Indiana Michigan Power Co. v. United States Department of Labor , 278 F. App'x 597 ( 2008 )


Menu:
  •                 NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
    File Name: 08a0282n.06
    Filed: May 20, 2008
    Nos. 06-4426, 07-3928
    UNITED STATES COURT OF APPEALS
    FOR THE SIXTH CIRCUIT
    INDIANA MICHIGAN POWER COMPANY,                        )
    )
    Petitioner-Appellant,                           )
    )
    V.                                                     )    ON APPEAL FROM THE UNITED
    )    STATES DEPARTMENT OF
    UNITED STATES DEPARTMENT OF LABOR,                     )    LABOR ADMINISTRATIVE
    )    REVIEW BOARD
    Respondent-Appellee,                            )
    )
    V.                                                     )
    )    OPINION
    KENNETH TIPTON,                                        )
    )
    Petitioner-Intervenor-Appellant.                )
    BEFORE:        COLE and GRIFFIN, Circuit Judges; FORESTER, Senior District Judge.*
    FORESTER, Senior District Judge.
    Petitioner Indiana & Michigan Power Company (“I&M”) appeals the order of the
    Administrative Review Board (“ARB”) for the United States Department of Labor (“DOL”) granting
    the complaint of its former employee, Kenneth Tipton, and awarding back pay, front pay and
    compensatory damages. Tipton’s complaint alleged that I&M retaliated against him for engaging
    in protected activity in violation of the whistle-blower provision of the Energy Reorganization Act,
    *
    The Honorable Karl S. Forester, Senior United States District Judge for the
    Eastern District of Kentucky, sitting by designation.
    1
    (“ERA”), 42 U.S.C. § 5851, and its implementing regulations at 29 C.F.R. § 24.
    Petitioner-Intervenor Tipton has filed a separate appeal with respect to the amount of front
    pay awarded to him by the ARB. These two appeals have been consolidated by this Court. Because
    we conclude that the DOL did not err in finding that Tipton’s employment was terminated in
    violation of the ERA or in awarding and calculating damages to Tipton, we affirm the judgment of
    the DOL.
    I.
    Tipton was employed by I&M as a test engineer at the Cook Nuclear Power Plant (the “Cook
    plant”) in Bridgman, Michigan from November 1999 until I&M terminated his employment on
    October 2, 2001. The events leading up to Tipton’s termination began in late August 2001, when
    an unplanned forced outage shut down both nuclear reactor units at the Cook plant. The outage was
    the result of a significant amount of silt from Lake Michigan entering the plant’s Essential Service
    Water (“ESW”) system to the extent that the nuclear reactors could not operate safely.
    Once the silt issue was identified and the ESW was cleaned out and repaired, I&M began the
    required testing of the ESW system. Before the plant could be restarted, the Maintenance Testing
    Group had to complete an ESW Flow Balance Test, which typically only takes one or two days.
    Tipton was the day shift test engineer for the Maintenance Testing Group, operating under the direct
    supervision of Ed Brouwer. Anthony Chacon was the night shift test engineer. Mark Turcotte was
    a contract engineer supporting the test engineers during the ESW flow test.      The Maintenance
    Manager, Mark Stark, was in charge of the overall supervision of test performance. Although the
    flow test began on September 18, 2001, a number of unsuccessful attempts to conduct the flow test
    meant that plant management believed the testing would not be completed until September 25, 2001.
    2
    As a result, plant management made the decision to work around-the-clock in order to expedite the
    plant’s re-start process, and the test engineers were scheduled to work 12-14 hour days.
    In conjunction with its operating license issued by the Nuclear Regulatory Commission
    (“NRC”), the Cook plant is required to comply with the NRC Policy Statement on Nuclear Power
    Plant Staff Working Hours (“Generic Letter 82-12") “to prevent situations where fatigue could
    reduce the ability of operating personnel to keep the reactor in a safe condition. The controls
    established should assure that, to the extent practicable, personnel are not assigned to shift duties
    while in a fatigued condition.” To comply with Generic Letter 82-12, the Cook plant implemented
    a Working Hour Limitation policy which provides that the “amount of overtime worked by staff
    members performing safety-related functions must be limited in accordance with the NRC policy
    contained in Generic Letter 82-12.” Generic Letter 82-12 prohibits, inter alia, personnel from
    working more than 72 hours out of a rolling 7-day time frame without written approval from
    management. Any deviation from these working hour guidelines should be documented in writing
    and available for review by the NRC.
