LaShip, L.L.C. v. Hayward Baker, Incorporat , 680 F. App'x 317 ( 2017 )


Menu:
  •      Case: 15-30816       Document: 00513892300         Page: 1     Date Filed: 03/01/2017
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    No. 15-30816
    Fifth Circuit
    FILED
    March 1, 2017
    LASHIP, L.L.C.; TERREBONNE PORT COMMISSION,                                 Lyle W. Cayce
    Clerk
    Plaintiffs - Appellants
    v.
    HAYWARD BAKER, INCORPORATED,
    Defendant - Appellee
    Appeals from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:11-CV-546
    Before JOLLY, HIGGINBOTHAM, and PRADO, Circuit Judges.
    PER CURIAM:*
    LaShip, LLC (“LaShip”) and Terrebonne Port Commission (“TPC”)
    brought this suit against Hayward Baker, Inc. (“HBI”), which performed soil
    stabilization work for a large shipbuilding facility in Houma, Louisiana.
    Trouble arose when the soil stabilization work began to fail. Disputes and
    finger-pointing ultimately gave rise to this litigation against HBI for, inter
    alia, breach of contract and negligent failure to warn under Louisiana law.
    * Pursuant to 5th Cir. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5th Cir.
    R. 47.5.4.
    Case: 15-30816    Document: 00513892300     Page: 2   Date Filed: 03/01/2017
    No. 15-30816
    The district court, after a ten-day bench trial, entered judgment for HBI,
    dismissing LaShip and TPC’s claims. We AFFIRM.
    I.
    LaShip is the owner and operator of a shipbuilding operation in Houma,
    Louisiana. TPC is a political subdivision of the State of Louisiana. From 2007
    to 2011, LaShip undertook the construction of a large shipbuilding facility in
    Houma (the “Project”) on land that it owned and on land belonging to TPC but
    under lease to LaShip. Phases I and III of the Project were completed on
    LaShip’s land; Phase II involved the bulkhead for the facility’s waterfront
    access and was located on TPC’s land.
    LaShip retained Lyle Stover Engineering, Inc., now known as Holon
    Engineering and Construction LLC (“LSE/Holon”), to craft a design for the
    foundation system in Phases I and III. Based on the results of soil borings
    conducted by Burns, Cooley, Dennis, Inc. (“BCD”), David Lyle of LSE/Holon
    concluded that soil-mixed columns were an appropriate option to support the
    foundation system.
    Drawing from the LSE/Holon design specifications and the soil boring
    tests performed by BCD, HBI submitted a bid to complete the soil mixing and
    drilled shaft work on the Project.      In July 2008, LaShip accepted HBI’s
    proposal.   The contractual agreement between LaShip and HBI involved
    several documents: HBI’s original proposal, the Revised Schedule of Price, the
    Performance Specifications, the Field Execution Plan, and a mobilization
    credit agreement.
    The contractual agreement between LaShip and HBI called for HBI to
    install subterranean soil-mix columns to form the foundation of the
    shipbuilding facility and prevent it from falling victim structurally to the soft
    and compressible Louisiana soil. As part of its Project obligations, HBI was to
    obtain “wet grab” samples from two of the columns made each day to ascertain
    2
    Case: 15-30816    Document: 00513892300     Page: 3   Date Filed: 03/01/2017
    No. 15-30816
    the columns’ strength. The sampling process required the lowering of a tool
    into the column at varying depths to recover a sample of the mixed material.
    The samples were then submerged in cylinders and tested for “unconfined
    compressive strength” intermittently over the course of twenty-eight days. Of
    the samples tested in Phase I, at least 90% possessed an unconfined
    compressive strength of at least 100 psi. All of the Phase II and III samples
    demonstrated a strength of at least 125 psi and 100 psi, respectively.
    Some of the six-foot diameter columns that were installed met the
    strength requirements, but nonetheless exhibited unwelcome spiraling,
    indicative of the presence of both mixed and unmixed soil. In addition, HBI
    experienced several cave-ins during its installation of the drill shafts on some
    of the columns. In November 2008, against HBI’s wishes, LaShip decided to
    abandon the 156 six-foot columns, move the footprint, and switch to eight-foot
    columns.    HBI recommenced the installation in the new location but
    nonetheless continued to encounter difficulties.
    No written contract linked HBI to TPC for HBI’s work on Phase II of the
    Project, because TPC awarded the Phase II contract to F. Miller Construction,
    which then subcontracted with HBI to complete the soil-mixing job. The work
    for Phase II was completed in 2010.
