O'Reilly v. US Army Corps of Eng ( 2023 )


Menu:
  • Case: 22-30608    Document: 00516928970       Page: 1     Date Filed: 10/12/2023
    United States Court of Appeals
    for the Fifth Circuit                            United States Court of Appeals
    Fifth Circuit
    ____________                             FILED
    October 12, 2023
    No. 22-30608                       Lyle W. Cayce
    ____________                             Clerk
    Loretto O’Reilly, Jr.; Healthy Gulf; Coalition for
    Responsible Zoning; Sierra Club, Delta Chapter,
    Plaintiffs—Appellants,
    versus
    All State Financial Company,
    Intervenor—Appellee,
    St. Tammany Parish Government,
    Intervenor Plaintiff—Appellee,
    United States Army Corps of Engineers; Scott A.
    Spellmon, Lieutenant General,
    Defendants—Appellees.
    ______________________________
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:21-CV-1027
    ______________________________
    Before Wiener, Graves, and Douglas, Circuit Judges.
    Case: 22-30608          Document: 00516928970             Page: 2      Date Filed: 10/12/2023
    No. 22-30608
    Per Curiam:*
    All State Financial Company (“All State”) wishes to dredge and fill
    24.58 acres of wetlands in St. Tammany Parish, Louisiana, to build a multi-
    use commercial and residential development. The United States Army Corps
    of Engineers (“Corps”) issued All State a permit to do so under § 404 of the
    Clean Water Act (“CWA”), after determining that the project would have
    no significant impact on the environment. Plaintiffs, residents of St.
    Tammany and other concerned environmental groups, appeal the district
    court’s affirmance of the Corps’ decision. Because the Corps’
    Environmental Assessment (“EA”) fails to articulate a reasonable basis for
    its Finding of No Significant Impact (“FONSI”), we reverse the district
    court and remand to the Corps for further proceedings consistent with this
    opinion.
    I. STATUTORY FRAMEWORK
    The National Environmental Policy Act (“NEPA”) imposes
    procedural requirements on public agencies to ensure that they consider “the
    environmental impact of their proposals and actions.” Dep’t of Transp. v.
    Pub. Citizen, 
    541 U.S. 752
    , 757 (2004) (citing 
    42 U.S.C. § 4332
    ). In
    complying with its responsibilities under NEPA, an agency must first prepare
    an EA to “briefly” determine the potential environmental impacts of a
    proposed action. 
    40 C.F.R. § 1508.9.1
     An EA is a “rough-cut, low-budget”
    statement that evaluates whether the proposed action will “significantly
    affect[] the quality of the human environment.” Sabine River Auth. v. U.S.
    _____________________
    *
    This opinion is not designated for publication. See 5th Cir. R. 47.5.
    1
    The Council on Environmental Quality (“CEQ”) published new rules in
    September 2020, revising earlier NEPA regulations, but the decisions challenged here were
    subject to the earlier version of the regulations. Thus, all citations to CEQ regulations
    herein refer to the regulations codified at 40 C.F.R. pt. 1500 (2018).
    2
    Case: 22-30608          Document: 00516928970              Page: 3     Date Filed: 10/12/2023
    No. 22-30608
    Dep’t of Interior, 
    951 F.2d 669
    , 676 (5th Cir. 1992) (quoting 
    42 U.S.C. § 4332
    (2)(C)). If it will, the agency must prepare a more detailed
    Environmental Impact Statement (“EIS”), including, inter alia, information
    on any adverse environmental effects of the project, “alternatives to the
    proposed agency action,” and “any irreversible and irretrievable
    commitments of Federal resources which would be involved in the proposed
    action should it be implemented.” 
    42 U.S.C. § 4332
    (C). If, on the other
    hand, the EA establishes that the action will not have a significant impact on
    the environment, the agency instead issues a FONSI. 
    40 C.F.R. § 1508.13
    .
    In determining whether to prepare an EIS or issue a FONSI, an agency
    must take a “hard look” at the context and intensity of the project’s potential
    impacts. Spiller v. White, 
    352 F.3d 235
    , 242 (5th Cir. 2003). Such impacts
    include the direct, indirect, and cumulative effects of the action. 
    40 C.F.R. §§ 1508.7-8
    . Considering the “context” of the effects requires that “the
    significance of an action [] be analyzed in several contexts such as society as
    a whole (human, national), the affected region, the affected interests, and the
    locality.” 
    40 C.F.R. § 1508.27
    (a). “Intensity,” on the other hand, concerns
    the “severity of the impact.” 
    40 C.F.R. § 1508.27
    (b). NEPA regulations list
    ten factors that agencies should consider in evaluating the intensity of a
    proposed project’s impacts.2 
    Id.
