XL Specialty Insurance v. Bollinger Shipyards Lockport LLC , 76 F. App'x 536 ( 2003 )


Menu:
  •                                                     United States Court of Appeals
    Fifth Circuit
    F I L E D
    UNITED STATES COURT OF APPEALS           September 10, 2003
    For the Fifth Circuit
    Charles R. Fulbruge III
    Clerk
    No. 02-30387
    XL SPECIALTY INSURANCE COMPANY,
    Plaintiff-Appellee-Cross-Appellant,
    VERSUS
    BOLLINGER SHIPYARDS LOCKPORT LLC,
    Defendant-Appellant-Cross-Appellee.
    NAVIGATORS INSURANCE COMPANY, INC.
    Plaintiff-Appellee-Cross-Appellant,
    VERSUS
    BOLLINGER SHIPYARDS LOCKPORT LLC,
    Defendant-Appellant-Cross-Appellee.
    Appeals from the United States District Court
    For the Eastern District of Louisiana
    (01-CV-623)
    Before HIGGINBOTHAM, EMILIO M. GARZA, and DENNIS, Circuit Judges.
    1
    PER CURIAM:*
    These consolidated declaratory judgment actions sounding in
    diversity were brought by the primary and excess general liability
    insurers of a Louisiana shipbuilding company.              The insurers seek a
    declaration that they are not obliged to pay certain repair costs
    or loss of profits or use paid by the shipbuilder to its customers.
    In counterclaims, the shipbuilder seeks approximately $7 million in
    coverage.      The district court granted summary judgment for the
    insurers but ordered each party to bear its own costs.              All parties
    appealed.    We now AFFIRM summary judgment, VACATE the denial of
    attorney    fees   and   costs,    and    REMAND    for   further   proceedings
    consistent with Part IV of this opinion.
    I.
    Bollinger Shipyards Lockport, LLC (“Bollinger”), built three
    lift boats for Cardinal Services (“Cardinal”) under a “Vessel
    Construction Agreement.”1         It built one lift boat for Montco, Inc.
    (“Montco”), under a “Construction Contract.”                  These contracts
    warrantied     workmanlike    performance          but    limited   Bollinger’s
    obligation to repair and replace defects to those problems arising
    from faulty workmanship discovered within 180 days of delivery and
    *
    Pursuant to 5TH CIR. R. 47.5, the Court has determined that this
    opinion should not be published and is not precedent except under
    the limited circumstances set forth in 5TH CIR. R. 47.5.4.
    1
    A liftboat is a supply vessel equipped with three or four
    hydraulic “jack-up” legs, which can be lowered and secured on the
    seabed so that the boat can be raised out of the water.
    2
    reported to Bollinger within 180 or 210 days of delivery.2              The
    agreements expressly disclaimed any obligation on the part of
    Bollinger for consequential damages, including loss of profits
    and/or use. The Cardinal contract stated that the warranty was “in
    lieu of all other express or implied warranties.”              The Montco
    contract   stated   that   all   other   warranties   by   Bollinger   were
    “expressly excluded and negated.”
    The three lift boats that Bollinger built for Cardinal under
    the “Vessel Construction Agreement” are the J. HANKINS, the W.
    LOPEZ, and the P.G. JONES.3       The boat built for Montco under the
    “Construction Contract” is the TAMMY.        The TAMMY was completed on
    May 15, 1997; the J. HANKINS on June 12, 1997; the W. LOPEZ on
    January 15, 1998; and the P.G. JONES on February 27, 1998.4
    On July 27, 2000, a crew member of the P.G. JONES noticed
    water seeping from one of the vessel’s jack-up legs.         The boat was
    taken to a Bollinger facility, where further inspection revealed
    cracks in each of its legs.       Bollinger began repairs on August 1,
    2000.   The parties do not dispute that it was quickly determined
    2
    Montco’s contract with Bollinger gave it 180 days to report
    defects. Cardinal’s contract gave it 210 days.
    3
    The J. HANKINS has a benighted history. It was launched as the
    D.L. HANSEN, capsized, and was launched again as the J. HANKINS.
    During its post-capsize repair, one of its legs was replaced.