    Unwanted settlement of the foundation columns occurred during Phase
    III much like it did during Phase I. After all of the foundation columns had
    been installed, LaShip commissioned additional strength testing of the
    columns—the results of which exhibited a range of column strengths—and
    hired A.H. Beck Foundation Co. (“Beck”) to perform what LaShip alleged to be
    remedial work on Phase I.
    On January 21, 2011, LaShip filed suit in state court in the 32nd Judicial
    District Court for the Parish of Terrebonne, Louisiana, asserting numerous
    claims against HBI. In March 2011, HBI filed a notice of removal to federal
    3
    Case: 15-30816     Document: 00513892300     Page: 4   Date Filed: 03/01/2017
    No. 15-30816
    court on the basis of diversity. LaShip, LLC v. Hayward Baker, Inc., No. 11-
    0546, 
    2013 WL 5781688
    , at *2 (E.D. La. Oct. 25, 2013). The federal district
    court dismissed LaShip’s unjust enrichment claim, and its claims for breach of
    contract, negligence, and breach of the implied duty of workmanlike
    performance proceeded to trial. HBI, in turn, brought a counterclaim against
    LaShip for breach of contract when LaShip failed to compensate HBI for the
    additional soil mixing that it completed during Phase I. TPC joined the lawsuit
    on March 6, 2013, when it filed a negligence claim against HBI, contending
    that HBI’s column installation was insufficient and that HBI acted negligently
    in failing to warn of a dangerous condition.
    At the conclusion of a ten-day bench trial, the district court’s 66-page
    ruling and judgment concluded with a holding in favor of LaShip with respect
    to a $375,000 mobilization refund that HBI owed to LaShip pursuant to their
    agreement.    In addition, the court held that LaShip failed to prove by a
    preponderance of the evidence its remaining claims against HBI. The court
    issued judgment in favor of HBI on its breach of contract counterclaim against
    LaShip. It also found that TPC’s claims against HBI were delictual in nature
    and were therefore prescribed because they were filed after the one-year cutoff
    date under Louisiana law. LaShip and TPC timely appealed.
    II.
    When a judgment from a bench trial is appealed, we review the district
    court’s conclusions of law de novo and findings of fact for clear error. Steele v.
    Leasing Enterprises, Ltd., 
    826 F.3d 237
    , 242 (5th Cir. 2016). Factual findings
    are clearly erroneous if they lack “substantial evidence to support [them], the
    court misinterpreted the effect of the evidence, or this court is convinced that
    the findings are against the preponderance of credible testimony.” 
    Id.
     (quoting
    Bd. of Trs. New Orleans Emp’rs Intern. Longshoremen’s Ass’n v. Gabriel,
    Roeder, Smith & Co., 
    529 F.3d 506
    , 509 (5th Cir. 2008)).
    4
    Case: 15-30816     Document: 00513892300     Page: 5   Date Filed: 03/01/2017
    No. 15-30816
    III.
    A.
    LaShip contends that the district court erred in finding that HBI
    satisfied its contractual obligations to LaShip and that HBI owed no duty to
    warn LaShip about alleged defects in the design of the columns. Moreover,
    LaShip argues that the district court erred in instructing LaShip to
    compensate HBI for its installation of 156 columns that were later abandoned
    when the footprint of the facility was moved.
    1.
    Because jurisdiction in federal court was based on diversity of citizenship
    between the parties, the district court properly applied Louisiana law in
    analyzing LaShip’s breach of contract claim. See Mozeke v. Int’l Paper Co., 
    856 F.2d 722
    , 724 (5th Cir. 1988). To prevail on a claim of breach of contract in
    Louisiana, a plaintiff must prove the following by a preponderance of the
    evidence: “(1) the obligor’s undertaking an obligation to perform, (2) the obligor
    failed to perform the obligation (the breach), and (3) the failure to perform
    resulted in damages to the obligee.” Favrot v. Favrot, 
    68 So. 3d 1099
    , 1108-09
    (La. Ct. App. 2011). The mutual intent of the parties dictates the terms of the
    contract, and when the terms of the contract are “clear and explicit and lead to
    no absurd consequences, no further interpretation may be made in search of
    the parties’ intent.” LA. CIVIL CODE art. 2046. Furthermore, each provision of
    the contract should be interpreted in the light of the other provisions, so as to
    give meaning to each. LA. CIVIL CODE art. 2050.
