McDermott, Inc. v. Iron ( 1992 )


Menu:
  •               IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 91-2246
    MCDERMOTT, INC.,
    Plaintiff-Appellee,
    Cross-Appellant,
    versus
    CLYDE IRON, ET AL.,
    Defendants,
    AmCLYDE, A Division of
    AMCA International, Inc., and
    RIVER DON CASTING LTD.,
    Defendants-Appellants,
    Cross-Appellees.
    Appeal from the United States District Court
    for the Southern District of Texas
    (December 11, 1992)
    Before HIGGINBOTHAM and DUHÉ, Circuit Judges, and HARMON,* District
    Judge.
    HIGGINBOTHAM, Circuit Judge:
    This is a suit for damage to property resulting from a failure
    of a large crane on an offshore platform.     AmClyde and River Don
    appeal from a judgment on the jury's verdict urging that AmClyde's
    contract with McDermott, and general maritime law, protect them
    from liability in warranty and tort in addition to the limits on
    tort liability under the East River doctrine and that, in any
    *
    Harmon, District Judge of the Southern District of Texas,
    sitting by designation.
    event, they are entitled to the credit of McDermott's settlement
    with others.    McDermott cross-appeals attacking the application of
    East River and the denial of recovery for damage to the crane
    itself. We reverse the judgment against AmClyde. We conclude that
    River Don is liable to McDermott, but hold that River Don is
    entitled to full credit for McDermott's settlement.
    I.
    On January 10, 1986, McDermott contracted to purchase a 5,000
    ton Shearleg crane designed and manufactured by AmClyde.                   The
    contract covered twenty-five pages and included several provisions
    purporting to limit potential liability. McDermott intended to use
    the crane to move the deck portion, the Snapper deck, of an
    offshore platform      used    in   drilling   for   oil   and   natural   gas.
    AmClyde designed the crane's hook.         River Don was not a party to
    the McDermott-AmClyde contract but manufactured the hook under a
    subcontract with AmClyde.
    On October 10, 1986, McDermott was using the crane to lift the
    approximately 3,950 ton Snapper deck. The crane was mounted aboard
    the vessel Intermac 600 in the Gulf of Mexico off the coast of
    Texas.    As the crane lifted the deck, one of the prongs on the hook
    and one of the slings holding the deck broke, and the deck fell
    onto the barge with serious damage to the crane and deck.                  This
    suit followed.
    McDermott sued AmClyde, River Don, two manufacturers of the
    slings, and another sling supplier asserting tort and contract
    claims.      AmClyde   filed    a    third-party     claim   against   Hudson
    2
    Engineering, the McDermott subsidiary that designed the sling
    rigging arrangement used for the lift. AmClyde also counterclaimed
    for the cost of replacing the allegedly defective hook.
    AmClyde and River Don moved for partial summary judgment
    arguing that AmClyde and McDermott agreed in the contract to
    restrict any tort and contract liability to repair or replacement
    and that under general maritime law there is no recovery for
    product   damage   and   resulting   economic   loss   under   East   River
    Steamship Corp. v. Transamerica Delaval, Inc., 
    476 U.S. 858
     (1986).
    The magistrate judge denied the motion.
    On the eve of trial, McDermott settled with the three sling-
    related defendants for $1 million.       AmClyde and River Don claimed
    a dollar-for-dollar credit for the $1 million settlement against
    any judgment against them, citing Hernandez v. M/V RAJAAN, 
    841 F.2d 582
     (5th Cir. 1988).        In his opening statement, counsel for
    McDermott told the jury that McDermott accepted responsibility for
    any part the slings played in causing the damage.         The settlement
    documents were not formally executed until after the jury returned
    its verdict.   That detail disclosed that the settlement agreement
    attributed one half of the total settlement to crane damages and
    one half to deck damages.
    Shortly after trial began, the magistrate judge, relying on
    East River, ruled that McDermott could not recover in tort for
    damage to the product itself, the crane and the hook, but that it
    could recover in tort for damage to the deck as "other property."
    3
    At trial then, McDermott's claim for damages to the crane was
    limited to the remedies provided for in its contract with AmClyde.
    The jury found the crane's hook to be defective, that the
    defect was one of materials or workmanship and misrepresentation,
    and that this defect was a producing cause of injury.                          The jury
    also found that AmClyde breached express and implied warranties
    that       were    a   producing   cause   of    injury.          The   jury    awarded
    compensatory damages of $2.1 million for damage to the deck,
    attributing the cause of the accident 32% to AmClyde, 38% to River
    Don,       0%     to   Hudson   Engineering     and   30%    to    "McDermott/sling
    defendants."            The jury was not asked to determine separately
    McDermott's contribution to the accident despite its assumption of
    any damage caused by the sling defendants.                  The court later denied
    AmClyde and River Don's request for a $1 million credit against the
    verdict and rendered judgment on the jury's verdict against AmClyde
    in the amount of $672,000.00 and against River Don in the amount of
    $798,000.00.2
    AmClyde and River Don appeal, and McDermott cross-appeals.
    AmClyde and River Don first argue that recovery for damages to the
    deck cannot be supported by a breach of contract, because the
    parties disclaimed all warranties, except a limited replacement and
    repair warranty for materials and workmanship.                          Second, they
    contend that McDermott was not entitled to any recovery in tort for
    damage to the deck, because (1) the McDermott-AmClyde contract
    2
    The jury also found in favor of McDermott on AmClyde's
    counterclaim. AmClyde does not appeal this determination.
    4
    waived all tort liability as to AmClyde and River Don, and (2) East
    River precludes any tort claims for damage to both the crane and
    the deck.     Third, AmClyde and River Don assert that the trial court
    should have granted their motions for directed verdict and judgment
    notwithstanding the verdict, because McDermott failed to prove
    causation.     Finally, AmClyde and River Don claim an offset of the
    $1 million settlement under Hernandez, alternatively, that they are
    entitled to a new trial because of various erroneous rulings on
    questions of evidence.