    4
    The parties do not identify the precise dates on which each
    vessel was delivered.   In the absence of any suggestion to the
    contrary, we assume that each vessel was delivered close to the
    date of its completion.
    3
    that Bollinger had performed faulty welds during the original
    construction of the vessels; that the defective welding had, at
    some point, resulted in cracks in the gear racks attached to the
    legs; and that this cracking had propagated into the legs.   The W.
    LOPEZ, the J. HANKINS, and the TAMMY were subsequently inspected
    and discovered to have similar cracks.5   Bollinger began repairs on
    the J. HANKINS on August 14, 2000.   In a letter dated August 19,
    2000, Bollinger informed Cardinal that it was “ready, willing, and
    able” to repair “weld cracking” on the W. LOPEZ.        Ultimately,
    Bollinger replaced a total of ten legs on four vessels, at a cost
    of approximately $4.5 million.
    Bollinger owned a comprehensive general liability (“CGL”)
    policy issued by XL Specialty Insurance (“XL Specialty”) that
    provided coverage between July 1, 2000, and October 1, 2001.    The
    policy provided primary liability coverage for sums that Bollinger
    became “legally obligated to pay as damages” because of “property
    damage” that was caused by an “occurrence” during the policy
    period.   It further provided that XL Specialty had “the right and
    duty to defend any ‘suit’ seeking these damages,” defining “suit”
    as “a civil proceeding in which damage because of ‘bodily injury,’
    ‘property damage,’ ‘personal injury’ or ‘advertising injury’ to
    which this insurance applies are alleged.”
    5
    The cracks in the J. HANKINS were discovered on August 13,
    2000; those in the W. LOPEZ on August 18, 2000; and those in the
    TAMMY on September 18, 2000.
    4
    Bollinger also purchased $25 million worth of excess CGL
    coverage for the policy period October 1, 1999, to October 1, 2001.
    The excess coverage was subscribed to by XL Specialty, Navigators
    Insurance Company, Inc. (“Navigators”), and National Union Fire
    Insurance Company.6      This umbrella policy also covered sums that
    Bollinger    became    “legally      liable       to   pay.”        Its   terms    were
    essentially identical to those of the primary coverage.
    On August 18, 2000, Bollinger’s insurance agent, Willis of
    Louisiana,    Inc.    (“Willis”),      notified        XL    Specialty’s        managing
    general partner, Trident Marine Managers, Inc. (“Trident”), of a
    new CGL claim involving vessels Bollinger had built for Cardinal
    and Montco.    On August 30, 2000, Willis sent a notice of loss to
    Trident.     The notice stated that four vessels built by Bollinger
    had   “sustained     cracks    in    some    of    the      legs”   sometime     “after
    10/1/98.”     It did not identify any related claims, demands, or
    suits.   On August 31, 2000, Willis informed Trident that Bollinger
    had begun to repair the vessels because it believed it bore
    responsibility for the damages: “Bollinger has investigated the
    matter and . . . feels responsible for the damages.”
    On September 18, 2000, Cardinal issued a written demand to
    Bollinger     relating    to    Bollinger’s            “breach      of    its    vessel
    construction contracts.”            The demand letter specifically stated
    6
    Navigators provided 50% of the excess coverage; XL Specialty
    provided 30%; and National Union provided 20%. National Union is
    not a part of these proceedings.
    5
    that Cardinal’s remedies against Bollinger lay “in contract rather
    than in tort.”
    At some point, Montco’s president told Bollinger’s chairman
    that his company expected the shipbuilder to pay for repairs to the
    TAMMY, as well as for its downtime.       According to the testimony of
    Montco’s president, Bollinger’s chairman agreed to the demand, even
    though he questioned his company’s obligation to do so under the
    terms of the Construction Contract.
    On September 19, 2000, Trident acknowledged its receipt of the
    loss notice sent by Willis on August 30.             Following additional
    correspondence, Trident sent Bollinger a reservation of rights
    letter on September 25, 2000, reserving the insurers’ right to
    contest coverage.
    On November 2, 2000, Bollinger notified Cardinal that it would
    pay up to $1.5 million to cover loss of use of the W. LOPEZ, the J.