     If an agency “concludes that the preparation
    _____________________
    2
    The ten listed factors are:
    (1) Impacts that may be both beneficial and adverse. A significant effect
    may exist even if the Federal agency believes that on balance the effect will
    be beneficial.
    (2) The degree to which the proposed action affects public health or safety.
    (3) Unique characteristics of the geographic area such as proximity to
    historic or cultural resources, park lands, prime farmlands, wetlands, wild
    and scenic rivers, or ecologically critical areas.
    3
    Case: 22-30608       Document: 00516928970                Page: 4       Date Filed: 10/12/2023
    No. 22-30608
    of an EIS is not required based on a FONSI, an aggrieved party may challenge
    the decision in federal court under the Administrative Procedures Act.”
    Sabine River, 951 F.2d at 677 (citing 
    5 U.S.C. § 706
    (2)(A)).
    One type of federal action requiring NEPA review is the issuance of
    permits under the CWA. Section 404 of the CWA authorizes the Corps to
    issue permits for the dredging or filling of navigable waters, such as wetlands.
    
    33 U.S.C. § 1344
    (a). NEPA mandates that the Corps complete an EA and
    either prepare an EIS or issue a FONSI before granting a § 404 permit
    application. See 
    33 C.F.R. § 230.7
    (a). Section 404 also has its own
    requirements for analysis prior to issuing a permit, including examining the
    _____________________
    (4) The degree to which the effects on the quality of the human
    environment are likely to be highly controversial.
    (5) The degree to which the possible effects on the human environment
    are highly uncertain or involve unique or unknown risks.
    (6) The degree to which the action may establish a precedent for future
    actions with significant effects or represents a decision in principle about a
    future consideration.
    (7) Whether the action is related to other actions with individually
    insignificant but cumulatively significant impacts. Significance exists if it
    is reasonable to anticipate a cumulatively significant impact on the
    environment. Significance cannot be avoided by terming an action
    temporary or by breaking it down into small component parts.
    (8) The degree to which the action may adversely affect districts, sites,
    highways, structures, or objects listed in or eligible for listing in the
    National Register of Historic Places or may cause loss or destruction of
    significant scientific, cultural, or historical resources.
    (9) The degree to which the action may adversely affect an endangered or
    threatened species or its habitat that has been determined to be critical
    under the Endangered Species Act of 1973.
    (10) Whether the action threatens a violation of Federal, State, or local law
    or requirements imposed for the protection of the environment.
    Spiller, 
    352 F.3d at
    242 n.3 (quoting 
    40 C.F.R. § 1508.27
    (b)).
    4
    Case: 22-30608     Document: 00516928970           Page: 5   Date Filed: 10/12/2023
    No. 22-30608
    cumulative impacts of the project on the aquatic environment and evaluating
    the relevant “public interest” factors. See 33 C.F.R. pt. 320.
    II. FACTUAL AND PROCEDURAL BACKGROUND
    On February 6, 2018, Bruce Wainer of All State applied to the Corps
    for a wetlands permit under § 404 of the CWA. All State sought permission
    to begin work on the Timber Branch II project (“TB II”), a proposed multi-
    use commercial and residential development located in Covington, a town in
    St. Tammany Parish, Louisiana. The plans for TB II include a business
    campus, a public utility facility, a restaurant, and an 80-home development.
    Wainer owns the 200-acre tract within which TB II would be located.
    TB II necessitated the Corps’ permission because it involves the
    filling of jurisdictional wetlands. See 
    33 U.S.C. § 1344
    . The total acreage of
    TB II, as described in the application, is 69.19 forested acres. Wetlands
    comprise 24.58 of those acres. Those wetlands are adjacent to the (Little)
    Tchefuncte River and the Timber Branch River, and are in a flood hazard
    area. To develop the area, All State would need to fill the wetlands with
    concrete.
    In 2000, the former owner of that tract applied for a § 404 permit for
    a project, also called Timber Branch II. The Corps granted that permit,
    allowing for the dredging and filling of 39.54 acres of wetlands. However, the
    district court enjoined that project, holding that the Corps abused its
    discretion in issuing the permit without any “real analysis or data.” O’Reilly
    v. U.S. Army Corps of Eng’rs, No. Civ.A. 04-940, 
    2004 WL 1794531
    , at *5
    (E.D. La. Aug. 10, 2004). This court upheld the district court’s injunction,
    agreeing that the Corps had failed to adequately explain its permit issuance
    decision. O’Reilly v. U.S. Army Corps of Eng’rs, 
    477 F.3d 225
    , 234 (5th Cir.
    2007). Specifically, we faulted the Corps for failing to explain how the noted
    environmental impacts of the project would be insignificant or would be
    5
    Case: 22-30608      Document: 00516928970            Page: 6    Date Filed: 10/12/2023
    No. 22-30608
    “reduced to insignificance by its prescribed mitigation measure.” 
    Id. at 232
    .
