L & A Contracting Co. v. Southern Concrete Services, Inc. , 17 F.3d 106 ( 1994 )


Menu:
  •                      United States Court of Appeals,
    Fifth Circuit.
    No. 93-7171.
    L & A CONTRACTING COMPANY, Plaintiff-Counter Defendant-Appellee,
    v.
    SOUTHERN CONCRETE SERVICES, INC., Defendant-Counter Claimant-
    Appellant,
    and
    Fidelity & Deposit Company of Maryland, Defendant-Appellant.
    March 25, 1994.
    Appeal from the United States District Court for the Southern
    District of Mississippi.
    Before WISDOM, HIGGINBOTHAM, and JONES, Circuit Judges.
    WISDOM, Circuit Judge:
    This case turns on the legal distinction between "breach" and
    "default".
    A primary contractor sued its bonded subcontractor and the
    bonding agent for damages arising from the subcontractor's breach
    of the subcontract.      The district court held the subcontractor and
    surety liable to the contractor. On this appeal, the subcontractor
    and surety challenge the district court's judgment.            We AFFIRM the
    district court's judgment against the subcontractor. We VACATE the
    judgment against the surety and RENDER judgment in the surety's
    favor.
    I. BACKGROUND
    L & A Construction Company ("L & A"), the general contractor
    on    a   project   to   build     a   bridge   in   Apalachicola,   Florida,
    1
    subcontracted   with   Southern   Concrete   Services   ("Southern")   to
    provide concrete for the project.         Southern, as required by the
    subcontract, obtained a performance bond from Fidelity & Deposit
    Company of Maryland ("F & D").     Southern began supplying concrete
    to L & A in early 1987.
    We need not chronicle the ensuing deterioration in business
    relations between L & A and Southern.      It suffices for this opinion
    to say that Southern failed to provide sufficient concrete to L &
    A in a timely manner and breached the subcontract in numerous other
    particulars.    L & A repeatedly complained to Southern about its
    slow delivery rates and the poor quality of the concrete Southern
    supplied.   On May 29, 1987, L & A sent Southern a letter stating
    that Southern had breached the contract and giving Southern five
    days to cure the deficiencies in its performance.         L & A sent a
    copy of the letter to F & D.       Southern's performance apparently
    improved after the May 29 letter.       In response to a routine inquiry
    from F & D on August 3, 1987, L & A stated that Southern was
    performing satisfactorily.
    Southern's improved performance did not last long, and L & A
    soon resumed its periodic complaints.        On January 12, 1988, L & A
    sent another letter to Southern and F & D in which it requested
    "that the Bonding Company take the necessary steps to fulfill this
    contract to prevent any further delays and costs to L & A".        F & D
    did not respond to the letter and took no action.              Southern
    completed its obligations under the subcontract on May 27, 1988.
    At no time did L & A refuse to accept Southern's performance.
    2
    L & A sued Southern and F & D for breach of contract in
    Mississippi     state    court   on     August   19,   1988.    The   defendants
    promptly removed the case to the United States District Court for
    the Southern District of Mississippi on the basis of diversity of
    citizenship.1      Southern counterclaimed against L & A alleging
    various breaches of the subcontract.
    The district court conducted a six-day bench trial beginning
    on August 17, 1992.          On September 22, 1992, the district court,
    applying Florida law,2 held that both Southern and L & A had
    breached the subcontract. The district court, after offsetting the
    award from Southern's counterclaim, held that L & A was entitled to
    recover   damages       of   $642,269    plus    postjudgment   interest   from
    Southern and F & D.3          After the district court overruled their
    1
    Southern averred in its petition for removal that it was a
    Michigan corporation having its principal place of business in
    Michigan, F & D was a Maryland corporation, and L & A was a
    Mississippi corporation. The amount in controversy indisputably
    exceeded the statutory minimum of 
    28 U.S.C. § 1332
    (a).
    2
    The parties agree on appeal that the district court
    correctly chose to apply Florida law. See Restatement (Second)
    of Conflict of Laws §§ 188, 194 (1971); Boardman v. United
    Servs. Auto. Ass'n, 
    470 So.2d 1024
    , 1032-34 (Miss.1985).
    3
    The district court appears to have miscalculated the damage
    award. In its judgment of September 22, 1992, the district court
    itemizes its damage award:
    Base damages                       $349,152
    Prejudgment interest                178,269
    Attorneys' fees                     115,048
    The sum of those figures is $642,469, or $200 more than the
    $642,269 the district court awarded. Because neither party
    called the discrepancy to our attention, however, we consider any
    argument over that $200 difference waived.