    HANKINS, and the P.G. JONES, in the event that its insurers denied
    coverage.   On February 13, 2001, Bollinger notified Montco that it
    would pay $875,000 to cover loss of use of the TAMMY, in the event
    that its insurers denied coverage.         Bollinger and Montco entered
    into a formal settlement agreement on June 28, 2001.         Bollinger and
    Cardinal    entered   into   such   an   agreement   on   July   25,   2001.
    Subsequently, Bollinger entered into new agreements with both
    Cardinal and Montco to build additional vessels.          Those agreements
    6
    were worth approximately $33 million.7
    On   March    9,   2001,   XL   Specialty      filed    suit     seeking    a
    declaration of its rights and obligations.               On March 13, 2001, it
    denied Bollinger’s claim.           Bollinger filed a counterclaim seeking
    coverage       and    bad   faith   damages.        Navigators     also    filed    a
    declaratory judgment action contesting coverage, in response to
    which Bollinger filed a counterclaim. The suits were consolidated.
    All parties moved for summary judgment. The district court granted
    summary judgment for the insurers but denied costs.
    Bollinger appeals from the court’s judgment finding a lack of
    coverage.       The insurers appeal from the court’s order that the
    parties bear their own costs.
    II.
    We review a grant of summary judgment de novo, applying the
    same standard as the district court.8              We likewise review matters
    of       contract     interpretation     de    novo.9    Summary    judgment        is
    appropriate if the movant demonstrates that there are no genuine
    issues of material fact and that it is entitled to a judgment as a
    7
    The insurers believe that Bollinger was eager to pay for
    Cardinal’s and Montco’s repairs and down time in order to preserve
    such future sales.
    8
    GeoSouthern Energy Corp. v. Chesapeake Operating Inc., 
    274 F.3d 1017
    , 1020 (5th Cir. 2001).
    9
    T.L. James & Co. v. Traylor Bros. Inc., 
    294 F.3d 743
    , 746 (5th
    Cir. 2002).
    7
    matter of law.10       Thus, “summary judgment is appropriate if the
    nonmovant fails to establish facts supporting an essential element
    of his prima facie claim.”11
    III.
    A.
    The policies at issue limited coverage to those sums that
    Bollinger was “legally obligated to pay as damages.”12                Because the
    record does not reasonably support the finding of a factual basis
    upon which Bollinger could potentially be liable to Cardinal or
    Montco, we conclude that there was no coverage under the policies.13
    The contracts under which Bollinger constructed the lift boats
    included     express     warranty     provisions        limiting      Bollinger’s
    obligation    to   repair     and   replace    defects    to    those    problems
    discovered and reported within 180 or 210 days of delivery.                     The
    lift boats were completed and delivered in 1997 and 1998, and the
    defective    welds     were   discovered      between    July   27,     2000,   and
    10
    Fed. R. Civ. P. 56(c).
    11
    GeoSouthern Energy, 
    274 F.3d at 1020
    .
    12
    Bollinger contends that the insurers merely attempt to “re-
    litigate the underlying claims between Bollinger, on the one hand,
    and Cardinal and Montco, on the other, by arguing that Bollinger
    could not have been found liable had the case proceeded to trial.”
    Because neither Cardinal nor Montco ever filed a lawsuit against
    Bollinger, however, no case between the parties existed; none was
    litigated; none could have proceeded to trial; and none can be
    “relitigated.”
    13
    For this reason, we need not consider the other triggers to
    coverage—whether there was “property damage” that was caused by an
    “occurrence” during the policy period.
    8
    September 18, 2000.                    Hence, the express warranties had expired
    before          the    cracking        in   the    jack-up      legs    was     discovered     and
    reported.              Furthermore,         the    construction        contracts       expressly
    precluded any obligation by Bollinger for consequential damages,
    including             loss   of    profits        and    use.      Because       the     warranty
    limitations             included       in   the     contracts      were       allowable     under
    Louisiana law,14 neither Cardinal nor Montco had a valid warranty
    claim against Bollinger. Accordingly, Bollinger faced no potential
    liability in contract.
