Bourg v. Continental Oil Co ( 1999 )


Menu:
  •                   UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    No. 98-30572
    RONALD C. BOURG; ET AL.,
    Plaintiffs,
    L & L SANDBLASTING, INC.,
    Intervenor Plaintiff -
    Third Party Defendant - Appellee,
    VERSUS
    CONTINENTAL OIL COMPANY, also known as Conoco, Inc.; ET AL.,
    Defendants,
    CNG PRODUCING COMPANY, also known as Consolidated
    Natural Gas Company,
    Defendant - Third Party
    Plaintiff - Appellant.
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    (95-CV-3192-D)
    August 13, 1999
    Before SMITH, DeMOSS, and STEWART, Circuit Judges
    PER CURIAM:*
    *
    Pursuant to 5TH CIR. R. 47.5, the Court has determined
    that this opinion should not be published and is not precedent
    except under the limited circumstances set forth in 5TH CIR. R.
    47.5.4.
    In this appeal we are asked to decide whether the district
    court properly granted summary judgment to third-party defendant-
    appellee, L & L Sandblasting (“L & L”), against the impleader claim
    asserted by third-party plaintiff-appellant, CNG Producing Company
    (“CNG”).   For the reasons that follow, we dismiss the instant
    appeal as untimely.
    I.
    Transcontinental Gas Pipe Line Corporation (“Transco”) owns
    and operates pipeline metering equipment.   In May, 1994, Transco
    contracted with L & L to sandblast and paint metering equipment
    located on offshore platforms in the Gulf of Mexico. To facilitate
    that operation, Transco chartered the M/V MISS JANE, a supply
    vessel owned by LaSalle Marine (“LaSalle”), to ferry L & L workers
    to the various platforms.
    Ronald Bourg (“Bourg”) was employed by L & L as a sandblaster
    and painter.   On October 6, 1994, Bourg was injured when he fell
    through deteriorated grating on the dolphin deck of Fixed Platform
    246-A, which was owned and operated by CNG.    At the time of his
    injury, Bourg was attempting to tie the M/V MISS JANE to the
    platform, which was located on the Outer Continental Shelf.
    Bourg filed suit against CNG and others in federal district
    court in the Eastern District of Louisiana.     CNG then demanded
    indemnification from Bourg’s employer, L & L, in accordance with an
    indemnification provision contained in an Offshore Master Service
    Contract it had executed with L & L on March 17, 1993.   When L & L
    2
    refused, CNG filed a third-party breach of contract claim against
    L & L.       L & L then moved for summary judgment on CNG’s claim, which
    the district court granted on February 24, 1997.2
    On    the    eve    of   trial,   the   remaining     parties   reached   a
    settlement agreement.            As a result, the district court entered an
    order dismissing the action on October 27, 1997.                    On April 29,
    1998, those same parties filed a joint motion to dismiss their
    claims.       The district court signed the motion on May 2, 1998, and
    the clerk entered the order on May 4, 1998.                  On May 21, 1998, CNG
    filed the instant appeal, challenging the district court’s order of
    February 27, 1997, granting L & L’s motion for summary judgment.3
    II.
    The first issue we address is whether we have jurisdiction
    over this appeal.            L & L contends that jurisdiction is lacking
    because CNG’s appeal was not timely filed.                   L & L points to the
    fact that CNG did not file its notice of appeal until May 21, 1998,
    well     after      the    district   court’s   order   of    October   27,   1997,
    dismissing the action. CNG, however, argues that the appeal was in
    time because the filing period did not begin to run until May 4,
    1998, the date the district court signed the parties’ joint motion
    to dismiss.         To resolve this issue, we first must determine the
    2
    The district court’s ruling was based on the finding that
    Louisiana law governed CNG’s demand, and that the indemnity
    obligation was therefore precluded by the Louisiana Oilfield
    Indemnity Act of 1981, La. Rev. Stat. § 9:2780.
    3
    CNG also appealed the district court’s May 27, 1997 order
    denying CNG’s motion for a new trial.
    3
    legal   effect    of   the     district   court’s    October    27   order.
    Specifically, we must decide whether the order amounted to a final
    judgment, and whether it was properly entered in accordance with
    the Federal Rules of Civil Procedure.        If so, CNG’s appeal is too
    late.
    A final judgment is one that “ends the litigation on the
    merits and leaves nothing for the court to do but execute the
    judgment.”    Coopers & Lybrand v. Livesay, 
    437 U.S. 463
    , 467 (1978).
    We   follow   a   practical,    rather    than   technical,    approach   to
    determining whether a district court decision meets this standard.
    “A judgment reflecting an intent to dispose of all issues before
    the court is final.”     Moreau v. Harris County, 
    158 F.3d 241
    , 244
    (5th Cir. 1998).