    During the day of September 25, 2001, Tipton and Turcotte discovered a problem related to
    the degree of “play” in two of the ESW valves. At the conclusion of his shift that evening, Tipton
    believed that he had either reached or exceeded the work hour limitations set by the NRC for the
    previous seven-day period. For that reason, and because he believed the ESW testing was completed
    and only paperwork remained to be finalized, Tipton informed Chacon, who was coming on for the
    night shift, that he was going to take the following day off because he was tired and needed to re-set
    his hours in accordance with the work hour limitations.
    During the night shift of September 25, plant management decided to undertake an analysis
    3
    to determine whether permitting a “plus or minus two turns” tolerance to the hand wheel positions
    of the ESW valves would solve the “play” problem without deviating from an acceptable flow rate.
    The analysis was to be prepared as a Design Information Transmittal (“DIT”) by I&M’s engineering
    department to be forwarded to the Maintenance Testing Group for incorporation into the Technical
    Data Book (“TDB”), if justified by the testing. The TDB is a compilation of information used by
    operations personnel that includes current valve settings. Plant managers charged Chacon with the
    responsibility of preparing a draft revision for the TDB incorporating the tolerance in anticipation
    of the DIT, which was due at 11:00 a.m. on September 26.
    On the morning of September 26 at approximately 6:30 a.m., Chacon engaged in a “turnover”
    with Turcotte who was coming in for his morning shift. “Turnover” is the term the Cook plant
    employees used to describe meetings related to the transfer of shift assignments from one shift to the
    next so that the work proceeds with continuity. Typically, Chacon and Tipton conducted turnovers
    “face to face,” followed up by an email to the person to whom the assignment was being transferred.
    At the 6:30 turnover between Chacon and Turcotte, Chacon transferred the responsibility for the
    TDB revisions to Turcotte both orally and in an email to Turcotte and Brouwer. Tipton, who was
    not present at the turnover, did not receive this email.
    At approximately 7:00 a.m. on September 26, Tipton received a phone call at his home from
    Brouwer. Turcotte and Chacon were also on the line. Brouwer informed Tipton that he needed to
    come in to work for a meeting. Tipton requested that Brouwer first verify that he was being required
    to come in by management since he had exceeded the work hour limitations and he requested that
    a work hour deviation be approved by management. Approximately five minutes later, Brouwer
    again called Tipton and confirmed that he needed to come in. Tipton reported to work between 8:00
    4
    and 8:30 a.m.
    Once at work, Tipton again expressed concerns about his excessive hours to Brouwer.
    Shortly before a 9:00 a.m. meeting, Brouwer presented Stark, the Maintenance Manager, with a
    written request for an exemption from the 72-hour work hour limitations, which Stark refused to
    sign. Stark then discouraged Brouwer from presenting the deviation request to Plant Manager Joe
    Polluck. Stark also ignored Tipton’s request during the meeting to sign the approval allowing him
    to work in excess of the 72 hour limit. Instead, Stark assigned Tipton the task of preparing the
    paperwork closing out the ESW testing.
    Turcotte, charged with finishing Chacon’s draft of the TDB, discovered errors needing
    correction. Stark had instructed Turcotte to complete the TDB by noon. Because the DIT, which
    was due at 11:00 a.m., was not ready, Turcotte elected to correct the errors in the Chacon draft, have
    the data reviewed by Tipton and approved by Brouwer, and then he intended to incorporate the DIT
    into his draft upon receiving it. As requested, Tipton reviewed the data in Chacon’s draft for
    transposition errors, completed his own assignment, and ultimately left the plant at approximately
    4:30 p.m. Prior to leaving, Tipton sent an email to Stark again requesting a copy of the authorization
    allowing him to work in excess of 72 hours.
