-
United States Court of Appeals Fifth Circuit F I L E D In the August 4, 2003 United States Court of Appeals Charles R. Fulbruge III for the Fifth Circuit Clerk _______________ m 02-30696 Summary Calendar _______________ CABLEGUARD SYSTEMS, INC., UNITED STATES OF AMERICA FOR THE USE OF, Plaintiff-Appellee, VERSUS MID-CONTINENT CASUALTY COMPANY; ET AL., Defendants, MID-CONTINENT CASUALTY COMPANY; PETE VICARI GENERAL CONTRACTOR, INC., Defendants-Appellants _________________________ Appeal from the United States District Court for the Eastern District of Louisiana m 99-CV-2064-A _________________________ Before JOLLY, HIGGINBOTHAM, and SMITH, wiring and the fire pull stations. Cableguard Circuit Judges. again sought payment, but Vicari refused. In November 1998, Cableguard therefore PER CURIAM:* submitted written notice to Vicari of its intent to collect the contractual amount from the Pete Vicari General Contractor Inc. (“Vica- payment bond under the Miller Act, 40 U.S.C. ri”), and its surety, Mid-Continent Casualty § 270b(a). Cableguard then sued Vicari and Company (“Mid-Continent”), appeal a Mid-Continent. judgment for Cableguard Systems, Inc. (“Cableguard”), in this Miller Act suit. The parties disputed one key factual ques- Finding no error, we affirm. tion, namely, whether Cableguard provided timely notice of its claim to Vicari. The Miller I. Act requires a supplier to give written notice In 1997, Vicari became the general to the general contractor “within ninety days contractor on a project to construct a building from the date on which [the supplier] did or for the United States Postal Service. As performed the last of the labor or furnished or required by the Miller Act, 40 U.S.C. § 270a- supplied the last of the material[.]” 40 U.S.C. (a)(2), Vicari (through its surety, Mid- § 270b(a); see generally J.D. Fields & Co. v. Continent) posted a payment bond to protect Gottfried Corp.,
272 F.3d 692, 696 (5th Cir. its subcontractors and suppliers of labor and 2001). Cableguard’s notice was timely if its material. October 1998 work is characterized as “labor,” but not if it is characterized as Vicari subcontracted the electrical work to “repairs.” See United States ex rel. Ga. Phoenix Electrical, Inc. (“Phoenix”), which Supply Co. v. United States Fid. & Guar. Co., contracted with Cableguard, doing business as
656 F.2d 993, 995-96 (5th Cir. Unit B Sept. Dictograph Security (“Dictograph”), for the 1981). supply and installation of a fire alarm and se- curity system. While Cableguard was The district court denied the parties’ performing its obligations in early 1998, a motions for summary judgment on this factual modification to the contract required it to question and submitted the case to a jury. The install two extra fire pull stations. Cableguard jury found that the October 1998 work was could not do so, however, because of “labor” under the Miller Act and, hence, that improper wiring in the post office. Cableguard had provided timely notice. The court then entered judgment for $51,261.41, Cableguard submitted a final bill to Vicari the stipulated amount of contractual damages, in July 1998 but did not receive payment. In plus pre-judgment interest of $13,290.77. October 1998, Cableguard removed the improper wiring and installed the correct On appeal, Vicari and Mid-Continent do not challenge the finding that the work was “labor,”1 but argue that several alleged proce- * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be pub- 1 lished and is not precedent except under the limited Actually, they raise this issue in their reply circumstances set forth in 5TH CIR. R. 47.5.4. (continued...) 2 dural and evidentiary errors require reversal. capacity to sue under Louisiana law. II. III. Vicari challenges Cableguard’s capacity to Vicari appeals the decision to admit into ev- sue. The district court entered summary judg- idence a work order for the October 1998 ment for Cableguard on this question. work. Vicari argues that the work order, Reviewing the judgment de novo, Hollowell v. which Cableguard offered to prove that it had Orleans Reg’l Hosp. LLC,
217 F.3d 379, 382 performed work within the Miller Act’s ninety- (5th Cir. 2000), and applying Louisiana day period, was inadmissible hearsay. The corporate law, FED. R. CIV. P. 17(b), we court admitted the work order under the affirm. business-records exception to the hearsay rule. FED. R. EVID. 803(6). We review this Vicari contends that Cableguard lacks capa- evidentiary ruling for abuse of discretion, city to sue for two reasons. First, Phoenix United States v. Wells,
