threatening emergency. 27
    26    W&T suggests as a last resort that this court may certify the question to the
    Louisiana Supreme Court. Because we conclude that the Louisiana Supreme Court resolved
    this issue in Lamar, certification is unnecessary here. Cf. Janvey v. Golf Channel, Inc., 
    792 F.3d 539
    , 547 (5th Cir. 2015) (“Given . . . that this is a question of state law that no on-point
    precedent from the Supreme Court of Texas has resolved, that the Supreme Court of Texas
    is the final arbiter of Texas’s law . . . we believe it is best to certify the question at issue.”).
    27 “Notwithstanding the foregoing, in the event of an emergency which poses a threat
    to life, safety, property, or the environment, the Operator is empowered to immediately make
    such expenditures for the Joint Account as, in its opinion as a reasonable and prudent
    Operator, are necessary to deal with the emergency.”
    11
    Case: 17-20599      Document: 00515035583        Page: 12    Date Filed: 07/16/2019
    No. 17-20599
    Apache disputes W&T’s reading of the contract, arguing that under
    Section 18.4, which covers government-mandated P&A operations, Apache was
    required to undertake its P&A of the Wells as the operator and was authorized
    to do so without obtaining an AFE from W&T pursuant to Section 6.2. Section
    18.4 provides that
    The Operator shall conduct the abandonment and removal of any
    well, Production System or Facilities required by a governmental
    authority, and the Costs, risks and net proceeds will be shared by
    the Participating Parties in such well, Production System or
    Facilities according to their Participating Interest Share.
    Apache asserts that this provision contemplates cost-sharing between the
    parties and does not incorporate Section 6.2’s AFE process. Apache stresses
    that requiring a Section 6.2 AFE for a government-mandated P&A operation
    would lead to an absurd result because the non-operator could essentially hold-
    up an operator from completing a P&A required by federal law to avoid sharing
    the costs.
    The district court denied W&T’s motion for summary judgment,
    concluding that the interplay between Section 6.2 and Section 18.4 was
    ambiguous, leaving a material question of fact as to the parties’ intent. In
    answering Question Three, the jury found that Apache was not required to
    obtain W&T’s approval through an AFE before conducting the P&A as required
    by Section 18.4 28
    Whether contract language is ambiguous under Louisiana law is a
    question of law. 29 Under Louisiana law, “[w]hen the words of a contract are
    clear and explicit and lead to no absurd consequences, no further
    28  “Was Apache required to obtain W&T’s approval under Section 6.2 of the Contract
    before Apache plugged and abandoned the MC-674 wells as required under Section 18.4 of
    the Contract?”
    29 Cadwallader v. Allstate Ins. Co., 
    848 So. 2d 577
    , 580 (La. 2003).
    12
    Case: 17-20599        Document: 00515035583          Page: 13     Date Filed: 07/16/2019
    No. 17-20599
    interpretation may be made in search of the parties’ intent.” 30 “[I]f a court finds
    the contract to be unambiguous, it may construe the intent from the face of the
    document—without considering extrinsic evidence—and enter judgment as a
    matter of law.” 31 If the court determines that there is an ambiguity, the
    question of intent is an issue of fact. 32 “Louisiana courts will not interpret a
    contract in a way that leads to unreasonable consequences or inequitable or
    absurd results even when the words used in the contract are fairly explicit.” 33
    Applying Section 6.2’s expenditure provision to a government-mandated
    P&A undertaken pursuant to Section 18.4 would lead to an absurd
    consequence: namely a situation where a non-operator is empowered to hold
    an operator hostage, preventing the operator from completing a legally
    required P&A, in order to extract a better bargain or avoid cost-sharing
    altogether. The oddity of that result is compounded by the fact that Section
    18.4 has its own cost-sharing provision, 34 making the idea that the operator
    was required to obtain an AFE to complete the P&A less tenable. In light of
    that absurd consequence, the district court correctly concluded that the jury
    needed to resolve the question of the parties’ intent. 35 We agree therefore that
    
    30 La. Civ
    . Code art. 2046.
    31  Preston Law Firm, L.L.C. v. Mariner Health Care Mgmt Co., 
    622 F.3d 384
    , 392 (5th
    Cir. 2010) (internal citation omitted).
    32 Gebreyesus v. F.C. Schaffer & Assocs., Inc., 
    204 F.3d 639
    , 643 (5th Cir. 2000).
    33 Tex. E. Transmission Corp. v. Amerada Hess Corp., 
    145 F.3d 737
    , 742 (5th Cir.
    1998); see also La. Civ. Code art. 2046 (“When the words of a contract are clear and explicit
    and lead to no absurd consequences, no further interpretation may be made in search of the
    parties’ intent.”).