    The 2000 Timber Branch II project did not proceed after our decision.
    We now return to the present permit. On March 19, 2018, the Corps
    posted a link on its website to a public notice of All State’s permit application
    for TB II, in accordance with the CWA. No public meeting or hearing was
    requested to discuss the application, but the Corps received several
    comments on the proposal. The United States Environmental Protection
    Agency and the National Marine Fisheries Service submitted comments,
    stating that they had no objection to the issuance of a § 404 permit as long as
    the project satisfied the statute’s requirements. The Tulane Environmental
    Law Clinic, on behalf of Hazel (Sinclair) Piazza, Loretto O’Reilly, and the
    Gulf Restoration Net-work, submitted a comment requesting denial of TB II
    as proposed. The Tulane Clinic expressed concerns about the high density of
    development in the area, the drainage and flooding, and the project’s impacts
    on wetlands, wildlife, traffic, noise, and water quality. The Tulane Clinic
    further noted that TB II is substantially similar to the 2000 Timber Branch II
    project. Because, in that case, this court enjoined the Corps from issuing a
    § 404 permit “until further orders of the district court consistent with this
    opinion,” the Tulane Clinic contended that the Corps could not grant All
    State’s present application. Other comments detailed further concerns about
    the floodplain and storm drainage impacts of the project.
    In November 2020, the Corps approved the permit application for TB
    II, issuing Permit MVN-2018-0215-EPP to All State. Alongside the permit,
    the Corps issued a 22-page Memorandum for Record (“MOR”),
    representing the EA in support of the Corps’ issuance decision as required
    by NEPA.3 The EA reviewed potential impacts of the project, evaluated
    _____________________
    3
    The document is styled as a “Memorandum for Record,” and the subject line is
    “Department of the Army Environmental Assessment and Statement of Findings for the
    6
    Case: 22-30608         Document: 00516928970              Page: 7       Date Filed: 10/12/2023
    No. 22-30608
    practicable alternatives, and described the compensatory mitigation required
    to offset any environmental effects. While the Corps did not itself respond to
    the public comments it had received, it provided All State’s replies. The
    Corps issued a FONSI, explaining that “the incremental contribution of [TB
    II] to cumulative impacts . . . are not considered to be significant” and that
    compensatory mitigation would “help offset the impacts to eliminate or
    minimize the proposed activity’s incremental contribution to cumulative
    effects.”
    Plaintiffs filed this case in the U.S. District Court for the Eastern
    District of Louisiana in May of 2021. Named as Defendants-Appellees were
    the Corps and the Corps’ Chief of Engineers Lieutenant General Scott
    Spellmon, in his official capacity. Plaintiffs sought declaratory and injunctive
    relief under the Administrative Procedure Act (“APA”), NEPA, and the
    CWA.4 Intervenor-Appellee All State and Intervenor Plaintiff-Appellee St.
    Tammany Parish Government (“St. Tammany”) were granted permission
    to intervene. Plaintiffs, All State, and the Corps filed cross-motions for
    summary judgment. In August 2022, the district court granted summary
    judgment in favor of the Corps and All State, holding that the TP II MOR did
    _____________________
    Above-Referenced Standard Individual Permit Application.” The document “constitutes
    the Environmental Assessment, 404(b)(1) Guidelines Evaluation, as applicable, Public
    Interest Review, and Statement of Findings.” Although it includes more than an EA—
    notably, the CWA’s § 404 permit requirements as well as those under NEPA—we refer to
    the MOR as an EA for ease.
    4
    Plaintiffs also disputed a permit that the Corps had granted for the Ochsner
    Extension Road project, which is a concrete fill project in wetlands less than two miles from
    the TB II area and in the same watershed. On appeal, Plaintiffs do not challenge the district
    court’s decision to affirm the issuance of the Ochsner permit.
    7
    Case: 22-30608         Document: 00516928970              Page: 8       Date Filed: 10/12/2023
    No. 22-30608
    not violate NEPA or the CWA.5 Plaintiffs filed a timely notice of appeal. Fed.
    R. App. P. 4(a)(1)(B).
    III. STANDARD OF REVIEW
    This court reviews the district court’s grant of summary judgment de
    novo, and applies the APA’s standard of review to the agency’s decision.
    Shell Offshore Inc. v. Babbitt, 
    238 F.3d 622
    , 627 (5th Cir. 2001); Medina Cnty.
    Env’t Action Ass’n v. STB, 
    602 F.3d 687
    , 699 (5th Cir. 2010). Under the APA,
    an agency action may be set aside only when it is determined to be “arbitrary,
    capricious, an abuse of discretion, or otherwise not in accordance with law.”