    Although the district court's judgment does not so state, it
    3
    posttrial motions, the defendants appealed to this Court.                         L & A
    cross-appealed      from      the     district       court's    judgment   but    later
    dismissed its cross-appeal.                Only the defendants' appeals remain
    for us to decide.
    This case turns on the language of the subcontract and
    Southern's performance and payment bond.                      "A bond is a contract,
    and,       therefore,    a   bond     is     subject     to    the   general   law    of
    contracts".4            We   review     de        novo   questions    involving      the
    construction or interpretation of contracts.5
    II.
    A. F & D's Liability Under its Bond
    We turn first to F & D's appeal.                       As a surety, F & D's
    liability is governed by the terms of its bond with L & A.                        While
    Southern is, of course, directly liable for its own breach of
    contract, the bond in this case imposes liability on F & D for
    Southern's breach only if two conditions exist.                      First, Southern
    must have been in default of its performance obligations under the
    subcontract.       Second, L & A must have declared Southern to be in
    default.6       The main focus of our inquiry is on the declaration
    appears from the record that Southern and F & D's liability to L
    & A was intended to be joint and several.
    4
    American Home Assurance Co. v. Larkin Gen. Hosp., Ltd., 
    593 So.2d 195
    , 197 (Fla.1992).
    5
    Gladney v. Paul Revere Life Ins. Co., 
    895 F.2d 238
    , 241
    (5th Cir.1990).
    6
    F & D's Subcontract Performance Bond provided that F & D
    would become liable to take certain actions to remedy Southern's
    breach "[w]henever Principal shall be, and shall be declared by
    Obligee to be in default under the subcontract, the Obligee
    4
    requirement, although we shall also briefly address the type of
    default that is required.
    We first must consider whether the bond term "declared ... to
    be   in    default"   is       ambiguous.7      While   the    construction     of
    unambiguous contracts is a matter of law, resolving ambiguous
    contracts     requires     a    fact-specific    inquiry      to   ascertain   the
    parties' intent.      That inquiry is best performed by the district
    court, and its factual determinations of the parties' intent will
    be reversed on appeal only if clearly erroneous.8
    A contractual term is ambiguous if it is reasonably subject
    to more than one meaning.9          Although the bond does not define the
    terms "declare" or "default", we consider the term "declared in
    default" unambiguous; the definition L & A offers is unreasonable.
    The only authority L & A offers for its view is Webster's Ninth New
    Collegiate Dictionary.           Webster's defines "declare" as "to make
    clear;    to make known formally or explicitly;            to make evident;    to
    having performed Obligee's obligations thereunder". Pl.'s Ex.
    189; Appellant's Record Excerpts tab J. In this tripartite
    suretyship arrangement, F & D was the "surety", Southern the
    principal obligor or simply the "principal", and L & A the
    "obligee". See In re Eli Witt Co., 
    2 B.R. 487
    , 491
    (Bankr.M.D.Fla.1979); Restatement (Third) of Suretyship § 1
    (Tent.Draft No. 1, 1992).
    7
    Whether a contract term is ambiguous is a question of law
    which we are free to decide de novo. See Carrigan v. Exxon Co.
    U.S.A., 
    877 F.2d 1237
    , 1240 (5th Cir.1989).
    8
    Godechaux v. Conveying Techniques, Inc., 
    846 F.2d 306
    , 314-
    15 (5th Cir.1988).
    9
    See Friedman v. Virginia Metal Prods. Corp., 
    56 So.2d 515
    ,
    517 (Fla.1952); Fireman's Fund Ins. Co. v. Murchison, 
    937 F.2d 204
    , 207 (5th Cir.1991).
    5
    state     emphatically"   and   "default"   as   "to   fail   to   fulfill   a
    contract, agreement, or duty".        Therefore, L & A concludes, any
    communication that "[made] it clear that [Southern] failed to
    fulfill a contract or duty" constituted a legal declaration of
    default.
    Three factors counsel rejection of L & A's popular dictionary
    authority.     First, L & A's proffered definition misapprehends the
    legal nature of the "default" that is required before the obligee's
    claim against the surety matures.        Although the terms "breach" and
    "default" are sometimes used interchangeably,10 their meanings are
    distinct in construction suretyship law.           Not every breach of a
    construction contract constitutes a default sufficient to require
    the surety to step in and remedy it.              To constitute a legal
    default, there must be a (1) material breach or series of material
    breaches (2) of such magnitude that the obligee is justified in
    terminating the contract.11        Usually the principal is unable to
    10
    See, e.g., Black's Law Dictionary 417 (6th ed. 1990),
    including "the omission or failure to perform a legal or
    contractual duty" among the definitions of "default".
