Lake Charles Steve v. Prof Vladimir Popov ( 2000 )


Menu:
  •                        REVISED, JANUARY 24,2000
    IN THE UNITED STATES COURT OF APPEALS
    FOR THE FIFTH CIRCUIT
    ____________________
    No. 98-30983
    ____________________
    LAKE CHARLES STEVEDORES, INC
    Plaintiff - Appellant
    v.
    PROFESSOR VLADIMIR POPOV MV, in rem
    Defendant - Appellee
    _________________________________________________________________
    Appeal from the United States District Court
    for the Eastern District of Louisiana
    _________________________________________________________________
    December 23, 1999
    Before KING, Chief Judge, and SMITH and STEWART, Circuit Judges.
    KING, Chief Judge:
    Plaintiff-Appellant Lake Charles Stevedores, Inc. appeals
    the district court’s dismissal of its in rem proceeding against
    Defendant-Appellee, the Professor Vladimir Popov M/V, arguing
    that the court erred in determining that the stevedores had no
    maritime lien.    We affirm.
    I. FACTS AND PROCEDURAL BACKGROUND
    As is often the situation in transactions involving the
    shipping of goods, a number of different parties were at least
    indirectly involved in the transaction at the heart of this case.
    Terms of the initially contemplated transaction were defined in
    January, 1997, when ED&F Man Sugar, Inc. (“Man Sugar”), a
    subsidiary of ED&F Man, Inc., agreed to purchase from Broussard
    Rice Mill, Inc. (“Broussard”) 5000 metric tons of rice at $18.40
    c.w.t. (price F.O.B. mill), for delivery some time between the
    last half of February and the first half of March.   The purchase
    agreement indicates that the final contract price would include
    the cost of the bags to contain the rice, of freight from the
    mill to the dock, of unloading the trucks, and of stowing and
    trimming (i.e., stevedoring services).    Adding the cost of these
    items to the base price for the rice alone ($18.40 c.w.t.) yields
    an anticipated final price of $20.05 c.w.t.   The sale of 5000
    tons of rice, under the same terms, was confirmed in a document
    Broussard sent to Man Sugar on February 3, 1997.
    In part because Man Sugar could not secure a vessel by mid-
    February, delivery could not occur when originally expected.     The
    contract was amended on March 24, 1997 to provide for 4600
    (rather than 5000) tons of rice at $20.05 c.w.t., delivery F.O.B.
    vessel sometime in early April.   The contract price again
    included stevedoring, with no change in the $.90 c.w.t. cost.
    Man Sugar also agreed to make progress payments of $19.15 c.w.t.
    when loads of 1500 tons reached the dock in order to prevent
    Broussard from having to carry the costs associated with delay in
    delivery.   The balance ($.90 c.w.t.) was due when full and
    complete shipping documents were presented.
    Man Sugar was able to gain access to the Professor Vladimir
    Popov M/V (the “Vessel”) in March 1997.   Savannah Chartering
    2
    Ltd., the disponent owner of the Vessel, had time chartered the
    Vessel to Marine Trading, Ltd. (“Marine Trading”) in June 1996.
    The charter party between Savannah Chartering and Marine Trading
    provided that
    [t]he Captain (although appointed by the Owners), shall be
    under the orders and direction of the Charterers as regards
    employment and agency; and Charterers are to load, stow and
    trim, and secure the cargo at their expense under the
    supervision of the Captain, who is to sign bills of lading
    for the cargo as presented, in conformity with the mate’s or
    talley clerk’s receipts.1
    In a document dated March 20, 1997, Marine Trading voyage
    chartered the Vessel to Sugar Chartering, Inc., another
    subsidiary of ED&F Man.       The charter party provided that
    stevedores were to be employed by Sugar Chartering.       Sugar
    Chartering subchartered the Vessel to Man Sugar.
    On April 24, 1997, freight forwarder Mary Reid of Reid &
    Company (“Reid”), acting on behalf of Broussard, asked Lake
    Charles Stevedores, Inc. (“LCS”) to submit a bid for loading the
    rice.       At the time Reid contacted LCS, it was told it would be
    working for Broussard.       Reid also obtained an “all inclusive” bid
    from another stevedoring concern in the area.       In order to assist
    in comparing the bids, Reid asked LCS to submit an all-inclusive
    bid.       Although the first bid LCS submitted to Reid was copied to
    Broussard, the second bid was not.       LCS’ second bid noted that
    the vessel’s gear would be used unless it was slow, in which case
    LCS’ shore gear would be used at LCS’ expense.       Broussard awarded
    1
    Under a rider clause, charterers, subcharterers, or their
    agents could sign bills of lading for and on behalf of the Master
    in conformity with the Mate’s receipt.
    3
    the contract to load the Vessel to LCS.   Reid relayed this
    information to LCS.   LCS had often worked for Broussard in the
    past, generally unloading its trucks at the docks, but also
    loading ships under prior F.O.B. contracts.
    During April, Broussard delivered the rice to the docks.
    After receiving confirmation that loads of rice had been
    delivered, Man Sugar made payments as per the parties’ agreement.
    Lake City Steamship Agency (“LCSA”), a division within LCS, was
    hired by Marine Chartering, an agent of Marine Trading, to act as
    vessel agent.   In this capacity, LCSA was responsible for
    coordinating the Vessel’s movement in and out of port and meeting
    its requirements while in port.   LCSA prepared the Notice of
    Readiness, indicating that the Vessel was in port and ready to be
    loaded, and transmitted it to Reid, who was also the local agent
    for Man Sugar, on April 30, 1997.
    LCS loaded the Vessel on May 1, May 2, and May 5, 1997.    The
    Vessel’s mate or master signed LCS’ Activity Sheets2 and Mate’s
    Receipt.   A clean bill of lading was signed by LCSA for the
    Vessel’s master.   When it received the required shipping
    documents from Reid, Man Sugar made its final payment, in the
    amount of $90,761.78, to Broussard.   This amount was described as
    stevedoring expenses in Man Sugar’s accounts.   LCS sent an
    invoice to Broussard, but to no other entity, for the stevedoring
    services rendered.    Although Broussard charged Man Sugar $18 per
    short ton of cargo for stevedoring services (or $.90 c.w.t.), LCS
    2
    Activity sheets, necessary to issue a Mate’s Receipt,
    described the work performed each day.
    4
    charged Broussard only $14 per short ton, yielding a total bill
    of $65,395.07.   The difference in price was attributed by the
    district court to Broussard’s acceptance of risk of loss due to
    weather conditions or other contingencies.
    LCS had never had difficulty collecting on its accounts with
    Broussard.   However, in this instance, the bill from LCS remained
    unpaid.   On September 30, 1997, after LCS learned that Broussard
    had been put into receivership, LCS had the Vessel arrested in
    order to secure payment for the stevedoring services.      ED&F Man
    and Sugar Chartering each filed claim for the Vessel.
    The Vessel’s claimants and LCS filed motions for summary
    judgment, each of which was denied.      The case was tried without a
    jury on July 28, 1998.   The district court held that LCS was not
    entitled to a lien because there was no contract between LCS and
    the charterers, there was no evidence that Broussard was the
    owner’s or a charterer’s agent, and the owner’s or charterer’s
    knowledge that LCS was apparently the stevedoring concern hired
    by Broussard to load the rice was insufficient to create a lien.
    LCS timely appeals.
    II. STANDARD OF REVIEW
    Because we face an admiralty case tried without a jury, we
    review the district court’s legal conclusions de novo.       See Nerco
    Oil & Gas, Inc. v. Otto Candies, Inc., 
    74 F.3d 667
    , 668 (5th Cir.
    1996).    The district court’s factual findings are reviewed under
    the clearly erroneous standard.       See Fed. R. Civ. P. 52(a);
    