    
    5 U.S.C. § 706
    (2)(A). A decision is arbitrary and capricious when the agency
    . . . has relied on factors which Congress had not intended it to
    consider, entirely failed to consider an important aspect of the
    problem, offered an explanation that runs counter to the
    evidence before the agency, or is so implausible that it could
    not be ascribed to a difference in view or the product of agency
    expertise.
    Fath v. Tex. Dep’t of Transp., 
    924 F.3d 132
    , 136 (5th Cir. 2018) (quoting Motor
    Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)).
    “This is a demanding standard.” Atchafalaya Basinkeeper v. U.S.
    Army Corps of Eng’rs, 
    894 F.3d 692
    , 697 (5th Cir. 2018). The district court is
    not permitted to conduct a de novo review of the permitting decision and
    ultimately substitute its own determination for that of agency’s. Avoyelles
    Sportsmen’s League, Inc. v. Marsh, 
    715 F.2d 897
    , 904 (5th Cir. 1983). As we
    recently reiterated, however, a reviewing court “must ensure that the agency
    _____________________
    5
    The district court also held that the Corps’ issuance of the TB II Permit did not
    violate the Fifth Circuit’s 2007 injunction in the previous O’Reilly litigation. On appeal,
    Plaintiffs do not challenge that decision, but instead contend that the earlier O’Reilly case
    is informative, but not binding, in the instant matter.
    8
    Case: 22-30608     Document: 00516928970           Page: 9   Date Filed: 10/12/2023
    No. 22-30608
    has acted within a zone of reasonableness and, in particular, has reasonably
    considered the relevant issues and reasonably explained the decision.” Data
    Mktg. P’ship, LP v. U.S. Dep’t of Labor, 
    45 F.4th 846
    , 855–56 (5th Cir. 2022)
    (internal quotation marks and citation omitted). The agency must examine
    the relevant data and articulate a satisfactory explanation for its action,
    including a “rational connection between the facts found and the choice
    made.” Atchafalaya Basinkeeper, 894 F.3d at 697 (quoting Motor Vehicle Mfrs.
    Ass’n, 463 U.S. at 43).
    IV. ANALYSIS
    On appeal, Plaintiffs assert that the district court erred in upholding
    the Corps’ decision. They contend that the EA failed to meaningfully
    consider the potential impacts of TB II, including its cumulative effects, in
    violation of both NEPA and the CWA.
    A. Potential Direct and Indirect Impacts
    The Corps issued a FONSI because it determined that TB II would
    not have a significant impact on the environment. The EA includes tables
    that summarize the Corps’ analysis of: (1) potential impacts on physical and
    chemical characteristics in the aquatic ecosystem; (2) potential impacts on
    biological characteristics in the aquatic ecosystem; (3) potential impacts on
    special aquatic sites; (4) potential impacts on human use characteristics; and
    (5) factual determinations of potential impacts. Each of those tables are
    drawn from the regulations associated with § 404 of the CWA. See 40 C.F.R.
    pt. 230. In those tables, the EA indicates whether TB II would have “no
    effect,” a “negligible effect,” a “minor effect (short term),” a “minor effect
    (long term),” or a “major effect” on the area. For example, in evaluating the
    project’s potential impact on the biological characteristics of the aquatic
    ecosystem, per 
    40 C.F.R. § 230.30
    , the Corps determined that the project
    would have no impact on threatened and endangered species, a short-term
    9
    Case: 22-30608        Document: 00516928970              Page: 10       Date Filed: 10/12/2023
    No. 22-30608
    minor impact on aquatic organisms, and a long-term minor impact on other
    wildlife. In another example, the Corps checked off “minor effect (long
    term)” for TB II’s impact on wetlands. In a one-sentence “discussion”
    following that particular table, the EA states that “compensatory mitigation
    should minimize negative impacts to wetland resources.”
    Consistent with its responsibility under the CWA, the EA also
    includes a Public Interest Review. The Corps again used a table to evaluate
    the effects of TB II, running from “detrimental” to “beneficial,” on twenty-
    one factors. Those factors cover a variety of considerations, including
    conservation, flood hazards, floodplain values, safety, and energy needs. The
    Corps concluded that the project would have a “neutral (mitigated)” impact
    on wetlands, a “negligible” impact on flood hazards, and a “detrimental”
    impact on recreation. The only discussion in that section states: “[t]opics
    noted as detrimental in Table 9 [the Public Interest Review] will be short-
    term and localized.”6
    Plaintiffs challenged the EA’s conclusions on the significance of those
    impacts, asserting that the Corps acted arbitrarily by “X-ing off” significance
    determinations without explanation. The district court disagreed. It noted
    that the Corps relied on a hydrological analysis submitted by All State in
    assessing the significance of the project’s impacts, and chose not to credit the
    opposing study offered by Plaintiffs from Dr. Tonja Koob. The district court
    also emphasized that the ten intensity factors in the CEQ regulations are not
    “categorical rules” that must be addressed separately and directly. The court
    thus held that the Corps did not act arbitrarily by not making express
    _____________________
    6
    Interestingly, the next page of the EA states that the “detrimental effects that the
    proposed work is likely to have on the public and private use” are “minimal and
    permanent.” (Emphasis added).