    11
    We draw this meaning from the words of a commentator:
    Not every breach of a construction contract, not even
    every material breach, constitutes a default under the
    contract as to justify termination and the involvement
    of a surety, if there is one. A default which would
    involve the surety is believed to require a material
    breach or series of breaches which are sufficient to
    justify termination of the contract by the
    owner/obligee.
    James A. Knox, Representing the Private Owner, in
    Construction Defaults: Rights, Duties, and Liabilities §
    9.3, at 201 (Robert F. Cushman & Charles A. Meeker eds.,
    1989). Accord Robert J. Hoffman & David L. Simmons, Suing
    6
    complete the project, leaving termination of the contract the
    obligee's only option.12      The definition of "default" implicit in
    L   &   A's   dictionary   analogy   impermissibly   blurs   the   distinct
    concepts of "breach" and "default".13
    Second, L & A's definition is impractical.      A definition of
    a contract term that leads to impractical or commercially absurd
    the Subcontractor and Material Supplier, in Construction
    Litigation: Representing the Contractor § 8.9 (Robert F.
    Cushman, John D. Carter & Alan Silverman eds., 1986). Mr.
    Knox has pointed out that a clear definition of "default" is
    most necessary in several common construction problems,
    including one that precisely matches the circumstances of
    this case. His list of circumstances in which a clear
    meaning of "default" is most necessary includes:
    4. When the all-too-common confused situation develops
    where the obligee is claiming the principal has
    defaulted and the principal is claiming that the owner
    is in default.
    5. A variation of the preceding situation, when the
    situation is confused, the obligee claims default but
    does not terminate and yet demands action by the
    surety.
    James A. Knox, What Constitutes a Default Sufficient to
    Justify Termination of the Contract: The Surety's
    Perspective, Constr.Law., Summer 1981, at 1.
    12
    See, e.g., Cotton States Mut. Ins. Co. v. Citizens and S.
    Nat'l Bank, 
    308 S.E.2d 199
    , 203 (Ga.Ct.App.1983), explaining that
    "default in the relevant sense occurs only when the principal
    finds itself unable to pay and calls upon the surety to pay in
    accordance with the terms of the bond" (emphasis added).
    13
    Our holding that a material breach of the subcontract is
    required before L & A may seek relief from F & D does not deprive
    L & A of a remedy for partial breaches of the subcontract. The
    subcontract itself prudently provides that L & A may withhold
    payments from Southern to compensate for partial breaches. See
    Pl.'s Ex. P-22, Appellants' Record Excerpts, tab I, sec. 3. L &
    A urges that the bond makes F & D an insurer even for those
    partial breaches, but we are unable to square that contention
    with the bond's requirement of a default.
    7
    results is unreasonable.14        Serious legal consequences attend a
    "declaration of default", particularly in cases such as this case
    involving multi-million-dollar construction projects.               Before a
    declaration of default, sureties face possible tort liability for
    meddling in the affairs of their principals.15          After a declaration
    of default, the relationship changes dramatically, and the surety
    owes immediate duties to the obligee.16 Given the consequences that
    follow a declaration of default, it is vital that the declaration
    be made in terms sufficiently clear, direct, and unequivocal to
    inform    the   surety   that   the   principal   has   defaulted    on   its
    obligations and the surety must immediately commence performing
    under the terms of its bond.      Sureties deprived of a clear rule for
    notices of default would be reluctant to enter into otherwise
    profitable contracts.       Nothing in the record suggests that the
    parties intended such an impractical result.
    Finally, L & A's definition does not promote the purpose for
    which the parties probably included a notice of default provision
    14
    See Lakeland Tool & Eng'g, Inc. v. Thermo-Serv, Inc., 
    916 F.2d 476
    , 481 (8th Cir.1990); G.M. Shupe, Inc. v. United States,
    5 Cl.Ct. 662, 704 (Cl.Ct.1984).
    15
    See, e.g., Gerstner Elec., Inc. v. American Ins. Co., 
    520 F.2d 790
     (8th Cir.1975); Cox v. Process Eng'g, Inc., 
    472 S.W.2d 585
    , 587 (Tex.Civ.App.—Amarillo 1971, no writ); Restatement
    (Second) of Torts §§ 766, 766A (1979). "Prior to default, a
    surety does not have a unilateral right to intervene in a
    contract dispute between an owner and a principal unless the
    indemnity agreement between the surety and principal provides
    otherwise". Robert F. Cushman, et al., Representing the
    Performance Bond Surety, in Construction Defaults, supra note 11,
    § 5.2, at 106.