    Here, the district court based its holding on the express language of the
    Performance Specifications and found that LaShip failed to prove by a
    preponderance of the evidence that HBI breached the contract.               It is
    undisputed that HBI fulfilled the Performance Specifications, namely that 90%
    of the Phase I and 100% of the Phase II and Phase III samples crossed the
    5
    Case: 15-30816     Document: 00513892300       Page: 6   Date Filed: 03/01/2017
    No. 15-30816
    minimum threshold for unconfined compressive strength. LaShip’s position is
    that the Performance Specifications were merely a component of HBI’s
    overarching obligation to properly install soil-mixed columns—it is with
    respect to this ultimate obligation that LaShip contends HBI fell short.
    LaShip, however, is unable to point to a specific provision of the contract that
    HBI allegedly breached.
    We commend the district court on its thorough decision. We find that the
    court did not err in identifying HBI’s obligation under the contract as the
    installation of soil-mix columns “such that, when tested as set out in the
    specifications, 90 percent of the Phase I samples demonstrated an unconfined
    compressive strength of at least 100 psi.” LaShip, LLC v. Hayward Baker, Inc.,
    No. 2:11-cv-00546-NJB-SS, slip op. at 29 (E.D. La. Aug. 13, 2015). Moreover,
    because the express specifications were met and because LaShip could not
    identify a specific provision in the contract as a point of breach, we hold that
    the district court did not clearly err in determining that HBI did not breach
    the contract with LaShip.
    2.
    LaShip also asserts a negligent failure to warn claim on appeal. It
    argues that the district court erred in finding that HBI owed no duty to warn
    LaShip about alleged defects in the design of the columns. Although LaShip
    raised this argument in the district court for the first time in post-trial briefing,
    we need not address the merits of this tardy assertion because we conclude
    that HBI is statutorily immune from this claim under Louisiana Revised
    Statute 9:2771. The applicable statute provides:
    No contractor, including but not limited to a residential building
    contractor . . . shall be liable for destruction or deterioration of or
    defects in any work constructed, or under construction, by him if
    he constructed, or is constructing, the work according to plans or
    specifications furnished to him which he did not make or cause to
    6
    Case: 15-30816     Document: 00513892300      Page: 7    Date Filed: 03/01/2017
    No. 15-30816
    be made and if the destruction, deterioration, or defect was due to
    any fault or insufficiency of the plans or specifications. This
    provision shall apply regardless of whether the destruction,
    deterioration, or defect occurs or becomes evident prior to or after
    delivery of the work to the owner or prior to or after acceptance of
    the work by the owner. . . .
    LSA-R.S. 9:2771. Generally, a contractor may rely on LSA-R.S. 9:2771 to
    shield it from liability for any defects that may arise as a result of the
    contractor’s adherence to plans and specifications that were provided to it.
    Such a contractor cannot escape liability, however, “if he has a justifiable
    reason to believe that adherence to plans and specifications would create a
    hazardous condition.” Oxley v. Sabine River Auth., 
    663 So. 2d 497
    , 504 (La. Ct.
    App. 3 Cir. 1995) (quoting Nolan v. S&W Steel Fabricators, Inc., 
    600 So. 2d 929
    , 932 (La. Ct. App. 2 Cir. 1992)).
    Here, HBI was given performance specifications that it did not “make or
    cause to be made.” LSA-R.S. 9:2771. Furthermore, the district court found
    based on the evidence presented at trial that the settlement of the structure in
    Phases I and III stemmed from a design defect in the length of the columns.
    LaShip, slip op. at 47. Thus, the “defect was due to . . . fault or insufficiency of
    the plans or specifications.”     LSA-R.S. 9:2771.     The statutory immunity,
    therefore, applies and relieves HBI of liability based on its installation of the
    columns according to the Performance Specifications. In addition, LaShip is
    unable to point to specific evidence indicating that HBI had a “justifiable
    reason to believe that adherence to the plans and specifications would create a
    hazardous condition.” Oxley, 
    663 So. 2d at 504
    . LaShip instead underscores
    HBI’s geotechnical expertise and asserts that HBI knew or should have known
    that the design was allegedly defective and thus had an affirmative tort duty
    7
    Case: 15-30816       Document: 00513892300          Page: 8     Date Filed: 03/01/2017
    No. 15-30816
    to warn LaShip. 1 We decline to broaden the scope of the affirmative tort duty
    of contractors under Louisiana law to the extent urged by LaShip.                          We
    therefore hold that HBI is immune from liability from the plaintiff’s tort claim
    under LSA-R.S. 9:2771. 2
    3.