    10
    Case: 22-30608       Document: 00516928970              Page: 11      Date Filed: 10/12/2023
    No. 22-30608
    significance findings for each factor in determining whether TB II’s potential
    impacts were severe enough to warrant a full EIS.
    We have repeatedly agreed that “mere perfunctory or conclusory
    language will not be deemed to constitute an adequate record and cannot
    serve to support the agency’s decision not to prepare an EIS.” O’Reilly, 
    477 F.3d at 231
     (quoting Citizen Advocates for Responsible Expansion, Inc. (I-Care)
    v. Dole, 
    770 F.2d 423
    , 434 (5th Cir. 1985)). An EA is intended to be a “rough-
    cut, low-budget preliminary look at the environmental impact of a proposed
    project,” but the Corps’ decision must still be reasonably supported. Sabine
    River, 951 F.2d at 677 (internal citation omitted). This court must ensure that
    the agency has “reasonably considered the relevant issues and reasonably
    explained the decision.” Fed. Commc’n Comm’n v. Prometheus Radio Proj., 
    592 U.S. 1152
    , 1158 (2021) (emphasis added).
    The Corps articulated no basis for its findings of significance. It failed
    to explain, for example, why it determined that TB II would have a short-
    term minor effect on aquatic organisms but a long-term minor effect on other
    wildlife. That failure to make a “rational connection between the facts found
    and the choice made” is a dereliction of the duty imposed by NEPA. Motor
    Vehicles Mfrs. Ass’n, 463 U.S. at 43 (internal citation omitted). Although an
    EA is intended to be short, it still must explain its reasoning. See id. The
    deficient EA in the 2003 O’Reilly litigation was nearly twice the length of this
    one, and included a paragraph about the significance of each physical impact.
    Even that was insufficient under NEPA. O’Reilly, 
    477 F.3d at 232
    . Here, the
    use of checkboxes without any comment or analysis is even less thorough and
    does not meet the level of scrutiny required by NEPA. 7
    _____________________
    7
    We do recognize that the EA is not entirely devoid of reasoning. In the table on
    factual determinations, for example, the Corps checked off “minor effect (long term)” for
    the project’s impact on aquatic ecosystem and organisms. In the five-sentence
    11
    Case: 22-30608        Document: 00516928970              Page: 12       Date Filed: 10/12/2023
    No. 22-30608
    The district court reasoned that the Corps came to its determination
    of significance by crediting All State’s expert’s analysis, which found that the
    project will “actually decrease floodwater runoff,” instead of that of Dr.
    Koob, which opined that the opposite would occur. This is an impermissible
    post-hoc rationalization, not supported by the EA, which nowhere mentions
    either study. See Motor Vehicles Mfrs. Ass’n, 463 U.S. at 50. Further, the
    Corps is not permitted to “reflexively rubber stamp a statement prepared by
    others.” Save Our Wetlands, Inc. v. Sands, 
    711 F.2d 634
    , 642 (5th Cir. 1983).
    Nothing in the record suggests that the Corps either performed the required
    independent evaluation of the applicant-submitted hydrologic study or
    conducted its own research. See 
    40 C.F.R. § 1506.5
    (a) (“The agency shall
    independently evaluate the information submitted and shall be responsible
    for its accuracy.”). Similarly, the EA does not provide any response to public
    comments; it includes only All State’s answers.8 The Corps was essentially
    silent as to why it agreed with All State and decided to issue a FONSI.
    By failing to explain how it determined TB II’s impacts would not rise
    to the level of significant, the Corps “entirely failed to consider an important
    aspect of the problem.” Motor Vehicles Mfrs. Ass’n, 463 U.S. at 43. The Corps
    _____________________
    “discussion” after the table, it noted that “[a]quatic organisms are typically motile and
    would attempt to avoid the work areas.” That helps to explain why TB II’s effect on aquatic
    organisms would not be major. On remand, the Corps must support its other findings with
    similar explanations.
    8
    Agencies are not required to respond to each comment individually, but the
    regulations contemplate some type of agency response. See 
    40 C.F.R. § 1503.4
    ; see also
    Nat’l Audubon Soc’y v. Dep’t of Navy, 
    422 F.3d 174
    , 185 (4th Cir. 2005) (interpreting
    § 1503.4 to mandate agency response); Mid States Coal. for Progress v. Surface Transp. Bd.,
    
    345 F.3d 520
    , 537 (8th Cir. 2003) (same); Utahns for Better Transp. v. U.S. Dep’t of Transp.,
    
    305 F.3d 1152
    , 1177 (10th Cir. 2003) (same). The EA as written prevents us from discerning
    whether the Corps assessed and approved of All State’s responses to the comments or
    simply “rubber stamp[ed]” them. Save Our Wetlands, 
    711 F.2d at 642
    .