262 F.3d 455, 459 (5th contracted with Dictograph, not Cableguard, Cir. 2001), and find no abuse. to install the fire alarm and security systems. Second, that contract prohibits assignment Rule 803(6) creates an exception to the without Phoenix’s written consent. Vicari hearsay rule for a record “if kept in the course concludes that without a valid contract of a regularly conducted business activity, and between Cableguard and Phoenix, Cableguard if it was the regular practice of that business cannot recover against the payment bond. activity to make the . . . record . . ., all as shown by the testimony of the custodian or Vicari mistakenly assumes, however, that other qualified witness[.]” FED. R. EVID. Cableguard and Dictograph are different enti- 803(6). Rea and Frank Soehnlein, Cable- ties. In fact, Edgar Rea, Cableguard’s guard’s general manager, competently testified president, attested that Dictograph is merely to these foundational requirements. In an assumed trade name of Cableguard. Under particular, they explained that Cableguard Louisiana law, “a corporation may enter into a installs fire alarm and security systems in the binding contract under an assumed name ab- course of its regular business and regularly sent any fraud or deceit.” Pro Source uses work orders to instruct its employees and Roofing, Inc., v. Boucher,
822 So. 2d 881, bill its customers. Rea also identified the no- 884 n.2 (La. App. 2d Cir. 2002). Vicari tation “FO” on the work order as the initials produced no evidence to dispute the identity of and handwriting of Frank Ohlinger, the Dictograph and Cableguard and has not employee who installed the fire pull stations.2 alleged fraud or deceit. Thus, Cableguard has Vicari nevertheless argues that “the source of information or the method or circumstances (...continued) of preparation [of the work order] indicate brief, provoking a motion from Cableguard, to lack of trustworthiness.” FED. R. EVID. strike the reply brief. We do not consider issues 803(6); Wells,
262 F.3d at 459-60(“Whether not raised in an appellant’s opening brief, Peavy v. WFAA-TV, Inc.,
221 F.3d 158, 179 (5th Cir. 2 2000), so we will not address this issue, and we Cableguard could not call Ohlinger as a wit- therefore deny Cableguard’s motion as moot. ness, because he died before trial. 3 evidence is admissible under Rule 803(6) is IV. chiefly a matter of trustworthiness.”) Vicari argues that the district court erred by (quotation marks omitted). First, Vicari refusing to give a proposed jury instruction.4 contends that Cableguard prepared the work We review the court’s refusal to give the in- order in anticipation of this lawsuit, not as a struction for abuse of discretion, which we will genuine business record. The record, find only if the jury instruction as a whole is however, contains no evidence to support this not a correct statement of the law and does assertion. Second, Vicari argues that Ohlinger not clearly instruct the jury on the legal “may” not have performed the work in principles applicable to the factual issues October 1998 and that he “possibly” forged before them. Cozzo v. Tangipahoa Parish the work order. Again, the record does not Council-President Gov’t,
279 F.3d 273, 293 support this rank speculation, as Vicari’s use (5th Cir. 2002). There is no abuse of of conditional verb tenses and adjectives discretion, because the proposed instruction reveals. was not relevant to the factual dispute before the jury. Third, Vicari notes that the local postmaster did not sign the work order on the customer Vicari asked the court to instruct the jury line. Yet, Rea’s uncontroverted testimony that a supplier to a subcontractor cannot explains this supposed discrepancy. extend the ninety-day notice period by Cableguard used work orders to instruct its furnishing labor or material directly to the employees on a particular assignment and to general contractor. As a statement of law, this bill its customers. On a fixed-price contract, instruction is certainly correct. See United however, the customer already had approved States ex rel. Harris Paint Co. v. Seaboard the job and the price; thus, Cableguard did not Sur. Co.,