    Nerco, 74 F.3d at 668
    .   The clearly erroneous standard of review
    5
    does not apply to factual findings made under an erroneous view
    of controlling legal principles.       See Delta S.S. Lines, Inc. v.
    Avondale Shipyards, Inc., 
    747 F.2d 995
    , 1000 (5th Cir. 1984).
    III.   DOES LCS HAVE A MARITIME LIEN?
    The purpose of maritime liens is “to enable a vessel to
    obtain supplies or repairs necessary to her continued operation
    by giving a temporary underlying pledge of the vessel which will
    hold until payment can be made or more formal security given.”
    Southern Coal & Coke Co. v. F. Grauds Kugniecibas (“The
    Everosa”), 
    93 F.2d 732
    , 735 (1st Cir. 1938); see also Piedmont &
    George’s Creek Coal Co. v. Seaboard Fisheries Co., 
    254 U.S. 1
    , 9
    (1920) (“Since she is usually absent from the home port, remote
    from the residence of her owners and without any large amount of
    money, it is essential that she should be self-reliant – that she
    should be able to obtain upon her own account needed repairs and
    supplies.”); A.L. Veverica v. Drill Barge Buccaneer No. 7, 
    488 F.2d 880
    , 883 (5th Cir. 1974) (“The very purpose of maritime
    liens is to encourage necessary services to ships whose owners
    are unable to make contemporaneous payment.”).3      They are largely
    3
    Although credit to the vessel remains a fundamental
    concept underlying the maritime lien, see Equilease Corp. v. M/V
    Sampson, 
    793 F.2d 598
    , 605 (5th Cir. 1986) (“Equilease II”), it
    is no longer the case that a claimant providing necessaries on
    the order of one with authority to procure them must prove that
    credit was given the vessel in order to establish a lien. See
    § 31342(a)(3); Piedmont & George’s Creek Coal Co. v. Seaboard
    Fisheries Co., 
    254 U.S. 1
    , 12 (1920) (“The act relieves the
    libelant of the burden of proving that credit was given to the
    ship when necessaries are furnished to her upon order of the
    owner . . . .”).
    6
    statutorily created.     See In re Admiralty Lines, Ltd., 280 F.
    Supp. 601, 604-05 (E.D. La. 1968) (“[A]dmiralty law has long ago
    ceased to create new liens.    The only liens recognized today are
    those created by statute and those historically recognized in
    maritime law.”).   Thus, in order to resolve the issues raised in
    this case, we must look to the Maritime Commercial Instruments
    and Liens Act (“MCILA”), 46 U.S.C. § 31301 et seq., which defines
    the circumstances under which a party is entitled to a maritime
    lien.
    In brief, the MCILA states that a person providing
    necessaries to a vessel on the order of the owner or a person
    authorized by the owner has a maritime lien on the vessel, see
    § 31342(a),4 unless the provider of the necessaries has waived
    its right to the lien.     See § 31305.   Section 31341(a) lists
    entities presumed to have authority to procure necessaries: (1)
    the owner; (2) the master; (3) a person entrusted with the
    management of the vessel at the port of supply; or (4) an officer
    or agent appointed by the owner, a charterer, an owner pro hac
    vice, or an agreed buyer in possession of the vessel.     An element
    common to these entities is that they may be presumed to have
    4
    Under § 31342(a),
    Except as provided in subsection (b) of this section, a
    person providing necessaries to a vessel on the order
    of the owner or a person authorized by the owner–
    (1) has a maritime lien on the vessel;
    (2) may bring a civil action in rem to enforce the
    lien; and
    (3) is not required to allege or prove in the action
    that credit was given to the vessel.
    46 U.S.C. § 31342(a).
    7
    authority to procure necessaries on the vessel’s account.     Cf.
    Ferromet Resources v. Chemoil Corp., 
    5 F.3d 902
    , 904 (5th Cir.
    1993) (“The ship’s master or other person, such as a charterer,
    to whom the vessel is entrusted is presumed to have authority to
    purchase necessaries to the credit of the vessel.”).5   The
    presumption created in § 31341 is not conclusive, see Marine
    5
    That § 31342(a) and § 31341(a) refer to authority to
    procure necessaries on the vessel’s account is also reflected in
    the law the MCILA replaced in 1988, the Federal Maritime Lien
    Act, 46 U.S.C. § 971 et seq., and in the 1971 amendments to that
    Act. Under the pre-1971 version of § 973 of the Federal Maritime
    Lien Act,
    [t]he officers and agents of a vessel specified in
    section 972, shall be taken to include such officers
    and agents when appointed by a charterer, by an owner
    pro hac vice, or by an agreed purchaser in possession
    of the vessel; but nothing in this chapter shall be
    construed to confer a lien when the furnisher knew, or
    by exercise of reasonable diligence could have
    ascertained, that because of the terms of a charter
    party, agreement for sale of the vessel, or for any
    other reason, the person ordering the repairs,
    supplies, or other necessaries was without authority to
    bind the vessel therefor.
    (emphasis added). The 1971 amendments eliminated all language
    after the semicolon in order to remove from suppliers the
    obligation to investigate whether the entity ordering necessaries
    was, in fact, with authority to bind the vessel. See Atlantic &
    Gulf Stevedores, Inc. v. M/V Grand Loyalty, 
    608 F.2d 197
    , 201
    (5th Cir. 1979). This created a statutory presumption that
    certain entities (those listed in § 972 and the remaining portion
    of § 973) had authority to bind the vessel. The MCILA maintains
    that presumption, with the entities now all listed in § 31341(a).
    Although the 1971 amendments made it easier for suppliers of
    necessaries to obtain liens, see 
    id., they did
    not alter the
    definition of “authority.” Cf. Jan C. Uiterwyk Co. v. MV Mare
    Arabico, 
    459 F. Supp. 1325
    , 1329 (D. Md. 1978) (noting that the
    1971 amendments to the Federal Maritime Lien Act did not
    eliminate the requirement that necessaries be procured by an
    entity with authority to do so). The definition of authority was
    also not changed when the MCILA was enacted. See H.R. REP. NO.
    100-918, reprinted in 1988 U.S.C.C.A.N. 6108, 6129, 6141 (noting
    that no substantive change from prior law is intended in enacting
    the MCILA).
    8
    Coatings v. United States, 
    932 F.2d 1370
    , 1376 (11th Cir. 1991),
    and thus can be rebutted by, for example, a showing that the
    provider of necessaries had actual knowledge of a no-lien clause
    that prevented the entity ordering those necessaries from binding
    the vessel.     See Belcher Oil Co. v. M/V Gardenia, 
    766 F.2d 1508
    ,
    1512 (11th Cir. 1985); Gulf Oil Trading Co. v. M/V Caribe Mar,
    
