United States Ex Rel. Wallace v. Flintco Inc. , 143 F.3d 955 ( 1998 )


Menu:
  •                  UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    _______________________
    No. 96-11360
    _______________________
    THE UNITED STATES OF AMERICA For the
    Use of MARSHALL E. WALLACE d/b/a
    WALLACE CONSTRUCTION COMPANY, ET AL.,
    Plaintiffs,
    MARSHALL E. WALLACE, doing business as Wallace
    Construction Company,
    Plaintiff - Counter Defendant
    Appellee-Cross-Appellant,
    versus
    FLINTCO INC.; AMERICAN HOME ASSURANCE CO.,
    Defendants-Counter-Claimants Third Party Plaintiffs
    Appellants-Cross-Appellees,
    versus
    VICTORE INSURANCE COMPANY,
    Third-Party Defendant-Appellee-Cross-Appellant.
    _________________________________________________________________
    Appeals from the United States District Court
    for the Northern District of Texas
    ________________________________________________________________
    June 29, 1998
    Before KING and JONES, Circuit Judges, and WERLEIN*, District
    Judge.
    By EWING WERLEIN, JR., District Judge:
    *
    District Judge of the Southern District of Texas, sitting by
    designation.
    This    case   presents   cross-appeals    by    a   contractor    and   a
    subcontractor, and their respective bond sureties, from an Amended
    Judgment entered after a two-week jury trial.              After a careful
    review of the trial proceedings, we conclude that those portions of
    the Amended Judgment of the district court that award costs to both
    sides against their respective adversaries, should be VACATED and
    REMANDED for further proceedings, and that the Amended Judgment, as
    reformed herein for clarification, should otherwise be AFFIRMED.
    Background
    The United States Army Corps of Engineers ("Corps”) engaged
    Flintco, Inc. ("Flintco"), a general contractor, to build an
    enlisted    dormitory   at   Sheppard   Air   Force   Base,   Texas,     ("the
    Project").     Flintco, in turn, subcontracted with Marshall E.
    Wallace d/b/a Wallace Construction Company ("Wallace") for Wallace
    to perform dirt and paving work on the Project.                Flintco and
    American Home Assurance Co. ("AHAC"), Flintco’s surety, furnished
    a payment bond pursuant to the Miller Act, 40 U.S.C. § 270a;
    Wallace and Victore Insurance Co. ("Victore"), Wallace's surety,
    furnished private payment and performance bonds.
    Wallace began work on the Project in March 1992.                  In July
    1992, August 1992, and January 1993, Wallace submitted change
    orders No. 1, No. 2, and No. 3, respectively, for additional
    2
    compensation. Each was approved, and pursuant to each, Wallace was
    compensated.
    In July 1993, the Corps issued a directive that the compaction
    of the subgrade of the parking lots be increased from 90% to 95%
    density.   Wallace began this work before submitting a claim to the
    Corps, through Flintco, for additional compensation. Wallace later
    submitted the claim, but before the claim was fully processed,
    Wallace ceased work on the Project and left the Project site on
    December 23, 1993, leaving his own subcontractors unpaid to the
    extent of approximately $101,000.    Flintco contracted with another
    dirt and paving subcontractor to complete the unfinished work.
    In April 1994, Wallace submitted a "Request for Equitable
    Adjustment" in which he sought $ 215,292.50 in compensation for the
    increased compaction.    The Corps responded with an award of only
    $7,000.00.     Wallace later submitted an amended claim which was
    denied.
    Wallace filed this suit against Flintco and AHAC for breach of
    contract and for quantum meruit. Wallace alleged that Flintco, the
    Corps, and other subcontractors interfered with his work on the
    Project, and caused him "productivity impact" damages. Flintco and
    AHAC counterclaimed against Wallace for breach of the subcontract,
    and filed a third party action against Victore on the performance
    and payment bonds.
    A two-week jury trial resulted in a special verdict for
    Wallace on all questions submitted.    Among other things, the jury
    3
    found that Flintco breached its contract with Wallace; that Wallace
    was entitled     to   a   quantum   meruit   recovery;    that    Wallace   had
    fulfilled all contractual conditions precedent to filing suit
    against Flintco and AHAC; and that Flintco and AHAC had breached
    the Miller Act bond by failing to pay Wallace.              Conversely, the
    jury also found that Wallace had not breached his contract with
    Flintco; that Wallace was not negligent in performing his work;
    that Wallace had not waived his claims against Flintco; that
    Flintco had not fulfilled all contractual conditions precedent to
    filing suit against Wallace and Victore; that Flintco did not
    acquire from Wallace’s subcontractor creditors their claims against
    Victore;   and   that     Wallace   and   Victore   did   not    breach   their
    obligations to Flintco under the payment bond.             The jury awarded
    $197,777.00 to Wallace and awarded nothing to Flintco.
    Wallace moved for entry of judgment; and Flintco and AHAC
    filed a “Motion for Judgment Notwithstanding the Verdict” under
    Fed. R. Civ. P. 50(b).1      The trial court granted in part Flintco’s
    and AHAC’s Rule 50(b) motion, holding as a matter of law that they
    were entitled to recover from Wallace and Victore approximately
    $101,000 that they had paid to Wallace’s subcontractors whom
    Wallace had not paid when he ceased work on the Project.            The trial
    1
    The correct terminology under Rule 50(b) is now “renewed
    motion for judgment as a matter of law,” although, as will be seen,
    Flintco and AHAC did not initially file a Rule 50(a) motion for
    judgment as a matter of law.
    4
    court ultimately signed an Amended Judgment, which is summarized as
    follows:
    !    Judgment for Wallace against Flintco on Wallace's
    state law quantum meruit claim for:
    “1.   Actual damages in the amount of $197,777.00;
    “2.   Pre-judgment interest thereon in the amount of
    $62,681.85;
    “3.   Post-judgment interest on all amounts awarded
    in item numbers one and two above at the
    currently prevailing rate pursuant to 28
    U.S.C. § 1961 of 5.90% per annum, compounded
    daily, from the date of this judgment until
    paid.”
    R. Vol. 13 at 3776-77 (footnotes omitted).
    !    A take nothing Judgment on Wallace's claim for
    breach of contract against Flintco;2
    !    Judgment for Wallace and against Flintco and AHAC,
    jointly and severally, on Wallace's Miller Act payment
    bond claim for:
    “1.   Actual damages in the amount of $197,777.00;
    “2.   Pre-judgment interest thereon in the amount of
    $62,681.85;
    “3.   Post-judgment interest on all amounts awarded
    in item numbers one and two above at the
    currently prevailing rate pursuant to 28
    U.S.C. § 1961 of 5.90% per annum, compounded
    daily, from the date of this judgment until
    paid.”
    
    Id. at 3777.3
    2
    This aspect of the Amended Judgment was based on
    Wallace's election to recover on his quantum meruit theory rather
    than for breach of contract.
    3
    It appears that the trial court did not intend for this
    three-numbered segment of the Amended Judgment and the first three-
    5
    !    A take nothing judgment on Flintco and AHAC's breach
    of contract claim against Wallace;
    !    Judgment for Flintco and AHAC and against Wallace
    and Victore, jointly and severally, on their third-party
    payment bond claim in the amount of $101,187.30, plus
    pre-judgment interest in the amount of $30,834.13, and
    post-judgment interest at a rate of 5.90%;
    !    A take nothing Judgment on Flintco and AHAC's third
    party performance bond claim against Victore;
    !    $73,778.43 in costs recoverable by Flintco and AHAC
    from Wallace and Victore, jointly and severally;
    !    $90,091.00 in costs recoverable by Wallace from
    Flintco and AHAC, jointly and severally;
    !    $256,338.00 in attorneys’     fees   recoverable   by
    Wallace from Flintco; and
    !    $183,425.78 in attorneys’     fees   recoverable   by
    Flintco from Wallace.
    It is this Amended Judgment that is the subject of the cross
    appeals in almost every respect.
    numbered segment of the Amended Judgment, first quoted above, to be
    a double recovery for Wallace, and the parties have not argued a
    contrary understanding. The Amended Judgment is intended to make
    one award to Wallace in the amount of $197,777.00, plus prejudgment
    interest of $62,681.85 and post-judgment interest, but adjudged
    against Flintco on two grounds -- on quantum meruit, in the first
    segment, and on the Miller Act payment bond, in the second segment.
    The joint and several liability of Flintco’s surety, AHAC, for that
    full sum arises only from its obligation on the Miller Act payment
    bond, in the second segment. For clarification, and to avoid any
    ambiguity about Wallace’s entitlement to recover only one sum of
    $197,777.00, plus interest, the Amended Judgment will be reformed
    to consolidate these two decretal segments.
    The Amended Judgment also orders that post-judgment interest
    be compounded daily. This is plain error; post-judgment interest
    is “computed daily to the date of payment” but “compounded
    annually.” 28 U.S.C. § 1961(b) (emphasis added).
    6
    7
    Analysis
    I.   Quantum Meruit and Miller Act Claims
    Flintco and AHAC first challenge the sufficiency of the
    evidence to support a judgment for Wallace on his quantum meruit
    and Miller Act claims because the Flintco-Wallace subcontract
    contained a "no damages for delay" clause.     In response, Wallace
    contends that Flintco failed to move for a “directed verdict”4 at
    the close of the evidence and thereby waived its right to appellate
    review of the sufficiency of the evidence.        Wallace therefore
    contends that this Court must review Flintco’s and AHAC’s arguments
    as if they are presented for the first time on appeal, under the
    plain error standard.
    A.   Standard of Review
    Challenges to the sufficiency of the evidence must be raised
    in a Fed. R. Civ. P. 50(a) motion for judgment as a matter of law
    before submission of the case to the jury.   If the trial court does
    not grant a motion for judgment as a matter of law made after the
    close of all the evidence, then the movant may renew its request
    for judgment as a matter of law after the entry of judgment.   Fed.
    4
    The correct terminology under Rule 50(a) is now “motion
    for judgment as a matter of law." See McCann v. Texas City Ref.,
    Inc., 
    984 F.2d 667
    , 670 n.3 (5th Cir. 1993).
    