    12
    Case: 22-30608     Document: 00516928970           Page: 13    Date Filed: 10/12/2023
    No. 22-30608
    thus acted arbitrarily in relying on this EA to issue a FONSI. See O’Reilly,
    
    477 F.3d at 234
    .
    B. Cumulative Impacts
    An action may individually affect the environment, directly or
    indirectly, or many small actions may accumulate to make a larger impact.
    Plaintiffs challenge the district court’s determination that the Corps’ FONSI
    was not arbitrary and capricious for its failure to analyze not only TB II’s
    individual impacts, but also the project’s cumulative effect on the
    environment. We begin with a review of the statutory framework under
    NEPA and the CWA, as both statutes require an analysis of the cumulative
    impacts of an agency action.
    NEPA defines cumulative impact as one that “results from the
    incremental impact of the action when added to other past, present, and
    reasonably foreseeable actions.” 
    40 C.F.R. § 1508.7
    . Cumulative impacts
    “can result from individually minor but collectively significant actions taking
    place over a period of time.” 
    Id.
     The statute requires an agency to consider
    cumulative impacts when assessing the severity of a proposed project’s
    environmental effects, as well as the scope of the action’s impact. 
    40 C.F.R. §§ 1508.25
    (a)(2), 1508.27(b)(7).
    The CWA itself also requires consideration of cumulative effects
    when making factual determinations about the impacts of the proposed
    discharge of fill material on the aquatic environment. 
    40 C.F.R. § 230.11
    (g).
    The Act defines cumulative impacts as environmental changes that “are
    attributable to the collective effect of a number of individual discharges.” 
    Id.
    It notes that “[a]lthough the impact of a particular discharge may constitute
    a minor change in itself, the cumulative effect of numerous such piecemeal
    changes can result in a major impairment of the water resources and interfere
    with the productivity and water quality of existing aquatic ecosystems.” 
    Id.
    13
    Case: 22-30608     Document: 00516928970            Page: 14    Date Filed: 10/12/2023
    No. 22-30608
    The TB II EA mentions cumulative impacts of the project in several
    areas. First, within the table on “factual determinations,” as required by the
    CWA, the Corps found that the project will have a long-term minor impact
    on the “cumulative effects on the aquatic ecosystem.” Section 9 of the EA,
    citing regulations from both the CWA and NEPA, purports to discuss “the
    overall impacts that will result from [TB II], in relation to the overall impacts
    from past, present, and reasonably foreseeable cumulative impacts in the
    area.” The Corps defined the geographic and temporal scope for the
    cumulative effects assessment, described the location of the project site, and
    determined that “the incremental contribution of the proposed activity to
    cumulative impacts on the area . . . are not considered to be significant.” The
    district court held that this discussion was sufficient under the APA.
    Although not mentioned in the district court’s decision on this point,
    the parties’ current disagreement about cumulative impact analysis centers
    on our decision in Atchafalaya Basinkeeper. There, we held that “a finding of
    no incremental impact relieves an agency of the necessity of extensive and
    ultimately uninformative discussion of cumulative effects pursuant to
    [NEPA].” 894 F.3d at 704. This makes logical sense: as All State points out,
    seven plus zero is still seven. When a project will not have any incremental
    effect on the environment, it cannot contribute to a wider cumulative effect.
    This is premised on the “rule of reason,” which “relieves agencies from
    preparing exhaustive reports that would serve no purpose in light of NEPA’s
    regulatory scheme as a whole.” Fath, 
    924 F.3d at 139
     (internal quotation
    marks and citation omitted).
    Appellees maintain that the Corps was relieved of its responsibility to
    conduct a cumulative impact analysis because the EA showed that TB II
    would not have any significant effects on the environment. Putting aside our
    earlier discussion of the arbitrary nature of the Corps’ individual significance
    determination, Appellees confuse incremental impact and significant impact.
    14
    Case: 22-30608        Document: 00516928970              Page: 15       Date Filed: 10/12/2023
    No. 22-30608
    NEPA requires consideration of cumulative impacts so as not to discount the
    effect of the “incremental impact[] of the action when added to other[s].” 
    40 C.F.R. § 1508.7
     (emphasis added). The EA determined that TB II would
    result in some level of habitat loss, and in an increase in traffic and noise,
    among other effects. Although such impacts were not anticipated to rise to
    the level of significant, they are at least incremental, as they do exist. This
    case is therefore distinguishable from Atchafalaya Basin, in which the EA
    found no incremental impact at all. 894 F.3d at 703.