    757 F.2d 743
    , 749 (5th Cir. 1985).     As a result, a supplier of
    necessaries ordered by a § 31341(a) entity subject to a no-lien
    clause not made known to the supplier has a maritime lien.
    It is undisputed that stevedoring services are necessaries,
    and that LCS provided those services.     The case thus raises two
    basic issues.    The first issue is whether “the person who placed
    the order had authority to do so, either real, apparent, or
    statutorily presumed,” i.e., whether LCS has a maritime lien.
    Belcher Co. v. M/V Maratha Mariner, 
    724 F.2d 1161
    , 1164 (5th Cir.
    1984); see also Atlantic & Gulf Stevedores, Inc. v. M/V Grand
    Loyalty, 
    608 F.2d 197
    , 202 (5th Cir. 1979) (“Authorization,
    actual or fairly presumed, given prior to or during rendition of
    services, or ratified subsequent to rendition will suffice.”).
    If LCS had a maritime lien, the second issue we must address is
    whether LCS waived its right to that lien.
    LCS takes issue with both the findings of fact and the
    conclusions of law underlying the district court’s determination
    that it was not entitled to a lien.     LCS states that the findings
    of fact are clearly erroneous, and also argues that the standard
    applied to find that LCS relied only on Broussard’s credit was
    improper.   Further, LCS argues that, contrary to the district
    9
    court’s determination, it obtained a valid maritime lien because
    (1) Broussard had actual authority from the Vessel’s owners; (2)
    Broussard had apparent authority; (3) the services it supplied
    were ratified by the master; and (4) it did not forgo its lien.
    A.   Authority - Real, Apparent, or Statutorily Presumed
    The parties stipulated that Broussard made the final
    selection of LCS as the company to load the bagged rice onto the
    Vessel.   If Broussard had authority to act on behalf of the
    Vessel when it employed LCS, then LCS has a maritime lien.      See
    § 31342(a).   Citing Jan C. Uiterwyk Co. v. MV Mare Arabico, 
    459 F. Supp. 1325
    (D. Md. 1978), in support, LCS points to the nature
    of services supplied to argue that Broussard had actual authority
    from the Vessel’s owners or charterers to engage LCS to supply
    stevedoring services.   LCS notes that the Jan C. Uiterwyk court
    specifically recognized that “[a]rrangements for these
    [stevedoring] services must be made by the ship’s master or
    someone authorized by 
    him”, 459 F. Supp. at 1330
    , and that “[i]t
    is hardly the responsibility of a mere shipper to arrange for
    services necessary for a vessel to enter a port, to receive cargo
    and to leave the port.”   
    Id. at 1331.
      LCS traces the line of
    authority from the charter to Marine Trading to the charter to
    Sugar Chartering, noting that the authority to employ stevedores
    was passed on at each stage.   LCS continues this line of
    reasoning to conclude that Broussard was authorized by the
    Vessel’s owners to employ stevedores to board and load the Vessel
    because the authority could come from nowhere else.   A similar
    10
    “nature of service” argument is made in support of LCS’
    contention that Broussard had apparent authority to hire the
    stevedores.6    Broussard is also argued to have been entrusted
    with the management of the Vessel at the port of supply because
    it employed LCS, a stevedoring concern.    Further, LCS contends
    that Broussard was able to, and did authorize the use of the
    Vessel’s gears when it accepted LCS’ bid, which indicated that
    the Vessel’s equipment could be used.    In addition, LCS points to
    the legislative history of the 1971 amendments to the Federal
    Maritime Lien Act, 46 U.S.C. § 971 et seq., as supporting the
    notion that stevedores can presume that they have a lien when
    they supply services to a vessel.
    The MCILA identifies in § 31341(a) the entities that can be
    statutorily presumed to have authority to procure necessaries on
    the vessel’s account.    The presumption created in § 31341 is not
    a function of the services supplied – both § 31341 and § 31342
    speak in terms of necessaries without further distinction.7
    Unless Broussard is one of the entities listed in § 31341(a), the
    6
    LCS also asserts that Reid had apparent authority to
    obtain stevedoring services, that Reid awarded the contract to
    LCS, and that she was a person entrusted with the management of
    the vessel at the port of supply, see § 31341(a), given her
    capacity as Man Sugar’s local agent. Because we find no
    indication in the record that the district court’s finding that
    LCS at all relevant times knew it was hired solely by Broussard
    is clearly erroneous, we must reject these arguments.
    7
    The MCILA separates stevedoring services from others in
    § 31301(5), which provides that a “preferred maritime lien” is
    one “(A) arising before a preferred mortgage was filed under
    section 31321 of this title . . . (C) for wages of a stevedore
    when employed directly by a person listed in section 31341 of
    this title.” This provision is not applicable to the instant
    case.
    11
    statute does not allow for a presumption that it had authority to
    procure the necessaries on the ship’s account simply because the
    necessaries provided were stevedoring services.
    We must therefore undertake to determine whether Broussard
    qualifies as any of the entities listed in § 31341(a).     Broussard
    is clearly not the owner of the Vessel, or its master.     It is
    also not “a person entrusted with the management of the vessel at
    the port of supply.” § 31341(a)(3); see also Dampskibsselskabet
    Dannebrog v. Signal Oil & Gas Co., 
    310 U.S. 268
    , 279-80 (1940)
    (describing management as “a broader term connoting direction and
    control for the purposes for which the vessel is used” and
    finding a charterer to have been entrusted with the management of
    the vessel).    In Atlantic & Gulf Stevedores, we found a chief
    officer to be a person to whom management of the vessel was
    entrusted, based on his position within the command hierarchy,
    his duties, which specifically included the direction and control
    of loading and unloading, and historic practice.     
    See 608 F.2d at 200
    .    There are no such indicators here.   This was Man Sugar’s
    first purchase of rice from Broussard.    Broussard was
    contractually obligated to undertake the steps necessary to get
    the specified quantity of rice onto the Vessel.     It was not
    entrusted with the management of the Vessel at the port of
    supply.
    Whether Broussard is an agent appointed by Man Sugar, as
    subcharterer, is a somewhat closer question.     In interpreting
    whether Broussard is an agent, we look to general principles of
    agency law, see Marine Fuel Supply & Towing, Inc. v. M/V Ken
    12
    Lucky, 
    869 F.2d 473
    , 477 (9th Cir. 1989); Cactus Pipe & Supply
    Co. v. M/V Montmartre, 
    756 F.2d 1103
    , 1111 (5th Cir. 1985); Esso
    Int’l, Inc. v. The SS Captain John, 
    443 F.2d 1144
    , 1146 (5th Cir.
    1971), and consider “the roles of the parties in the
    transactions.”   Marine Fuel 
    Supply, 869 F.2d at 477
    .   Unless the
    district court’s findings regarding the existence of an agency
    relationship are clearly erroneous, we must accept those
    findings.   See Equilease v. M/V Sampson, 
    756 F.2d 357
    , 363 (5th
    Cir. 1985) (“Equilease I”) (en banc) (“The existence of any
    agency relationship is a question of fact which should not be
    reversed on appeal unless it is clearly erroneous.”)(citing
    Strachan Shipping Co. v. Dresser Indus., Inc., 
    701 F.2d 483
    , 487
    (5th Cir. 1983)).
    We assume that Man Sugar had authority to employ stevedores
    on the Vessel’s account.8   It is clear from the contract between
    Man Sugar and Broussard that Broussard was not given express
    authority to employ stevedores on behalf of the Vessel.    The
    sales contract makes no reference to Broussard’s acting as Man
    Sugar’s agent.
    Given the terms of the sales contract and the parties’
    actions under that contract, Broussard also did not have implied
    authority to procure stevedoring services on the Vessel’s
    8
    The terms of the subcharter between Sugar Chartering and
    Man Sugar do not include language expressly pertaining to
    procuring stevedoring services. Under § 31341(a), however, Man
    Sugar would be presumed to have authority to procure such
    services on the Vessel’s account. See Marine Fuel 
    Supply, 869 F.2d at 476
    n.3 (noting that a subcharterer is treated as a
    charterer for purposes of the Maritime Lien Act).
    13
    account.9   Because the contract provided for delivery F.O.B.
    vessel,10   title to the rice was to stay with Broussard until
    loading was completed.   Broussard was therefore responsible for
    loading its, not Man Sugar’s, rice.   The sales contract also set
    the cost for stevedoring services at $.90 c.w.t., with no
    allowance for delays or other contingencies.   Cf. South Carolina
    State Ports Auth. v. M/V Tyson Lykes, 
    67 F.3d 59
    , 61 (4th Cir.
    1995) (finding no agency relationship where subcontractor billed
    only the contractor, there was no contract between the
    subcontractor and the charterer, and under the agreement between
    the charterer and the general contractor, the charterer was to
    pay the contractor on a flat “pick-rate,” i.e., per container,
    9
    Much of LCS’ argument in support of its contention that
    Broussard had “authority” to employ stevedores appears to rest on
    the assumption that because Broussard was able to employ an
    independent stevedoring concern, Broussard had the authority to
    employ stevedores on the Vessel’s account. LCS argues that,
    given the circumstances, Broussard and Man Sugar anticipated that
    Broussard would employ an independent stevedoring concern and
    thus that Broussard had the authority under the sales contract to
    do so. We do not consider the ability to employ LCS as
    synonymous with the authority to employ LCS on the Vessel’s
    account. See 
    note 5 supra
    . Moreover, we view the expectation
    that Broussard would use an independent concern to load the rice
    as insufficient to grant to Broussard the authority to hire
    stevedores on the Vessel’s account, and therefore reject the
    approach apparently taken in Riedel Envtl. Servs., Inc. v. M/V
    Tula, 
    1987 A.M.C. 2378
    (S.D. Ala. 1987). See discussion of
    general contractor and middle-man cases infra.
    10
    LCS uses this fact to argue that Broussard was given
    authority to hire stevedores. That the final contract price
    would include costs of loading the rice onto the Vessel, however,
    was a term of the agreement reached in January, 1997, before Man
    Sugar had access to a ship, let alone the Vessel. Although the
    contract was amended after Man Sugar became the subcharterer to
    the Vessel, the F.O.B. delivery term was not among the terms
    altered. Under these circumstances, it is difficult to find that
    the F.O.B. terms are responsible for transferring the requisite
    authority from Man Sugar to Broussard.
    14
    basis).    Broussard thus agreed to shoulder the risk that actual
    stevedoring costs may have been greater than the amount owed by
    Man Sugar.11
    The crux of LCS’ “nature of services” argument appears to be
    that because stevedores must board a vessel in order to supply
    their services, authority to hire LCS must have passed from the
    Vessel’s owners through all intermediate parties to Broussard.
    We must reject this argument.    Man Sugar may have granted
    Broussard, and by extension, its employees, and its
    subcontractors permission to board.    However, this does not
    translate to authority to employ stevedores on the Vessel’s
    account.    On brief, LCS characterizes the F.O.B. terms as Man
    Sugar’s allocating to Broussard the responsibility for choosing,
    and paying, a stevedoring concern.    There is no suggestion in the
    record that Man Sugar retained any control over Broussard’s
    selection of stevedores, or over the price Broussard was to pay
    for actual stevedoring services rendered.    Neither Broussard nor
    Reid approached Man Sugar with the stevedoring bids before LCS
    was selected.    Cf. 
    id. (“[I]t has
    not been shown that a court has
    found an agency relationship between an operator and a stevedore
    in the absence of contractual provisions or clear evidence of
    control and supervision by the operator.”).    In short, the
    11
    For an example of a contractor incurring substantially
    greater costs than initially anticipated when the agreement
    between the contractor and the vessel’s charterers was reached,
    see Cresent City Marine, Inc. v. M/V Nunki, 
    20 F.3d 665
    (5th Cir.
    1994). In that case, the contractor was paid $27,644.64 by the
    charterer, but was billed for $80,768.66 by the subcontractors.
    