    16
    Zoby v. United States, 
    364 F.2d 216
    , 219 (4th Cir.1966);
    In re Wilson, 
    9 B.R. 723
    , 725 (Bankr.E.D.N.Y.1981).
    8
    in F & D's bond.        That purpose was to avoid the common-law rule
    that a secondary obligor such as F & D is not entitled to notice
    when the time for its performance is due.17              That purpose is not
    served if L & A can fulfill its duty to provide "notice of default"
    to F & D by sending letters containing no mention of a default.
    We conclude, therefore, that F & D's is the only reasonable
    view.     A declaration of default sufficient to invoke the surety's
    obligations under the bond must be made in clear, direct, and
    unequivocal language.      The declaration must inform the surety that
    the principal has committed a material breach or series of material
    breaches     of   the   subcontract,       that   the   obligee   regards   the
    subcontract as terminated, and that the surety must immediately
    commence performing under the terms of its bond.
    Under this standard, L & A's evidence is insufficient as a
    matter of law to establish a declaration of default.              None of the
    letters L & A sent to Southern and F & D even contained the word
    "default", nor do we find an unequivocal declaration of default in
    the other items of correspondence L & A's brief calls to our
    attention.18      Accordingly, we must VACATE the district court's
    17
    See Restatement of Security § 136 & cmt. a (1941).
    18
    After inviting us to write Webster's Ninth New Collegiate
    Dictionary into Florida law, L & A provides a list of ten letters
    it sent to Southern, each of which it characterizes as a
    "declaration of default" under its definition even though only
    two of the letters were sent to F & D. Appellee's Principal
    Brief at 14-15. The sizeable volume of correspondence that fits
    L & A's definition of "declaration of default" underscores the
    overbreadth of the definition. A declaration of default is an
    act of legal significance marking a fundamental change in
    relations among the parties to a suretyship contract. The burden
    is on the party initiating that fundamental change to express it
    9
    judgment against F & D for Southern's breach, because L & A has
    failed to prove a necessary precondition to F & D's liability under
    its bond.19
    B. F & D's Liability for Delay Damages
    F & D next challenges the district court's judgment holding
    it liable for delay damages.          We need not linger long on this
    question because it is directly controlled by the Florida Supreme
    Court's opinion in American Home Assurance Co. v. Larkin General
    Hospital, Ltd.20 The Larkin Court held that "the surety's liability
    plainly and unequivocally. Letters from general contractors
    attempting to prod subcontractors into improved performance are
    inevitably abundant in large construction projects but are not
    generally thought to constitute declarations of default. See
    Knox, Representing the Private Owner, supra note 11, § 9.2, at
    200. It is not asking too much of obligees to require that when
    they wish to give up on a principal and look to the surety for
    satisfaction, rather than merely to urge the principal to what
    they hope will be better performance, they must say so to the
    surety in clear, unequivocal terms. See, e.g., id. § 9.7, at
    217-18.
    19
    Part IV.C of the district court's opinion dealt with what
    the district court characterized as F & D's breach of its own
    surety bond. On this appeal, L & A seizes on that language to
    argue that F & D's actions exposed it to liability for its own
    breach of contract notwithstanding Southern's conduct. Obviously
    L & A intends this argument to bring it within the protection of
    some favorable language in footnote 2 of the Florida Supreme
    Court's Larkin opinion, which we address below. We reject L &
    A's argument. L & A's failure to declare Southern in default
    excuses F & D's failure to remedy Southern's breach. F & D did
    not breach the terms of its bond and accordingly has no liability
    under the bond.
    Because we conclude that L & A failed to declare
    Southern in default, we need not resolve the question
    whether the first requirement of the bond—that Southern
    actually be in default—was met here.
    20
    
    593 So.2d 195
     (Fla.1992).
    10
    for damages is limited by the terms of the bond".21    The bond here
    contained no provision imposing liability on F & D for delay
    damages, and the district court may not imply such a provision. 22
    Therefore, the district court erred in holding F & D liable for
    delay damages.          We are not persuaded by L & A's attempts to
    distinguish away the clear command of Larkin.23      Accordingly, we
    VACATE the award of delay damages against F & D.
    C. F & D's Liability for Attorney Fees
    Because F & D is not liable under the terms of its bond, it
    is not liable for consequential damages, such as attorney fees,
    flowing from Southern's breach of its contract.      Accordingly, to
    21
    
    Id. at 198
    .
    22
    "[T]he liability of a surety should not be extended by
    implication beyond the terms of the contract, i.e., the
    performance bond". 
    Id.
