United States Ex Rel. Shannon v. Federal Insurance , 251 F. App'x 269 ( 2007 )


Menu:
  •                                                      United States Court of Appeals
    Fifth Circuit
    F I L E D
    UNITED STATES COURT OF APPEALS
    September 4, 2007
    FOR THE FIFTH CIRCUIT
    Charles R. Fulbruge III
    Clerk
    06-60906
    Summary Calendar
    UNITED STATES OF AMERICA
    for the use and benefit of ROY SHANNON,
    Plaintiff-Appellant,
    v.
    FEDERAL INSURANCE COMPANY; FIDELITY & DEPOSIT COMPANY OF
    MARYLAND; WHITESELL-GREEN INC., Individually and jointly with
    W.G. Yates & Sons Construction Co., a Mississippi Corporation;
    W.G. YATES & SONS CONSTRUCTION CO., Individually and jointly
    with Whitesell-Green Inc., a Florida Corporation,
    Defendants-Appellees.
    Appeal from the United States District Court
    for the Southern District of Mississippi, Gulfport
    1:05-CV-54
    Before HIGGINBOTHAM, BARKSDALE, and BENAVIDES, Circuit Judges.
    PER CURIAM:*
    Plaintiff Roy Shannon (“Shannon”) was employed as a project
    manager at Whitesell-Green, Inc. (“WGI”). WGI entered into a joint
    venture (“Joint Venture”) with another company, W.G. Yates & Sons
    *
    Pursuant to 5th Cir. R. 47.5, the Court has determined that
    this opinion should not be published and is not precedent except
    under the limited circumstances set forth in 5th Cir. R. 47.5.4.
    Construction Company (“Yates”), so that they could pool their
    resources and bid on construction contracts at Keesler Air Force
    Base in Biloxi, Mississippi (“Keesler”).         Shannon assumed the
    position of project manager for the Joint Venture.      He was put on
    the Joint Venture’s payroll in October of 1998.      Shannon remained
    the project manager of the Joint Venture at Keesler until February
    2004, when he was terminated.
    Shannon’s contract with the Joint Venture was unwritten, and
    though the parties to this case all agree that a contract existed,
    they disagree about the terms.        It is undisputed that Shannon’s
    position carried a salary of $2,000 per week, plus an annual
    Christmas bonus of at least $50,000.       It is also undisputed that
    Shannon received this sum for approximately five and a half years.
    However, Shannon claims that he was entitled to receive additional
    compensation of three types. First, he claims that he was entitled
    to one-half the profits above and beyond the originally anticipated
    profits, if any, earned by the Joint Venture on the first project.
    Second, he says that once the Joint Venture began to bid on
    additional contracts, there was an unwritten agreement that he
    would receive one percent of the contract amount of each subsequent
    contract, regardless of profit.   Third, Shannon says that an SUV,
    which was purchased by the company but used exclusively by him, was
    his to keep, and that the Joint Venture breached its unwritten
    agreement by repossessing the vehicle some six months after his
    termination.   Having not received the compensation to which he
    2
    believed he was entitled, Shannon filed this lawsuit, asserting
    claims   for    breach   of   contract,   quantum   meruit,   and   wrongful
    discharge.
    Shannon also included a federal claim under the Miller Act, 40
    U.S.C. §§ 3131, 3133, which explains how an otherwise ordinary
    contract case, raising several questions of Mississippi state law,
    ended up in federal court.          Under the Miller Act, before any
    contract of more than $100,000 for the construction, alteration, or
    repair of any public building or public work of the United States
    is awarded to any person, such person is required to furnish to the
    United States both a performance bond and a payment bond.                The
    performance bond guarantees federal taxes on wages paid by the
    contractor to his or her employees.         The payment bond is “for the
    protection of all persons supplying labor and material in carrying
    out the work provided for in the contract for the use of each
    person.”     40 U.S.C. § 3131(b)(2).      The purpose of the Act is “to
    protect those whose labor and materials go into public projects,”
    MacEvoy Co. v. United States, 
    322 U.S. 102
    , 107 (1944) (citations
    omitted).      On this basis, Shannon brought a federal claim against
    the sureties charged with protection of the payment bond.
    The district court granted summary judgment for the defendants
    on all four of Shannon’s claims, and Shannon appealed.              We review
    motions for summary judgment de novo, applying the same standards
    as the district court.         FED R. CIV. P. 56.     Summary judgment is
    3
    inappropriate whenever a genuine issue of material fact exists.   A
    genuine issue of material fact exists when, in the context of the
    entire record, a reasonable fact-finder could return a verdict for
    the non-movant.    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    ,
    248–49 (1986).    All evidence must be construed in the light most
    favorable to the party opposing summary judgment. Matsushita Elec.