437 F.2d 37(5th Cir. 1971). But the need the customer’s signature on the work or- instruction is as irrelevant to this case as it is der. Because the post office project was a correct. The key factual dispute at trial was fixed-price contract, Cableguard did not need whether Cableguard performed “labor” or the postmaster’s signature. And, in any event, “repairs” in October 1998 (which in turn Phoenix, not the postmaster, was Cableguard’s determined whether it gave timely notice to customer on the contract.3 Vicari). However characterized, though, there is no factual dispute that Cableguard 3 performed the work pursuant to its contract Vicari also challenges what it calls the court’s decision to exclude evidence that Vicari paid Phoenix. At a pretrial conference, the court excluded the evidence as irrelevant under the Miller 3 (...continued) Act. After Cableguard presented its case, the court entire issue bewildering, especially because Vicari reversed itself and ruled that Vicari could offer does not identify, on appeal, what other evidence or evidence of payment from Vicari to Phoenix within testimony it would have introduced. unspecified “strict guidelines.” Peter Vicari then 4 testified that Vicari had paid Phoenix. Vicari’s Vicari actually appeals the court’s refusal to counsel also reminded the jury of this testimony in give eight proposed instructions, but we treat its closing arguments. In other words, the court did arguments on seven of these instructions as waived not exclude the evidence. We therefore find the for failure to brief adequately on appeal. FED. R. (continued...) APP. P. 28(a)(9)(A). 4 with Phoenix, not for Vicari. The court Real Support Group, Inc.,
950 F.2d 284, 287- therefore did not err. 88 (5th Cir. 1992). In Louisiana, interest is recoverable on a contractual debt from the V. time the debt becomes due, unless otherwise Vicari appeals the decision to use a general stipulated. Corbello v. Iowa Prod., No. 2002- verdict. The form asked simply whether Ca- C-0826,
2003 La. LEXIS 613, at *50 (La. bleguard had provided labor or materials with- Feb. 25, 2003), rehearing granted in part on in ninety days of its written notice to Vicari. other grounds,
2003 La. LEXIS 1913(La. Vicari argues that the court instead should June 20, 2003).7 The Phoenix-Cableguard have used Vicari’s proposed forty special in- contract therefore determines the assessment terrogatories. “The decision to use a general of pre-judgment interest against the payment verdict rather than a special verdict . . . is a bond. Lochridge-Priest,
950 F.2d at 289. matter of discretion” to which we give Under that contract, Phoenix’s debt to Cable- especially high deference. Martin v. Texaco, guard became due ten days after Cableguard Inc.,
726 F.2d 207, 217 (5th Cir. 1984).5 The completed performance. The jury found that general verdict form accurately stated the Cableguard completed performance in October determinative factual question for the jury, 1998. Thus, the court rightly allowed pre- whereas the proposed forty special judgment interest from that date.8 interrogatories are confusing, duplicative, and often irrelevant. The court did not abuse its AFFIRMED. discretion by refusing to use the proposed interrogatories. VI. Finally, Vicari contends that the court erred by awarding Cableguard pre-judgment interest.6 Reviewing the award for abuse of discretion, Reyes-Mata v. IBP, Inc.,
299 F.3d 504, 507 (5th Cir. 2002), we affirm. Louisiana law applies to a motion for pre- 7 judgment interest under the Miller Act. Unit- See also Schiro-Del Bianco Enters., Inc. v. ed States ex rel. Lochridge-Priest, Inc. v. Con- NSL, Inc.,
765 So. 2d 1087, 1092 (La. App. 4th Cir), writ denied,
774 So. 2d 146(2000) (“In an action on a building contract, interest is recover- able from the time the debt becomes due unless 5 “[T]here ought never be a reversal for use or otherwise stipulated.”). nonuse of special verdicts.” 9A CHARLES A. 8 WRIGHT & ARTHUR R. MILLER, FEDERAL PRAC- Vicari relies on Roques v. Alfonso, 399 So. 2d TICE AND PROCEDURE § 2505, at 165 (2d ed. 1294, 1296 (La. App. 4th Cir. 1981), holding that 1995). interest on “[a]n unliquidated claim is due from the time it becomes ascertainable.” In Roques, 6 Vicari argues that Cableguard is not entitled however, the parties disputed both the amount of to any pre-judgment interest, but does not dispute the debt and a potential offset. This cases involves the court’s calculation of that interest. no such disputes. 5
Document Info
Docket Number: M 02-30696
Citation Numbers: 73 F. App'x 28
Judges: Higginbotham, Jolly, Per Curiam, Smith
Filed Date: 8/4/2003
Precedential Status: Non-Precedential
Modified Date: 10/18/2024