Davis v. EGL Eagle Global Logistics LP ( 2007 )


Menu:
  •                                                        United States Court of Appeals
    Fifth Circuit
    F I L E D
    IN THE UNITED STATES COURT OF APPEALS           July 9, 2007
    FOR THE FIFTH CIRCUIT
    Charles R. Fulbruge III
    Clerk
    No. 06-31019
    Summary Calendar
    RUFUS DAVIS, JR,
    Plaintiff-Appellant,
    v.
    EGL EAGLE GLOBAL LOGISTICS LP,
    Defendant-Appellee.
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    No. 2:06-CV-2888
    Before DeMOSS, STEWART, and PRADO, Circuit Judges.
    Per Curiam:*
    Plaintiff-Appellant Rufus Davis Jr. (“Davis”) appeals from the
    district court’s grant of summary judgment in favor of Defendant-
    Appellee EGL Eagle Global Logistics, L.P. (“EGL”).     Davis contends
    that the district court erred in two respects. First, according to
    Davis, the district court erroneously determined that the Federal
    Arbitration Act (“FAA”), 9 U.S.C. § 1, et seq., applied to his
    *
    Pursuant to 5TH CIRCUIT RULE 47.5, the court has determined
    that this opinion should not be published and is not precedent
    except under the limited circumstances set forth in 5TH CIRCUIT
    RULE 47.5.4.
    1
    claim because he was an independent contractor, and not an employee
    of EGL.     Second, Davis argues that the district court erred in
    rejecting his argument that his contract with EGL was unenforceable
    because it was unconscionable, ambiguous, internally inconsistent,
    and lacked mutuality.        We AFFIRM the judgment of the district court
    for the reasons stated below.
    I.     FACTUAL AND PROCEDURAL BACKGROUND
    On September 22, 2003, Davis and EGL entered into a contract
    entitled “EGL Global Logistics LP Agreement for Leased Equipment
    and    Independent       Contractor     Services     (Pick-up    &      Deliver)”
    (“Agreement”).        As indicated by the title, the Agreement consisted
    primarily of a lease of Davis’s vehicle to EGL for the purpose of
    shipping goods, and an agreement that Davis provide transportation
    services for the leased vehicle, either by driving himself or by
    hiring another person to drive.             The Agreement stated that EGL
    would pay Davis sixty percent of the total amount that it received
    for each shipment picked-up or delivered by Davis.
    With respect to the relationship between the parties, Section
    I of the Agreement attempted to create an independent contractor
    relationship. In support of this intention, the Agreement included
    a provision, written in bold, capital letters and separately
    initialed by both Davis and EGL, requiring Davis to notify EGL if
    he    believed   at    any   point   that   a   relationship    other    than   an
    2
    independent contractor relationship existed.1
    The Agreement also included three appendices which were signed
    and dated on the same day as the Agreement.         Appendix I identified
    the leased vehicle. Appendix II listed the expenses that EGL could
    deduct from any compensation due to Davis.          Finally, Appendix III
    specified the rate of compensation paid to Davis for each shipment
    picked-up or delivered.
    Two additional sections of the Agreement are of importance to
    this appeal.     Section 4.07 of the Agreement provides that all
    settlements--that is, compensation due less authorized deductions--
    are final and forbids Davis to make any claim for additional
    settlement   monies   “unless   Contractor     [Davis]   notifies   EGL   in
    writing by certified mail of any discrepancies or additional claims
    within fifteen (15) days of settlement of computation or said
    settlement by EGL.”    Section 6.07 of the Agreement mandates, “any
    controversy or claim arising out of or relating to this Agreement
    . . . shall be determined and settled in accordance with the
    Commercial     Arbitration   Rules       of   The   American   Arbitration
    Association.”    Section 6.07 further states that “[w]ritten notice
    of a demand for arbitration must be mailed to the other party and
    1
    The provision stated:
    IF AT ANY TIME DURING THE TERM OF THIS AGREEMENT
    CONTRACTOR IS OF THE OPINION THAT SOMETHING OTHER THAN AN
    INDEPENDENT CONTRACTOR RELATIONSHIP EXISTS BETWEEN
    CONTRACTOR AND EGL, CONTRACTOR SHALL IMMEDIATELY NOTIFY
    THE MANAGER OF SHARED RESOURCES OF EGL.