    McDermott contends that it is entitled to recover for damage
    to the crane as well as the deck.       McDermott requests a remand for
    trial on the amount of damages to the crane only, contending that
    the jury has already determined the liability of AmClyde and River
    Don.     McDermott argues that it should not be limited to the
    replacement of defective parts under the contract, because (1)
    AmClyde's refusal to replace the hook free of charge caused the
    limited warranty to fail of its essential purpose; (2) AmClyde made
    broad   and    undisclaimed   warranties   by   incorporating   technical
    specifications into the document; (3) the warranty was modified by
    later dealings between the parties and assurances from AmClyde that
    it would "stand behind its product"; (4) the replacement warranty
    applies only to AmClyde's manufacture of the crane, not to its
    design and sale.     Second, McDermott contends that East River does
    not bar recovery for damage to the crane, because other property,
    the deck, along with the crane was damaged.            Third, McDermott
    argues that its claims against River Don should not be governed by
    5
    the    rule    of   East    River     because      there   was    no   contractual
    relationship directly between them. Finally, McDermott claims pre-
    judgment interest and urges that the jury's verdict should be
    corrected to show that the jury allocated causation and not fault.
    II.
    We are convinced that the contract between McDermott and
    AmClyde controls AmClyde's liability to McDermott.                     It is urged
    that       McDermott's     recovery    in       warranty   is    limited   to   the
    replacement/repair warranty in the McDermott-AmClyde contract, and
    the contract precludes McDermott from recovering in tort. We agree
    and reverse the judgment against AmClyde.                  Although we conclude
    that River Don is not protected by the limited liability provisions
    in the contract between McDermott and AmClyde, and River Don is
    liable to McDermott, we find that River Don is entitled to a credit
    of McDermott's settlement with the sling defendants.                    We address
    AmClyde first, then River Don.
    III.
    The language of the contract is critical to McDermott's
    recovery against AmClyde in warranty, and we focus on Article XV3.
    3
    ARTICLE XV - WARRANTY
    A.   The Seller warrants equipment of its own manufacture to
    be free from defects in materials and workmanship under
    normal use and service for a period of six (6) months after
    first use and not to exceed twelve (12) months after
    shipment or notification of readiness for shipment. This
    warranty extends only to the Buyer, and in no event shall
    the Seller be liable for property damage sustained by a
    person designated by the law of any jurisdiction as a third
    party beneficiary of this warranty or any other warranty
    held to survive the Seller's disclaimer. This warranty does
    not extend to normal wear and tear or to the equipment,
    6
    The parties agree that we must look to the law of New York in
    interpreting this contract.   Under New York law, these issues of
    contract interpretation are considered questions of law.   Maio v.
    Gardino, 
    585 N.Y.S.2d 529
    , 530 (N.Y. App. Div. 1992); Trustco Bank
    materials, parts and accessories manufactured by others, and
    THE BUYER AGREES THAT IT MUST RELY SOLELY ON THE
    MANUFACTURER'S WARRANTIES APPLICABLE, AND THAT IT SHALL HAVE
    NO REMEDY AGAINST THE SELLER FOR BREACH OF A MANUFACTURER'S
    WARRANTY. This warranty shall be NULL AND VOID if any
    repairs, modifications or alterations are made to the
    equipment supplied hereunder during the warranty period by
    the Buyer or by others on his behalf without the prior
    written consent of the SELLER. THE WARRANTY DESCRIBED IN
    THIS PARAGRAPH SHALL BE IN LIEU OF ALL OTHER WARRANTIES,
    EXPRESS OR IMPLIED, INCLUDING, BUT NOT LIMITED TO, ANY
    IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR A
    PARTICULAR PURPOSE.
    B.   Upon written notification received by the Seller within
    the above stated warranty period of any failure to conform
    to the above warranty, upon return prepaid to the Seller of
    any nonconforming original part of component and upon
    inspection by the Seller to verify said nonconformity, the
    Seller shall repair or replace said original part or
    component without charge to the Buyer. The Seller shall
    ship the repaired or replaced part or component to the Buyer
    at the Buyer's expense. Correction of nonconformities, in
    the manner provided above, shall constitute fulfillment of
    all liabilities of the Seller to the Buyer or any other
    person whether based upon Contract, tort, strict liability
    or otherwise.
    C.   The remedies set forth herein are exclusive, without
    regard to whether any defect was discoverable or latent at
    the time of delivery of the apparatus to the Buyer. The
    essential purpose of this exclusive remedy shall be to
    provide the buyer with repair or replacement of parts or
    components that prove to be defective within the period and
    under the conditions previously set forth. This exclusive
    remedy shall not have failed of its essential purpose (as
    that term is used in the Uniform Commercial Code) provided
    the Seller remains willing to repair or replace defective
    part to components within a commercially reasonable time
    after it obtains actual knowledge of the existence of a
    particular defect.
    7
    v. 11 North Pearl Assoc., 
    580 N.Y.S.2d 847
    , 848 (N.Y. Sup. Ct.
    1992).   Thus, our review is de novo.
    A.
    In Article XV, AmClyde warrants that equipment of its own
    manufacture will be free from defects in materials and workmanship
    and that the exclusive remedy for the breach of this limited
    warranty will be repair or replacement of defective parts.      Such
    agreed upon limits on remedy are generally valid.    
    N.Y. U.C.C. Law § 2-719
     (McKinney 1991)4; Employers Ins. of Wausau v Suwannee River
    Spa Lines, Inc., 
    866 F.2d 752
    , 776 (5th Cir. 1989); American Elec.
    Power Co. v. Westinghouse Elec., 
    418 F. Supp. 435
    , 452-53 (S.D.N.Y.
    1976).
    The jury found a defect in materials or workmanship, and
    therefore, a breach of this limited warranty.     McDermott attempts
    to escape the restriction on remedy that it agreed to urging that
    this remedy "failed of its essential purpose."5
    4
    
    N.Y. U.C.C. § 2-719
    (1) provides:
    Subject to the provisions of subsections (2) and (3) of this
    section and of the preceding section on liquidation and
    limitation of damages,
    (a) the agreement may provide for remedies in addition to or
    in substitution for those provided in this Article and may
    limit or alter the measure of damages recoverable under this
    Article, as by limiting the buyer's remedies to return of
    the goods and repayment of the price or to repair and
    replacement of non-conforming goods or parts; and
    (b) resort to a remedy as provided is optional unless the
    remedy is expressly agreed to be exclusive, in which case it
    is the sole remedy.