    8 Rawle Civ
    . P. 50(b).      A party that fails to move for judgment as a
    matter of law under Rule 50(a) on the basis of insufficient
    evidence at the conclusion of all of the evidence waives its right
    to file a renewed post-verdict Rule 50(b) motion, and also waives
    its right to challenge the sufficiency of the evidence on appeal.
    Bay Colony, Ltd. v. Trendmaker, Inc., 
    121 F.3d 998
    , 1003 (5th Cir.
    1997) ("Generally, a party who fails to renew his motion for
    directed verdict at the close of all the evidence waives his right
    to challenge the sufficiency of the evidence."); Polanco v. City of
    Austin,   Tex.,   
    78 F.3d 968
    ,   974   (5th   Cir.   1996)   ("Where   the
    defendant failed to timely move for judgment as a matter of law, we
    will consider the issue as waived by the defendant and will treat
    the issue as being raised for the first time on appeal."); Allied
    Bank-West, N.A. v. Stein, 
    996 F.2d 111
    , 114-115 (5th Cir. 1993) (a
    district court cannot consider a Rule 50(b) motion for judgment as
    a matter of law unless the movant has first sought a directed
    verdict).
    The Rule serves two purposes:
    to enable the trial court to re-examine the sufficiency
    of the evidence as a matter of law if, after verdict, the
    court must address a motion for judgment as a matter of
    law, and to alert the opposing party to the insufficiency
    of his case before being submitted to the jury.
    MacArthur v. University of Tex. Health Ctr. at Tyler, 
    45 F.3d 890
    ,
    897 (5th Cir. 1995).     Rule 50(b) is to be examined and applied "``in
    the light of the accomplishment of [its] particular purpose[s] as
    well as in the general context of securing a fair trial for all
    9
    concerned in the quest for truth.’"           Bay 
    Colony, 121 F.3d at 1003
    (quoting 
    McCann, 984 F.2d at 671
    (alterations in original)).
    In certain cases in which a party has failed to meet the
    technical requirements of Rule 50(a) but has still satisfied the
    Rule's purposes, non-compliance has been excused.              See, e.g., 
    id. at 1003-04
    (defendant's motion for directed verdict at the close of
    plaintiff's    case-in-chief,       which    asserted   that   there   was   no
    evidence or insufficient evidence for the issue to go to the jury,
    and defendant's subsequent objections, on the same grounds, to the
    proposed jury charge, satisfied the purposes of Rule 50(b));
    
    Polanco, 78 F.3d at 974-75
    (defendant's motion for judgment as a
    matter of law at the close of plaintiff's case, which was taken
    under advisement by the court and followed by the presentation of
    thirteen defense witnesses and no rebuttal witnesses, alerted
    plaintiff and the court to defendant's challenge to the sufficiency
    of plaintiff's proof).         Although Rule 50's requirements have been
    liberally construed in this circuit, Hinojosa v. City of Terrell,
    Tex., 
    834 F.2d 1223
    , 1228 (5th Cir. 1988), cert. denied, 
    493 U.S. 822
    , 
    110 S. Ct. 80
    (1989), "[e]ven with a liberal interpretation
    [of   Rule   50(b)],   .   .    .   this    circuit   has   never   completely
    disregarded the requirement that the defendant must move for
    judgment as a matter of law at the close of all the evidence."
    
    Polanco, 78 F.3d at 974
    .
    10
    Flintco did not do so.         It neither moved for judgment as a
    matter of law under Rule 50(a) at the close of Wallace's case or at
    the    close    of   all   the   evidence.        Moreover,    Flintco       did   not
    challenge the sufficiency of the evidence in connection with or as
    a    basis   for     making   objections     to   the    court’s      jury   charge.
    Nonetheless, Flintco contends that the purposes of the Rule were
    satisfied by its attempt to comply with the Rule's requirements, by
    the trial court’s perceived understanding of Flintco’s unstated
    insufficiency points and disinclination to hear the motions until
    after a verdict was received, and by Flintco’s general objections
    to    certain    issues    being   submitted      to    the   jury.      The   Court
    disagrees, although the argument requires a careful review of the
    record.
    At the close of Wallace's evidence, Mr. Sessions, Flintco's
    counsel, stated his desire to present "certain motions," to which
    the trial court replied that motions could be presented at the
    lunch recess.        R. Vol. 21 at 706, lines 5-11.5             During a recess
    later that morning, but before the lunch recess, the trial court
    5
    The exchange occurred as follows:
    Mr. Sessions stated, "Your Honor, I believe it's at this time
    traditionally when we present certain motions to the Court.
    I believe the Court has already indicated -- "
    The trial court interjected, "We can do that at lunch time."
    Mr. Sessions responded, "That'll be fine. We'll go forward
    with it," and proceeded to call Flintco's first witness. R.
    Vol. 21 at 706, lines 5-11.
    11
    informed counsel that such matters would be considered instead
    during a recess "a little after" lunch.        
    Id. at 783,
    lines 1-4.6
    During the same exchange, the trial court commented, "I suspect I'm
    going to have a motion here that I told Mr. Sessions would be
    deferred so I have some legal decisions to make here on the current
    state of this record . . . ."      
    Id. at 787,
    lines 10-13.   During the
    recesses and the hearings outside the presence of the jury that
    followed, Flintco addressed a number of matters with the court but
    never reminded the court of Flintco’s previously-indicated desire
    to present “certain motions,” and never moved for judgment as a
    matter of law based on the evidence at the close of Plaintiff’s
    case-in-chief.
    At the close of Defendants’ evidence7 and before submission of
    the case to the jury, the Court observed that motions had not been
    "formally made" because the Court had "cut [] off" Mr. Sessions.
    R. Vol. 22 at 947, lines 15-17.      The Court then stated that motions
    could be made post-verdict.8       R. Vol. 22 at 947, lines 17-22; R.
    6
    Specifically,      the trial court stated, "There's been a
    change in plans. What        I told you we were going to do at lunch
    time, we'll do a little      after and take a break about then. I'll
    just let you know as we      go." R. Vol. 21 at 783, lines 1-4.
    7
    Wallace presented no witnesses in rebuttal.
    8
    Specifically, the trial court stated, "I know that although
    it was not formally made because I cut everyone off or cut you off,
    Mr. Sessions, any type of motion practice anyone may have with
    regard to claims by the opponents can all be taken up post verdict.
    There's no point in me deciding something if I don't have to decide
    it. The Jury decides it for me. But -- well, that speaks for
    itself." R. Vol. 22 at 947, lines 15-22.
    12
    Vol. 23 at 996, lines 2-4, 14-23.           Flintco did not object to the
    trial court’s deferral of the parties’ “motion practice,” and again
    did not orally attempt to present a motion for judgment as a matter
    of law.      Moreover, Flintco did not file a written motion for
    judgment as a matter of law.
    The next morning during a lengthy jury charge hearing held
    outside of the presence of the jury, Flintco objected to certain
    instructions    and   portions   of   the    proposed   charge,   including
    portions addressing its liability under quantum meruit and the
    Miller Act.      The court sustained some of the objections and
    modified the instructions.        Flintco made no objection to the
    proposed charge, however, on grounds pertaining to the sufficiency
    of the evidence.      R. Vol. 23 at 973-983, 985-987. In particular,
    Flintco made no objection that there was insufficient evidence to
    warrant submission of liability issues on Wallace’s breach of
    contract, quantum meruit, and Miller Act claims or submission of
    damages questions related to those claims.
    After hearing the parties' objections to the proposed jury
    charge and making certain changes in the charge, the trial court
    commented,
    One other thing so that -- so that you aren't blind sided
    or no one is blind sided, and I'm saying this to let you
    know so that it's on the record, and I have not
    formulated any final opinions one way or another, but
    after sitting here for two weeks and listening to this
    case and looking at everything again, I want to let you
    know that there was no motion -- you can make all this
    post-verdict, but I, as a matter of law, am concerned
    13
    about two things.    And one is that -- is the partial
    summary judgment Mr. Sessions filed against Victore about
    conditions precedent about the materials and whether that
    was triggered or not. And we can talk about that later
    and revisit that issue, but I'm even more concerned about
    the damage -- the aspect of damages that the Plaintiff
    proved and whether or not as a matter of law that a
    reasonable fact finder could could [sic] find -- find
    that.
    I'm just putting you on notice now so you won't think
    it's something I haven't been thinking about all along,
    but there are motions, but I am going to go ahead and get
    the jury verdict.
    