    3
    the American Arbitration Association within ninety (90) days of the
    occurrence of the claimed breach or other event giving rise to the
    controversy or claim.”     Failure to give the written notice of
    demand for arbitration within the ninety-day period erects an
    absolute bar to the institution of any proceedings.
    Davis and EGL performed under the contract until December 20,
    2004, at which time the Agreement was terminated.
    On January 3, 2006, Davis filed a putative class action suit
    in Louisiana state court alleging that Davis and other class
    members (EGL’s independent contractor drivers over the past ten
    year period) had been underpaid.2        EGL then removed the suit to
    federal district court and filed a motion to dismiss under Federal
    Rule of Civil Procedure 12(b)(6). EGL contended that dismissal was
    warranted because the Agreement mandates arbitration and Davis
    failed to make a timely demand for arbitration.       The district court
    treated EGL’s motion to dismiss as a summary judgment motion under
    Federal Rule of Civil Procedure 56(c).
    Thereafter, the district court granted EGL’s summary judgment
    motion and dismissed Davis’s complaint.      The district court based
    its ruling on the conclusion that, as a matter of law, Davis was an
    independent   contractor   under   the   Agreement.     Therefore,   the
    Agreement’s arbitration provision was valid and enforceable under
    2
    As explained by the district court, this suit was never
    certified as a class action despite being filed as such, nor did
    Davis make a showing that class certification would be appropriate.
    4
    the FAA,     and    the      exception    for       “contracts    of    employment”   of
    interstate commerce workers did not apply to Davis, an independent
    contractor.      Davis now appeals.
    II.   JURISDICTION AND STANDARD OF REVIEW
    Davis appeals from a final judgment of the district court, so
    this court has jurisdiction under 28 U.S.C. § 1291.
    We review the district court’s grant of summary judgment de
    novo.     Chacko v. Sabre, Inc., 
    473 F.3d 604
    , 609 (5th Cir. 2006).
    A grant of summary judgment is warranted if the evidence discloses
    “no genuine issue as to any material fact and that the moving party
    is entitled to a judgment as a matter of law.”                          FED. R. CIV. P.
    56(c); see Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322-23 (1986).
    A genuine issue of material fact exists if “the evidence is such
    that a reasonable jury could return a verdict for the nonmoving
    party.” Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986).
    In ruling on a summary judgment motion, courts shall not weigh the
    evidence    or     make      credibility          determinations.        
    Id. at 255.
    Furthermore, all justifiable inferences are made in favor of the
    nonmoving party.          
    Id. III. DISCUSSION
    Generally, the FAA “compels judicial enforcement of a wide
    range of written arbitration agreements.”                        Terrebonne v. K-Sea
    Transp.    Corp.,      
    477 F.3d 271
    ,   278     (5th   Cir.      2007)   (internal
    quotation marks omitted).              The Supreme Court has recognized that
    5
    Congress enacted the FAA in order to “reverse the longstanding
    judicial    hostility       to     arbitration        agreements.”            Gilmer   v.
    Interstate/Johnson        Lane      Corp.,       
    500 U.S. 20
    ,       24    (1991).
    Accordingly, we have noted that the FAA “establishes a federal
    policy favoring arbitration.”            
    Terrebonne, 477 F.3d at 285
    .
    Though   the     FAA        establishes      a    federal       policy     favoring
    arbitration, Section 1 of the FAA does not, however, “apply to
    contracts of employment of seamen, railroad employees, or any other
    class of workers engaged in foreign or interstate commerce.”                           9
    U.S.C. § 1.   In Circuit City Stores, Inc. v. Adams, 
    532 U.S. 105
    ,
    119 (2001), the Supreme Court construed the extent of Section 1.