    5
    
    N.Y. U.C.C. § 2-719
    (2) provides:
    Where circumstances cause an exclusive or limited remedy to
    fail of its essential purpose, remedy may be had as provided
    8
    The policy behind the failure of essential purpose rule is to
    insure that the buyer has "at least minimum adequate remedies."
    U.C.C. § 2-719 Comment 1.      Typically, a limited repair/replacement
    remedy fails of its essential purpose where (1) the "[s]eller is
    unsuccessful     in    repairing   or       replacing    the     defective    part,
    regardless of good or bad faith; or (2) [t]here is unreasonable
    delay in repairing or replacing defective components."                       Cayuga
    Harvester, Inc. v. Allis-Chalmers, Corp., 
    465 N.Y.S.2d 606
    , 613
    (N.Y. App. Div. 1983).       McDermott and AmClyde were aware of this
    rule, expressly addressing the doctrine in their contract. Article
    XV.C, provides:       "[t]his exclusive remedy shall not have failed of
    its essential purpose . . . provided the Seller remains willing to
    repair   or    replace     defective     part     to    components     within       a
    commercially reasonable time after it obtains actual knowledge of
    the existence of a particular defect."           See James J. White & Robert
    S. Summers, Uniform Commercial Code § 12-10 (3d ed. 1988) (stating
    that such a clause may give the seller greater protection).
    McDermott    argues    that   the      limited     remedy    failed     of   its
    essential purpose, because AmClyde did not replace the crane hook
    free of charge.        McDermott, with agreement of AmClyde and River
    Don, sent the hook to Packer Engineering for testing.                        Packer
    determined that the hook was defective, and McDermott demanded a
    replacement from AmClyde under the limited warranty.                         AmClyde
    responded that McDermott must first send them a purchase order.
    McDermott sent the purchase order, and AmClyde later sent a new
    in this Act.
    9
    hook, both parties expressly reserving their rights.           AmClyde, as
    we noted, counterclaimed for the cost of the replacement hook,
    arguing that the hook was not defective, but failed at McDermott's
    negligent hand.       Based on the jury's verdict, the magistrate judge
    refused to order payment for the replacement hook.
    McDermott's assertion that AmClyde did not replace the hook
    free of charge is apparently based on AmClyde's requirement of a
    purchase order and the contest of its obligation to provide a free
    replacement.      McDermott received a new hook and at no cost.
    AmClyde never denied its obligation to replace a defective hook.
    It only denied that the hook was defective.          It lost that argument
    and honored its obligation.        We find no failure of purpose.6
    B.
    McDermott argues that in addition to the limited warranty in
    Article   XV,   the    contract   gained   another   express   warranty   by
    incorporating design specifications.7          The Specifications state
    6
    McDermott further argues that the replacement warranty
    applies only to AmClyde's manufacturing of the crane, not to its
    design and sale. We find no merit to this contention. See e.g.,
    American Elec. Power Co. v. Westinghouse Corp., 
    418 F. Supp. 435
    (S.D.N.Y. 1976) (court recognized the validity of a similar
    limitation of warranty/exclusive remedy provision where
    defendant's responsibility encompassed manufacturing,
    construction, and design); Shipco 2295, Inc. v. Avondale
    Shipyards, Inc., 
    631 F. Supp. 1123
     (E.D. La. 1986), aff'd, 
    825 F.2d 925
     (5th Cir. 1987), cert. denied, 
    485 U.S. 1007
     (1988)
    (Avondale's limited warranty/exclusive remedy provision was
    enforced notwithstanding Avondale's involvement in manufacturing,
    construction, and design).
    7
    ARTICLE I - SCOPE OF WORK
    A.   Provide one 5000 short ton shearleg derrick package for
    barge mounting in accordance with specification no. 8506-
    12D/B REV 2 entitled "Specifications for 5000 short ton
    10
    that "[t]he crane when erected will be capable of lifting 5000 ST
    to a reach of 100 feet measured from the boom heel pin."          McDermott
    argues that this language created an express warranty of the
    crane's lifting capacity or a "design warranty."
    We decline this journey, however, because assuming there was
    a "design warranty," it was not breached.      The jury found that the
    defect in the crane was one of materials or workmanship and
    misrepresentation and specifically not a defect in design.
    McDermott   also    argues   that   AmClyde   gave   other     express
    warranties after the parties executed the contract.           McDermott
    relies on an exchange of letters between AmClyde vice president
    Michael J. Ucci and McDermott vice president W.L. Higgins.             Mr.
    Ucci wrote in part:
    In the unlikely event the 5000 ST Shearleg Derrick being
    designed by Clyde does not perform according to the
    specification, Clyde would ensure that any deficiencies are
    corrected. Our track record in this area should speak for
    itself, but in addition I am giving you my personal assurance
    that we will stand behind our product.
    Mr. Higgins responded:
    To the extent that you have expanded on the intent of the
    warranty of the 5000 ST Shearleg Derrick, we understand you to
    say that Clyde will correct any such deficiencies and will
    cooperate with McDermott to do so expeditiously and with a
    minimum of inconvenience and expense. This of course would
    conceptually include having the work done locally to avoid the
    time and expense of taking the equipment out of service and
    sending it to Duluth, Minnesota to correct deficiencies.
    shearleg derrick" dated December 12, 1985 (EXHIBIT A) and as
    described in your Proposal dated December 9, 1985, all of
    which are incorporated by this reference.
    (emphasis added).
    11
    We accept your personal assurance that Clyde will accept the
    additional warranty responsibility. McDermott trusts that the
    entire Clyde organization endorses the intent of your Comfort
    Letter and in particular, the notion that Clyde will stand
    behind its product.
    McDermott argues that these letters created a new warranty.
    An express warranty arises through "[a]ny affirmation of fact
    or promise by the seller to the buyer which relates to the goods
    and becomes part of the basis of the bargain."              
    N.Y. U.C.C. § 2
    -
    313(1)(a) (McKinney 1991).      We do not read these two letters to
    create a new or different warranty.               Instead, Mr. Ucci only
    reaffirmed AmClyde's obligation to repair or replace any defective
    parts.   Regardless,      McDermott    cannot    overcome    the   contract's
    integration      clause   requiring        a   signed   writing     for   its
    modification.8     These provisions are specifically validated by
    U.C.C. § 2-209(2), and a signed writing is required to modify or
    rescind them.9     McDermott counters with a waiver argument.              As
    8
    ARTICLE XXI - INTEGRATION
    This document constitutes the entire Agreement between the
    parties. There are no understandings as to the subject
    matter of this Agreement other than as herein set forth.
