Jems Fabrication, Incorporated v. Benetech, L.L.C. ( 2014 )


Menu:
  •      Case: 13-30934      Document: 00512613754         Page: 1    Date Filed: 04/30/2014
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    United States Court of Appeals
    Fifth Circuit
    FILED
    No. 13-30934                            April 30, 2014
    Summary Calendar
    Lyle W. Cayce
    Clerk
    JEMS FABRICATION, INCORPORATED, USA for use and benefit of,
    Plaintiff - Appellee
    v.
    FIDELITY & DEPOSIT COMPANY OF MARYLAND; ZURICH AMERICAN
    INSURANCE COMPANY,
    Defendants - Appellants
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:12-CV-393
    Before WIENER, OWEN, and HAYNES, Circuit Judges.
    PER CURIAM:*
    Fidelity and Deposit Company of Maryland (“Fidelity”) and Zurich
    American Insurance Company (“Zurich,” and collectively with Fidelity, the
    “Sureties”) appeal the district court’s entry of a final judgment in favor of
    JEMS Fabrication, Inc. (“JEMS”) on its claim under the Miller Act, 40 U.S.C.
    §§ 3131–3134. We AFFIRM.
    * Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH
    CIR. R. 47.5.4.
    Case: 13-30934    Document: 00512613754       Page: 2   Date Filed: 04/30/2014
    No. 13-30934
    I.    Background
    The United States Army Corps of Engineers (the “Corps”) contracted
    with Benetech, LLC (“Benetech”), a construction contractor, to renovate and/or
    redevelop pumping stations at various sites located on the Mississippi River
    (the “JSP-05 Project”). Thereafter, the Sureties issued a payment bond (the
    “Payment Bond”) pursuant to the Miller Act on behalf of Benetech to protect
    subcontractors on the JSP-05 Project against the risk of non-payment by
    Benetech. Benetech then entered into a subcontract (the “Contract”) with
    JEMS in which JEMS agreed to provide certain custom-fabricated structural
    steel for the JSP-05 Project in exchange for a payment of $2,350,000. This
    figure included $202,432 for shop drawings, $1,316,584 for materials, and
    $830,984 for labor. Benetech and JEMS subsequently approved a change order
    for additional materials, increasing the total contract amount to $2,379,739.60.
    Later, JEMS and Benetech agreed to a modification of the Contract to permit
    Benetech to provide the on-site labor going forward in order to satisfy certain
    self-performance requirements of the Corps. Although this modification was
    not memorialized in writing, JEMS thereafter terminated its on-site labor
    force although it continued to incur certain labor-related expenses.
    JEMS delivered all of the drawings required by the Contract. JEMS also
    delivered many of the materials required by the Contract. However, JEMS did
    not deliver one building required by the Contract (the “Hero Building”);
    instead, Benetech and JEMS agreed that Benetech would purchase the Hero
    Building directly from a subcontractor for $54,000. During its performance
    under the Contract, JEMS did not submit periodic invoices to Benetech.
    Rather, JEMS delivered shipping tickets to Benetech of materials provided and
    Benetech provided periodic payments to JEMS over the course of the Contract.
    However, the shipping tickets did not indicate the price of the materials
    delivered and Benetech’s periodic payments did not detail which shipping
    2
    Case: 13-30934       Document: 00512613754          Page: 3     Date Filed: 04/30/2014
    No. 13-30934
    tickets were being paid. In total, Benetech paid JEMS $996,882.14 for its work
    on the Contract. 1 However, Benetech claimed that JEMS was not entitled to
    the remainder of the payment due under the Contract, because JEMS had
    failed to deliver all of the materials required by the Contract.