    Indus. Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587–88 (1986)
    (citations omitted).
    1.   Breach of Contract
    The district court granted summary judgment on Shannon’s
    breach of contract claim after finding that it was barred by the
    statute of limitations. There is no dispute that the relevant
    limitations period for breach of an unwritten contract is one year
    from the time the cause of action accrued.    Miss. Code § 15-1-29
    (1972).   The only dispute is the date of accrual.   In Mississippi,
    a cause of action accrues as soon as the cause of action exists.
    See, e.g., Greenlee v. Mitchell, 
    607 So. 2d 97
    , 110 (Miss. 1992).
    In breach of contract cases, that is the time “when the breach, not
    the injury, accrues,” or, in other words, “at the time of the
    breach regardless of when damages resulting from the breach occur.”
    First Trust Nat’l Ass’n v. First Nat’l Bank of Commerce, 
    220 F.3d 331
    , 334–35 (5th Cir. 2000).   Because the plaintiff, in effect, is
    alleging two different breaches, one for the first project and one
    for all subsequent projects, we treat them separately.
    4
    As to the first project, Shannon claims that he was entitled
    to one half of the profits above and beyond $2.5 million, which was
    the original estimated profit.        As of September 29, 2003, Shannon
    knew that the operation would be more profitable than originally
    anticipated, and thus that he was entitled to some gain.            However,
    at that point Shannon says he could not have known exactly how
    profitable the project would be, and thus could not know exactly
    how much money he would receive.          Instead, he argues that the
    accrual date is the date the project was physically completed,
    which occurred some time in December of 2004.          Shannon did not file
    his lawsuit until February, 2, 2005.
    We find Shannon’s argument unavailing.          First, the foregoing
    case law makes plain that the date of breach, not the date of
    injury (or, in Shannon’s case, the date on which the full extent of
    the injury was finally calculable) is the controlling date for
    accrual purposes. Shannon has presented no case law to support the
    proposition that a party must know to a mathematical certainty the
    amount of recovery to which he is entitled.          In fact, the analogous
    case law in Mississippi suggests otherwise.          See, e.g., Jackson v.
    State Farm Mut. Auto. Insur. Co., 
    880 So. 2d 336
    , 341 (Miss. 2004)
    (holding, in uninsured motorist context, that action accrues once
    someone “knows, or reasonably should know, that the damages he or
    she   claims   to   have   suffered   exceed   the   limits   of   insurance
    available to the alleged tortfeasor”).         Second, we must note that
    5
    Shannon drastically overstates his uncertainty as of September
    2003.   Shannon stated in his response to an interrogatory that on
    September 29, 2003, he knew “as a fact [that] 99% of the job costs
    were complete,” because he “was provided a written copy of the
    profits from Yates.”       At that time, then, Shannon had nearly
    perfect   knowledge   of   the   amount   of   money    to    which   he   was
    purportedly entitled, and he further knew that so long as the
    defendants had not paid him his due, they were in breach of the
    unwritten contract.    In fact, he stated in both his complaint and
    his deposition that he had made repeated demands on the Joint
    Venture to pay him what he was owed on the first project since
    August of 2000, or roughly four and a half years before he filed
    this lawsuit. In sum, the record clearly indicates that any breach
    as to the first project occurred more than a year before the suit
    was filed, and that Shannon knew as much.             Summary judgment was
    therefore proper.
    Summary   judgment    was   also   proper   as    to    the   additional
    projects.   Shannon alleges that he was to receive one percent of
    the contract price of each additional project that he secured for
    the Joint Venture. Under the terms of the agreement, Shannon would
    be entitled to payment once the contracts were awarded.             The Joint
    Venture won several additional contracts, the last of which came on
    December 29, 2003.     Any breach as to these additional projects
    therefore occurred more than a year before this suit was filed, and
    6
    summary judgment was proper.1
    2.   The Miller Act
    As we have said, the Miller Act protects those “whose labor
    and materials go into public projects.”           MacEvoy Co. v. United
    States, 
    322 U.S. 102
    , 107 (1944) (citations omitted).          Shannon’s
    claim under the Act turns on whether or not he performed “labor” as
    that term is used in the statute.       The district court found that he
    did not, and we agree.      Shannon concedes that any duties he was
    required to perform as project manager are irrelevant for purposes
    of the Miller Act because he was already compensated for them.         The
    Miller Act only affords him relief if he performed additional labor
    for which he was not compensated.          Shannon alleges that he did
    perform such additional duties, which he describes as “negotiating
    new contracts, determining bid amounts and change orders, preparing
    bid   proposals,   negotiating   and    signing   new   subcontracts   and
    purchase orders.”   He also claims that his labor included living on
    the job site, cleaning the office and bathrooms, and other such
    tasks.