    All previous communications concerning the subject matter of
    this Agreement are hereby abrogated and withdrawn. This
    Agreement may not be modified except by a writing signed by
    both parties, and any printed terms and conditions submitted
    by either party during the course of this Agreement shall be
    of no force or effect, unless expressly agreed to the
    contrary in writing by both parties.
    9
    
    N.Y. U.C.C. § 2-209
    (2) provides:
    A signed agreement which excludes modification or rescission
    except by a signed writing cannot be otherwise modified or
    rescinded, but except as between merchants such a
    requirement on a form supplied by the merchant must be
    separately signed by the other party.
    12
    circular as the notion may be, it is true that an integration
    clause can be waived, see U.C.C. § 2-209(4),10 but we conclude that
    no waiver occurred.
    McDermott states that both parties "as a normal course of
    conduct . . . regularly accommodated, modified, supplemented, and
    finalized important aspects of the Shearleg Crane and its warranted
    qualities after signing an initial contract document," and contends
    that this course of dealing constituted a waiver of the contract's
    modification requirement.        The only case McDermott cites on this
    point is Linear Corp. v. Standard Hardware Co., 
    423 So. 2d 966
    (Fla. Dist. Ct. App. 1982).        That case involved a contract for the
    sale of electronic security devices between a manufacturer and a
    wholesaler.      The contract expressly stated that the goods were not
    purchased on consignment and could not be returned.            The contract
    further required a signed writing to modify.             The court found a
    waiver     of   this   writing   requirement   and   a   new   agreement   to
    repurchase, concluding from a number of letters and telephone
    conversations that the seller had agreed to a return of unsold
    equipment.
    In Linear, the new agreement involved a major change to the
    contract, the right to return the goods.         The changes referred to
    by McDermott involved technical details that would have been
    difficult to spell out in the contract.              More important, the
    10
    
    N.Y. U.C.C. § 2-209
    (4) provides:
    Although an attempt at modification or recision does not
    satisfy the requirements of subsection (2) or (3) it can
    operate as a waiver.
    13
    McDermott-AmClyde contract authorized changes to "plans, designs,
    or specifications."11     These changes did not modify the contract;
    they were contemplated by the parties, and the parties specifically
    provided for them in the contract.            Relatedly and significantly,
    AmClyde     and   McDermott    abided    by   the   integration   clause   in
    performing the contract, executing a modification by a signed
    writing on one occasion.        Representatives of McDermott and AmClyde
    executed a formal contract Addendum changing the indemnity/Hold
    Harmless provisions.          At the same time, the parties left the
    WARRANTY and INTEGRATION clauses untouched.            If Mr. Ucci and Mr.
    Higgins intended to create a new warranty, they could have done so
    by complying with the contract's integration clause.
    C.
    The jury found that AmClyde breached an implied warranty of
    the hook.     AmClyde argues, however, and we agree that this finding
    has no legal consequence.         The McDermott-AmClyde contract waived
    all implied warranties.          
    N.Y. U.C.C. Law § 2-316
    (2) (McKinney
    1991).12    Moreover, McDermott admitted that the contract waived all
    11
    ARTICLE V - CHANGES
    A.   Buyer may, at any time by a written order, make changes
    within the general scope of this Contract in any one or more
    of the plans, designs, or specifications. If any such
    change causes an increase or decrease in the cost of or the
    time required for the performance of any part of this
    Contract, the Seller must advise Buyer Representative
    immediately and confirm to Buyer in writing within 5 working
    days. Nothing in this section shall excuse Seller from
    proceeding with the Contract as changed.
    12
    
    N.Y. U.C.C. § 2-316
    (2) provides:
    Subject to subsection (3), to exclude or modify the implied
    14
    implied warranties under Fed. R. Civ. P. 36(b).           AmClyde asked
    McDermott to admit or deny "[t]hat the Contract for Supply of 5,000
    Short Ton Shearleg Derrick between McDermott and Clyde Iron dated
    January 10, 1986, in Article XV(A), waived any implied warranty."
    McDermott replied "Admitted."      The magistrate should have ignored
    the jury's answer to this question.      American Automobile Ass'n. v.
    AAA Legal Clinic, 
    930 F.2d 1117
    , 1120 (5th Cir. 1991).
    IV.
    This brings us to McDermott's tort claims against AmClyde.
    Article   XV   of   the   McDermott-AmClyde   contract   provides   that:
    "Correction of nonconformities, in the manner provided above, shall
    constitute fulfillment of all liabilities of the Seller to the
    Buyer or any other person whether based upon Contract, tort, strict
    liability or otherwise."       (emphasis added).    AmClyde argues that
    this provision protects it from liability to McDermott in tort. We
    agree.
    Contractual provisions waiving negligence and strict liability
    claims are enforceable under New York law.         See Laudisio v. Amoco
    Oil Co., 
    437 N.Y.S.2d 502
    , 504 (N.Y. Sup. Ct. 1981) (negligence);
    Velez v. Craine & Clark Lumber Corp. 
    350 N.Y.S.2d 617
    , 623 (N.Y.
    1973) (strict liability).       Contractual waivers of liability are
    warranty of merchantability or any part of it the language
    must mention merchantability and in case of a writing must
    be conspicuous, and to exclude or modify any implied
    warranty of fitness the exclusion must be by a writing and
    conspicuous. Language to exclude all implied warranties of
    fitness is sufficient if it states, for example, that "There
    are no warranties which extend beyond the description on the
    face hereof."
    15
    subject to close judicial scrutiny and "it must appear plainly and
    precisely that the limitation extends to negligence or other fault
    of the party attempting to shed his ordinary responsibility."
    Howard v. Handler Bros. & Winell, 
    107 N.Y.S.2d 749
    , 752 (N.Y. App.
    Div. 1951), aff'd, 
    106 N.E.2d 67
     (N.Y. 1952); Gross v. Sweet, 
    424 N.Y.S.2d 365
    , 368 (N.Y. 1979).               McDermott does not attack the
    exculpatory provision in the McDermott-AmClyde contract as being
    vague or ambiguous.         The provision is precise.       It specifically
    mentions   "tort"     and    "strict     liability,"   terms   familiar     to
    sophisticated business entities such as these.              See Gross, 424
    N.Y.S.2d   at   368   (noting    that    broadly   worded   clauses   may   be
    sufficient where sophisticated business entities are involved).