    Id. at 667.
    15
    district court did not err in concluding that Broussard was not
    the Vessel’s agent.
    LCS also argues that Broussard had apparent authority to
    procure stevedoring services.   Because LCS testified that it did
    not know the identity of the company to which Broussard was
    supplying rice, but did know that a company separate from
    Broussard was involved in the transaction, Broussard’s purported
    principal was partially disclosed.     A partially disclosed
    principal may be liable if its actions before LCS led LCS
    reasonably to believe that Broussard was acting as its agent.
    See Cactus 
    Pipe, 756 F.2d at 1111
    (“Apparent authority is created
    as to a third person by conduct of the principal which,
    reasonably interpreted, causes the third person to believe that
    the principal consents to the act done on his behalf by the
    person purporting to act for him.”); Restatement (Second) of
    Agency, § 159 cmt. e (1958) (“There may be apparent authority in
    the case of a partially disclosed principal.     This is created
    where, by means of a document or other thing, the principal
    manifests that the agent is to act for whoever made the
    manifestation.”); Restatement (Second) of Agency § 8 cmt. c
    (“Apparent authority exists only to the extent that it is
    reasonable for the third person dealing with the agent to believe
    that the agent is authorized.”).     We must therefore assess
    whether the owner, Marine Trading, Sugar Chartering, or Man Sugar
    undertook actions that caused LCS reasonably to believe that
    Broussard was its agent.
    The record shows limited contact between LCS and the
    16
    Vessel’s owner or charterers.   LCS testified it did not know who
    owned the rice when it was loaded, and that no one told LCS that
    Broussard had the authority to commit another entity to the
    payment of stevedoring services.     LCS sent invoices only to
    Broussard, and did not pursue alternate means of payment until
    after it learned Broussard went into receivership.     The parties
    stipulated that prior to commencement of stevedoring services,
    the master provided instructions to LCS as to how the stevedoring
    was to be performed.   The record contains a May 1 document signed
    by the Captain of the Vessel regarding the shoes the stevedores
    were to wear, their use of metal hooks, and what was to be done
    with damaged bags of rice.   The crew opened and closed the
    Vessel’s hatches for the stevedores.     The mate or the master of
    the ship signed LCS’ Activity Sheets and the Mate’s Receipt.     An
    agent of Marine Trading signed the bill of lading.     Based on this
    evidence, the district court’s finding that LCS had no reason to
    believe, and did not in fact believe that Broussard was acting on
    the Vessel owner’s order when it retained LCS to load the rice
    was not clearly erroneous.
    An important feature of the instant case is the absence of a
    contract between Man Sugar (or Sugar Chartering) and LCS.     This
    is not an unusual set of circumstances facing a supplier of
    necessaries.   There are two lines of cases that deal with such
    circumstances: the general contractor/subcontractor line, see,
    e.g., Galehead, Inc. v. M/V Anglia, 
    183 F.3d 1242
    (11th Cir.
    1999); Cresent City Marine, Inc. v. M/V Nunki, 
    20 F.3d 665
    (5th
    Cir. 1994); Port of Portland v. M/V Paralla, 
    892 F.2d 825
    (9th
    17
    Cir. 1989), Integral Control Sys. Corp. v. Consolidated Edison
    Co., 
    990 F. Supp. 295
    (S.D.N.Y. 1998); South Carolina State Ports
    Auth. v. M/V Tyson Lykes, 
    837 F. Supp. 1357
    (D.S.C. 1993), aff’d,
    