    Thereafter, JEMS filed the instant federal action, alleging Miller Act
    claims against Benetech, Fidelity, and Zurich, as well as a breach of contract
    claim and a Louisiana state law claim against Benetech. After a two-day trial,
    the district court entered a final judgment in favor of JEMS, ordering that
    Benetech, Fidelity, and Zurich were jointly and severally liable to JEMS in the
    amount of $497,873.46, plus interest. The Sureties timely appealed. 2
    II.   Standard of Review
    We review a district court’s conclusions of law de novo. See J.D. Fields
    & Co., Inc. v. Gottfried Corp., 
    272 F.3d 692
    , 696 (5th Cir. 2001). However, we
    review a district court’s findings of fact for clear error. See id.; see also FED. R.
    CIV. P. 52(a)(6). A finding of fact is clearly erroneous when “although there is
    evidence to support it, the reviewing court on the entire evidence is left with
    the definite and firm conviction that a mistake has been committed.” Anderson
    v. City of Bessemer City, N.C., 
    470 U.S. 564
    , 573 (1985) (quotations omitted).
    Therefore, “[w]here there are two permissible views of the evidence, the
    factfinder’s choice between them cannot be clearly erroneous.” 
    Id. at 574.
                                         III.    Discussion
    The Miller Act requires that a general contractor on a federal project post
    a bond for the purpose of protecting the suppliers of materials for the project.
    See Arena v. Graybar Elec. Co., Inc., 
    669 F.3d 214
    , 220 (5th Cir. 2012). It
    1Specifically, Benetech paid JEMS the following lump sums over the course of the
    Contract: $50,000, $300,000, $396,882.14, $150,000, and $100,000.
    2 Benetech did not appeal the district court’s entry of final judgment and is not a party
    to this appeal.
    3
    Case: 13-30934     Document: 00512613754    Page: 4   Date Filed: 04/30/2014
    No. 13-30934
    provides suppliers and subcontractors with the right to sue a prime contractor
    to recover on the bond for the amounts owed to them.             See 40 U.S.C.
    § 3133(b)(1). This statutory scheme “was created to protect parties such as
    subcontractors or suppliers who work on federal projects as state-law liens
    cannot be applied against federally-owned property and traditional state-law
    remedies are unavailable.” 
    Arena, 669 F.3d at 220
    . The Miller Act is “highly
    remedial in nature” and “is entitled to a liberal construction and application in
    order properly to effectuate the Congressional intent to protect those whose
    labor and materials go into public projects.” Clifford F. MacEvoy Co. v. U.S.
    for Use & Benefit of Calvin Tomkins Co., 
    322 U.S. 102
    , 107 (1944).
    The elements of a Miller Act claim are:        (1) the plaintiff supplied
    materials in prosecution of the work provided for in the contract; (2) the
    plaintiff has not been paid; (3) the plaintiff had a good faith belief that the
    materials were intended for the specified work; and (4) the plaintiff meets the
    jurisdictional requisites of timely notice and filing. See U.S. for Use & Benefit
    of Carlson v. Cont’l Cas. Co., 
    414 F.2d 431
    , 433 (5th Cir. 1969); U.S. for Use &
    Benefit of Martin Steel Constructors, Inc. v. Avanti Constructors, Inc., 
    750 F.2d 759
    , 761 (9th Cir. 1984).
    First, the Sureties argue that the district court erred in entering
    judgment in favor of JEMS because JEMS failed to demonstrate at trial either:
    (1) that it supplied materials to Benetech in prosecution of the JSP-05 Project;
    or (2) that it had a good faith belief that the materials supplied to Benetech
    were intended for the JSP-05 Project. See 
    Carlson, 414 F.2d at 433
    ; see also
    United States v. C. J. Elec. Contractors, Inc., 
    535 F.2d 1326
    , 1328–29 (1st Cir.
    1976).     Specifically, the Sureties assert that JEMS supplied materials to
    Benetech for other unrelated projects that were not covered by the Payment
    Bond at the same time as it supplied materials to Benetech for the JSP-05
    Project.    The Sureties argue that JEMS failed to demonstrate that the
    4
    Case: 13-30934      Document: 00512613754         Page: 5    Date Filed: 04/30/2014
    No. 13-30934
    materials it supplied were intended for the JSP-05 Project, not other projects,
    or that it had a good faith belief that the supplied materials were intended for
    the JSP-05 Project, not other projects.