    Because Stark had a noon deadline for the TDB, Turcotte decided to submit the TDB
    revisions without the DIT tolerances, as approved by Brouwer, to Stark. Stark, unaware that the
    TDB revisions did not include the DIT, notified management that the tolerances were approved.
    Thereafter, however, Stark learned that the DIT had not yet been issued, and thus notified plant
    management that the TDB revisions did not contain the tolerance data. An investigation ensued to
    determine why the TDB did not incorporate the DIT as originally ordered by management. Tipton
    5
    and Turcotte were suspended and their access to the Cook plant was turned off on September 27,
    2001.
    As a result of the investigation, Stark and Donna Kelly, Human Resources Administrator,
    recommended that Tipton be terminated. I&M terminated Tipton’s employment on October 2, 2001,
    claiming that he failed to follow management’s directive to wait for the DIT before issuing the TDB,
    he lied during the fact-finding investigation, and he had a poor disciplinary history at the plant.
    On January 28, 2002, Tipton filed a Complaint with the United States Department of Labor
    (“DOL”) alleging that I&M violated the ERA by suspending his employment on September 27,
    2001, and then terminating his employment on October 2, 2001, in retaliation for engaging in
    protected conduct. Specifically, Tipton alleged that he had been terminated based on conversations
    and emails on September 26, 2001 wherein he requested a copy of a form he believed had been
    signed and would authorize him to exceed work hour limitation guidelines mandated by the NRC.
    The Occupational Safety and Health Administration investigated Tipton’s complaint and
    issued a recommendation of dismissal on July 11, 2002, which Tipton appealed on July 16, 2002.
    Then, on December 4, 2002, the NRC advised I&M’s parent company that an investigation by its
    Office of Investigations into Tipton’s allegations determined that his complaint was unsubstantiated.
    Tipton then requested a hearing pursuant to 29 C.F.R. § 24.4(d)(3). A formal hearing before
    ALJ Kane was held on July 22-30, 2003. On June 29, 2004, the ALJ issued his Recommended
    Decision and Order (“RD&O”), finding by a preponderance of the evidence that Tipton had engaged
    in protected activity that was more than likely a contributing factor to his suspension and
    termination. Furthermore, the ALJ determined that I&M failed to prove by clear and convincing
    evidence that its proffered reasons for Tipton’s termination were legitimate. In reaching this
    6
    decision, the ALJ noted that circumstantial evidence combined to provide a preponderance of
    evidence weighing in Tipton’s favor. Considering I&M’s proffered reasons for Tipton’s termination,
    the ALJ found these reasons “disingenuous and intentionally polemic.” As a result, the ALJ
    recommended that Tipton be awarded back pay, bonus and pay raise, front pay, attorneys’ fees,
    compensatory damages, the value of lost fringe benefits, and a purging of his personnel file with
    regard to his termination.
    I&M filed a timely petition for review with the ARB. On September 29, 2006, the ARB
    issued a Final Decision & Order (“FD&O”), adopting the findings and holdings of the ALJ’s RD&O
    in all respects, with the exception of reversing the ALJ’s award of $10,744 to cover Tipton’s
    replacement insurance expenses because it constitutes a double recovery. I&M timely filed an appeal
    with this Court on October 30, 2006 after it had filed a motion for reconsideration with the ARB on
    October 10, 2006. This Court placed I&M’s appeal in abeyance on December 26, 2006, pending the
    ARB’s determination on reconsideration. On June 27, 2007, the ARB granted I&M’s motion for
    reconsideration on the issue of damages and reduced Tipton’s award of front pay from $91,038 to
    $64,350 by calculating the front pay award without including any pay raises or applying a discount
    rate. Tipton timely filed an appeal with this Court on the front pay issue on July 23, 2007. These
    appeals were consolidated by the Court on August 6, 2007.
    Because the Secretary of the DOL has delegated authority to the ARB to review the ALJ’s
    decision in cases arising under the ERA, the ARB’s decision is the DOL’s final agency decision.
    29 C.F.R. § 24.110(a). This Court has jurisdiction to review the DOL’s decision pursuant to 42
    U.S.C. § 5851(c)(1).
    II.