    LaShip further challenges the district court’s ruling in favor of HBI on
    HBI’s counterclaim against LaShip. HBI asserted in its counterclaim that it
    was not compensated for the 156 soil-mix columns that it installed prior to
    LaShip’s decision to move the facility footprint. LaShip argues that it does not
    owe HBI compensation for the 156 columns because they “were necessarily
    abandoned due to their defects and lack of reliability.” HBI argues, in turn,
    that it disagreed with LaShip’s decision to abandon the columns, a decision
    that was also opposed by LSE/Holon. Further, HBI asserts, LaShip did not
    allow HBI to load test the 156 columns before they were abandoned.
    In deciding in favor of HBI, the district court considered the Project’s
    Revised Schedule of Prices, which provided that “final payment will be based
    on the actual quantities.” Both parties agreed that “HBI originally agreed to
    mix 40,290 cubic yards of soil on Phase I, but that HBI actually mixed
    65,571.69 cubic yards of soil on that Phase.” LaShip, slip op. at 64. In the light
    1 LaShip relies on the Louisiana case Bunge Corp. v. GATX Corp., 
    557 So. 2d 1376
    (La. 1990), in which the Louisiana Supreme Court held that the contractor of a grain storage
    tank had a duty to warn the owner of the possibility of rupture resulting from the contractor’s
    construction of the tank. The Bunge court’s reasoning was that “the superior knowledge of
    the builder” renders him logically in a position, when he “acquires knowledge that can
    prevent personal injury or property loss,” to “convey that information to those for whom he
    has built.” 
    Id. at 1385
    . The court in Bunge, however, did not address statutory immunity
    under LSA-R.S. 9:2771. Moreover, the contractor in Bunge both designed and constructed
    the storage tank; such a situation is distinguishable from that of the instant case, in which
    HBI did not design the soil-mix column specifications. Thus, LaShip’s reliance on Bunge is
    misplaced.
    2 Our holding on the negligent failure to warn issue encompasses any argument by
    LaShip that HBI negligently failed to warn it of a dangerous condition resulting from
    allegedly deficient column construction.
    8
    Case: 15-30816    Document: 00513892300     Page: 9   Date Filed: 03/01/2017
    No. 15-30816
    of this fact and other corroborating evidence, the court held that HBI was not
    compensated for 23,652.69 cubic yards of soil and thus requires compensation.
    Id. at 65. We agree with the district court’s findings.
    B.
    We now turn to the claims of TPC against HBI. TPC contends that the
    district court erred in rejecting TPC’s claim of contra non valentem and finding
    that TPC’s claims were prescribed. Even if TPC’s claims were not prescribed,
    the district court found that they would have nonetheless failed on the merits.
    TPC also appeals the district court’s exclusion of the expert testimony of TPC
    witness Joseph Waxse and argues that the district court’s reliance on HBI’s
    experts was improper. We hold that the district court did not err in its findings
    and holdings.
    1.
    In general, Louisiana Civil Code Article 3492 applies a one-year
    prescription period to all delictual actions—that is, actions involving the
    causing of damages to another that are not governed by a contract. Specific to
    immovable property, Article 3493 provides, “[T]he one year prescription
    commences to run from the day the owner of the immovable acquired, or should
    have acquired, knowledge of the damage.” LA. CIVIL CODE art. 3493. Although
    HBI completed its work on Phase II of the Project in 2010, TPC did not file suit
    until March 2013. Thus, the action is prescribed on its face. Louisiana case
    law recognizes that when an action is facially prescribed, the plaintiff bears
    the burden of proving that prescription was “interrupted, suspended, or
    renounced.” Gary v. Camden Fire Ins. Co., 
    676 So. 2d 553
    , 555 (La. 1996).
    TPC contends that the doctrine of contra non valentem applies and
    should have suspended the running of prescription, thereby preserving the
    viability of TPC’s claim. Under Louisiana law, the doctrine of contra non
    valentem suspends the running of prescription in “exceptional circumstances.”
    9
    Case: 15-30816    Document: 00513892300       Page: 10   Date Filed: 03/01/2017
    No. 15-30816
    Lapuyade v. Rawbar, Inc., 
    190 So. 3d 1214
    , 1220 (La. Ct. App. 2016). Louisiana
    courts apply the doctrine of contra non valentem in four situations:
    (1) where there was some legal cause which prevented the courts
    or their officers from taking cognizance of or acting on the
    plaintiff’s action;
    (2) where there was some condition coupled with the contract or
    connected with the proceedings which prevented the creditor
    from suing or acting;
    (3) where the debtor himself has done some act effectually to
    prevent the creditor from availing himself of his cause of action;
    or
    (4) where the cause of action is neither known nor reasonably
    known by the plaintiff even though plaintiff’s ignorance is not
    induced by the defendant.