    67 F.3d 59
    (4th Cir. 1995), and the principal/agent, or middle-
    man, line of cases, see Marine Fuel Supply & Towing, Inc. v. M/V
    Ken Lucky, 
    869 F.2d 473
    (9th Cir. 1989); Tramp Oil & Marine, Ltd.
    v. M/V “Mermaid I”, 
    805 F.2d 42
    (1st Cir. 1986); Belcher Co. v.
    M/V Maratha Mariner, 
    724 F.2d 1161
    (5th Cir. 1984).
    Under the general contractor line, the general contractor
    supplying necessaries on the order of an entity with authority to
    bind the vessel has a maritime lien.   See 
    Galehead, 183 F.3d at 1245
    (holding that contractor had lien and could recover for
    services performed by subcontractors); Gulf Oil 
    Trading, 757 F.2d at 750-51
    (finding general contractor who hired subcontractor to
    supply barge service had lien prior to having actual notice of a
    no-lien clause); Ceres Marine Terminals, Inc. v. M/V Harmen
    Oldendorff, 
    913 F. Supp. 919
    , 923 (D. Md. 1995) (holding that
    contractor had lien and could recover amounts attributable to
    services actually performed by subcontractors).   However,
    subcontractors hired by those general contractors are generally
    not entitled to assert a lien on their own behalf, unless it can
    be shown that an entity authorized to bind the ship controlled
    the selection of the subcontractor and/or its performance.     See,
    e.g., South Carolina State Ports 
    Auth., 67 F.3d at 61
    ; Port of
    