    7
    A.     STANDARD OF REVIEW
    The ERA whistleblower provision, 42 U.S.C. § 5851(c), mandates that this Court’s review
    of the final decision of the DOL shall conform to the Administrative Procedures Act (“APA”), 5
    U.S.C. § 706. Pursuant to the APA, this Court may reverse the agency’s findings and conclusions
    if they are found to be “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance
    with law” or “in excess of statutory jurisdiction” or “unsupported by substantial evidence.” 5 U.S.C.
    § 706. Certainly, this is a highly deferential standard of review, and requires this Court to defer to
    the inferences that the DOL derives from the evidence. Varnadore v. Secretary of Labor, 
    141 F.3d 625
    , 630 (6th Cir. 1998). Any factual determinations by the Department of Labor “must be affirmed
    if they are supported by substantial evidence,” which is “more than a scintilla, but less than a
    preponderance, of the evidence.” R.P. Carbone Constr. Co. v. Occupational Safety & Health Rev.
    Comm’n, 
    166 F.3d 815
    , 818 (6th Cir. 1998). Substantial evidence is “such relevant evidence as a
    reasonable mind might accept as adequate to support the conclusion reached.” 
    Id. Moreover, this
    court “will not normally disturb the credibility assessments of the Board or an administrative law
    judge, ‘who has observed the demeanor of the witnesses.’” Litton Microwave Cooking Prods. Div.,
    Litton Sys., Inc. v. NLRB, 
    868 F.2d 854
    , 857 (6th Cir. 1989), citing NLRB v. Baja’s Place, 
    733 F.2d 416
    , 421 (6th Cir. 1984)). Finally, if there is substantial evidence in the record as a whole to support
    the DOL’s conclusions, this Court may not reverse, “even if [the court] could justifiably have made
    a different choice judging the matter de novo.” NLRB v. Brown-Graves Lumber Co., 
    949 F.2d 194
    ,
    196 (6th Cir. 1991).
    B.     THE ENERGY REORGANIZATION ACT
    The ERA prohibits entities licensed by the NRC from retaliating against employees for
    8
    reporting and pursuing nuclear safety concerns. 42 U.S.C. § 5851. The ERA itself sets out the
    burden shifting framework relevant to the analysis of this case. Under the statutory framework, a
    complainant must first make a “prima facie showing” that retaliation for protected activity “was a
    contributing factor in the unfavorable personnel action alleged in the complaint” in order for the
    Secretary to investigate. 42 U.S.C. § 5851(b)(3)(A). If the complainant succeeds in setting forth a
    prima facie case, then the investigation must go forward unless the employer “demonstrates, by clear
    and convincing evidence, that it would have taken the same unfavorable personnel action in the
    absence of such behavior.” 42 U.S.C. § 5851(b)(3)(B). “For employers, this is a tough standard, and
    not by accident. Congress appears to have intended that companies in the nuclear industry face a
    difficult time defending themselves.” Stone & Webster Eng. Corp. v. Herman, 
    115 F.3d 1568
    , 1572
    (11th Cir. 1997).
    C.     TIPTON WAS ENGAGED IN PROTECTED ACTIVITY
    The first issue for review, then, is whether Tipton was engaged in protected activity when
    he raised concerns about his excessive work hours and sought to confirm management’s
    authorization for working those hours. The Court reviews the DOL’s legal decision that the ERA
    protected Tipton’s activity de novo; however, the question of whether Tipton actually engaged in
    such activity is fact-based, and thus governed by the substantial evidence standard.
    To constitute protected activity under the ERA, “an employee’s acts must implicate safety
    definitively and specifically.” American Nuclear Resources., Inc. v. U.S. Department of Labor, 
    134 F.3d 1292
    , 1295 (6th Cir. 1998). I&M argues that Tipton never raised any question about his ability
    to safely perform his job, but rather only complained about I&M’s failure to complete ministerial
    paperwork.