    Marin v. Exxon Mobil Corp., 
    48 So. 3d 234
    , 245 (La. 2010). The Louisiana
    Supreme Court has also noted that the analysis of the fourth prong of the
    contra non valentem doctrine and that of Article 3493 of the Louisiana Civil
    Code are the same, because they both involve the suspension of prescription
    until the plaintiff knew, or reasonably should have known, of the damage
    caused. 
    Id.
     The key inquiry in the analysis is whether knowledge, either
    actual or constructive, existed to trigger the running of the prescriptive period.
    To identify constructive knowledge, the court looks to “the reasonableness of
    the plaintiff’s action or inaction in light of his education, intelligence, and the
    nature of the defendant’s conduct.” 
    Id. at 246
    .
    The district court concluded here that the contra non valentem doctrine
    was inapplicable because TPC failed to establish the “reasonableness of its
    inaction with respect to filing [a] lawsuit within the one year prescription
    period.” LaShip, slip op., at 62. The district court pointed out that the only
    evidence presented in support of TPC’s contra non valentem argument was the
    testimony of TPC’s Executive Director, David Rabalais. Rabalais testified that
    he became aware for the first time in early 2013 that the soil-mixed columns
    10
    Case: 15-30816    Document: 00513892300     Page: 11   Date Filed: 03/01/2017
    No. 15-30816
    exhibited problems.     He also noted, however, that TPC’s engineer and
    representatives had continuously monitored the work site and HBI’s
    installation of the soil-mix columns. The court reasoned that the ongoing
    presence of these officials on-site was sufficient to demonstrate the existence
    of constructive knowledge on the part of TPC. Thus, the court held that TPC
    could not rely on contra non valentem to shield it from prescription. We find
    that the district court thoroughly considered the evidence before it and agree
    with the district court’s conclusion that TPC’s claims against HBI were
    prescribed because they were filed after the one-year prescriptive period for
    delictual actions.
    2.
    TPC also contends that the district court erred in excluding the expert
    testimony of geotechnical engineer Joseph Waxse, which TPC attempted to
    enter under Rule 26(a)(2)(C) of the Federal Rules of Civil Procedure. Further,
    TPC argues that the district court erred by relying on HBI’s experts. We
    disagree.
    Rule 26(a)(2)(C) addresses the disclosure of expert witnesses who were
    involved in the events leading up to litigation and may testify both as an expert
    and as a fact witness. The rule states:
    (C) Witnesses Who Do Not Provide a Written Report. Unless
    otherwise stipulated or ordered by the court, if the witness is not
    required to provide a written report, this disclosure must state:
    (i)    the subject matter on which the witness is expected to present
    evidence under Federal Rule of Evidence 702, 703, or 705; and
    (ii)   a summary of the facts and opinions to which the witness is
    expected to testify.
    FED. R. CIV. P. 26(a)(2)(C).   Subsection (C) is to be contrasted with Rule
    26(a)(2)(B), which accounts for experts who are retained specifically for
    11
    Case: 15-30816     Document: 00513892300       Page: 12   Date Filed: 03/01/2017
    No. 15-30816
    litigation. Rule 26(a)(2)(B) expert witnesses are required to file a written
    report. See FED. R. CIV. P. 26(a)(2)(B).
    The district court found that Waxse did not fit the criteria for
    classification as a Rule 26(a)(2)(C) witness.       Waxse works with Terracon
    Consultants, Inc. When Beck contracted with LaShip and TPC to complete
    LaShip’s remediation work on the Project, Beck subcontracted with Terracon
    to complete Cone Penetrometer Testing (“CPT”) to “measure soil strength and
    compressibility and to assess the soil type in areas where HBI had installed
    soil-mixed columns.” To explain its reasoning, the court referred to emails
    between the plaintiffs and Waxse, as well as the content of Waxse’s
    testimony—both of which supported the district court’s conclusion that
    Waxse’s opinion was prepared specifically for litigation and did not equate to
    the ground-level opinion of an expert who was involved in the events leading
    up to litigation. We apply an abuse of discretion standard and agree that the
    district court did not err in excluding Waxse’s expert testimony because an
    expert report pursuant to Rule 26(a)(2)(B) was not filed.
    With respect to TPC’s claim that the district court improperly relied on
    the testimony of HBI’s experts, we decline to disturb the district court’s expert
    witness credibility determination.      Moreover, because we hold that TPC’s
    claims are prescribed, we need not analyze this issue further.
    IV.
    In sum, we have considered the arguments of each party with respect to
    the issues present in the instant case, and we AFFIRM the judgment of the
    district court on all the issues.
    12