    Portland, 892 F.2d at 828
    ; Farwest Steel Corp. v. Barge Sea-Span
    241, 
    828 F.2d 522
    , 526 (9th Cir. 1987).   But see Skandinaviska-
    Enskilda Banken v. C.L.C. Marine Servs., Ltd. (In re SeaEscape
    18
    Cruises, Ltd.), 
    172 B.R. 1002
    , 1008 (S.D. Fla. 1994) (finding
    subcontractor had a lien without analyzing authority of
    contractor); Riedel Envtl. Servs., Inc. v. M/V Tula, 
    1987 A.M.C. 2378
    (S.D. Ala. 1987) (holding plaintiff, a subcontractor, had
    made out a prima facie case showing it was entitled to a lien in
    part because contractor was impliedly authorized to use
    subcontractors).   Under the middle-man line of cases, despite
    what can be a large number of intermediaries, the ultimate
    supplier of the necessaries may obtain a maritime lien under
    certain circumstances.    See, e.g., Marine Fuel 
    Supply, 869 F.2d at 477
    .
    LCS argues strenuously that LCS, not Broussard, is a general
    contractor, and that Broussard is a middle-man.   The sales
    contract between Man Sugar and Broussard merely allocated to
    Broussard the responsibility for identifying and paying the
    stevedores.   The primary distinguishing characteristic between a
    general contractor and a middle-man that LCS identifies is that a
    general contractor can be expected to supply the necessary
    itself, whereas a middle-man is not expected to do so.    According
    to LCS, because Broussard, as a rice mill, could not be expected
    to supply stevedoring services itself, it was a middle-man and
    not entitled to a lien.   Instead, LCS, as the actual supplier of
    the necessaries, has the lien.
    A review of the so-called middle-man cases does not reveal,
    contrary to what LCS suggests, that the actual deliverer of
    necessaries to the vessel is the entity entitled to a lien in
    every instance.    For example, the court in Exxon Corp. v. Central
    19
    Gulf Lines, Inc., 
    780 F. Supp. 191
    (S.D.N.Y. 1991), taking note
    of the Supreme Court’s view of the circumstances of the case, see
    Exxon Corp. v. Central Gulf Lines, Inc., 
    500 U.S. 603
    , 612-13
    (1991), held that the party contractually obligated to supply the
    fuel (Exxon) was entitled to a lien, despite the fact that it had
    caused another supplier to actually deliver the ordered fuel to
    the vessel.   
    See 780 F. Supp. at 194
    .
    A similar result was obtained in A/S Dan-Bunkering Ltd. v.
    M/V Zamet, 
    945 F. Supp. 1576
    (S.D. Ga. 1996).   Dan-Bunkering,
    which had a contract with the charterer to supply the
    necessaries, contacted a broker, which in turn caused two other
    independent firms to deliver the necessaries to the vessel.   The
    court found that Dan-Bunkering was entitled to a lien.    
    Id. at 1579.
      Moreover, although the parties viewed the two firms
    actually delivering the necessaries as entitled to the lien, the
    court thought it “conceivable” that this was not the case, citing
    Bonanni Ship Supply, Inc. v. United States, 
    959 F.2d 1558
    , 1565
    (11th Cir. 1992), a “general contractor” case, in support.    
    Id. Under general
    contractor cases, the actual deliverer of
    necessaries often is not entitled to a lien.    See, e.g.,
    
    Galehead, 183 F.3d at 1245
    (“[A]lthough Polygon did not
    physically supply the bunkers, a party need not be the physical
    supplier or deliverer to have ‘provided’ necessaries under the
    statute.”).
    In two of the cases LCS cites in support of its middle-man
    argument, the court suggested that the actual deliverers of the
    necessaries would be entitled to liens.   See Tramp Oil & Marine,
    