    Bollinger argues that it was subject to potential liability
    for breach of the implied warranty against redhibitory vices and
    defects. We disagree. Under the Louisiana Civil Code, redhibition
    is        the   rescission        of    a   sale    on   account       of   a   defect    in   the
    manufacture or design of a thing sold:
    The seller warrants the buyer against                              redhibitory
    defects, or vices, in the things sold.
    A defect is redhibitory when it renders the thing
    useless, or its use so inconvenient that it must be
    presumed that a buyer would not have bought the thing had
    he known of the defect. The existence of such a defect
    gives a buyer the right to obtain rescission of the
    sale.15
    Because redhibition is the avoidance of a sale, there can be no
    14
    See FMC Corp. v. Continental Grain Co., 
    355 So. 2d 953
    , 957-58
    (La. App. 4th Cir. 1977).
    15
    La. Civ. Code art. 2520; see also Patin v. Thoroughbred Power
    Boats Inc., 
    294 F.3d 640
    , 655 (5th Cir. 2002); see generally Saúl
    Litvinoff, Sale and Lease in Louisiana Jurisprudence 439-40 (4th
    ed. 1997) (discussing the general principles of the warranty
    against redhibitory vices and defects).
    9
    redhibition in the absence of a contract of sale.16
    We find that there is no genuine issue of material fact about
    the nature of the contracts under which Bollinger built the lift
    boats for Cardinal and Montco.   They were contracts to build.   The
    record unequivocally shows that the vessels were built to the
    specifications of Cardinal and Montco; that both contracts were
    negotiated; and that Bollinger supplied the skill, labor, and
    materials.17    Because the contracts between Bollinger and both
    Cardinal and Montco were contracts to build rather than contracts
    of sale, and because redhibition is not applicable to construction
    contracts, Bollinger faced no potential liability for a breach of
    16
    Airco Refrigeration Serv., Inc. v. Fink, 
    134 So. 2d 880
    , 883
    (La. 1961) (explaining that Article 2520 applies only to contracts
    of sale); Hebert v. McDaniel, 
    479 So. 2d 1029
    , 1033 (La. App. 3d
    Cir. 1985) (“[T]he law in Louisiana is that redhibition applies
    only to contracts of sale and not to contracts to build.”); Duhon
    v. Three Friends Homebuilders Corp., 
    396 So. 2d 559
    , 560 (La. App.
    3d Cir. 1981) (same, citing La. Civ. Code art. 2520).
    17
    See La. Civ. Code art. 2756 (“To build by a plot, or to work
    by the job, is to undertake a building or a work for a certain
    stipulated price.”); Airco Refrigeration, 
    134 So. 2d at
    882 (citing
    art. 2756); Hebert, 
    479 So. 2d at 1032
     (“Three major factors are
    used to determine whether or not a contract is one of sale or one
    to build: (1) The buyer has some control over the specifications of
    the object, (2) the negotiations generally take place before the
    object is constructed, and (3) the parties contemplate that one of
    them will supply the materials and his skill and labor in order the
    construct the specified object.”); Duhon, 
    396 So. 2d at 561
     (same);
    see generally Swope v. Columbian Chems. Co., 
    281 F.3d 185
    , 202-04
    (5th Cir. 2002) (explaining that under Louisiana law “[t]he
    distinction between obligations to give, e.g., sales, and
    obligations to do, e.g., building constructions, is material to the
    judicial determination of questions involving . . . remedies”).
    10
    the warranty against redhibitory vices and defects.18
    In sum, we find that there was no coverage of Bollinger’s
    claim because it was not potentially obligated to pay the sums it
    expended on repairs and paid to Cardinal and Montco for down time.
    B.