    TB II is the very type of project that cumulative impact analysis is
    intended to address. Without that important step, projects like TB II, which
    result in a number of incremental impacts on the environment, could pile up
    and lead to something significant, while escaping the eye of the Corps.9 The
    Corps has fielded over eighty § 404 permit applications in the last five years
    in an area within three miles of the TB II site. If each of those projects has
    only an incremental environmental impact of 0.1 (an arbitrary small number
    that represents the incremental anticipated impact of TB II), the Corps’
    reasoning here would relieve it from its responsibility to conduct a
    cumulative assessment. However, such analysis would be valuable since it
    _____________________
    9
    While we used the words “incremental” and “significant” somewhat
    interchangeably and perhaps imprecisely in our decision in Fath, in that case our policy
    concerns were different. There, the proposed project involved overpasses in an already
    highly-developed and highly-trafficked urban area. 
    924 F.3d at 139
    . This court determined
    that engaging in a full cumulative assessment would “serve no purpose,” as the proposed
    action would not “change the environmental status quo” of an already urban site. 
    Id. at 139-40
    . That is not the case here, as All State is proposing to permanently fill 24.58 acres
    of wetlands and develop what is still a natural environmental area. This case is more like
    Fritiofson v. Alexander, in which we explained that the “unique and fragile nature of wetland
    areas” means that incremental impacts are more likely to compound into a cumulatively
    significant effect. 
    772 F.2d 1225
    , 1246 (5th Cir. 1985), abrogated on other grounds by Sabine
    River, 
    951 F.2d 669
    . The “rule of reason” does not support a decision to forego cumulative
    analysis here. Fath, 
    924 F.3d at 139
    .
    15
    Case: 22-30608       Document: 00516928970          Page: 16   Date Filed: 10/12/2023
    No. 22-30608
    would reveal that, cumulatively, the projects have a significant effect on the
    environment. While seven plus zero is still seven, seven plus eight (0.1 times
    80) is fifteen.
    The district court’s holding that the Corps did not need to conduct a
    cumulative impact analysis was premised on a different line of reasoning, viz.,
    that cumulative impact is one of ten “non-categorical factors” in the
    regulations. While this may be true in the list of intensity factors in 
    40 C.F.R. § 1508.27
    , that is not the only regulation requiring cumulative analysis under
    NEPA. The regulations also mandate consideration of cumulative impact
    when addressing types and the scope of effects. See 
    40 C.F.R. §§ 1508.7
    ,
    1508.25(a)(2). And we have said that “agencies must consider each
    cumulative impact of permitted actions.” Atchafalaya Basinkeeper, 894 F.3d
    at 703 (emphasis added) (internal quotation marks omitted). Unless the
    project will have no incremental environmental impacts whatsoever, as
    discussed above, some amount of cumulative analysis is required.
    Because the EA determined that TB II would have some level of
    incremental impact on the environment, it was arbitrary and capricious for
    the Corps to limit its cumulative impact analysis. See Fath, 
    924 F.3d at 140
    .
    And the limited analysis that is included in the EA does not meet the
    requirements of NEPA. A cumulative effects assessment must include
    consideration of “past, present, and reasonably foreseeable future actions”
    that have had or are expected to have impacts in the same geographic area.
    
    40 C.F.R. § 1508.7
    . The EA does not mention any of those other actions. See
    While the Corps is entitled to consider the effects of past actions “in the
    aggregate” without mentioning specific individual past projects, the Corps
    failed to do even that. See James L. Connaughton, Guidance on the
    Consideration of Past Actions in Cumulative Effects Analysis (Mem.), COUNCIL
    ON   ENV’T QUALITY (June 24, 2005), https://ceq.doe.gov/docs/ceq-
    regulations-and-guidance/regs/Guidance_on_CE.pdf. The EA nowhere
    16
    Case: 22-30608     Document: 00516928970            Page: 17    Date Filed: 10/12/2023
    No. 22-30608
    refers to two past phenomena that constitute important context for the TB II
    proposal: (1) the dozens of permits that the Corps has granted recently in the
    Liberty Bayou-Tchefuncta area, and (2) the catastrophic 2016 flooding in St.
    Tammany, both of which were raised by several public comments. The Corps
    failed to consider how the incremental effects of the project might compound
    these preexisting environmental concerns. Or, if it did, it did not adequately
    document its analysis so that we could meaningfully review its decision. See
    Motor Vehicles Mfrs. Ass’n, 463 U.S. at 43.