    Moreover, similar clauses are common in commercial markets.                 See
    e.g. Nicor Supply Ships Assocs. v. General Motors, 
    876 F.2d 501
    ,
    504 (5th Cir. 1989); Arkwright-Boston Mfrs. Mutual Ins. Co. v.
    Westinghouse Elec. Corp., 
    844 F.2d 1174
    , 1181 n.15 (5th Cir. 1988);
    American Electric, 
    418 F. Supp. at
    452 n.25.13
    We hold that McDermott has no claims against AmClyde, except
    for breach of the limited warranty in their contract.            We reverse
    this portion of the judgment of the district court.
    14 V. 13
    The exculpatory provision's preclusion of liability in
    tort bars McDermott's misrepresentation claim as well.
    Therefore, the jury's finding of a misrepresentation defect was
    of no legal significance.
    14
    Because we reverse the judgment against AmClyde, we need
    not address AmClyde's other assignments of error.
    16
    Turning to River Don, McDermott's contention that it should
    have been allowed to proceed against River Don for a breach of
    warranty is unclear.             On one hand, McDermott states it "was not
    allowed to proceed in contract against River Don for any damages
    but was restricted to tort damages by River Don to the deck section
    alone,"    and    "[t]he     court,      inexplicably,      would     not   allow   any
    evidence    of     contract       remedies       that   River   Don   would   owe    to
    McDermott, Inc., directly or as third party beneficiary, per
    Article XV."           On the other hand, McDermott says "the evidence
    adduced at trial demonstrated that River Don made express and
    implied warranties regarding the Hook which were communicated to
    McDermott with the expectation that these representations would be
    relied upon."          Regardless, McDermott has not preserved this issue
    for appeal.
    The magistrate judge did not rule on McDermott's contract
    claim against River Don.           The magistrate relied upon East River in
    ruling that McDermott could recover in tort for the damage to the
    deck but not to the crane.            Without objection, the district judge
    submitted only McDermott's warranty claims to the jury.
    VI.
    River       Don    argues    that     the    exculpatory    provision    in    the
    McDermott-AmClyde contract protects it as well as AmClyde from
    liability in tort.         River Don relies on Aeronaves De Mexico, S.A.
    v. McDonnell Douglas, 
    677 F.2d 771
     (9th Cir. 1982).                    In that case,
    an   airplane's         landing     gear     failed.        Aeromexico      sued    the
    manufacturer of the plane, McDonnell Douglas, and the subcontractor
    17
    who manufactured the landing gear assembly, Menasco.                     
    Id. at 772
    .
    The contract between Aeromexico and McDonnell Douglas contained a
    warranty     provision,   similar      to    that    in    the   McDermott-AmClyde
    contract, barring a negligence action against McDonnell Douglas.
    
    Id. at 773
    .         Aeromexico did not contest the validity of that
    provision but on appeal argued that the exculpatory provision did
    not bar its suit against Menasco, because Aeromexico and Menasco
    were   not    in    privity.     The    court       rejected     this    contention,
    concluding that recovery by Aeromexico from Menasco would be a
    windfall.     The court relied on the fact that if Aeromexico were
    allowed to sue Menasco directly, Menasco could file a third party
    claim against McDonnell Douglas.             
    Id.
        In fact, the district court
    found that the contract between McDonnell Douglas and Menasco
    permitted such a claim.          Id. at n.4.              The liability would be
    visited upon McDonnell Douglas, "thus nullifying the contractual
    allocation of risks" between McDonnell Douglas and Aeromexico. Id.
    at 773.
    We decline to apply the rationale of Aeronaves de Mexico.                  We
    are mindful of the fact that we must apply New York law to
    interpret the McDermott-AmClyde contract.                   We are not persuaded
    that New York would here abandon the rule of privity.                   If River Don
    had a claim against AmClyde and thus could shift ultimate liability
    to AmClyde, this fact would not persuade us that McDermott is
    barred from recovering against River Don.                   If AmClyde wanted to
    prevent River Don from shifting liability, AmClyde could have
    sought    this     protection   from   River       Don    in   their    subcontract.
    18
    AmClyde only warranted equipment of its own manufacture.                    The
    contract    did      not    preclude    McDermott       from     suing   other
    manufacturers.15
    River Don's tort liability turns then on the East River
    doctrine.    In East River Steamship Corp. v. Transamerica Delaval,
    Inc., 
    476 U.S. 858
    , 871 (1986), the Supreme Court held that "a
    manufacturer in a commercial relationship has no duty under either
    a negligence or strict products liability theory to prevent a
    product from injuring itself."          The Court reasoned that when the
    only damage is economic loss to the product itself, the purchaser
    has simply lost the benefit of its contractual bargain and should
    be limited to its contractual warranty remedies.               
    Id. at 872-876
    .
    McDermott argues that East River does not shield River Don
    from tort liability, because River Don is not a party to the
    contract between McDermott and AmClyde.             In Shipco 2295, Inc. v.
    Avondale Shipyards, Inc., 
    825 F.2d 925
    , 929 (5th Cir. 1987), we
    held that under East River there is "no rational reason to give the
    buyer greater rights to recover economic losses for a defect in the
    product    because    the   component       is   designed,   constructed,    or
    furnished by someone other than the final manufacturer."              Allowing
    such a recovery would "undermine the objective of East River that
    the parties receive the benefit of their bargain."              Id.; see also
    Nathaniel Shipping, Inc. v. General Elec. Co., 
    920 F.2d 1256
    , 1263-
    15
    Article XV provides in part: THE BUYER AGREES THAT IT
    MUST RELY SOLELY ON THE MANUFACTURER'S WARRANTIES APPLICABLE, AND
    THAT IT SHALL HAVE NO REMEDY AGAINST THE SELLER FOR BREACH OF A
    MANUFACTURER'S WARRANTY.
    19
    64, modified, 
    932 F.2d 366
     (5th Cir. 1991).                Thus, East River
    applies to River Don.