    The Court rejected the view that Section 1 excluded all employment
    contracts from the FAA.            Instead, the Court held that Section 1
    “exempts    from    the      FAA     only       contracts      of     employment       of
    transportation workers.”           
    Id. In this
    case, although the Agreement contains an arbitration
    provision, Davis argues that he is exempt from arbitrating his
    claim because he is not an independent contractor but an EGL
    employee.   As a truck driver employed by EGL, Davis maintains that
    he is exempt from the FAA’s reach because he was a transportation
    worker.
    A.   Employment Status
    The district court rejected Davis’s contention that he was an
    employee of    EGL,   holding        instead     that    he    was    an   independent
    6
    contractor.       In so doing, the district court appears to have
    improperly weighed or made credibility determinations of some of
    the factual statements in Davis’s affidavit.3             See 
    Anderson, 477 U.S. at 255
    .        Consequently, we have some doubts as to whether,
    given a proper consideration of Davis’s statements, the summary
    judgment can be affirmed on employment status grounds.             The record
    shows, however, that EGL proffered several grounds for summary
    judgment to the district court.            Therefore, we need not reach the
    issue of employment status, but instead may review the summary
    judgment on the additional grounds raised below but not addressed
    by the district court.       See Johnson v. Sawyer, 
    120 F.3d 1307
    , 1316
    (5th Cir. 1997) (explaining that while summary judgment may be
    affirmed “on grounds not relied on by the district court, those
    grounds must at least have been proposed or asserted in that court
    by the movant”).
    B.   Texas Arbitration Act
    In EGL’s motion to dismiss, EGL argued that even assuming the
    Agreement    fell    under   the    FAA’s    exception   for   transportation
    workers,    the   arbitration      provision   was   nonetheless   valid   and
    3
    For example, Davis stated in his affidavit that, in spite of
    the Agreement’s terms, he was required to work exclusively for EGL
    and work at least forty hours per week.       The district court,
    however, concluded that Davis was “free to serve other carriers.”
    Additionally, Davis asserted that EGL required him to attend
    meetings twice a week at the EGL office and to keep and use EGL
    communications equipment. These four statements, arguably the most
    significant indications of control by EGL, were either contradicted
    or simply not addressed by the district court.
    7
    enforceable under the Texas General Arbitration Act (“TGAA”), Texas
    Civil Practices and Remedies Code § 171.001, et seq.     We agree.
    Where “an agreement contains a clause designating Texas law
    but does not exclude the FAA, the FAA and Texas law, including that
    state’s arbitration law, apply concurrently.”       Freudensprung v.
    Offshore Technical Servs., Inc., 
    379 F.3d 327
    , 338 n.7 (5th Cir.
    2004).   Here, Section 7.03 of the Agreement contains a choice-of-
    law provision which designates Texas law as the law governing the
    Agreement.     Thus, because the Agreement’s choice-of-law provision
    does not exclude the FAA, both the TGAA and FAA apply to the
    contract.
    However, while both federal and state arbitration law may
    apply to a contract, these laws do not necessarily operate in
    harmony.     Specifically, the FAA will preempt any state laws that
    “contradict the purpose of the FAA by ‘requir[ing] a judicial forum
    for the resolution of claims which the contracting parties agreed
    to resolve by arbitration.’” 
    Id. (quoting Pedcor
    Mgmt. Co. Welfare
    Benefit Plan v. Nations Pers. of Tex., Inc., 
    343 F.3d 355
    , 362 (5th
    Cir. 2003)).    In other words, “[f]or the FAA to preempt the [TGAA],
    state law must refuse to enforce an arbitration agreement that the
    FAA would enforce.”     In re D. Wilson Constr. Co., 
    196 S.W.3d 774
    ,
    780 (Tex. 2006); see also Miller v. Pub. Storage Mgmt., Inc., 
    121 F.3d 215
    , 219 (5th Cir. 1997) (“The FAA preempts conflicting state
    antiarbitration law.”) (emphasis added).
    8
    Here, the FAA does not preempt the TGAA because this case
    presents   the   situation    where   the   FAA   refuses     to   enforce   an
    arbitration provision (assuming for the moment that Davis meets the
    exception for transportation workers) that the TGAA would enforce.