    9
    However, the NRC’s Generic Letter ties excessive work hours to the potential for fatigue,
    which directly impacts the safety of the nuclear reactor. The express purpose of the work hour
    limitations contained in Generic Letter 82-12 is “to prevent situations where fatigue could reduce
    the ability of operating personnel to keep the reactor in a safe condition.” Generic Letter 82-12
    specifically provides that normally operating personnel should work an 8-hour day and a 40-hour
    week while the plant is operating. It permits overtime only when “unforeseen problems require
    substantial amounts of overtime to be used, or during extended periods of shutdown for refueling,
    major maintenance or major plant modifications, on a temporary basis. . . .” Any deviation from the
    work hour limitations should be permitted only for “very unusual circumstances,” and any “deviation
    shall be authorized by the plant manager or his deputy, or higher levels of management.” Deviations
    must then be documented and available for NRC review to enable the NRC to monitor whether
    plants are abusing the work hour limitations.
    The burden of addressing fitness for duty at nuclear plants rests on the NRC licensees, not
    the employees. See 10 C.F.R. § 26. Moreover, the Generic Letter 82-12 places the burden of
    compliance on the plant, not the employee, by stating that “[a]n individual should not be permitted
    to work more . . . than 72 hours in any seven day period. . . .” Because the work hour limitations are
    in place specifically to prevent fatigued workers from impacting the safety of the nuclear reactor, an
    employee’s complaints that his work hours exceed the work hour limitations and his requests for the
    written authorization for deviation from the work hour limitations certainly impact nuclear safety
    and thus constitute activity protected by the ERA.
    In this case, Tipton notified Brouwer over the telephone on the morning of September 26 that
    he was over his work hours; nevertheless, Brouwer indicated to Tipton that he was required to report
    10
    to work that day. Tipton reasonably assumed that the appropriate authorization for deviation from
    the work hour limitations would be completed by plant management. Once at the plant, Tipton again
    expressed concern about his hours to Brouwer, who passed these concerns along to Stark. Although
    Stark’s hearing testimony and deposition testimony were inconsistent as to when he learned that
    Tipton was over on his hours, the ALJ concluded that Stark was aware that Tipton had exceeded
    the work hour limitations at the 9:00 a.m. meeting.       Nevertheless, Stark refused to sign the
    authorization presented to him by Brouwer, and discouraged Brouwer from pursuing the issue up
    the chain of command. Stark was, however, aware that Tipton had been assigned additional job
    duties on that day. Tipton again complained to Stark and other management at the plant before
    leaving late in the day on September 26 that he had worked excessive hours and that a written
    authorization was required. Based on Tipton’s repeated efforts to notify plant management that he
    was over his hours and his multiple requests to obtain written authorization for exceeding the work
    hours limitations, substantial evidence supports the DOL’s conclusion that Tipton was engaged in
    protected activity.
    D.     TIPTON’S PARTICIPATION IN ACTIVITY PROTECTED BY THE ERA
    WAS A CONTRIBUTING FACTOR IN I&M’S TERMINATION OF HIS
    EMPLOYMENT
    Once Tipton establishes that he was engaged in protected activity, he must also prove that
    I&M knew he engaged in protected activity, and that the protected activity was a contributing factor
    to the “unfavorable personnel action.” 42 U.S.C. § 5851(b)(3)(C); Bartlik v. U.S. Department of
    Labor, 
    73 F.3d 100
    , 103, n.6. (6th Cir. 1996). There is no dispute that I&M was aware of Tipton’s
    expressed concerns relating to exceeding the work hour limitations or that Tipton’s suspension and
    termination amounted to an “unfavorable personnel action.” While there is no direct evidence of
    11
    retaliatory intent on behalf of I&M, the DOL may rely on circumstantial evidence to infer improper
    motive. Blalock v. Metals Trades, Inc., 
    775 F.2d 703
    , 707 (6th Cir. 1985).
    A review of the record reveals substantial circumstantial evidence to support a finding that
    I&M was motivated in part by Tipton’s protected activity to suspend and terminate his employment.
    First, the ALJ relied on I&M’s hostility for the NRC work hour limitations as revealed by
    management’s economic decision to work until the ESW Flow Balance Test was complete in order
    to restart the plant as soon as possible without regard to the excessive hours worked by the test
    engineers. Stark’s refusal to sign the work hours deviation form and the fact that he discouraged
    Brouwer from pursuing the issue up the chain of command further reveals this hostility, as does the
    fact that I&M falsified a Condition Report filed on September 28, 2001, indicating that Tipton had
    been sent home early on September 25, 2001 in an effort to feign compliance with the work hour
    limitations when in fact he was at work on September 25 and 26, 2001.
