Audubon Commission v. Roy Frischhertz Construction Co. (In Re Roy Frischhertz Construction Co.) , 401 F. App'x 861 ( 2010 )


Menu:
  •      Case: 08-30993 Document: 00511290584 Page: 1 Date Filed: 11/10/2010
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT  United States Court of Appeals
    Fifth Circuit
    FILED
    November 10, 2010
    No. 08-30993                         Lyle W. Cayce
    Clerk
    In the Matter of: ROY FRISCHHERTZ CONSTRUCTION CO. INC.,
    Debtor.
    AUDUBON COMMISSION,
    Appellant–Cross-Appelle,
    v.
    ROY FRISCHHERTZ CONSTRUCTION CO. INC.,
    Appellee–Cross-Appellant,
    OHIO CASUALTY INSURANCE CO.,
    Appellee.
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    USDC No. 2:08-CV-89
    USDC No. 2:07-CV-9426
    Before DAVIS, OWEN, and HAYNES, Circuit Judges.
    PER CURIAM:*
    *
    Pursuant to 5TH CIR . R. 47.5, the court has determined that this opinion should not
    be published and is not precedent except under the limited circumstances set forth in 5TH CIR .
    R. 47.5.4.
    Case: 08-30993 Document: 00511290584 Page: 2 Date Filed: 11/10/2010
    No. 08-30993
    The judgment of the bankruptcy court is reversed in part and we remand
    for the following reasons:
    1. Section 14.1.1 of the construction contract requires only an actual work
    stoppage of thirty consecutive days following a government act or acts that
    require work to be stopped. The bankruptcy court did not clearly err when it
    determined that the August 28, 2005, “Promulgation of Emergency Orders,”
    which instituted a mandatory evacuation of “all of the Parish of Orleans,”
    required work to be stopped and that “it was not possible for RFCC to man the
    Audubon project” for thirty consecutive days following the evacuation order.
    2. The bankruptcy court properly denied Audubon its completion costs and
    proof of claim in the main bankruptcy proceeding.
    3. The bankruptcy court did not abuse its discretion in excluding Roy
    Frischhertz, III’s video deposition testimony from evidence at trial.
    4. The bankruptcy court did not err in its determination that the evidence
    was insufficient to support RFCC’s claim to compensation for lost overhead and
    profit in addition to recovery of the contract price for work actually completed.
    5. The bankruptcy court erred in determining that RFCC was not entitled
    to the retainage withheld by Audubon. “Retainage is a portion or percentage of
    payments due for the work completed on a contract that is held back until the
    entire job is completed satisfactorily.”1 As is typical in construction contracts,2
    the agreement between RFCC and Audubon provided for monthly progress
    payments and withholding of retainage.
    Under the terms of the contract, RFCC has the right to recover retainage
    after termination. Specifically, § 14.1.3 provides:
    1
    Quality Design & Constr., Inc. v. City of Gonzales ex rel. Berthelot, 06-2211, p. 2 n.1
    (La. App. 1 Cir. 11/28/07); 
    977 So. 2d 87
    , 88 n.1.
    2
    See State v. Laconco, Inc., 
    430 So. 2d 1376
    , 1381-82 (La. Ct. App. 1983).
    2
    Case: 08-30993 Document: 00511290584 Page: 3 Date Filed: 11/10/2010
    No. 08-30993
    If one of the reasons described in Section 14.1.1 or 14.1.2 exists, the
    Contractor may, upon seven days’ written notice to the Owner and
    Architect, terminate the Contract and recover from the Owner
    payment for Work executed and for proven loss with respect to
    materials, equipment, tools, and construction equipment and
    machinery, including reasonable overhead, profit and damages.
    Because RFCC properly terminated the contract, this section unequivocally
    entitles RFCC to “payment for Work executed,” irrespective of substantial
    completion. Therefore, this section allows RFCC to recover the contractually
    agreed upon compensation for completed work. Because retainage is simply 5%
    of the compensation properly due, the plain language of the provision allows
    RFCC to recover retainage. RFCC is entitled to retainage.
    *        *         *
    REVERSED in part and REMANDED.
    3
    

Document Info

Docket Number: 08-30993

Citation Numbers: 401 F. App'x 861

Judges: Davis, Owen, Haynes

Filed Date: 11/10/2010

Precedential Status: Non-Precedential

Modified Date: 10/19/2024