    Bollinger contends that the insurers forfeited their right to
    invoke the coverage limitation imposed by the phrase “legally
    obligated   to   pay   as   damages”   because    they   refused   to   defend
    Bollinger against Cardinal’s and Montco’s claims and then denied
    coverage.    This argument is meritless.         By its terms, the primary
    insurance policy required XL Specialty to provide a defense only
    for any “suit” seeking damages.19           Because neither Cardinal nor
    Montco named Bollinger in a “suit,” defined in the policy as a
    “civil proceeding,” there was no duty to defend.20            In any event,
    18
    Bollinger asserted at oral argument that the replacement leg
    used in reconstructing the J. HANKINS was purchased pursuant to a
    contract of sale, thus suggesting that Cardinal had a redhibition
    claim as to that leg. But because it identifies no record evidence
    supporting its assertion, there is no triable issue of such a
    redhibition claim. Likewise, the record evidence does not support
    Bollinger’s argument that it faced liability for an unnamed tort,
    the elements of which it does not articulate.
    19
    The excess insurers had only a secondary duty to defend. See
    American Home Assurance Co. v. Czarniecki, 
    230 So. 2d 253
     (La.
    1969); see also William Shelby McKenzie & H. Alston Johnson III, 15
    Louisiana Civil Law Treatise: Insurance Law & Practice § 214
    (1986).
    20
    Even if there had been a suit based on Cardinal’s and Montco’s
    demands for contract damages, there would not have been a duty to
    defend because those demands, construed as the allegations of a
    hypothetical legal petition, “unambiguously excluded coverage” for
    the reasons stated above. See Cuté-Togs of New Orleans, Inc. v.
    11
    the wrongful denial of a defense would not have expanded coverage.21
    Finally,   in    response     to    Bollinger’s        assertion    that   its
    settlement    was      reasonable,    we        note   that    Bollinger    assumed
    responsibility for the damages almost immediately after they were
    discovered and negotiated down-time compensation with Cardinal and
    Montco long before the insurers denied coverage.                    Bollinger may
    have made an astute business decision in paying for Cardinal’s and
    Montco’s losses.        But Bollinger cannot transfer costs it was not
    legally obligated to pay to the insurers.22
    IV.
    The insurers complain that the district court erroneously
    ordered the parties to bear their own costs.                  “[C]osts . . . shall
    be allowed as of course to the prevailing party unless the court
    Louisiana Health Serv. & Indem. Co., 
    386 So. 2d 87
    , 89 (La. 1980)
    (“[T]he insurer’s duty to defend suits brought against its insured
    is determined by the allegations of the injured plaintiff’s
    petition, with the insurer being obligated to furnish a defense
    unless the petition unambiguously excluded coverage.” (quoting
    Czarniecki, 
    230 So. 2d at 259
    )).
    21
    See Enserch Corp. v. Shand Morahan & Co., 
    952 F.2d 1485
    , 1493
    (5th Cir. 1992) (explaining that even in the face of a breach of
    the duty to defend, coverage “cannot be created ex nihilo by
    estoppel” (quoting Hartford Cas. Co. v. Cruse, 
    938 F.2d 601
    , 605
    (5th Cir. 1991)); see also Foster v. Hampton, 
    352 So. 2d 197
    , 203
    (La. 1979) (stating the basic rule that there can be no liability
    on the part of an insurer where there is no liability on the part
    of its insured).
    22
    Because we hold that Bollinger cannot establish coverage, we
    need not consider whether it is entitled to damages for the
    wrongful denial of coverage.
    12
    otherwise directs . . . .”23      Our cases recognize that there is a
    strong presumption that the prevailing party will be awarded its
    costs.24 While the court has wide discretion to award or deny
    costs,25 it must provide reasons if it denies costs.26    Because the
    district court here did not provide reasons, we vacate that portion
    of the judgment ordering each party to bear its own costs and
    remand for either an award of costs to the prevailing parties or an
    explanation of reasons for the denial of such an award.
    V.
    For the foregoing reasons, we AFFIRM summary judgment, VACATE
    the denial of attorney fees and costs, and REMAND for further
    proceedings consistent with Part IV of this opinion.
    AFFIRMED in part, VACATED in part, and REMANDED.
    23
    Fed. R. Civ. P. 54(d)(1).
    24
    Sheets v. Yahama Motors Corp., USA, 
    891 F.2d 533
    , 539 (5th Cir.
    1990).
    25
    Hall v. State Farm Fire & Cas. Co., 
    937 F.2d 210
    , 216 (5th Cir.
    1991).
    26
    Sheets, 
    891 F.2d at 539
    .
    13