    Second, the ALJ relied on the mindset of the Cook plant management, notably the pressure
    to get the plant running as expeditiously as possible notwithstanding the work hour limitations, as
    further circumstantial evidence of retaliatory intent. Third, the ALJ inferred a retaliatory intent on
    the part of I&M based on the fact that Tipton’s suspension and termination so closely followed his
    protected activity.
    Fourth, the ALJ inferred circumstantial evidence of discriminatory intent based on his
    determination that I&M’s proffered reasons for Tipton’s termination were false. Although I&M
    asserts that it fired Tipton for lying during the fact finding investigation and for his past performance
    problems, the ALJ considered the testimony of Turcotte, Brouwer, and Chacon and determined that
    there was no evidence that Tipton lied during the investigation or failed to adhere to the direction
    12
    of management with regard to the TDB. Moreover, the ALJ found that although Tipton has received
    four written warnings, two suspensions, and a substandard performance appraisal during his twenty-
    three month employment at I&M, there was no evidence that he exhibited any unfavorable conduct
    that would warrant his termination during the period since his last unfavorable action. Thus, the ALJ
    determined that I&M failed to establish by clear and convincing evidence that Tipton’s past
    performance problems led to the decision to terminate him in spite of his protected activities. Based
    on I&M’s contrived reasons for terminating Tipton, the ALJ determined that this circumstantial
    evidence supports an inference of discriminatory intent.
    Fifth, the ALJ considered the disparate treatment afforded Turcotte, Brouwer, Chacon and
    Tipton regarding the events of September 26, 2001. Specifically, the ALJ determined that although
    Turcotte engaged in the same alleged instances of misconduct as Tipton, Tucotte was not disciplined.
    Also, even though Brouwer played a larger role in regard to the TBD than Tipton, Brouwer was not
    suspended during the fact finding investigation. Nor was Chacon disciplined, sanctioned, or even
    suspended despite the fact that his TDB draft contained errors and resulted in the delay. Instead,
    from the beginning of the fact finding investigation, the ALJ found that the investigation centered
    only on Tipton despite the fact that the TDB listed Turcotte as the initiator and Brouwer as the
    approver. Lastly, in inferring discriminatory intent on the part of I&M, the ALJ considered the fact
    that I&M failed to follow its own progressive disciplinary policy as indicative of an unlawful motive.
    The ARB concurred with the ALJ’s conclusion that I&M violated the ERA by suspending
    and terminating Tipton, relying specifically on the fact that I&M’s adverse action closely followed
    Tipton’s protected activity and the fact that I&M’s proffered reasons for firing Tipton were
    unsubstantiated. Thus, the ARB concluded that Tipton’s protected activity was a contributing factor
    13
    to the unfavorable personnel action, and that I&M failed to show by clear and convincing evidence
    that it would have taken the same unfavorable personnel action in the absence of such protected
    activity. The record certainly contains more than substantial evidence to support the DOL’s finding
    that I&M violated the whistleblower provisions of the ERA by suspending and terminating Tipton.
    E.     THE DOL DID NOT ERR IN DECLINING TO MITIGATE I&M’S
    DAMAGES BASED ON THE ASSERTION THAT TIPTON’S
    EMPLOYMENT WOULD HAVE BEEN TERMINATED BASED UPON THE
    DISCOVERY OF “AFTER-ACQUIRED” EVIDENCE
    In an effort to mitigate its damages, I&M argues that Tipton would have been terminated in
    March 2002 after discovery of personal or objectionable e-mails in his mailbox. Based on the United
    States Supreme Court’s ruling in McKennon v. Nashville Banner Publishing Co., 
    513 U.S. 352
    (1995), this post hoc evidence of alternative grounds for termination is irrelevant to the
    determination of whether I&M legitimately terminated Tipton; however, it may be relevant to the
    issue of damages. The burden is on I&M to “establish that the wrongdoing was of such severity that
    the employee in fact would have been terminated on those grounds alone if the employer had know
    of it at the time of the discharge.” 