    34 “The Operator shall conduct the abandonment and removal of any well, Production
    System or Facilities required by a governmental authority, and the Costs, risks and net
    proceeds will be shared by the Participating Parties in such well, Production System or
    Facilities according to their Participating Interest Share.”
    
    35 La. Civ
    . Code art. 2046 (“When the words of a contract are clear and explicit and
    lead to no absurd consequences, no further interpretation may be made in search of the
    parties’ intent.”); Stewart Enters., Inc. v. RSUI Indem. Co., Inc., 
    614 F.3d 117
     (5th Cir. 2010)
    (holding that the most straightforward reading of the contract would lead to an absurd result
    that “could not have been intended by the parties”).
    13
    Case: 17-20599    Document: 00515035583          Page: 14     Date Filed: 07/16/2019
    No. 17-20599
    the question of whether Section 6.2’s expenditure requirement applies to
    government-mandated P&A undertaken pursuant to Section 18.4—which
    itself mandates cost-sharing—is ambiguous and was properly put to the jury.
    W&T’s response to the absurdity concern is unavailing. It suggests that
    if the parties fail to agree on costs through the AFE process, the government
    can simply conduct the P&A operation itself and charge the operator and non-
    operator later. 36 W&T does not dispute that federal law required the P&A
    operation of the Wells—rather it reads the Section 6.2 AFE requirement to
    apply to government-mandated P&A operations and urges that Apache, having
    failed to obtain an AFE from W&T, could have decided not to comply with
    federal regulations and allow the government to P&A the Wells itself. Allowing
    Apache to evade its obligations under federal law to P&A the Wells is contrary
    to its duty to conduct all operations as would a prudent operator. 37 W&T’s
    proposed answer to the troubling consequences of its reading is no solution at
    all.
    V.
    Finally, W&T claims that even if Apache was not barred from recovering
    damages, W&T is entitled to an offset based on Jury Question No. 5 and that
    the damages award of $43,214,515.83 should be reduced by $17 million. As to
    the legal basis for the offset, W&T points to “the basic law of damages” in
    Louisiana set out in La. Civ. Code art. 1995 that damages cannot place the
    obligee in a better position than it would have been in if the contract had been
    fulfilled. W&T posits that the jury determined that a $17 million offset was
    36“If parties cannot agree about costs and thus fail to P&A wells, the government can
    arrange for the P&A, deem the bond the working interest owners were required to provide
    forfeited to the amount that would cover P&A costs, and charge the working interest owners
    for any excess costs.”
    37 “The Operator shall conduct all operations in a good and workmanlike manner, as
    would a prudent operator under the same or similar circumstances.”
    14
    Case: 17-20599      Document: 00515035583         Page: 15    Date Filed: 07/16/2019
    No. 17-20599
    appropriate to account for the savings that Apache enjoyed by not incurring
    the stacking costs for the rigs. In its view, the jury credited testimony that
    Apache would have incurred stacking costs between $29.5 million and $36.4
    million and adopted the $17 million figure as a reasonable determination of
    Apache’s windfall. The district court denied W&T’s motion for entry of
    judgment and motion for a new trial, concluding that W&T was not entitled to
    an offset on the basis of Question 5. Specifically, the district court determined
    that Questions 2 and 5 were not linked, and offset was unavailable as an
    affirmative defense under any of W&T’s theories.
    Article 1995 provides that “[d]amages are measured by the loss
    sustained by the obligee and the profit of which he has been deprived.” 38 “The
    measure of damages for a breach of contract is the sum that will place plaintiff
    in the same position as if the obligation had been fulfilled.” 39 On Question 2,
    the jury was instructed in accordance with Article 1995 to calculate “an
    amount that is fair compensation for those damages.” The court then explained
    to the jury:
    Damages are measured by the loss sustained by the non-breaching
    party. These are called compensatory damages. The damages
    amount is the amount that will place Apache in the position it
    would have been in if the parties’ contract had been properly
    performed. The damages include the amount a party owed under
    the contract.
    The jury was instructed to determine the actual loss sustained without
    reference to Question 5. W&T’s own closing argument emphasized this
    understanding, encouraging the jury in calculating an amount for Question 2
    to subtract the amount of savings W&T attributed to Apache’s avoiding the
    
    38 La. Civ
    . Code art. 1995.
    39 Gloria’s Ranch LLC v. Tauren Exploration, Inc., 
    252 So. 3d 431
    , 445–46 (La. 2018)
    (internal citation and quotation marks omitted).