    However, the Sureties never argued to the district court that JEMS’
    claim included materials supplied to Benetech for other projects.                  Absent
    extraordinary circumstances not present here, we do not consider arguments
    not previously raised before the district court. See Vogel v. Veneman, 
    276 F.3d 729
    , 733 (5th Cir. 2002).
    Second, the Sureties assert that the district court erred in entering final
    judgment in favor of JEMS because the shop drawings prepared by JEMS for
    Benetech are not compensable labor under the Miller Act. The district court
    court concluded that “Benetech already paid for the [shop] drawings . . .
    because Benetech’s payments of $996,882.14 covered the amount JEMS was
    owed for the [shop] drawings.” The Sureties contend that the district court
    erred in concluding that Benetech’s payment of $996,882.14 covered the cost of
    the shop drawings. Specifically, the Sureties assert that, under Louisiana’s
    law of imputation, the district court should have imputed Benetech’s payment
    of $996,882.14 to the cost of the materials, not the cost of the shop drawings.
    See La. Civ. Code Ann. art. 1868 (providing that payments must be imputed to
    secured debts in preference to unsecured debts where the debts are
    simultaneously incurred). 3 The Sureties failed to raise this argument before
    the district court. In fact, the district court noted that “the Sureties provide no
    justification as to why the amount due for the drawings should be deducted
    3 The Sureties maintain that the cost of the materials is a secured debt and the cost
    of the shop drawings is an unsecured debt because materials, but not shop drawings, are
    compensable under the Miller Act. We need not resolve the question of whether shop
    drawings are compensable labor under the Miller Act because Louisiana’s law of imputation
    does not apply here.
    5
    Case: 13-30934       Document: 00512613754          Page: 6     Date Filed: 04/30/2014
    No. 13-30934
    from the top of the remainder of the Contract Price owed to JEMS, rather than
    attributed to the amounts already paid by Benetech.” We thus decline to
    consider this argument. See 
    Vogel, 276 F.3d at 733
    . 4
    Third, the Sureties argue that the district court erred in entering final
    judgment in favor of JEMS because the Sureties were entitled to a setoff in the
    amount of $408,759.13. Specifically, the Sureties assert that JEMS failed to
    deliver all of the materials required by the Contract and that, as a result,
    Benetech was forced to procure additional materials for the JSP-05 Project
    from other suppliers at a cost of $408,759.13. The district court concluded both
    that “JEMS delivered the material required by the Contract” and that
    Benetech was not entitled to deduct any expenditures in excess of the $54,000
    attributable to the Hero Building because “Benetech failed to provide JEMS
    with notice of any deficiency and an opportunity to cure [pursuant to the
    Contract] before incurring the[se] additional expenses.”
    4 Even if we did consider it, Louisiana’s law of imputation only applies where “[a]n
    obligor . . . owes several debts to an obligee.” La. Civ. Code Ann. art. 1864; see also
    Delesdernier v. Delesdernier, 
    95 So. 3d 588
    , 595 (La. App. 5 Cir. 2012) (“Because spousal
    support is a single obligation, the law of imputation does not apply.”). Here, Benetech
    incurred a single lump-sum debt to JEMS pursuant to the Contract and therefore Louisiana’s
    law of imputation does not apply. After reviewing the evidence presented at trial, the district
    court found that JEMS completed all of the shop drawings required by the Contract and
    further found that Benetech’s payment of $996,882.14 covered the cost of the shop drawings.