    20 805 F.2d at 44
    (“No one disputes that Exxon and Colonial, as
    direct suppliers to the Mermaid, would be entitled to a maritime
    lien.”); 
    Belcher, 724 F.2d at 1163
    (“Thus, when Belcher supplied
    fuel to the [vessel], a maritime lien may have arisen by
    operation of law . . . .”); 
    id. at 1164
    (“If American law had
    been applicable when the vessel was attached in the Netherlands,
    the supplier of fuel would have had a lien on the vessel . . .
    .”).    However, it was not necessary for these courts to consider
    whether Exxon, Colonial, or Belcher had a maritime lien under
    U.S. law, and thus we need not consider ourselves bound by these
    statements.    Cf. Cresent City 
    Marine, 20 F.3d at 670
    (noting that
    language from Belcher relied on by party was dicta).
    In the final case cited by LCS, Marine Fuel Supply & Towing,
    Inc. v. M/V Ken Lucky, 
    869 F.2d 473
    (9th Cir. 1989), a
    subcharterer’s managing agent, acting on the subcharterer’s
    orders and instructions, contacted a firm it was authorized to
    order fuel through,, which in turn instructed another firm to
    place the order for the vessel’s supplies with Marine Fuel.
    Marine Fuel was subsequently notified that it had been nominated
    by the vessel’s owner to supply the vessel.     It was also notified
    of the identity of the vessel’s husbanding agent, which arranged
    for delivery of the necessaries.      Marine Fuel supplied the fuel,
    which the master of the vessel accepted.     The court found that
    the order originated from the subcharterer, who had authority to
    bind the vessel, and that, under the circumstances, Marine Fuel
    was entitled to a lien.    With the exception of the master’s
    acceptance of the necessaries, LCS can point to no similar
    21
    circumstances here.
    We are persuaded by our review of these cases that it is not
    whether an intermediary can be expected to supply the necessaries
    itself that distinguishes instances in which the actual suppliers
    have liens, but it is rather the nature of the relationship
    between each pair of entities that are involved in the
    transaction at issue (e.g., agent vs. independent contractor).
    We view the facts of the instant case as more akin to those in
    which general contractors have been engaged to supply a service
    and have called upon other firms to assist them in meeting their
    contractual obligations.   Had Broussard not delivered the rice in
    accordance with the sales contract’s terms, it would have been
    liable for breach.    As noted above, Man Sugar retained no control
    over the selection of a stevedoring concern, and Broussard
    accepted all the risk associated with the occurrence of events
    that would increase the costs of stevedoring services beyond what
    the sales contract provided.    Simply put, Broussard was obligated
    to provide for the delivery of rice onto the Vessel, but was not
    authorized to act on behalf of Man Sugar in procuring stevedoring
    services.
    Whether a contractor could be expected to hire
    subcontractors has been considered in assessing whether the
    subcontractors have liens.     See 
    Galehead, 183 F.3d at 1246
    (noting that contractor was seemingly capable of performing under
    its agreement without resort to subcontractors); Stevens
    Technical Services, Inc. v. United States, 
    913 F.2d 1521
    , 1534
    (11th Cir. 1990) (noting that the owner knew contractor was
    22
    incapable of doing the work itself).   However, decisions have
    generally not suggested that such an expectation is sufficient to
    grant the requisite authority.   The Stevens court, for example,
    also noted that the contract with the general contractor listed
    the subcontractor, the general contractor refused to take
    responsibility for subcontractor’s work, and that the vessel’s
    operators dealt with subcontractor representatives in discussing,
    testing, and inspecting the subcontractor’s work.   See 
    id. at 1534-35.
      Other courts have seemingly ignored evidence suggesting
    that the vessel’s owners or charterers were aware that a
    subcontractor would be used, see, e.g., Cresent City 
    Marine, 20 F.3d at 668
    , and even that a particular subcontractor would most
    likely be used.   See, e.g., South Carolina State Ports 
    Auth., 67 F.3d at 60
    (noting that the subcontractor was the only entity
    that possessed the equipment necessary to perform the work); Port
    of 
    Portland, 892 F.2d at 828
    (“The most the Port has shown is the
    fact that it was most likely, even perhaps rather certain, that
    Northwest would choose the facilities of the Port when it did its
    work.”).
    In keeping with the notion that subcontractors may acquire
    liens where the vessel’s owners retain control over their
    selection and/or performance,12 the Ninth and Second Circuits
    12
    The connection to principal/agent concepts is clear.
    This has been the connection for some time. See The Juniata, 
    277 F. 438
    , 440 (D. Md. 1922) (“The cases in which a so-called
    subcontractor has been held entitled to a lien or a right in the
    nature of a lien against the ship appear all to have been cases
    in which, upon the facts, it was possible reasonably to hold that
    he was not a subcontractor at all, but had an agreement with the
    owner, made through the contractor as the owner’s agent . . .
    23
    require that an entity with authority to bind the vessel direct
    that the general contractor hire a particular subcontractor in
    order for that subcontractor to be entitled to a lien.       See Port
    of 
    Portland, 892 F.2d at 828
    ; 
    Farwest, 828 F.2d at 526
    ; Integral
    Control 
    Sys., 990 F. Supp. at 301
    .     In other cases in which
    subcontractors have been found to be entitled to a lien, those
    subcontractors were identified and accepted by the vessel’s owner
    or charterer prior to performance.     See 
    Stevens, 913 F.2d at 1525
    , 1534; Turecamo of Savannah, Inc. v. United States, 824 F.
    Supp. 1069, 1072 (S.D. Ga. 1993).     Owner involvement in
    directing, testing, and/or inspecting subcontractor performance
    has also been cited in support of finding a lien in favor of a
    subcontractor.    See 
    Stevens, 913 F.2d at 1535
    ; cf. Marine
    
    Coatings, 932 F.2d at 1375
    n.9 (listing operator’s inspecting
    subcontractor work and giving provisional and final acceptance to
    work performed by the subcontractor among evidence that supported
    court’s conclusion that a genuine issue of fact existed regarding
    general contractor’s authority to bind the vessel).     Based on
    these cases, we agree with the district court that LCS has not
    shown it was entitled to a lien under the circumstances presented
    here.
    It is possible that § 31341 allows entities other than those
    listed to be proved to have authority to order necessaries on
    behalf of the vessel.    See Marine 
    Coatings, 932 F.2d at 1376
    .
    However, our respect for the principle of stricti juris prevents
    .”).
    24
    us from holding that a supplier of rice that is party to an
    F.O.B. vessel contract has been given the authority, by virtue of
    that contract, to employ the stevedores on the Vessel’s account.
    Cf.   Atlantic & Gulf 
    Stevedores, 608 F.2d at 200-01
    (“[M]aritime
    liens are to be strictly construed, i.e., they are not to be
    lightly extended by construction, analogy, or inference . . .
    .”); Integral Control 
    Sys., 990 F. Supp. at 301
    (assessing
    whether the Eleventh Circuit’s approach in
    contractor/subcontractor cases should be adopted, and deciding
    against doing so given the Second Circuit’s commitment to a
    stricti juris approach to maritime liens).
    B. Ratification
    LCS argues that the actions on the part of the master of the
    Vessel operated to ratify its providing stevedoring services and
    thereby to bind the Vessel.   A large portion of its ratification
    argument rests on the absence of any objection on the part of the
    Vessel’s agents to LCS boarding the Vessel, and on its contention
    that the Vessel’s awareness that LCS was supplying the
    necessaries is sufficient under the MCILA to constitute
    authorization.   The evidence that LCS looks to as supporting its
    ratification arguments includes:     LCS was provided instructions
    prior to loading the Vessel; the Vessel’s hatches were opened and
    closed for the stevedores by the crew; the mate or the master of
    the ship signed LCS’ Activity Sheets and the Mate’s Receipt; the
    stevedores were allowed on board without objection; and they used
    the Vessel’s gear; and the crew, not Broussard, supervised the
    25
    loading operation.
    Much of this evidence reduces to a showing that the master
    of the Vessel allowed LCS on board to perform stevedoring
    services and accepted those services.   Under the contract between
    Man Sugar and Broussard, Broussard was obligated to deliver the
    rice free-on-board the Vessel.   Had the Vessel’s agents not
    allowed the stevedores to load the rice, they would have
    prevented Broussard from fulfilling its contractual obligations.
    Under these circumstances, we are hesitant to declare that the
    Vessel’s agents subjected the res to liability for stevedoring
    services necessary to enable Broussard to deliver the rice as per
    its agreement with Man Sugar.
    As the district court noted, awareness on the part of the
    Vessel’s agents that LCS was apparently the firm chosen by
    Broussard to load the rice is insufficient under the MCILA to
    constitute authorization.   See 
    Galehead, 183 F.3d at 1246
    (“That
    a charterer of a vessel becomes aware that some work performed
    was by a party somewhere down the chain of contracting and re-
    contracting does not give rise to a maritime lien.”); Port of
    