    East River applies when the action is for damage to the
    product itself and not for damage to "other property." Shipco, 
    825 F.2d at 929
    .   Therefore, the issue in this case is whether the deck
    is "other property" so as to escape East River's bar to recovery in
    tort.    We ask "what is the object of the contract or bargain that
    governs the rights of the parties?"       
    Id. at 928
    ; see also Petroleum
    Helicopters, Inc. v. Avco Corp., 
    930 F.2d 389
    , 393 n.9 (5th Cir.
    1991); Nicor Supply Ships Assocs. v. General Motors, 
    876 F.2d 501
    ,
    505 (5th Cir. 1989).
    River Don argues that the deck is not "other property,"
    because McDermott owns the deck as well as the crane, pointing to
    Nicor.     Nicor   Supply   Ships   chartered      its   vessel   to   Digicon.
    Digicon then installed structures and equipment on the vessel for
    use during the term of the charter.          A fire damaged the ship and
    Digicon's equipment.    Nicor and Digicon sued several parties.             
    876 F.2d at 502-03
    .    East River barred Nicor's claim for damage to the
    ship.     Digicon's   claim   for   damage    to   its    equipment    survived
    "[b]ecause these items were not part of the contract under which
    the vessel was sold."       
    Id. at 506
    .      The decision did not turn on
    Digicon's ownership of the damaged equipment.              The object of the
    McDermott-AmClyde contract was the manufacture, design, and sale of
    the crane, and that is the relevant inquiry.             The deck was not the
    object of the sales contract rather the deck is "other property."
    20
    McDermott argues that River Don is liable for damage to the
    crane, because when a plaintiff suffers damage to "other property",
    East River allows recovery of all damages.         East River allows
    recovery for damage to other property, 
    476 U.S. at 875-76
    , but when
    there is damage to other property, recovery for the loss to the
    product itself is still in contract and not tort.      We emphasized
    this point in Nicor.     Speaking of Digicon's recovery in tort, we
    stated
    [h]aving sustained "physical injury to a proprietary
    interest," Digicon may recover for economic loss as well, but
    its recovery for loss of profits is limited to losses
    resulting from its inability to use the "other property" it
    placed on the vessel as a result of the casualty. Digicon is
    not entitled to recover for its loss of profits resulting from
    its inability to use the vessel itself or for its inability to
    use the "other property" if that resulted solely from the
    disability of the vessel itself.
    
    876 F.2d at 506
     (emphasis added).       Therefore, this contention is
    without merit.16     The trial court correctly applied East River to
    allow McDermott's recovery against River Don for damage to the
    deck, but not the crane.
    VII.
    River Don argues that McDermott failed to prove causation. We
    review the evidence in the light most favorable to McDermott.
    Martin v. American Petrofina, Inc., 
    779 F.2d 250
     (5th Cir. 1985).
    The verdict stands if reasonable jurors could reach different
    conclusions.   
    Id.
        We decline to disturb the verdict.
    16
    McDermott also attempts to circumvent East River by
    arguing that the decision is inapplicable to the crane, a product
    that is unreasonably dangerous. The Supreme Court rejected this
    distinction East River. 
    476 U.S. at 869-70
    .
    21
    At trial, McDermott and River Don offered different theories
    of causation.   McDermott argued that the hook was defective, and
    the defect caused the hook to break.    River Don conceded that the
    hook contained flaws but argued that McDermott's use of a right
    hand to left hand cable laid sling arrangement caused the hook to
    break.   That is, McDermott's sling arrangement allowed the slings
    to rotate during the lift.    This rotation caused the slings to
    break first, putting more stress on the hook than it was designed
    to handle.
    McDermott offered the testimony of Dr. Kenneth Packer, an
    expert in foundry practice, welding, and metallurgy.         Packer
    testified that the hook contained a flaw that caused the hook to
    fail; that the hook broke first.    On cross-examination, Dr. Packer
    testified that the hook was flawed when it left River Don's
    foundry.
    River Don argues that Dr. Packer failed to substantiate
    McDermott's theory of causation and could not discount other
    plausible theories, namely that the slings broke first.    River Don
    refers to the fact that the crane, with the flaw, lifted objects
    weighing as much or more than the deck before the accident and in
    fact successfully lifted the deck on one occasion.        Therefore,
    River Don argues that the flaw could not have caused the hook to
    fail.
    We find that McDermott presented sufficient evidence for the
    jury to conclude that hook failure caused the deck to fall.     See
    Brown v. Parker-Hannifin Corp., 
    919 F.2d 308
    , 312 (5th Cir. 1990)
    22
    ("To establish causation, [plaintiff] need not rule out every
    conceivable explanation for the failure . . .").    First, the jury
    could have reasonably inferred that the flaw in the hook caused it
    to break.   The jury could have considered the presence of the flaw
    in earlier lifts in evaluating the likelihood that the hook caused
    the accident, but the presence of the flaw from the beginning does
    not eliminate it as a cause of the accident.    Second, Dr. Packer
    was not the only witness to testify that the hook failed first.
    Steven Whitcomb, a project manager at Hudson Engineering, prepared
    a report on the cause of the accident.   The report was based on a
    computer analysis of the two theories of causation, hook failure
    and sling failure.   He delivered this report in a presentation to
    AmClyde.    At trial, he testified about his report to AmClyde in
    which he concluded that the hook failed first and was the cause of
    the accident.     McDermott also presented eye witnesses to the
    accident who testified that the hook broke first.
    VIII.
    River Don contends that any judgment rendered against it must
    be offset by the $1 million settlement between McDermott and the
    sling defendants under Hernandez v. M/V RAJAAN, 
    841 F.2d 582
     (5th
    Cir. 1988).   Hernandez held that a maritime plaintiff "is entitled
    to receive a full damage award less any amount he recovered in a
    settlement with third-party defendants."     
    Id. at 591
    ; see also
    Constructores Tecnicos v. Sea-Land Serv., Inc., 
    945 F.2d 841
     (5th
    Cir. 1991); Rollins v. Cenac Towing Co., 
    938 F.2d 599
     (5th Cir.
    1991); Myers v. Griffin-Alexander Drilling Co., 
    910 F.2d 1252
     (5th
    23
    Cir. 1990). This rule of setoff "ensure[s] that the plaintiff does
    not   recover    more   than   the    damages   determined   at   trial."