    Id. at 995-996.
    In sum, when Plaintiff rested his case-in-chief, Flintco’s
    counsel observed that “it’s at this time traditionally when we
    present certain motions to the court.”   R. Vol. 21 at 706, lines 5-
    7.   That was the one and only allusion ever made by defense counsel
    of a desire to make a motion for judgment as a matter of law under
    Rule 50(a).     At the close of all of the evidence and before
    submission of the case to the jury, Flintco never filed a written
    Rule 50(a) motion; never asked to make an oral Rule 50(a) motion;
    never objected to the trial court’s statement that “any type of
    motion practice . . . can all be taken up post-verdict”; never
    stated the grounds that would form the basis of a motion for
    judgment as a matter of law if one were to be made, either in
    writing or orally; never insisted upon its right either to file or
    orally to make a Rule 50(a) motion even though the court chose not
    to rule upon it until after a verdict; and never voiced objections
    14
    to the submission of liability and damage questions on grounds of
    insufficiency of evidence.
    Flintco argues that the purposes of Rules 50(a) and (b) were
    served by the trial court’s above-quoted comment that he was
    “concerned” about “the aspect of damages that the Plaintiff proved
    and whether or not as a matter of law that a reasonable factfinder
    could find -- find that.”       R. Vol. 23 at 996, lines 9-13.         Flintco
    argues that the judge’s comment relates solely to the insufficiency
    of Plaintiff’s evidence as a matter of law and that the purposes of
    Rule 50 were thereby served.         Flintco, however, did not follow up
    the trial court’s comment with a Rule 50(a) motion.                    Nor did
    Flintco state on the record what would be the basis of such a
    motion had one been made.       Under Rule 50(a), a movant is required
    to “specify the judgment sought and the law and the facts on which
    the moving party is entitled to the judgment.”                Fed. R. Civ. P.
    50(a)(2).      Flintco never did this.
    It   is    not   enough   for   a    party   to   rely   upon   “concerns”
    volunteered by a trial judge as a substitute for making a Rule
    50(a) motion.      Not even a court of appeals, in holding that there
    was sufficient evidence to send to the jury a question on gross
    negligence and reversing the case for retrial on that issue, can
    excuse the defendant from making a Rule 50(a) motion before the
    case is submitted to the jury in the new trial.                  This is what
    happened in Sims’ Crane Serv., Inc. v. Ideal Steel Prods., Inc.,
    
    800 F.2d 1553
    (11th Cir. 1986).          On retrial, the defendant did not
    15
    make a motion for directed verdict on the gross negligence issue
    because the court of appeals had previously ruled that the evidence
    was sufficient to require its submission and because defendant
    viewed the court of appeals’ decision as having declared the law of
    the case.        
    Id. at 1557.
      After the new verdict was returned for
    plaintiff, the trial court granted a judgment notwithstanding the
    verdict.    On appeal from this judgment, the Eleventh Circuit Court
    of Appeals held that the failure of defendant to have made a Rule
    50(a) motion limited the court’s review to a determination of plain
    error.     
    Id. The appellate
    court wrote that although defendant’s
    reasons for having not made a Rule 50(a) motion were
    persuasive to some extent, we note that counsel sometimes
    must take certain required, albeit formalistic, steps to
    preserve the rights of their client and to perfect the
    record for post-verdict proceedings.
    Objections, proffers, and motions are frequently
    required in trials even when it may seem certain to the
    pertinent lawyer that the trial judge’s view is that such
    efforts ought not to prevail. Of course, almost nothing
    is really certain in litigation; ``[i]ndeed, it is always
    probable that something improbable will happen.’ Warren
    v. Purtell, 
    63 Ga. 428
    , 430 (1879) (Bleckley, J.). Thus,
    it is hard to know when some act would have been truly
    useless. In any event, orderly and definite procedural
    steps are necessary to sharpen the issues before the
    court and to avoid misunderstanding. While it is true
    that this Circuit has not been strict about motions for
    directed verdicts, we cannot depart completely from Rule
    50(b).
    
    Id. In the
    instant case, Flintco, in arguing now that it should be
    excused for not having made the motion because of the trial court’s
    volunteered declaration of its “concerns” about the evidence, has
    16
    a far less cogent excuse than that given by the defendant in Sims’
    Crane.   The Eleventh Circuit summarized the law as follows:
    A lawyer who never moves for directed verdict, given the
    wording of Rule 50(b) and the clear case law regarding
    the effect of such a decision -- regardless of the
    reasons for such a decision, must realize that a
    subsequent motion for jnov can be granted only if plain
    error can be proven.
    Id.; see also 
    McCann, 984 F.2d at 672
    (“While it is true that this
    Circuit approaches such questions [about compliance with Rule
    50(b)] with a ``liberal spirit,’ we are not willing to rewrite the
    Federal Rules of Civil Procedure.”) (internal citation omitted).
    Because Flintco made no Rule 50(a) motion and did not specify
    what judgment was sought and the law and the facts that would
    entitle Flintco to such a judgment, we conclude that the second
    purpose of Rule 50 -- to alert Wallace to the specific grounds for
    an anticipated challenge to the sufficiency of its proof and to
    allow Wallace the opportunity to move to cure any such deficiency
    -- was not served.   In that the purposes of Rule 50 were not met,
    non-compliance with the Rule cannot be excused.   
    McCann, 984 F.2d at 671
    ("In each case where we have excused noncompliance with Rule
    50(b), this Court has concluded that the purposes of the rule had
    been satisfied.") (emphasis in original); see, e.g., Guilbeau v.
    W.W. Henry Co., 
    85 F.3d 1149
    , 1160 (5th Cir. 1996) (the purpose of
    Rule 50(a)'s requirement that a motion for judgment as a matter of
    law specify the law and the facts upon which the moving party
    17
    relies “is to assure the responding party an opportunity to cure
    any deficiency in that party's proof that may have been overlooked
    until   called   to    the   party's       attention    by   a   late   motion   for
    judgment") (citing Fed. R. Civ. P. 50 advisory committee's note
    (1991 amendment)), cert. denied, ___ U.S. ___, 
    117 S. Ct. 766
    (1997); 
    Hinojosa, 834 F.2d at 1228
    (“In this case [defendant] did
    not at any time move for a directed verdict in his favor . . . ,
    nor did he object to the submission of any of the interrogatories
    pertaining to these claims on the ground that the claims were
    unsupported by the evidence. . . .                [Defendant thus] failed to
    alert [plaintiff], prior to submission of the case to the jury, to
    the possibility that insufficient evidence was presented . . . .").
    Because of Flintco’s non-compliance with Rule 50(a), we must
    consider Flintco's objections to the sufficiency of Wallace's
    evidence on its quantum meruit and Miller Act claims as though they
    were raised for the first time on appeal.              
    Polanco, 78 F.3d at 974
    .
    "It is the unwavering rule in this Circuit that issues raised for
    the first time on appeal are reviewed only for plain error.                       In
    other   words,      this   Court    will    reverse     only     if   the   judgment
    complained of results in a ``manifest miscarriage of justice.'"
    