    The term “labor” in the Miller Act was primarily designed to
    encompass physical or manual labor.          See United States ex rel.
    Constructors, Inc. v. Gulf Ins. Co, 
    313 F. Supp. 2d 593
    , 597 (E.D.
    1
    Shannon’s claim for equitable estoppel as to the statute of
    limitations is similarly unavailing. The record does not reveal
    any representations on the part of the Joint Venture that could
    reasonably have induced Shannon’s reliance to his own detriment.
    
    7 Va. 2004
    ) (holding that “[p]aying invoices, reviewing proposals,
    and supervising hiring are clerical or administrative tasks which,
    even if performed at the job site, do not involve the physical toil
    or manual work necessary to bring them within the scope of the
    Miller Act”); see also United States for the Use of Barber-Colman
    Co. v. United States Fid. & Guar. Co., 
    19 F.3d 1431
    (4th Cir. 1994)
    (unpublished opinion) (noting that “labor” includes “physical toil,
    but not work by a professional, such as an architect or engineer”
    (internal quotation omitted)); United States ex rel. Olson v. W.H.
    Cates Constr. Co., Inc., 
    972 F.2d 987
    , 990 (8th Cir. 1992) (“[O]nly
    certain professional supervisory work is covered by the Miller Act,
    namely,   skilled     professional       work   which        involves     actual
    superintending,     supervision,   or    inspection     at    the   job   site.”
    (internal quotation omitted)); Glassell-Taylor Co. v. Magnolia
    Petroleum Co., 
    153 F.2d 527
    , 529–30 (5th Cir. 1946) (discussing
    purpose of Act and surveying cases of qualifying labor, all of
    which are manual or physical in nature). The additional labor that
    Shannon claims to have provided does not match this description.
    Moreover, any potentially qualifying “supervisory” work that he
    might have provided at the site fell under his role as a project
    manager, and he has already been compensated for it.                      Summary
    judgment was therefore proper as to Shannon’s Miller Act claim.
    3.   Quantum Meruit
    Shannon proffers an alternative theory under quantum meruit,
    8
    in the event that a contract is not found to exist.                      Because the
    district court found, by the parties’ own admissions, that an
    enforceable agreement did exist, it denied any recovery under
    quantum meruit, noting that under Mississippi law, “[w]here there
    is a contract, parties may not abandon same and resort to quantum
    meruit.” Sentinel Indus. Contracting Corp. v. Kimmins Indus. Serv.
    Corp.,      
    743 So. 2d 954
    ,    970    (Miss.    1990)    (internal        quotation
    omitted).         On appeal, Shannon argues that the parties do not
    concede that a contract exists.                His argument seems to be that the
    purported         agreements      for    additional       compensation        were   new
    contracts, that the defendants deny their existence, and therefore
    that   recovery       is   available      in    quantum    meruit.       We    are   not
    persuaded.         Clearly the parties all admit that an enforceable
    contract existed; they simply dispute some of its terms.                         On the
    basis of that contract, Shannon provided services to the Joint
    Venture for over five years, during which time he collected payment
    in excess of $2,000 per week, plus an annual bonus.                  He now claims
    that, under the terms of that contract, was entitled to more.                        That
    is a contract claim, plain and simple, and had Shannon filed it in
    time, it would have been actionable.                   Having failed to do so,
    however, he cannot now sidestep that agreement and pursue a theory
    of quantum meruit.         Summary judgment was proper as to this claim.
    4.    Wrongful Discharge
    Finally, Shannon includes a claim for wrongful discharge. The
    9
    district court dismissed this claim on the basis that Shannon was
    an “at will” employee, and thus cannot bring a suit for wrongful
    discharge under Mississippi law. See Levens v. Campbell, 
    733 So. 2d 753
    , 760 (Miss. 1999) (“[A]bsent an employment contract expressly
    providing to the contrary, an employee may be discharged at the
    employer’s will for good reason, bad reason, or no reason at all,
    excepting reasons only declared legally impermissible.”); see also
    Perry v. Sears, Roebuck & Co., 
    508 So. 2d 1086
    , 1088 (Miss. 1987)
    (explaining longstanding rule that “at will” employment is inferred
    where there is no contract of employment or contract does not
    specify definite term of employment).      Shannon’s contract of
    employment did not expressly specify a definite term, rendering him
    an “at will” employee.   Thus, the district court properly granted
    summary judgment as to this claim.
    CONCLUSION
    For the reasons stated herein, the district court’s grant of
    summary judgment is AFFIRMED.
    10