    Id. at 362-63.
    In light of the fact that the evidence revealed that other employees at the Cook plant received
    and/or forwarded the same or similar e-mails, yet were not sanctioned or disciplined, I&M’s
    assertion is tantamount to an acknowledgment that Tipton would have been treated differently than
    other employees. Thus, I&M cannot establish that it would have terminated Tipton’s employment
    upon the discovery of the prohibited emails. Consequently, substantial evidence supports the DOL’s
    refusal to use this alleged post hoc evidence to mitigate I&M’s damages.
    F.     THE DOL ACTED WITHIN ITS DISCRETION WHEN IT USED THE
    “TOTAL OFFSET” METHOD TO CALCULATE THE AMOUNT OF FRONT
    14
    PAY DUE TO TIPTON
    In his RD & O, the ALJ initially awarded Tipton front pay in the amount of $81,967 plus the
    3% [projected salary] increase “in accordance with Complainant’s Exhibit 15" outlining his
    damages. However, Tipton’s Exhibit 15 calculates front pay to be $91,038, based on a projected 3%
    increase in salary for a period of 2 years. Thereafter, on July 2, 2004, the ALJ issued an Erratum and
    Recommended Order (“E&RO”), effective immediately, which awarded front pay to Tipton in the
    amount of $91,038, consistent with Tipton’s Exhibit 15.
    On September 29, 2006, the ARB issued its FD& O affirming all of the ALJ’s RD&O and
    E&RO, with the exception of the replacement insurance expenses which the ARB determined
    amounted to a double recovery. I&M subsequently filed a motion for reconsideration, arguing that
    the ARB should have discounted the ALJ’s front pay award to present value. On reconsideration,
    however, the ARB noted that “neither party offered any evidence or testimony before the ALJ in
    support of an appropriate discount rate to be applied in this case. I&M never raised the issue of
    discounting the front pay award before the ALJ, and Tipton only alluded to it in his post-hearing
    brief.” Furthermore, with respect to the parties’ briefs to the ARB, the ARB noted that “the parties
    have offered the Board very little guidance for calculating an appropriate front pay award.”
    As a result, the ARB adopted the total offset approach, whereby courts refrain from
    calculating future salary increases into the front pay award, thereby obviating the need to discount
    the award to present value. See Beaulieu v. Elliott, 
    434 P.2d 665
    , 673 (Alaska 1967). The Sixth
    Circuit affirmed the use of the total offset approach in Jackson v. City of Cookeville, 
    31 F.3d 1354
    ,
    1361 (6th Cir. 1994), where “the rule resulted in a reasonable damage calculation.”
    Applying the total offset approach in this matter, the ARB multiplied Tipton’s I&M salary
    15
    of $95,000, before the addition of annual increases and bonuses, by three to yield a three year
    projected salary of $285,000. Then the ARB added fringe benefits of $94,050 (33% of salary) and
    bonus pay of $28,500 (10% of base pay), to determine that Tipton’s total earnings at I&M would
    have been $407,550. The ARB then applied the total offset approach to Tipton’s earnings at his
    subsequent employment for three years, resulting in total earnings of $343,200. The difference in
    what Tipton would have earned at the Cook plant ($407,550) and what Tipton actually earned
    ($343,200) - $64,350 - equals the amount of front pay the ARB awarded to Tipton.
    This Court reviews the DOL’s calculation of damages under the abuse of discretion standard.
    Killian v. Yorozu Automotive Tennessee, Inc., 
    454 F.3d 549
    , 557 (6th Cir. 2006); United States v. City
    of Warren, Mich., 
    138 F.3d 1083
    , 1097 (6th Cir. 1998). While the Sixth Circuit has not mandated
    application of the total offset approach with respect to front pay, it did find that this approach is
    appropriate when it provides a “reasonable approximation” of front pay. See 
    Jackson, 31 F.3d at 1361
    . In this case, where the parties disagreed over the proper discount rate and provided very little
    guidance to the ALJ and ARB on this issue, the DOL acted within its discretion in applying the total
    offset approach to Tipton’s front pay.
    IV.
    For the reasons set forth above, the decision of the DOL is affirmed.
    16