    Under the TGAA, a written agreement to arbitrate is generally valid
    and enforceable with respect to controversies that exist at the
    time of the agreement or arise thereafter. See TEX. CIV. PRAC. & REM.
    CODE ANN. § 171.001.      Unlike the FAA, the TGAA does not exclude a
    specific class of employees from its coverage.           See 
    id. § 171.002.
    Thus, even if Davis were an employee of EGL, he would still be
    subject to arbitration under the TGAA.          We therefore hold that the
    Agreement’s arbitration provision is valid and enforceable under
    the TGAA, even if the Agreement is excepted from application of the
    FAA.
    C.     Ambiguity and Inconsistency
    In Davis’s second argument, he contends that the arbitration
    provision of the Agreement is unenforceable due to ambiguities and
    inconsistencies in the Agreement. Because of these ambiguities and
    inconsistencies, Davis asserts, EGL cannot prove as a matter of law
    that Davis’s     claims   fall   under    the   scope   of   the   arbitration
    provision. We address each of Davis’s ambiguity arguments in turn.
    Whether a contract is ambiguous is a question of law decided
    by the court.      D. Wilson Const. 
    Co., 196 S.W.3d at 781
    .                  In
    construing contract language, the primary objective is to discern
    9
    the true intention of the parties. J.M. Davidson, Inc. v. Webster,
    
    128 S.W.3d 223
    , 229 (Tex. 2003).                   Ambiguity in a contract exists
    where    the    agreement        “is    subject     to       two    or    more    reasonable
    interpretations          after         applying        the     pertinent          rules    of
    construction.”        
    Id. If, however,
    a contract can be “given a
    definite or certain legal meaning,” no ambiguity exists.                             
    Id. First, Davis
    contends that Section 6.07 of the Agreement, the
    arbitration provision, conflicts with Appendix II of the Agreement,
    which lists deductions from Davis’s compensation.                          Section 6.07 of
    the Agreement states that “any claim or controversy arising out of
    or relating to this Agreement, or the breach thereof . . . shall be
    determined      and   settled          in     accordance           with   the     Commercial
    Arbitration      Rules      of    The       American     Arbitration        Association.”
    Appendix II, on the other hand, enumerates the expenses which EGL
    may deduct from Davis’s compensation.                        In essence, Davis argues
    that    while   the   arbitration           provision        requires      “any    claim   or
    controversy” to be arbitrated, Appendix II inconsistently permits
    EGL to take self-help remedies for a variety of claims under the
    contract.
    Contrary to Davis’s assessment, we find only one reasonable
    interpretation and no inconsistency.                     Appendix II, rather than
    containing a list of claims, merely contains an agreed list of
    expenses that EGL may deduct from Davis’s settlement payments. The
    intent and effect of Appendix II is simply to allocate onto Davis
    10
    the initial payment of Davis’s contractual expenses and the risk of
    a mistake.    Any claim or controversy involving the deductions, for
    example a disagreement over the value, must still be arbitrated
    according to Section 6.07 of the Agreement, albeit at Davis’s
    request rather than EGL’s.       Such an arrangement is analogous to the
    typical employment compensation arrangement: the employer pays what
    the employer believes to be the correct compensation; any mistake
    in pay must be challenged by the employee.        Therefore, we conclude
    that   no   ambiguity    or   inconsistency   exists    between   these   two
    provisions.
    Second, Davis alleges that the Agreement contains ambiguous
    and    inconsistent     notification    requirements.     Section   6.07(a)
    provides: “Written notice of a demand for arbitration must be
    mailed to the other party . . . within ninety (90) days of the
    occurrence of the claimed breach or other event giving rise to the
    controversy or claim.”        Thus, the provision places on both parties
    a ninety-day notice requirement of a demand for arbitration.