    15
    Case: 17-20599       Document: 00515035583          Page: 16     Date Filed: 07/16/2019
    No. 17-20599
    stacking costs by using the rigs. 40 W&T’s offset argument on appeal ignores
    the fact that the jury instructions with respect to Question 2 tracked the
    language of Article 1995. The two cases W&T relies on do not offer a theory
    entitling W&T to offset. In Evangeline Parish School Bd. v. Energy Contracting
    Servs., Inc., the Louisiana appellate court considered a damages award in favor
    of an obligee to an energy-savings services contract. 41 The court reaffirmed the
    general principle of Article 1995 that “[d]amages for obligor’s failure to perform
    are measured by the loss sustained by the obligee and the profit of which he
    has been deprived” and remanded, noting that the experts failed to calculate
    the amount overcharged and the appellate court was therefore “unable to make
    such a determination from the record.” 42 There is no lack of clarity in the record
    here—W&T simply disputes the jury’s rejection of its stacking costs theory. In
    Swoboda v. SMT Prop., LLC, the Louisiana appellate court considered the
    damages award in a contract dispute involving the construction of a residential
    home. 43 In accordance with Article 1995, the court “consider[ed] the benefit to
    plaintiffs in maintaining ownership and possession of the adjacent lot [and]
    conclude[ed] that plaintiffs [we]re not entitled to reimbursement.” 44 Again,
    W&T ignores that the jury was instructed in accordance with Article 1995 and
    explicitly calculated the actual loss sustained by Apache. W&T’s stacking costs
    theory was rejected by the jury and it has offered no legal theory to support
    upsetting that verdict.
    40  “Number two is the damage issue. We believe that if you get to that issue, and you
    believe that somehow damages should be awarded in this case, they say it is 43.2 million. We
    think they benefited anywhere . . . between 29 to 36 million. So we believe you should subtract
    that from any damage amount you decide to award in the case.”
    41 
    617 So. 2d 1259
     (La. App. 3d. 1993).
    42 Id. at 1267.
    43 
    975 So. 2d 691
     (La. App. 2008).
    44 Id. at 695.
    16
    Case: 17-20599       Document: 00515035583         Page: 17     Date Filed: 07/16/2019
    No. 17-20599
    W&T posits two additional legal bases to support an offset in Apache’s
    damages award. First, W&T suggests that Article 2323, governing comparative
    fault, provides an independent legal basis for a reduction. Article 2323 applies
    in tort cases; the Civil Code provides its own rule governing comparative fault
    in contract cases—Article 2003—that we have already determined does not aid
    W&T here. 45 W&T also claims the doctrine of compensation under Article 1893
    gives independent grounds for an offset. 46 As the district court correctly noted,
    W&T “previously admitted neither [compensation or unjust enrichment] could
    be the basis of the jury’s finding, as that was not the nature of the evidence
    presented to the jury.” In its post-verdict briefing, W&T conceded that Article
    1893 did not apply, because “the jury was not instructed on the specific
    requirements of the traditional doctrine of offset or setoff, which requires debts
    owed by both parties being offset against each other.” Neither comparative
    fault nor compensation provide a basis for a reduction in the damages award
    here.
    Finally, W&T offers a last-ditch argument that the jury award was
    clearly excessive because of Apache’s savings on the stacking costs. The district
    court did not abuse its discretion in denying W&T’s motion for a new trial or
    remittitur. We agree with the district court the damages award was supported
    by substantial evidence. The jury logically awarded the precise amount that
    W&T shorted by making a partial payment after the P&A operation. Such an
    award was not excessive or “contrary to right reason”—rather, it reflects that
    45See Justiss Oil Co. v. Oil Country Tubular Corp., 
    216 So. 3d 346
    , 356–57 (La. Ct.
    App.), writ denied, 
    227 So. 3d 830
     (La. 2017) (quoting Hanover Ins. Co. v. Plaquemines Parish
    Gov’t, No. 12–1680, 
    2015 WL 4167745
    , at *5–6 (E.D. La. July 9, 2015).
    46 Article 1893 provides that “Compensation takes place by operation of law when two
    persons owe to each other sums of money or quantities of fungible things identical in kind,
    and these sums or quantities are liquidated and presently due. In such a case, compensation
    extinguishes both obligations to the extent of the lesser amount.” La. Civ. Code art. 1893.
    17
    Case: 17-20599      Document: 00515035583        Page: 18   Date Filed: 07/16/2019
    No. 17-20599
    the jury’s consideration of the evidence led it to reject W&T’s assertion that
    Apache enjoyed a windfall by avoiding the stacking costs. 47
    VI.
    For the foregoing reasons, the judgment of the district court is affirmed.
    47 Laxton v. Gap, Inc., 
    333 F.3d 572
    , 586 (5th Cir. 2003) (“When a damage award is
    merely excessive or so large as to appear contrary to right reason, remittitur is the
    appropriate remedy.”).
    18