    Portland, 892 F.2d at 828
    (“It cannot be denied that [the
    vessel’s owner] knew that [the general contractor] was using the
    Port’s facilities, but that has never been held to be sufficient
    to establish a lien.”).   A holding that awareness that
    necessaries are being supplied was sufficient, even though those
    necessaries were procured by an entity without authority to bind
    the vessel, would render the statute’s authority requirement
    meaningless.
    26
    We must also reject LCS’ contention that acceptance of LCS’
    services and the rice aboard ship provided the necessary
    authorization to entitle it to a lien.      It is a settled principle
    of contract law that a contract requiring A to supply X to C is
    satisfied if B, hired by A, provides X to C.      See 
    Galehead, 183 F.3d at 1245
    (citing Restatement (Second) of Contracts § 318 cmt.
    a, illus. 2, in support of its holding that a contractor provided
    necessaries to a vessel when the contractor’s subcontractor
    delivered fuel to the vessel).    Under the circumstances here, the
    delivery of the rice, though performed by LCS, is attributed to
    Broussard.   Acceptance of the rice on the part of the Vessel,
    through signing of Activity Sheets and the Mate’s Receipt, was
    therefore acceptance of Broussard’s rice and Broussard’s delivery
    of that rice.   See 
    Galehead, 183 F.3d at 1245
    ; Ceres Marine
    
    Terminals, 913 F. Supp. at 923
    .    As a result, we do not view the
    activities on the part of the Vessel’s master and crew to
    constitute ratification.
    The cases LCS cites in support of its ratification argument
    are distinguishable.   In Yacht, Mary Jane v. Broward Marine,
    Inc., 
    313 F.2d 516
    (5th Cir. 1963), the “real” captain did not
    object while work ordered by the “nominal” captain was going on.
    The nominal captain had no actual authority to place orders.       We
    affirmed the lower court’s conclusion that this supported a
    finding of implied authorization.      Had the case been brought
    under the Federal Maritime Lien Act, the nominal captain would no
    doubt have been viewed as clothed with presumed authority to bind
    the vessel, having been named the “master” and appointed by the
    27
    owner of the vessel.   Cf. Port of 
    Portland, 892 F.2d at 827
    (citing Yacht, Mary Jane as an example of courts finding implied
    authority in individuals listed in § 972).   The Jan C. Uiterwyk
    court found that the vessel’s charterer and master approved of
    the use of JCU, a firm providing agency and terminal services,
    authorized JCU firm to sign bills of lading on behalf of the
    master and/or owner, and ordered services directly from JCU.   LCS
    can point to no similar actions on the part of the charterers,
    the master, or the crew here.13
    Because we find that the district court was correct in
    holding LCS was not entitled to a maritime lien, we need not
    consider the waiver issue.
    IV.   CONCLUSION
    For the foregoing reasons, we AFFIRM the district court’s
    dismissal of LCS’ in rem action against the Vessel.
    13
    Although a stevedoring concern was also a plaintiff in
    this case, it may be argued that the finding that JCU was
    accepted as ship’s agent was crucial to the stevedores being
    entitled to a lien. JCU had either supplied, or procured, all of
    the services at issue in the case. See Jan C. Uiterwyk, 459 F.
    Supp. at 1327.
    28
    

Document Info

Docket Number: 98-30983

Filed Date: 1/24/2000

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (34)

Jan C. Uiterwyk Co., Inc. v. MV Mare Arabico , 459 F. Supp. 1325 ( 1978 )

Exxon Corp. v. Central Gulf Lines, Inc. , 111 S. Ct. 2071 ( 1991 )

Integral Control Sys. Corp. v. Consol. Edison Co. of NY, ... , 990 F. Supp. 295 ( 1998 )

South Carolina State Ports Authority v. M/V Tyson Lykes , 837 F. Supp. 1357 ( 1993 )

A/S Dan-Bunkering Ltd. v. M/V ZAMET , 945 F. Supp. 1576 ( 1996 )

Skandinaviska-Enskilda Banken v. C.L.C. Marine Services, ... , 172 B.R. 1002 ( 1994 )

a-l-veverica-dba-a-l-veverica-salvage-co-v-drill-barge-buccaneer , 488 F.2d 880 ( 1974 )

Marine Fuel Supply & Towing, Inc., a Foreign Corporation v. ... , 869 F.2d 473 ( 1989 )

gulf-oil-trading-company-a-division-of-gulf-oil-co-cross-appellant-v , 757 F.2d 743 ( 1985 )

Yacht, Mary Jane, Her Engines, Tackle, Apparel, Furniture ... , 313 F.2d 516 ( 1963 )

south-carolina-state-ports-authority-v-mv-tyson-lykes-ex-delaware-bay , 67 F.3d 59 ( 1995 )

cactus-pipe-supply-co-inc-cross-appellee-v-mv-montmartre-her , 756 F.2d 1103 ( 1985 )

The Belcher Company of Alabama, Inc. v. M/v Maratha Mariner,... , 724 F.2d 1161 ( 1984 )

Piedmont & Georges Creek Coal Co. v. Seaboard Fisheries Co. , 41 S. Ct. 1 ( 1920 )

Galehead, Inc., an Oregon Corporation, Cross-Appellee v. M/... , 183 F.3d 1242 ( 1999 )

Dampskibsselskabet Dannebrog v. Signal Oil & Gas Co. of Cal. , 60 S. Ct. 937 ( 1940 )

farwest-steel-corporation-and-shuman-equipment-inc , 828 F.2d 522 ( 1987 )

the-port-of-portland-an-oregon-municipal-corporation-and-the-connecticut , 892 F.2d 825 ( 1989 )

esso-international-inc-plaintiff-appellee-cross-v-the-ss-captain-john , 443 F.2d 1144 ( 1971 )

bonanni-ship-supply-inc-v-united-states-of-america-as-owner-of-usns , 959 F.2d 1558 ( 1992 )

View All Authorities »