    McCann, 984 F.2d at 673
    (internal citation omitted).                        On plain
    error review "the question before this Court is not whether there
    was substantial evidence to support the jury verdict, but whether
    there   was   any     evidence     to   support   the    jury     verdict."      
    Id. 18 (emphasis
    in original). If any evidence supports the jury verdict,
    the verdict will be upheld.   
    Polanco, 78 F.3d at 974
    .
    B.   Discussion
    Flintco challenges the sufficiency of the evidence to support
    the jury verdict on Wallace's quantum meruit and Miller Act claims.
    Flintco specifically argues that Wallace's damages are precluded by
    the "no damages for delay" clause in the parties' subcontract, that
    there is insufficient evidence to support the amount of damages
    awarded by the jury, and insufficient evidence of the actual "out
    of pocket expenses" Wallace incurred in support of a verdict on the
    Miller Act claim.   Because our review is under the plain error
    standard, the jury verdict in Wallace's favor on its quantum meruit
    and Miller Act claims will be upheld unless there is no evidence to
    support the jury's verdict on those claims.
    19
    1.     There is some evidence that Wallace's damages fall
    outside of the "no damages for delay" clause in the
    parties' subcontract.
    The "no damages for delay" clause at issue provided:
    In the event delays in the performance of this
    Subcontract are occasioned by FLINTCO, Owner, Architect
    or some other subcontractor, an extension of time for the
    completion of this Subcontract shall be granted for a
    period   of   time  equal   to   the   delay  caused   to
    Subcontractor. Such extension of time shall be in lieu
    and in full satisfaction of any and all claims whatsoever
    of Subcontractor against Owner, Architect, FLINTCO or
    other subcontractor causing such delay.
    R. Excerpt 5D to Appellant’s Brief at ¶ 11.         Clauses such as this
    have been upheld under Texas law, and have been found to bar damage
    claims that are based on delay. United States ex rel.       Straus Sys.,
    Inc. v. Associated Indem. Co., 
    969 F.2d 83
    , 85 (5th Cir. 1992)
    (applying Texas law to "no damages for delay" clause); City of
    Houston v. R.F. Ball Constr. Co., 
    570 S.W.2d 75
    , 77 (Tex. Civ.
    App.--Houston [14th Dist.] 1978, writ ref'd n.r.e.).           "No damages
    for delay" clauses will be strictly construed and enforced unless
    the delay at issue (1) was not contemplated by the parties; (2) was
    so long as to justify abandonment of the contract; (3) was caused
    by fraud, misrepresentation, or bad faith; or (4) was caused by
    actual    interference   with   the   performance   required    under   the
    contract.    R.F. 
    Ball, 570 S.W.2d at 77
    & n.1.
    Wallace argues that his complaint is not one of delay within
    the meaning of the “no damages for delay” clause, but is for
    20
    Flintco’s     active    interference          and   hindrance    of     Wallace’s
    performance.      Indeed, a leading Texas decision on this subject
    upheld damages, notwithstanding a “no damages for delay” clause,
    where the defendant was found to have committed the following acts
    and omissions:
    (1) Failure to plan development and construction of whole
    project; (2) Failure to furnish master progress schedule;
    (3) Failure to coordinate work of various prime
    contractors; (4) Failure to proceed with underground
    utilities contract until August 1, 1952; (5) Failure to
    proceed with the sidewalks contract until July 1, 1953;
    (6) Failure to expedite flow of information; (7) Failure
    to decide on type of water heaters; (8) Failure to
    deliver water heaters; (9) Arbitrary and capricious
    requirements of Architects; (10) Instructions to asphalt
    tile sub-contracts; (11) Refusal to accept the buildings
    within reasonable time after August 25, 1953.
    Housing Auth. of Dallas v. Hubbell, 
    325 S.W.2d 880
    , 890 (Tex. Civ.
    App.--Dallas 1959, writ ref’d n.r.e.).              The Court explained:
    [T]he ``no-damage-for-delay’ provision did not give Owner
    a license to cause delays ``willfully’ by ``unreasoning
    action’, ``without due consideration’ and in ``disregard of
    the rights of other parties’, nor did the provision grant
    Owner immunity from damages if delays were caused by
    Owner under such circumstances.
    
    Id. at 891.
    In the instant case, there is evidence from Rodney Wallace, Ed
    Wallace,    and   Donald      McDonald    that      Flintco,    and   the   other
    subcontractors     on   the    site   over     which   Flintco    had   control,
    disrupted and actively interfered with Wallace's performance under
    the subcontract. That disruption and active interference consisted
    of (1) Flintco's failure properly to coordinate and sequence the
    21
    work done by all the subcontractors on the job; (2) Flintco's
    direction of Wallace to small, piecemeal jobs on the site; (3)
    Flintco's failure to ensure that its other subcontractors removed
    their materials and debris from the areas in which Wallace had to
    work; (4) Flintco's improper surveying and staking of an area
    around two of the buildings on the project that required Wallace to
    regrade areas it believed had been completed to specifications; (5)
    Flintco's failure to locate timely and remove physical obstacles
    (power poles and a gas line) from the areas in which Wallace had to
    work; and (6) Flintco's failure to ensure that the work Wallace had
    completed was not adversely affected by the other subcontractors on
    the site.       This disruption and interference, according to the
    testimony of Rodney Wallace, Ed Wallace, and Donald McDonald,
    caused    Wallace     to   suffer   productivity   impacts,   resulting   in
    increased labor costs, increased equipment costs, and increased
    overhead expenses.         Because the record contains some evidence that
    the   actions    of   Flintco    constituted   active   interference   with
    Wallace's performance and that Flintco breached the contract, and
    because Texas law recognizes that a “no damages for delay” clause
    does not preclude a contractor from recovering damages when the
    delay is caused by active interference with the contractor’s
    performance,9 there is no plain error in the Court’s submission of
    9
    Flintco relies on Black Lake Pipe Co. v. Union Constr. Co.,
    Inc., 
    538 S.W.2d 80
    , 86 (Tex. 1976) to argue that Wallace cannot
    recover in quantum meruit because the damages it claims are covered
    by the parties’ contract.     Black Lake Pipe, however, does not
    22
    questions and the jury’s findings on Flintco’s liability and
    Wallace's damages.
    2.   There is some evidence to support the amount of damages
    awarded to Wallace by the jury on the quantum meruit
    claim.
    Damages   must   be   proven   to   a   reasonable   certainty,   but
    mathematical precision is not required.
    All that the law requires is that the best evidence of
    which a case is susceptible be produced, and if from such
    evidence the amount of damages caused by the defendant
    can be inferred or estimated by the jury with reasonable
    certainty, then the amount of such damages is for the
    jury.
    Bildon Farms, Inc. v. Ward County Water Improvement Dist. No. 2,
    