    Even if we considered this argument, and even if we concluded that the debts were separable
    and applied Louisiana’s law of imputation, we would nevertheless conclude that the district
    court did not err in imputing Benetech’s payment of $996,882.14 to the cost of the shop
    drawings. JEMS introduced evidence at trial indicating that it prepared the shop drawings
    first and the materials second, and the Sureties do not challenge this factual finding on
    appeal. Under such circumstances, Louisiana’s law of imputation requires that the district
    court impute payment to the earlier incurred debt. See La. Civ. Code Ann. art. 1868 (“When
    the parties have made no imputation, payment must be imputed to the debt that is already
    due.”); see also Hattiesburg Mfg. Co. v. Pepe, 
    140 So. 2d 449
    , 456 (La. App. 1 Cir. 1962)
    (“[P]ayments on a single account must be imputed to the oldest items thereon.”). The Sureties
    have failed to establish any grounds upon which we could conclude that these factual findings
    were clearly erroneous. See FED. R. CIV. P. 52(a); 
    Anderson, 470 U.S. at 573
    –74.
    6
    Case: 13-30934       Document: 00512613754         Page: 7     Date Filed: 04/30/2014
    No. 13-30934
    The Sureties maintain that, unlike Benetech, it is not bound by the
    “notice and cure” provisions of the Contract and that it should not be precluded
    from obtaining a setoff on that basis. However, while a Miller Act surety is not
    a party to a contract between a subcontractor and a contractor, see U.S. for &
    on behalf of Portland Constr. Co. v. Weiss Pollution Control Corp., 
    532 F.2d 1009
    , 1012 (5th Cir. 1976), it nonetheless stands in the shoes of the contractor
    and is bound by its dealings for these purposes, see U.S. for Benefit & on Behalf
    of Sherman v. Carter, 
    353 U.S. 210
    , 217–18 (1957); see also Hous. Fire & Cas.
    Ins. Co. v. E. E. Cloer Gen. Contractor, 
    217 F.2d 906
    , 910 (5th Cir. 1954).
    Therefore, the Sureties, like Benetech, are bound by the terms of the Contract,
    including its “notice and cure” provisions. The Sureties do not dispute that
    Benetech failed to comply with these provisions. As a result, we conclude that
    the district court did not err in concluding that neither Benetech nor the
    Sureties were entitled to a setoff for these additional expenses. 5
    Moreover, JEMS introduced substantial evidence at trial indicating that
    it had supplied all of the materials, with the exception of the Hero Building,
    required by the Contract, including testimony from several witnesses, shipping
    tickets, and bills of lading. Although Benetech introduced evidence indicating
    5 The Sureties also argue that they should have been credited $147,000 for the
    purchase of the Hero Building, not $54,000. At trial, JEMS introduced evidence that it had
    contracted with a subcontractor to purchase the Hero Building for $54,000. Benetech and
    JEMS subsequently agreed that Benetech would purchase the Hero Building directly from
    the subcontractor. Benetech claimed that thereafter it spent $147,000 to purchase the Hero
    Building due to changes in the building specifications for the Hero Building made by the
    Corps requiring the purchase of additional materials. The district court concluded that
    Benetech failed to comply with the “notice and cure” provisions of the Contract before
    incurring these additional expenses and could not therefore claim them as a setoff at trial.
    The Sureties do not dispute that Benetech failed to comply with these provisions. The district
    court also concluded that, to the extent these additional expenses were incurred due to
    subsequent changes in the building specifications imposed by the Corps, “the expenses do not
    fall within the scope of JEMS’ work.” The Sureties do not challenge this conclusion. We
    therefore conclude that the district court did not err in crediting Benetech and the Sureties
    $54,000, and not $147,000, for the cost of the Hero Building.
    7
    Case: 13-30934    Document: 00512613754     Page: 8   Date Filed: 04/30/2014
    No. 13-30934
    that it purchased materials for the JSP-05 Project, it did not introduce evidence
    directly linking the invoices for its purchases with specific materials that
    should have been delivered by JEMS under the Contract. As a result, we
    conclude that the district court did not clearly err in concluding that “JEMS
    delivered the material required by the Contract.” See FED. R. CIV. P. 52(a)(6);
    
    Anderson, 470 U.S. at 573
    –74.
    AFFIRMED.
    8