    23
    L & A first contends that the bond in Larkin contained
    different language from F & D's bond. Even if that is true—and F
    & D contends that it is not—it is irrelevant. Larkin did not
    turn on the language of the particular bond before the Court in
    that case, but rather stated what was obviously intended to be a
    general proposition of law. Second, L & A contends that F & D's
    bond was ambiguous. We conclude that the bond was not ambiguous,
    but even if it were, that is irrelevant to this issue. Larkin
    plainly states that the express terms of the bond provide the
    sole measure of F & D's obligation. If F & D's liability for
    delay damages is not "expressed in the bond ", 
    id. at 198
    (emphasis added, internal quotation omitted), F & D has no such
    liability. Finally, L & A relies on footnote 2 of Larkin for the
    proposition that Larkin does not apply to cases involving a
    surety's liability for its own breach of its bond. That is what
    Larkin says, but this is not that case. L & A plainly seeks
    recovery from F & D for Southern's breach of the subcontract.
    That is precisely the circumstance Larkin covers.
    The district court similarly distinguished Larkin on
    grounds irrelevant to the holding of that case, but our
    discussion of L & A's objections to Larkin should dispose of
    the district court's reasoning as well.
    11
    the extent the district court held F & D liable for attorney fees,
    we VACATE the award.
    III.
    A. Southern's Liability for Delay Damages
    We turn now to Southern's appeal.     Southern challenges its
    liability for delay damages, arguing that L & A failed to prove
    that Southern's delay resulted in the project as a whole becoming
    overdue.     Southern   contends    that,   under   Florida   law,   a
    subcontractor may not be held liable for delay damages unless the
    general contractor was late in completing the construction project.
    The cases Southern cites do not support that proposition, however.24
    24
    Fred Howland, Inc. v. Gore, 
    152 Fla. 781
    , 
    13 So.2d 303
    (Fla.1942), held simply that an owner cannot be awarded
    liquidated damages under a clause providing for damages in the
    event of a 30-day delay in completion of the project unless the
    owner proves that the condition precedent occurred; in other
    words, proves that the project was delayed for thirty days.
    Southern cites no similar clause in its contract with L & A.
    Lynch v. Florida Mining & Materials Corp., 
    384 So.2d 325
     (Fla.App.1980), primarily involved damages for
    defective, not delayed, performance. Lynch did not hold
    that a general contractor's timely completion of the project
    absolves the subcontractor from liability for delay damages.
    In Tuttle/White Constr., Inc. v. Montgomery Elevator
    Co., 
    385 So.2d 98
     (Fla.App.1980), the subcontractor sued the
    general contractor for payment under the subcontract, and
    the general contractor counterclaimed for late performance.
    The court held that the general contractor could offset
    against its liability the damages the subcontractor caused
    it by not timely performing. The court did not hold,
    however, that a delay in the completion of the overall
    project was a condition precedent to the subcontractor's
    liability for delayed performance.
    Finally, Haney v. United States, 
    676 F.2d 584
    (Ct.Cl.1982) involved a dispute between the owner and the
    general contractor. Obviously, a general contractor is not
    liable to the owner for delay damages unless it has untimely
    12
    In this case, Southern was held liable for its own delay in
    completing     its       obligation   to     L    &   A.      Southern's    untimely
    performance imposed unanticipated costs on L & A, and L & A is
    entitled to recover those costs regardless of whether it timely
    completed     its    own     obligation      to    the     Florida   Department     of
    Transportation.25
    B. Southern's Liability for Attorney Fees
    Southern challenges the district court's attorney fee award
    of $115,048, or half the $230,095 L & A requested.                    We review an
    award of attorney fees for abuse of discretion.26                    Southern cites
    no authority in its one-page argument on the attorney fee question,
    however,     and    we    consider    the    challenge       abandoned     for   being
    inadequately briefed.27
    IV.
    In conclusion, we VACATE the district court's judgment and
    award of damages against F & D in its entirety and RENDER judgment
    for F & D.    We AFFIRM the award against Southern for $642,269 plus
    postjudgment interest as the district court calculated.
    performed its obligation to the owner. Haney does not
    imply, however, that timely performance by the general
    contractor absolves the subcontractor from liability for
    untimely performing its own obligations.
    25
    See District Concrete Co. v. Bernstein Concrete Corp., 
    418 A.2d 1030
    , 1038 (D.C.1980).
    26
    Palmco Corp. v. American Airlines, Inc., 
    983 F.2d 681
    , 688
    (5th Cir.1993).
    27
    See Dardar v. Lafourche Realty Co., Inc., 
    985 F.2d 824
    ,
    831 (5th Cir.1993); Fed.R.App.P. 28(a)(5).
    13