    On the other hand, we are not persuaded that, as Plaintiffs argue, the
    Corps acted arbitrarily or abused its discretion by failing to consider
    reasonably foreseeable future actions in its cumulative assessment. A
    reasonably foreseeable action is one that is “sufficiently likely to occur that a
    person of ordinary prudence would take it into account in reaching a
    decision.” City of Shoreacres v. Waterworth, 
    420 F.3d 440
    , 453 (5th Cir. 2005)
    (citation omitted). Plaintiffs contend that the record shows that it is
    reasonably foreseeable that the TB II project will be expanded to cover the
    rest of Bruce Wainer’s land. In support of this contention, Plaintiffs offer two
    affidavits from residents who represent that Wainer showed them his plans
    to develop the rest of the site. Such evidence is not enough to establish that
    future development is “sufficiently likely,” rather than merely a possibility.
    City of Shoreacres, 
    420 F.3d at 453
    . Indeed, this court has found that future
    development need not be considered in cumulative impact analyses when
    permit applications have been filed but the Corps has not yet begun working
    on an EIS, since the plans could still be “cancelled or drastically altered.”
    Gulf Restoration Network v. U.S. Dep’t of Transp., 
    452 F.3d 362
    , 370 (5th Cir.
    2006). Wainer’s alleged plans are far less established. The Corps did not
    abuse its discretion in failing to specifically address those future actions.
    A brief word is in order regarding the CWA, as Plaintiffs challenge the
    Corps’ permitting decision under both NEPA and the CWA. We have
    17
    Case: 22-30608        Document: 00516928970               Page: 18        Date Filed: 10/12/2023
    No. 22-30608
    determined that the Corps acted arbitrarily when it issued a FONSI without
    conducting a sufficient analysis in the EA of TB II’s cumulative impacts – all
    in violation of NEPA. As described above, the CWA has its own cumulative
    assessment requirements beyond and apart from NEPA, focused on the
    aquatic environment. The district court declined to consider the cumulative
    effects of TB II under the CWA because it was “not persuaded that the
    specific cumulative impacts concerns raised by Plaintiffs actually implicate
    the CWA’s zone of interests.” We disagree. The CWA requires the Corps
    to consider the “changes in an aquatic ecosystem that are attributable to the
    collective effect of a number of individual discharges of dredged or fill
    material.” 
    40 C.F.R. § 230.11
    (g)(1). Plaintiffs raised concerns about the
    cumulative impact of the large number of § 404 permits issued in the area by
    the Corps in recent years. That, in turn, permitted activity which has led to a
    higher number of dredging or filling projects, rendering it directly related to
    the CWA’s “zone of interests.”10
    Under the APA, the Corps must adequately explain its decision
    making, regardless of the statute under which its action is challenged. See
    Ohio Valley Env’t Coalition v. Aracoma Coal Co., 
    556 F.3d 177
    , 209 (4th Cir.
    2009) (reviewing cumulative analysis under both the CWA and NEPA). Just
    as the analysis of potential impacts of TB II was deficient under NEPA, so
    too are the considerations of the impacts on the aquatic ecosystem under the
    CWA. The Corps must explain why it concluded that “[c]umulatively,
    similar projects could have a long-term impact on the aquatic ecosystem.”
    Without this “rational connection between the facts found and the choice
    _____________________
    10
    Assuming the district court was referring to Plaintiffs’ central focus on flooding,
    changes in the floodplain would certainly impact the area’s aquatic environment. And
    Plaintiffs did in fact raise specific concerns about the impact of the project on water quality
    and the habitat of aquatic wildlife.
    18
    Case: 22-30608     Document: 00516928970            Page: 19   Date Filed: 10/12/2023
    No. 22-30608
    made,” this court cannot perform its duty in ensuring that the Corps’
    decision was not “arbitrary, capricious, an abuse of discretion, or otherwise
    not in accordance with law.” Motor Vehicle Mfrs. Ass’n, 463 U.S. at 41, 43
    (quoting 
    5 U.S.C. § 706
    (2)(A)).
    V. CONCLUSION
    We understand that an EA is intended to be a concise document. 
    40 C.F.R. § 1508.9
    (a). Yet it must also “provide sufficient evidence and
    analysis” for determining whether to prepare an EIS or issue a FONSI. 
    Id.
    Because the TB II EA lacks sufficient detail, we cannot say whether or not
    the project will have a significant effect on the environment—it remains “an
    open question.” Fritiofson, 
    772 F.2d at 1247
     (quoting La. Wildlife Fed., Inc. v.
    York, 
    761 F.2d 1044
    , 1053 (5th Cir. 1985)). We remand this case to the Corps
    to reassess the significance of the instant project in light of this Court’s
    opinion.
    We therefore (1) REVERSE and VACATE the district court’s Order
    of August 15, 2022; (2) ENJOIN the Corps from issuing a § 404 permit until
    the district court issues further orders; and (3) REMAND this case to the
    Corps for further proceedings consistent with this opinion, including the
    preparation of a new EA.
    19
    

Document Info

Docket Number: 22-30608

Filed Date: 10/12/2023

Precedential Status: Non-Precedential

Modified Date: 10/12/2023