    415 S.W.2d 890
    , 897 (Tex. 1967); see also South Builders, Inc. v.
    preclude Wallace from obtaining a quantum meruit recovery. When a
    general contractor actively interferes with its subcontractor’s
    performance, the subcontractor may “treat the contract as rescinded
    and recover under quantum meruit the full value of the work done.”
    McCracken Constr. Co. v. Urrutia, 
    518 S.W.2d 618
    , 621-22 (Tex. Civ.
    App.--El Paso 1974, no writ); see also United States ex rel. Aucoin
    Elec. Supply Co. v. Safeco Ins. Co. of Am., 
    555 F.2d 535
    , 542 (5th
    Cir. 1977) (when general contractor prevents performance,
    subcontractor may recover in quantum meruit); Citizens Nat’l Bank
    v. Vitt, 
    367 F.2d 541
    , 546 (5th Cir. 1966) (“``Once a subcontractor
    has established a breach of contract by the prime, he can recover
    the value of the work he has done or the service he has rendered.
    In other words, he is entitled to a quantum meruit.’”) (quoting
    McBride and Wachtel, Government Contracts 49-185, § 49.150(4));
    Kleiner v. Eubank, 
    358 S.W.2d 902
    , 905 (Tex. Civ. App.--Austin
    1962, writ ref’d n.r.e.). In this case, the jury found in response
    to Jury Question No. 1 that Flintco had breached the parties’
    contract. Given that finding of a breach by Flintco, Wallace was
    entitled to “treat the contract as rescinded and recover under
    quantum meruit the full value of the work done.”      
    Kleiner, 358 S.W.2d at 905
    .
    23
    Brown, 
    449 S.W.2d 542
    , 548 (Tex. Civ. App--Eastland 1969, writ
    ref'd n.r.e.) (a subcontractor suing a general contractor for
    breach of the subcontract is required to prove his damages in such
    detail that the jury can make an estimate of the damages with
    reasonable certainty).      In reviewing whether damages have been
    proven to a reasonable certainty, all evidence is to be considered
    in the light most favorable to the party that was awarded damages.
    Thompson and Wallace of Memphis, Inc. v. Falconwood Corp., 
    100 F.3d 429
    , 435 (5th Cir. 1996).
    Donald McDonald, Wallace's damages expert, testified without
    objection to his estimate of quantum meruit damages in the amount
    of $297,643.88.   R. Vol. 17 at 149-151, 156.   The estimate appears
    not to have been based on the reasonable value of the work
    performed but instead, like his estimate of contract damages, on
    man and machine hour averages.   This methodology has been accepted
    in calculating damages in construction cases.      See U.S. Indus.,
    Inc. v. Blake Constr. Co., Inc., 
    671 F.2d 539
    , 547 (D.C. Cir.
    1982); see also Servidone Constr. Corp. v. United States, 
    931 F.2d 860
    , 861-62 (Fed. Cir. 1991) (modifying the total cost method to
    account for bid inaccuracies was a proper method of calculating
    damages); Neal & Co., Inc. v. United States, 
    36 Fed. Cl. 600
    , 638
    (Fed. Cl. 1996), aff’d, 
    121 F.3d 683
    (Fed. Cir. 1997) (allowing
    modified total cost method of calculating damages).    We have found
    no precedent, however, specifically approving the use of this
    24
    methodology to prove quantum meruit damages.   Nonetheless, given
    our inability to review the sufficiency of the evidence and the
    fact that there is some evidence of quantum meruit damages in the
    approximate amount of $297,000, the jury's award of $197,777.00 to
    Wallace on its quantum meruit claim does not constitute plain
    error.
    25
    3.   There is some evidence to support the judgment awarding
    damages to Wallace on the Miller Act claim.
    Under the Miller Act, 40 U.S.C. § 270b, only out-of-pocket
    costs of delay are recoverable.        In awarding Miller Act damages,
    the district court must be assured that the subcontractor did not
    cause the delay and then "carefully limit the recovery to 950 F.2d 284
    , 287 (5th Cir. 1992) (quoting United States ex
    rel. T.M.S. Mechanical Contractors, Inc. v. Millers Mut. Fire Ins.
    Co. v. The Craftsmen, Inc., 
    942 F.2d 946
    , 952 (5th Cir. 1991))
    (emphasis in original).
    The Miller Act claim was submitted to the jury as follows:
    QUESTION NO. 14:
    INSTRUCTIONS:
    AHAC issued a Miller Act bond to the Army Corps of
    Engineers on behalf of Flintco in order to protect anyone
    who furnishes labor and material for the construction, to
    insure that they will be paid. A person is entitled to
    payment under the Miller Act bond if he has furnished
    labor or materials which, in good faith, were believed to
    be necessary and furnished, or incorporated into the
    project, for the work to be performed under the
    construction contract, and if he has not been paid in
    full for that work within 90 days after the last day on
    which the labor was done or the materials were furnished.
    Generally, where a subcontractor is entitled to recover
    from a general contractor for breach of contract or
    quantum meruit, the subcontractor may recover from the
    general contractor, as principal, and its surety under
    the Miller Act bond.
    26
    In this case, the Army Corps of Engineers required
    Flintco to furnish bonds guaranteeing that should Flintco
    fail to pay its project bills or complete the contract
    work, a bonding company or surety would do so.        The
    Miller Act imposed upon Flintco an obligation to furnish
    to the Army Corps of Engineers separate payment and
    performance bonds to guarantee the contract in question.
    These two bonds were executed by Flintco and its contract
    surety, AHAC, in favor of the Army Corps of Engineers.
    QUESTION:
    Do you find from a preponderance of the evidence
    that Flintco and American Home Assurance Company breached
    the Miller Act bond by failing to pay Wallace
    Construction Company?
    ANSWER:       yes
    (yes or no)
    R. Vol. 11 at 3070.    A separate damage question on the Miller Act
    claim was not submitted.         Neither party made a request for a
    separate   damage     question    or     objected   to   its   omission.
    Consequently, the trial court determined that damages on the Miller
    Act claim were the same as those found by the jury in response to
    Jury Question No. 6:
    QUESTION NO. 6:
    . . . what sum of money, if any, if paid now in
    cash, would fairly compensate Wallace Construction
    Company for labor, material, or services that they
    provided Flintco which remain unpaid by Flintco, if any?
    ANSWER:     $197,777.00
    R. Vol. 11 at 3068.
    On appeal, Flintco and AHAC challenge the damage award on the
    Miller Act claim on the basis that Wallace presented no evidence of
    27
    the actual labor, material and equipment costs it had expended and
    for which it had not been paid.      Neither Wallace nor AHAC made this
    objection before submission of the case to the jury.             Thus, the
    award of damages to Wallace on its Miller Act claim is reviewed
    only for plain error to determine whether “there is any evidence to
    support the amount of damages” awarded to Wallace.              Resolution
    Trust Corp. v. Cramer, 
    6 F.3d 1102
    , 1107-08 (5th Cir. 1993)
    (emphasis in original); see also House of Koscot Dev. Corp. v.
    American Line Cosmetics, Inc., 
    468 F.2d 64
    , 68 n.5 (5th Cir. 1972)
    (When sufficiency of the evidence is not preserved for review, “we
    may inquire whether there was any evidence supporting the issue of
    damages   to   the   jury,   even   though   we   may   not   question   the
    sufficiency of such evidence as we do find.”); United States v.
    33.5 Acres of Land, 
    789 F.2d 1396
    , 1400-1401 (9th Cir. 1986)
    (upholding on plain error review a damage award that was $36,000
    less than the expert’s damage calculation).
    Expert testimony was received from Donald McDonald.             Based
    upon his review of numerous records and logs, including among
    others Wallace's certified payroll records, Wallace's daily records
    that showed the use of the equipment on the project, and the
    Corps’s cost rates for equipment, McDonald found that Wallace had
    suffered net damages in the total amount of approximately $297,000.
    There is evidence that at least to some extent McDonald considered
    sums actually expended by Wallace.            To engage in a detailed
    28
    analysis of all of the elements considered by McDonald, such as
    Wallace’s costs of labor, equipment, and material, would require a
    review of the sufficiency of the evidence, which we cannot do.          In
    this review only for plain error, we observe that McDonald included
    in    his   estimate   at   least   some   elements   that   are   properly
    recoverable under the Miller Act, that the district court granted
    judgment in favor of Wallace on his Miller Act payment bond claim
    in an amount which was approximately $100,000 less than the net
    damage figure to which McDonald testified, and that Flintco and
    AHAC have failed to demonstrate that any improper elements of
    damages included in McDonald’s estimate of damages, if entirely
    disregarded, would leave the trial court’s judgment on damages
    without any support in the evidence.        We find that the trial court
    did not commit plain error by entering judgment in Wallace’s favor
    in the amount of $197,777.00 on the Miller Act claim.
    II.    Flintco’s Claim that Wallace Breached the Subcontract
    Flintco’s final argument is that the trial court erred in
    sustaining the jury’s finding that Wallace had not breached the
    subcontract by abandoning the work.        Flintco contends that it had
    proved beyond a preponderance of the evidence, and as a matter of
    law, that Wallace had so breached the contract, and that the trial
    court erred by failing to disregard the jury’s answers that Wallace
    had not breached its contract with Flintco, and that Flintco was
    entitled to no recovery of damages from Wallace.
    29
    A.   Standard of Review
    Unlike the preceding points where Wallace had the burden of
    proof and Flintco attempted to challenge the sufficiency of the
    evidence to support findings favorable to Wallace, on this point --
    that of proving that Wallace breached the subcontract -- Flintco
    had the burden of proof.    A claimant who bears the burden of proof
    and who believes that he is entitled to judgment as a matter of
    law, is also obliged to move for judgment as a matter of law before
    the case is submitted to the jury.          Fed. R. Civ. P. 50(a); see,
    e.g.,   Bender   v.   Brumley,   
    1 F.3d 271
    ,   275   (5th   Cir.   1993)
    (plaintiff's failure to move for directed verdict on his federal
    claims at the close of all evidence limited the court of appeals to
    a review of whether any evidence supported the jury verdict);
    Illinois Cent. Gulf R.R. Co. v. International Paper Co., 
    889 F.2d 536
    , 541 (5th Cir. 1989) (given the plaintiff's failure to move for
    directed verdict at the close of evidence, the court of appeals
    could only review the evidence to support the jury verdict for
    plain error); Coughlin v. Capitol Cement Co., 
    571 F.2d 290
    , 297
    (5th Cir. 1978) (absent motion for directed verdict, appellate
    court cannot review jury verdict for sufficiency of the evidence);
    Rawls v. Daughters of Charity, 
    491 F.2d 141
    , 147 (5th Cir.) (same),
    cert. denied, 
    419 U.S. 1032
    , 
    95 S. Ct. 513
    (1974); Parker v.
    American Oil Co., 
    327 F.2d 987
    , 988 (5th Cir. 1964) (same); McCarty
    30
    v. Pheasant Run, Inc., 
    826 F.2d 1554
    , 1555-56 (7th Cir. 1987)
    (motion   for   directed   verdict    is   a   prerequisite   to   judgment
    notwithstanding the verdict).        If a party with the burden of proof
    has conclusively established all of the elements of its claim with
    evidence that the jury cannot reject, that party must move for
    judgment as a matter of law under Rule 50(a) at the close of all
    evidence in order to preserve its ability, in the event that the
    jury finds to the contrary, to move for judgment as a matter of law
    under Rule 50(b).     See 
    id. Otherwise, the
    claimant must depend on
    the plain error standard for review or move for a new trial under
    Rule 59.10
    At the close of all evidence on its breach of contract claim
    against Wallace, Flintco did not move under Rule 50(a) for judgment
    as a matter of law.    Given Flintco's failure to make such a motion,
    and because no exception to the requirement has been shown to
    apply, Flintco waived its right to file a renewed motion for
    judgment as a matter of law under Rule 50(b).        Therefore, the plain
    error standard of review applies.
    10
    9A Charles Alan Wright & Arthur R. Miller, Federal Practice
    and Procedure § 2539 (2d ed. 1995) ("The availability of the
    alternative motion for a new trial is beneficial also to the party
    who has lost a verdict and who would be entitled to judgment as a
    matter of law save for some procedural blunder. For example, the
    evidence may be wholly insufficient to support the verdict but the
    trial court cannot order judgment as a matter of law under Rule
    50(b) if the party neglected to move for judgment at the close of
    all the evidence or if the party did not properly renew the motion
    after the unfavorable verdict was returned.").
    31
    B.     Discussion
    Wallace introduced evidence that it was Flintco that first
    breached the subcontract by requiring Wallace to perform work for
    which he was not paid.     Wallace also offered evidence of numerous
    acts and omissions by Flintco that Wallace relied upon for proof of
    Flintco’s active interference with Wallace’s performance.          Under
    Texas law, if one party to a contract breaches, there is no
    obligation for the non-breaching party to continue performance.
    See O'Shea v. International Bus. Machs. Corp., 
    578 S.W.2d 844
    , 846
    (Tex. Civ. App.--Houston [1st Dist.] 1979, writ ref'd n.r.e.) ("As
    a general rule, performance is excused when a party to a contract
    prevents the other party from performing."); L. H. Land Painting
    Co., Inc. v. S & P Constr., Inc., 
    516 S.W.2d 14
    , 16 (Tex. Civ.
    App.--Fort Worth 1974, writ dism'd) ("The law is that if one party
    to a contract is prevented by the acts of the other party to the
    contract from performing such contract, then the party so prevented
    from   performing   is   excused   from   further   performance   of   the
    contract.");    see also D.E.W., Inc. V. Depco Forms, Inc., 
    827 S.W.2d 379
    , 382 (Tex. App.--San Antonio 1992, no writ) ("[A] party
    who is in default or breach cannot maintain a suit for breach of
    contract."). Given that there is some evidence of record that
    Flintco first breached the subcontract, there is no plain error
    associated with the jury verdict against Flintco on its claim that
    Wallace breached the contract.
    32
    III. Wallace’s and Victore’s Payment Bond Liability to Flintco
    Wallace’s and Victore’s first three points on their cross-
    appeal against   Flintco      and   AHAC    relate   to   the    trial    court’s
    disregarding the jury answers and entering judgment for Flintco and
    AHAC for recovery of $101,187.30, plus prejudgment interest, on
    their payment bond claim.           Flintco and AHAC had alleged that
    Wallace and its surety, Victore, breached their duties under the
    payment bond which was issued to insure payment of Wallace’s
    suppliers.    When Wallace stopped work and, along with Victore,
    failed to pay those suppliers, Flintco and AHAC did so and sought
    to recover the sums that they had paid to Wallace’s suppliers on
    behalf of Wallace and Victore.
    A.   Standard of Review
    Again,   Flintco   and    AHAC   are    claimants    and,    in     order   to
    preserve their right to file a Rule 50(b) renewed motion for
    judgment as a matter of law, were required to have filed a Rule
    50(a) motion for judgment as a matter of law before submission of
    the case to the jury.    They did not do so, and therefore the plain
    error standard of review applies.          Likewise, the trial court could
    grant Flintco’s motion for judgment as a matter of law only if it
    found plain error in the jury verdict.           Sims' 
    Crane, 800 F.2d at 1557
    ("A lawyer who never moves for directed verdict, given the
    wording of Rule 50(b) and the clear case law regarding the effect
    33
    of such a decision--regardless of the reasons for such a decision,
    must realize that a subsequent motion for jnov can be granted only
    if plain error can be proven.").     In the absence of plain error,
    the trial court could not consider Flintco's Rule 50(b) motion.
    Purcell v. Seguin State Bank & Trust Co., 
    999 F.2d 950
    , 956-57 (5th
    Cir. 1993); 
    McCann, 984 F.2d at 670-73
    . Accordingly, we review the
    trial court's ruling on Flintco’s and AHAC's payment bond claim to
    determine whether that ruling was required to cure plain error in
    the jury verdict.
    34
    B.   Discussion
    The jury findings on Flintco’s and AHAC's payment bond claim
    were as follows:
    QUESTION NO. 15:
    Did Flintco acquire from Wallace Construction
    Company's project creditors claims against Victore
    Insurance Company?
    ANSWER:          No.
    (Yes or No)
    QUESTION NO. 16:
    Do you find from a preponderance of the evidence
    that Wallace and Victore breached their obligations to
    Flintco under the payment bond issued by Victore?
    ANSWER:          No.
    (Yes or No)
    QUESTION NO. 17:
    What amount of money, if paid now in cash, would
    fairly and reasonably compensate Flintco for its damages
    proximately caused by Wallace's and Victore's breach of
    the payment bond, if any?
    ANSWER:   $    None
    R. Vol. 11 at 3071-3073.        In disregarding the foregoing jury
    findings on the payment bond claim, the trial court wrote in its
    “Order Partially Disregarding Jury Verdict”:
    35
    Flintco and AHAC reurge their arguments contained in
    their August 25, 1995 Motion for Summary Judgment, or in
    the Alternative, for Partial Summary Judgment, which
    addressed whether Victore breached its Miller Act payment
    bond.   The Court denied this motion before trial, on
    November 2, 1995, in order to allow the parties to more
    fully uncover and develop the facts relating to this
    claim.    At trial, Flintco proved by a substantial
    preponderance of the evidence and as a matter of law that
    it was entitled to recover sums justly due from Victore,
    Wallace's bonding company, for breach of its Miller Act
    payment bond when Wallace failed to pay its materialmen
    and suppliers. Under the terms of the payment bond, it
    was undisputed that Flintco needed only show, and did
    show, that Wallace was supposed to, but did not pay the
    five materialmen and suppliers in question in full within
    ninety days after Wallace abandoned the Project.      The
    evidence was that Flintco stepped in and paid five of
    Wallace's   materialmen   and   suppliers   a  total   of
    $101,187.30 in claims unpaid by Wallace, Victore's
    principal.    In exchange for paying Wallace's unpaid
    bills, Flintco received an assignment from each creditor
    of all their claims against Wallace and Victore.       In
    other words, Wallace defaulted to its creditors and
    Flintco paid the claims itself. Instead of reimbursing
    Flintco for Wallace's bills which Flintco paid per the
    terms of the payment bond, Victore refused to recognize
    its liability to Wallace's creditors and their assignee.
    R. Vol. 13 at 3665-3666 (footnotes omitted).     The trial court’s
    statement of the evidence is accurate, and a review of the trial
    record reflects nothing to controvert the overwhelming evidence in
    support of Flintco’s and AHAC's payment bond claim.   Because there
    is no evidence to support the jury's verdict on Question Nos. 15-
    17, the jury's findings on those questions constitute plain error.
    The assignability arguments advanced by Victore as to why it
    should not be held liable on the payment bond claim were also
    thoroughly and correctly addressed by the trial court in connection
    with its grant of judgment as a matter of law to Flintco and AHAC
    36
    on their payment bond claim.11   Wallace and Victore argue that the
    11
    On Victore’s assignability issues, the trial court correctly
    reasoned and concluded:
    Victore paradoxically argued that (1) the assignment did
    not cover claims against Victore since Victore was not
    mentioned by name; and (2) the assignment released
    Victore even though it was not mentioned by name.
    Victore's first contention, that Flintco did not acquire
    any claims against it from Wallace's unpaid suppliers but
    only acquired claims against Wallace, is legally
    incorrect. Flintco acquired claims from the creditors it
    paid against Victore and Wallace, even though not
    specifically mentioned, because Victore's obligations
    were co-extensive with those of Wallace.      This point
    seems too obvious to merit comment since construction
    financiers routinely rely upon assignments naming
    contractors only, and since Victore's unsupported legal
    contention/objection     is     wholly    impracticable.
    Accordingly, since the assignments of claims against
    Wallace transferred to Flintco the derivative right to
    pursue payment under Victore's payment bond, Victore's
    first contention fails.
    Victore's second contention, that Wallace's unpaid
    suppliers' assignment to Flintco released Victore even
    though it was not mentioned by name, is equally
    incorrect. According to Victore, the provision in the
    assignment that releases Flintco "and any other
    party(ies) or surety(ies) from which Claimant might seek
    payment for materials and/or labor supplied to Wallace
    . . . " operates to excuse Victore from paying anyone,
    whether as original obligee or assignee.       Texas law,
    however, adheres to the "unity of release" rule which
    considers a party released "only if the release refers to
    him by name or with such descriptive particularity that
    his identity or connection with the tortious event cannot
    be doubted." Randall v. Dallas Power & Light Co., 
    745 S.W.2d 397
    , 401 (Tex. App.--Dallas 1987), rev'd on other
    grounds, 
    752 S.W.2d 4
    (Tex. 1988) (emphasis in original)
    (citing Duncan v. Cessna Aircraft Co., 
    665 S.W.2d 414
         (Tex. 1984).    Under this rule, "[t]he reference in a
    release to 'all other persons, firms, or corporations
    liable, or who might be claimed to be liable, does not
    supply the descriptive particularity necessary to
    specifically    identify   an   otherwise    unnamed   or
    unidentified tortfeasor." Banowsky v. State Farm Mut.
    37
    amounts Flintco paid to Wallace's materialmen and suppliers were
    offset by the jury in assessing Wallace's Miller Act and quantum
    meruit damages.   This argument is also without merit.     The jury
    instructions did not ask for or require any such offset, and this
    Court cannot impute to the jury’s answers to Question Nos. 15, 16,
    and 17, a conjectural explanation for answers which on their face
    have no support in the evidence and that are plainly in error.
    Moreover, the jury specifically was instructed not to "increase or
    reduce the amount of damages, if any, in one question because of
    the instructions regarding or your answers to any other questions
    about damages, and do not speculate about what a party's ultimate
    recovery may or may not be."   R. Vol. 11 at 3066.   We presume that
    the jury followed these instructions.
    Because there is no evidence to support the jury verdict on
    Question Nos. 15, 16, and 17, the verdict on Flintco’s and AHAC’s
    payment bond claim was plain error that affected substantial rights
    and required correction when the judgment was entered.    The trial
    court cured that plain error with its grant of judgment to Flintco
    and AHAC on their payment bond claim, and its judgment on this
    point is upheld under the plain error standard of review.
    Auto. Ins. Co., 
    876 S.W.2d 509
    , 513 (Tex. App.--Amarillo
    1994, no writ) (citing 
    Duncan, 665 S.W.2d at 419-20
    ).
    Since the language now relied upon by Victore is
    virtually identical to that rejected by the court in
    Banowsky, it is clear that Victore is not "released."
    R. Vol. 13 at 3666-3668 (footnotes omitted).
    38
    39
    IV.   Attorney’s Fees and Costs
    Finally, Wallace argues that the trial court abused its
    discretion by awarding attorney’s fees and costs to Flintco.              In
    its Amended Judgment the district court awarded to each side a
    recovery from the other side of the full amount of its attorney’s
    fees and costs, without any segregation by the parties of the
    portions of their attorney’s fees and costs that were attributable
    to the issues upon which they had prevailed. According to Wallace,
    because Flintco and AHAC prevailed only on the payment bond claim,
    Flintco should not have been awarded attorney's fees or costs.
    Wallace maintains that the district court at the very least erred
    in failing to segregate and to limit the awards of attorney’s fees
    and costs only to those incurred on the payment bond claim upon
    which Flintco and AHAC prevailed.           Under Texas law, when a
    case involves more than one claim, ordinarily attorney’s fees can
    be awarded only for necessary legal expenses incurred in connection
    with the claims upon which the recovery of fees is authorized.
    Bank One, Texas, N.A. v. Taylor, 
    970 F.2d 16
    , 35 (5th Cir. 1992),
    cert. denied, 
    508 U.S. 906
    , 
    113 S. Ct. 2331
    (1993).               Wallace,
    however, did not object at any time to Flintco’s failure to
    segregate   its   requested   attorney’s   fees   or   to   the   award   of
    attorney’s fees to Flintco.        This Court generally refuses to
    consider issues not raised below unless the issue presents a pure
    question of law or an issue which, if ignored, would result in a
    40
    miscarriage of justice.       Deshotels v. SHRM Catering Servs., Inc.,
    