    Constructores, 
    945 F.2d at 850
    .
    McDermott argues that Leger v. Drilling Well Control, Inc.,
    
    592 F.2d 1246
     (5th Cir. 1979), states the law of this circuit and
    does not entitle River Don to a dollar-for-dollar credit.         A recent
    panel of this court suggested that it is unclear whether Leger or
    Hernandez provides the rule of settlement credit in this circuit.
    See Hardy v. Gulf Oil Corp., 
    949 F.2d 826
    , 835 (5th Cir. 1992).
    Judge Brown wrote a concurring opinion to emphasize the need to
    resolve this conflict en banc.       Id. at 836.   However, we think that
    Hernandez is the law of this circuit.      The panel in Myers attempted
    to make this point clear:
    we read Hernandez as adopting the reasoning of the Eleventh
    Circuit opinion in Self v. Great Lakes Dredge & Dock Co., 
    832 F.2d 1540
     (11th Cir. 1987), which declined to follow Leger on
    grounds that Leger was inconsistent with Edmonds v. Compagnie
    Generale Transatlantique, 
    443 U.S. 256
    , 99 S. Ct 2753, 
    61 L. Ed. 2d 521
     (1979).
    Myers, 
    910 F.2d at 1256
    .
    Until the Eleventh Circuit decided Self, Leger was binding
    precedent in that circuit as well as our own.         See Bonner v. City
    of Prichard, 
    661 F.2d 1206
     (11th Cir. 1981) (en banc) (adopting as
    binding precedent all decisions of the former Fifth Circuit handed
    down before the close of business on September 30, 1981).         In Self,
    the Eleventh Circuit decided that Leger's pro rata approach to
    settlement credit was inconsistent with the Supreme Court's opinion
    in Edmonds.     Thus, in Self, the Eleventh Circuit returned to the
    pro tanto or dollar-for-dollar approach to credit set out in our
    24
    earlier opinion in Billiot v. Seward Seacraft, 
    382 F.2d 662
    , 664-65
    (5th Cir. 1967).    We had abandoned Billiot in Leger based on United
    States v. Reliable Transfer Co., 
    421 U.S. 397
     (1975). Today, there
    is no doubt in the Eleventh Circuit that Self overruled Leger.
    Great Lakes Dredge & Dock Co. v. Tanker, 
    957 F.2d 1575
    , 1580
    (1992).
    In Hernandez, we explicitly adopted the Eleventh Circuit's
    reasoning in Self. Therefore, we also overruled Leger as precedent
    in this circuit and returned to the rule in Billiot.         See, e.g.,
    Pruitt v. Levi Strauss & Co., 
    932 F.2d 458
    , 465 (5th Cir. 1991) (a
    panel may ignore the decision of a prior panel in the event of a
    superceding decision by the Supreme Court).         Since Hernandez, we
    have applied its dollar-for-dollar approach.         See Constructores,
    
    945 F.2d 841
    ; Rollins, 
    938 F.2d 599
    ; Myers, 
    910 F.2d 1252
    .             Two
    recent panels cited Leger, suggesting that it remains good law.
    See Empresa Lineas Maritimas v. Schichau-Unterweser, 
    955 F.2d 368
    ,
    374 (5th Cir. 1992); Teal v. Eagle Fleet, Inc., 
    933 F.2d 341
    , 346
    (5th Cir. 1991).     However, they did not apply the Leger approach.
    We continue to apply Hernandez in calculating settlement credit.
    The district court refused to allow any set-off, concluding
    that McDermott would not be paid for more than its injury, because
    East River left it otherwise uncompensated for the damage to the
    crane.    This is true, but not relevant.     The jury determined that
    McDermott's total loss for the damage to the deck was $2.1 million,
    $1.47 million after a reduction of 30% for the responsibility
    attributed   to    McDermott/sling    defendants.    $1.47   million   is
    25
    McDermott's "full damage award."     It cannot recover more.   We must
    then deduct the Hernandez credit.
    This requires us to address McDermott's post-trial revelation
    that half of the settlement was allocated to the crane and half to
    the deck.   McDermott urges that because River Don is only liable
    for the deck, it is only entitled to credit for that part of the
    settlement covering damage to the deck.    River Don urges us not to
    consider this allocation, because it was made after trial, it was
    not a party to the agreement and the settlement is not in the
    record.
    We see little reason to give effect to this allocation and
    strong reasons not to do so.       Where defendants are potentially
    liable for the same damages and less than all defendants settle,
    uncertainty of the effect upon the nonsettling defendants does
    little to facilitate settlement and may well frustrate the single
    recovery rule itself.   A plaintiff should not be able to wait for
    the jury's verdict to allocate the settlement in a way that reduces
    the remaining defendants' credit. See King Cotton, Ltd. v. Powers,
    
    409 S.E.2d 67
    , 70 (Ga. Ct. App. 1991); see also Alexander v.
    Seaquest Inc., 
    575 So. 2d 765
    , 766 (Fla. Dist. Ct. App. 1991)
    (apportionment of settlement comes too late if done after jury
    verdict, because nonsettling tortfeasors lose the right to settle);
    Dionese v. City of West Palm Beach, 
    500 So. 2d 1347
    , 1351 (Fla.
    1987) (disclosure of settlement's terms may lead the non-settling
    defendant to settle instead of going to trial).
    26
    Rejecting McDermott's allocation of one-half to the crane and
    one-half to the deck leaves two options.                We    could apportion the
    settlement ourselves, or use the entire sum in calculating any
    credit due River Don.          We decline the first option.             See Lendvest
    Mortgage, Inc. v. De Armond, 
    123 B.R. 623
    , 624-25 (Bankr. N.D. Cal.
    1991) (rather than attempt to allocate a settlement, a court should
    offset the entire amount).            There is no evidence in the record
    concerning McDermott's damages to the crane. A remand to the trial
    court offers no solution.