    In this case, the parties entered a settlement agreement on
    October 26, 1997, which resolved all remaining issues in the case.
    Accordingly, at that point in time the litigation had ended, the
    rights of the parties were no longer in dispute, and the district
    court was left with nothing more to do but dismiss the case.          After
    being notified of the settlement, the district court entered its
    order of October 27, entitled “Order of Dismissal.”            In a short,
    perfunctory order, the district court noted that the case had
    settled, and dismissed the action.        On these facts we are inclined
    to believe that the district court entered its order of dismissal
    intending to put a final end to the litigation.
    CNG, however, argues that the order was not final because the
    district court’s dismissal was conditional in nature.           CNG points
    4
    to   the    fact    that   in   the   order   the   district    court   retained
    jurisdiction over the settlement “for enforcement purposes,” and
    granted the parties 60 days to enforce the agreement if so needed.
    CNG’s argument misses the mark.
    The    district      court’s    dismissal     of   this   suit    was   not
    conditional.        It is true, as CNG alleges, that the district court
    dismissed this suit while simultaneously retaining jurisdiction
    over the settlement.        But the district court in no way conditioned
    its dismissal on the parties’ performance under the settlement
    agreement.         The district court’s order allowed the parties to
    enforce the settlement for 60 days, if needed, but it did not allow
    the parties to relitigate the merits of the underlying action.4
    Additionally, even if the district court’s dismissal was
    conditional, that condition was intended to last for only 60 days.
    Thus, on December 26, 1997, when those 60 days were up, the
    district court’s order ripened into an appealable final judgment,
    and the time to file a notice of appeal began to run.              Because CNG
    did not file the instant appeal until May 21, 1998, it is untimely
    4
    CNG’s argument overlooks the fact that a district court
    may render final judgment on the merits, and yet retain
    jurisdiction over the settlement agreement. This is so because a
    final judgment on the merits is independent from the rights a party
    may later assert pursuant to a settlement agreement.       A final
    judgment is the formal and legal end to litigation on the merits.
    A settlement agreement, on the other hand, creates new contractual
    rights that are distinct from the rights asserted in the earlier
    litigation. See Kokkonen v. Guardian Life Ins. Co. of America, 
    511 U.S. 375
    (1994) (recognizing that a suit to enforce a settlement
    agreement is distinct from the original litigation, and thus
    usually requires its own basis of jurisdiction). Thus, the mere
    fact that the district court retained jurisdiction over the
    settlement does not make its order any less final.
    5
    even under CNG’s proffered rationale.      See Fed. R. App. P. 4.   For
    these reasons we conclude that the district court’s order of
    October 27 was a final judgment.       We turn next to the question of
    whether the order was properly entered in the record.
    Rule 58 provides that “[e]very judgment shall be set forth on
    a separate document.”   Fed. R. Civ. P. 58.       It further provides
    that “[a]ttorneys shall not submit forms of judgment except upon
    direction of the court, and these directions shall not be given as
    a matter of course.”    
    Id. In this
    case, the district court’s
    October 27 order is set forth on its own separate document.
    Moreover, it was not a form of judgment submitted by the attorneys
    and merely signed by the district judge.      Although the October 27
    “Order of Dismissal” is not entitled “final judgment,” the label is
    unimportant.
    If the language used by the court clearly
    evidences the judge’s intention that it shall
    be his final act it constitutes a final
    judgment, and when such intention has been so
    evidenced and the docket entry has been made a
    final judgment has been pronounced and entered
    and the time to appeal starts to run.
    Erstling v. Southern Bell Tel. & Telegraph Co., 
    255 F.2d 93
    , 95
    (5th Cir. 1958).5
    5
    We are aware that in Banker’s Trust Co. v. Mallis, 
    435 U.S. 381
    , 387-88 (1978), the Supreme Court held that the Second
    Circuit properly assumed jurisdiction of an appeal from an order of
    dismissal, despite the lack of a separate judgment, when (1) the
    order was the final decision in the case, and (2) the appellee did
    not object to the taking of the appeal. We are also aware that in
    accordance with Mallis, this Circuit will, when circumstances
    permit, find waiver of the separate document requirement to avoid
    the termination of an appeal. See Hammack v. Baroid Corp., 
    142 F.3d 266
    (5th Cir. 1998); Baker v. Mercedes Benz of N. Am., 
    114 F.3d 57
    (5th Cir. 1997). Mallis’ waiver rule is inapplicable in
    6
    We thus conclude that the district court’s October 27 order
    was a final judgment properly entered in the record.   Accordingly,
    CNG’s appeal is untimely and must be dismissed.
    DISMISSED.
    the present case, however, because L & L, the appellee, expressly
    objected to the taking of this appeal.
    g:\opin\98-30572.opn                7