    842 F.2d 116
    , 120 (5th Cir. 1988) (citing Volkswagen of America,
    Inc. v. Robertson, 
    713 F.2d 1151
    , 1166 (5th Cir. 1983)).            Likewise,
    a new argument raised for the first time on appeal, even if it
    concerns an issue considered by the trial court, will not be
    addressed unless it meets the plain error standard.             Forbush v.
    J.C. Penney Co., 
    98 F.3d 817
    , 822 (5th Cir. 1996) (new argument on
    appeal regarding award of attorney’s fees rejected as not meeting
    plain error standard).         The rule applicable here, as regards
    Wallace’s complaint on appeal about the award of attorney’s fees to
    Flintco and AHAC,    is as it was stated in Powell v. Old Southern
    Life Ins. Co., 
    780 F.2d 1265
    , 1268 (5th Cir. 1986):
    [N]o issue concerning the amount of fees due or the
    method of calculating the award was raised in the
    district court, and we do not consider issues not raised
    below unless they present a pure question of law or a
    refusal to do so would “result in a miscarriage of
    justice.”
    (quoting Volkswagen of America, 
    Inc., 713 F.2d at 1166
    ).             Flintco
    and   AHAC   prevailed   on   a   portion   of   the   litigation    and,   in
    particular, upon their successful motion for judgment as a matter
    of law notwithstanding an adverse jury verdict on Flintco’s and
    AHAC’s payment bond claim.        Upon this record, and given Wallace’s
    waiver of the fee segregation issue in the trial court, we affirm
    the district court’s determination on attorney’s fees.
    41
    Wallace did object in the trial court that Flintco and AHAC
    were not entitled to recover costs because the costs sought by them
    were not incurred in connection with the claim upon which Flintco
    and AHAC were successful.12    Wallace especially complained that
    $40,415 of the $73,778 in costs awarded to Flintco and AHAC were
    for expert witness fees although Flintco’s and AHAC’s expert did
    not testify regarding the payment bond claim on which Flintco and
    AHAC prevailed.   In this appeal Wallace argues that the trial
    court’s award of $73,778.43 in costs to Flintco and AHAC, including
    $40,415.68 for fees for an expert witness who offered no evidence
    on the one claim on which Flintco and AHAC prevailed, constitutes
    an abuse of discretion.   Flintco and AHAC argue that the award was
    within the trial court’s broad discretion, but also point out that
    of the $90,091 in costs awarded to Wallace, $76,610 was for his
    expert’s fees.
    12
    In his Motion for Entry of Judgment based on the Jury
    Verdict, Wallace requested attorney’s fees and costs. Flintco, in
    its Motion for Judgment Notwithstanding the Verdict, also requested
    attorney’s fees and costs.      Flintco did not oppose Wallace’s
    request to recover his attorney’s fees and costs and, remarkably
    enough, Wallace did not argue against Flintco’s request to recover
    its attorney’s fees and costs. In the Order Partially Disregarding
    the Jury Verdict, the district court awarded costs of $71,546.50 to
    Flintco and AHAC, and $90,091.00 in costs to Wallace.        In his
    Motion to Alter and Amend, Wallace argued that it was error to
    award costs to Flintco and AHAC when the costs incurred by them
    were not related to the one claim (the payment bond claim) upon
    which they ultimately prevailed. Flintco did not object in the
    trial court to the costs awarded to Wallace. Despite Wallace’s
    costs argument, the Amended Judgment included cross-awards of costs
    to Flintco and AHAC in the total sum of $73,778.43 and to Wallace
    in the total sum of $90,091.00.
    42
    As set forth above, Flintco and AHAC prevailed only on the
    payment bond claim, and Flintco and AHAC incurred no expert witness
    fees in prosecuting that claim.       We agree that the trial court
    abused its discretion when it included $40,415.68 in expert witness
    fees as part of the costs that it awarded to Flintco and AHAC.13
    Wallace’s complaint on this point, however, requires us to
    observe a more fundamental error of law, namely, that the cross-
    awards of costs include amounts for expert witness fees in excess
    of the amounts allowed by 28 U.S.C. § 1821.        Flintco and AHAC
    claimed and were awarded expert witness fees in the sum of $40,415
    and Wallace and Victore claimed and were awarded expert witness
    fees in the sum of $76,610.   Both sides sought recoveries of those
    expert witness fees in the trial court by relying upon Copper
    Liquor Inc. v. Adolph Coors, Co., 
    684 F.2d 1087
    , 1100 (5th Cir.
    1982), which had held that expert witness fees in excess of that
    provided for by 28 U.S.C. § 1821 may be awarded in “exceptional
    circumstances” such as when the “expert testimony was necessary or
    helpful to a presentation of civil rights claims, or indispensable
    to the determination of the case.”     That holding of Copper Liquor
    was directly overruled by International Woodworkers of Am. v.
    13
    Such an award may be viewed as impermissibly shifting the
    costs incurred by Flintco and AHAC on claims on which they did not
    prevail to Wallace and AHAC. See Hall v. State Farm Fire & Cas.
    Co., 
    937 F.2d 210
    , 216 (5th Cir. 1991)(“A trial court has wide
    discretion with regard to the costs in a case and may order each
    party to bear his own costs. The judge cannot, however, order the
    prevailing party to share, or shoulder all of, the costs of a
    nonprevailing party unless the costs serve as a sanction.”).
    43
    Champion Int’l Corp., 
    790 F.2d 1174
    , 1175-76 (5th Cir. 1986) (en
    banc), aff’d sub nom Crawford Fitting Co. v. J.T. Gibbons, Inc.,
    