    Including    the      full   amount      of   McDermott's      settlement     in
    calculating any credit due River Don is the best solution.                          See
    U.S. Indus., Inc. v. Touche Ross & Co., 
    854 F.2d 1223
    , 1262 (10th
    Cir.    1988)    (where       nonsettling       defendants    are     not   privy    to
    settlement negotiations, burden shifts to plaintiff to show that
    settlement did not represent common damages); see also Hess Oil
    Virgin Islands Corp. v. UOP, Inc., 
    861 F.2d 1197
     (10th Cir. 1988)
    ("If [plaintiff] wanted to have any particular application of its
    settlement      with    the     settling     defendants      toward     [nonsettling
    defendant's] liability, it should have specifically stipulated in
    the    settlement      documents     what       allocations    of     damages   were
    applicable to each cause of action."); but see Force v. Director,
    OWCP, Dept. of Labor, 
    938 F.2d 981
    , 985 (9th Cir. 1991) (defendant-
    employer bears burden of proving settlement allocation, because the
    LHWCA's   policy       "of    compensating      employees    for    their   injuries
    requires that 'all doubtful questions of fact be resolved in favor
    of the injured employee'").
    27
    McDermott had a claim against the sling defendants for damage
    to the crane and the $1 million payment obtained a release of that
    claim as well as the claim for damage to the deck.                       It was
    McDermott's burden to demonstrate that its jury award did not
    exceed its right to full compensation for a particular injury.
    McDermott has not met its burden of demonstrating that the proceeds
    of the settlement with the sling defendants were for damage to the
    crane and not the deck.     We hold that the entire $1 million should
    be included in calculating any credit due River Don.                    See U.S.
    Industries, 
    854 F.2d at 1262-63
    ; Hess Oil, 
    861 F.2d at 1209
    ;
    Lendvest Mortgage, 
    123 B.R. at 625
    .      Alexander, 575 So. 2d at 765;
    King Cotton, 
    409 S.E.2d at 70
    ; Dionese, 500 So.2d at 1349.17
    Applying Hernandez, McDermott's full damage award is $1.47
    million   ($2.1   million   jury   verdict      less   30%    attributed      to
    McDermott/sling   defendants).      We   then    deduct      the   $1    million
    received in settlement to reach $470,000.         By the jury's finding,
    River Don is liable to McDermott for its portion of McDermott's
    loss (38% of $2.1 million or $798,000).      However, McDermott is only
    entitled to recover an additional $470,000 from any defendant.                We
    therefore modify the judgment against River Don for $798,000, and
    enter judgment against River Don and in favor of McDermott in the
    amount of $470,000.
    17
    Our conclusion that River Don is entitled to credit for
    McDermott's settlement makes consideration of River Don's
    alternative argument for a new trial based on evidentiary rulings
    unnecessary.
    28
    It does not follow that McDermott's decision at trial to
    assume the fault of the sling defendants was unwise.        To the
    contrary, this tactical move made more difficult any effort of
    River Don and AmClyde to lay any fault on the absent sling
    defendants.       But for this move the jury may well have been
    persuaded that the sling defendants were liable for more than 30%
    and the other defendants, including River Don for less.     Seen in
    the light of these realities of trial, this result makes sense.
    IX.
    McDermott claims pre-judgment interest.    The jury awarded no
    interest.      McDermott does not challenge the jury instruction,18
    which tracked the law of this circuit.19 See Orduna S.A. v. Zen-Noh
    18
    The jury was charged as follows:
    In admiralty cases, the award of pre-judgment interest from
    the date of the loss is the rule rather than the exception.
    The decision to deny pre-judgment interest must be based on
    the existence of peculiar circumstances because pre-judgment
    interest is awarded as a compensation for a wrong done. It
    is your responsibility to determine whether to award
    McDermott, Inc. pre-judgment interest. If you determine
    that the - that the Plaintiff is entitled to pre-judgment
    interest; that is, interest from the date of the loss until
    the date you render your verdict, you must determine the
    rate at which the interest will be calculated. The
    circumstances which may justify denial of an award for pre-
    judgment interest are as follows: A genuine dispute over a
    good faith claim exists in a mutual fault situation - mutual
    fault setting; the damages awarded are substantially less
    than the amount claimed by the Plaintiff; the Plaintiff's
    contributory negligence is to such a magnitude as to make
    and award of pre-judgment interest inequitable.
    19
    McDermott refers us to Texas, New York, and Louisiana law;
    however, pre-judgment interest on a maritime tort claim is
    governed by general maritime law. Wyatt v. Penrod Drilling Co.,
    
    735 F.2d 951
    , 955 (5th Cir. 1984); Robinson v. Pocahontas, Inc.,
    
    477 F.2d 1048
    , 1053 (5th Cir. 1973).
    29
    Grain Corp., 
    913 F.2d 1149
    , 1157 (5th Cir. 1990) (noting the
    reasons for denying pre-judgment interest).      Rather, McDermott
    argues that the circumstances justifying denial of pre-judgment
    interest were not present in this case.   We disagree.
    The jury could have found there was a genuine dispute over a
    good faith claim in a mutual fault setting.        "Our cases have
    consistently upheld denials of prejudgment interest in cases of
    apportioned fault."   Inland Oil and Transport Co. v. Ark-White
    Towing Co., 
    696 F.2d 321
    , 328 (5th Cir. 1983).    In this case, the
    jury assessed responsibility 32% to AmClyde, 38% to River Don, and
    30% to McDermott/sling defendants.   See 
    id.
     (upholding a denial of
    pre-judgment interest where the plaintiff was found to be 25% at
    fault).
    X.
    Finally, McDermott asks us to correct the judgment to show
    that the jury apportioned causation and not fault.     The judgment
    paraphrased the jury verdict as follows:     "thirty percent (30%)
    fault allocated to plaintiff, McDermott, Inc., thirty-two percent
    (32%) fault allocated to AmClyde, a Unit of AMCA International
    Corporation, and thirty-eight percent (38%) fault allocated to
    River Don Castings, Ltd."   (emphasis added).    McDermott contends
    that the judgment incorrectly paraphrased the jury's verdict which
    allocated causation and not fault.   Interrogatory #5 asked:
    You have been instructed that the failure of the sling at a
    load less than its rated minimum breaking strength is a cause
    of damage to the deck and crane. If you have also answered
    interrogatories 1 and 2 "yes," please state what proportion or
    percentage   of  plaintiff's    damages   you  find   from   a
    30
    preponderance of the evidence to have been legally caused by
    the fault of the respective parties?
    We agree that in answering this interrogatory the jury determined
    the percentage of injury caused by each defendant.
    REVERSED in part and AFFIRMED as modified in part.
    31