    Section 4.07 of the Agreement states: “Contractor will not make any
    claim or bring any action against EGL for additional settlement
    monies unless Contractor notifies EGL in writing by certified mail
    of any discrepancies or additional claims within fifteen (15) days
    of settlement.”       This section requires Davis to notify EGL of any
    alleged settlement errors within fifteen days of the settlement
    payment as a prerequisite to bringing a claim on the disputed
    11
    settlement.
    Again,      we        conclude      that   only      a      single       reasonable
    interpretation exists for these two provisions.                           Section 4.07
    requires notice of erroneous settlement payments prior to demanding
    arbitration, while Section 6.07(a) requires notice of a demand for
    arbitration.          It   is   clear    that   Davis     must    comply        with   both
    provisions to have a claim for settlement monies arbitrated.
    Although Davis may regard the notice requirement for arbitration as
    unnecessarily duplicative in light of the notice requirement for
    incorrect settlements, the two provisions are not ambiguous or
    inconsistent.
    Given that there is only one reasonable interpretation of the
    Agreement and that its provisions do not conflict, we hold that
    Davis   has     not    shown    any     ambiguity    or    inconsistency          in   the
    Agreement.
    D.   Unconscionability and Lack of Mutuality
    Finally, Davis asserts that the arbitration provision of the
    Agreement is unconscionable and lacks mutuality, and is therefore
    unenforceable.
    The party opposing arbitration bears the burden of showing
    that the arbitration provision is unconscionable. In re FirstMerit
    Bank,   N.A.,    
    52 S.W.3d 749
    ,    756   (Tex.     2001).        The     test   for
    unconscionability          assesses     whether,    in    light    of     the    parties’
    general commercial background and needs, the provision is so
    12
    unilateral as to have been unconscionable at the time of formation.
    
    Id. at 757.
            The objective is to prevent oppression and unfair
    surprise, not to disturb the allocation of risks stemming from one
    party’s superior bargaining position.              
    Id. As to
    the reasons why the Agreement’s arbitration provision is
    unconscionable, Davis points to the “employment status of the
    drivers     [and]    the    ambiguous      and   unilateral    nature   of     the
    arbitration clause.” First, we have already addressed the issue of
    ambiguity and held that Davis did not show ambiguity in the
    arbitration provision.            Second, Davis does not explain how one’s
    status as an employee as opposed to an independent contractor would
    change the unconscionability analysis.             Lastly, the mere existence
    of unequal bargaining power does not make an arbitration clause
    unconscionable, nor does the fact that limited exceptions exist
    which permit        one   party    to   seek   judicial   remedies   instead    of
    submitting to arbitration.              See 
    id. at 757-58
    (holding that an
    arbitration clause that permitted the stronger party to litigate
    certain claims was not unconscionable).             Thus, Davis has failed to
    satisfy his burden of showing unconscionability.
    Lack    of     mutuality      generally     refers   to   the   concept    of
    consideration.       See Fed. Sign v. Tex. S. Univ., 
    951 S.W.2d 401
    , 408
    (Tex. 1997) (“A contract must be based upon a valid consideration,
    in other words, mutuality of obligation.”), superseded by statute
    on other grounds, TEX. GOV’T CODE §§ 2260.001-.108, as recognized in
    13
    Gen. Servs. Comm’n v. Little-Tex Insulation Co., 
    39 S.W.3d 591
    , 593
    (Tex. 2001).      Consideration is comprised of the “benefits and
    detriments   to   the   contracting    parties.”   
    Id. at 409.
        “The
    detriments must induce the parties to make the promises and the
    promises must induce the parties to incur the detriments.”           
    Id. In the
    present case, Davis did not point to any evidence of a lack of
    mutuality of obligations in the Agreement.4        Therefore, we reject
    Davis’s contention that the Agreement lacked mutuality.
    IV.   CONCLUSION
    For the reasons stated above, we AFFIRM the judgment of the
    district court.
    AFFIRMED.
    4
    We also note that mutuality of remedy does not apply to this
    case because specific performance is not an issue. Fed. 
    Sign, 951 S.W.2d at 409
    (“Mutuality of remedy is the right of both parties to
    a contract to obtain specific performance.”)
    14