    482 U.S. 437
    ,    107    S.    Ct.   2494    (1987).        In    International
    Woodworkers,      this      Circuit    held    that   “the    fees     of    non-court-
    appointed expert witnesses are taxable by federal courts in non-
    diversity cases only in the amount specified by § 1821, except that
    fees   in     excess   of    that     amount   may    be   taxed      when    expressly
    authorized by Congress, or when one of the three narrow equitable
    exceptions recognized by Alyeska applies.”                   
    Id. at 1181.
          None of
    the Alyeska exceptions14 applies to this case.
    Because expert witness fees in excess of those provided for by
    28 U.S.C. § 1821 may not be awarded as costs in a nondiversity case
    such as this, International 
    Woodworkers, 790 F.2d at 1175
    , and
    because neither side in this dispute limited its claims for costs
    to those amounts allowed by § 1821, the cross-awards of costs in
    this case constitute plain error.
    14
    Costs in excess of that allowed by § 1821 may be awarded
    under the exceptions announced in Alyeska Pipeline Serv. Co. v.
    Wilderness Soc’y, 
    421 U.S. 240
    , 
    95 S. Ct. 1612
    (1975) when:
    (1) the trustee of a fund or property, or a party in
    interest, preserved or recovered the fund for the benefit
    of others in addition to himself;
    (2)   a party acted in wilful disobedience of a court
    order; or
    (3)    the losing party had acted in bad faith,
    vexatiously, wantonly, or for oppressive reasons.
    International 
    Woodworkers, 790 F.2d at 1177
    .
    44
    To reverse Flintco’s and AHAC’s erroneous recovery of $40,415
    in expert witness fees but to leave standing Wallace’s erroneous
    recovery of $76,610 in expert witness fees would amount to a
    manifest miscarriage of justice.        Moreover, since the district
    court must reconsider the taxation of costs on remand, in a case
    such as this -- where each party has prevailed on a portion of the
    case -- the district court should have before it the entire costs
    issue. Otherwise, the district court would effectively be deprived
    of its broad discretion to consider the total costs that are
    properly taxable and the competing arguments of the parties as to
    how those costs should be fairly borne.        Because the cross-awards
    of taxable costs that were adjudged here are both unusual and
    intertwined, and because the awards are infected with erroneous
    inclusions of expert witness fees in excess of what is permitted
    under § 1821, we conclude that a manifest miscarriage of justice
    can be avoided on this issue only by setting aside the cross-awards
    of costs and remanding the costs issue for further proceedings by
    the district court.
    Conclusion
    For   the   foregoing   reasons,   we   REVERSE   and   VACATE   those
    portions of the Amended Judgment that adjudge cross-recoveries of
    costs by Flintco and AHAC from Wallace and Victore, and by Wallace
    from Flintco and AHAC, and we REMAND this case to the district
    court for further proceedings consistent with this opinion on the
    45
    taxation of costs; we REFORM the Amended Judgment to consolidate
    the two segments discussed above in footnote 3, as follows:
    It is ORDERED and ADJUDGED that Marshall E.
    Wallace, d/b/a Wallace Construction Company, shall
    recover from Flintco, Inc. and American Home
    Assurance Co., jointly and severally:
    1.   Actual   damages   in   the   amount    of
    $197,777.00;
    2.   Pre-judgment interest thereon in the amount of
    $62,681.85;
    3.   Post-judgment interest on all amounts
    awarded in item numbers one and two above
    at the currently prevailing rate pursuant
    to 28 U.S.C. § 1961 of 5.90% per annum,
    compounded annually, from the date of
    this judgment until paid;
    we REFORM all awards of post-judgment interest in the Amended
    Judgment to provide that post-judgment interest shall be compounded
    annually; and the Amended Judgment is otherwise AFFIRMED.
    46
    

Document Info

Docket Number: 96-11360

Citation Numbers: 143 F.3d 955, 1998 U.S. App. LEXIS 14507

Judges: King, Jones, Werlein

Filed Date: 6/29/1998

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (40)

Neal & Company, Inc. v. United States , 121 F.3d 683 ( 1997 )

Duncan v. Cessna Aircraft Co. , 27 Tex. Sup. Ct. J. 213 ( 1984 )

Randall v. Dallas Power & Light Co. , 1987 Tex. App. LEXIS 9270 ( 1987 )

City of Houston v. R. F. Ball Construction Co. , 1978 Tex. App. LEXIS 3500 ( 1978 )

Illinois Central Gulf Railroad Company, Cross-Appellee v. ... , 889 F.2d 536 ( 1989 )

Citizens National Bank of Orlando and West Construction ... , 367 F.2d 541 ( 1966 )

Betty I. Hardy Hall, Cross-Appellee v. State Farm Fire & ... , 937 F.2d 210 ( 1991 )

united-states-of-america-for-the-use-and-benefit-of-lochridge-priest-inc , 950 F.2d 284 ( 1992 )

Joseph F. Powell v. Old Southern Life Insurance Co. , 780 F.2d 1265 ( 1986 )

Banowsky v. State Farm Mutual Automobile Insurance Co. , 876 S.W.2d 509 ( 1994 )

Bildon Farms, Inc. v. Ward County Water Improvement Dist. ... , 10 Tex. Sup. Ct. J. 408 ( 1967 )

Olan J. Guilbeau, Sr., Plaintiffs-Intervenors-Appellees v. ... , 85 F.3d 1149 ( 1996 )

Frank Coughlin, Padre Concrete Corporation, A. W. Van ... , 571 F.2d 290 ( 1978 )

62-fair-emplpraccas-bna-1336-62-empl-prac-dec-p-42573-walter-p , 999 F.2d 950 ( 1993 )

Polanco v. City of Austin, Tex. , 78 F.3d 968 ( 1996 )

67-fair-emplpraccas-bna-400-31-fedrserv3d-1149-cassandra-macarthur , 45 F.3d 890 ( 1995 )

Sims' Crane Service, Inc. v. Ideal Steel Products, Inc. , 800 F.2d 1553 ( 1986 )

U. S. Industries, Inc. v. Blake Construction Co., Inc., U. ... , 671 F.2d 539 ( 1982 )

united-states-of-america-for-the-use-and-benefit-of-straus-systems-inc , 969 F.2d 83 ( 1992 )

Volkswagen of America, Inc. v. Willard E. Robertson, Etc. , 713 F.2d 1151 ( 1983 )

View All Authorities »