Alpha Telecommunications, Inc. v. International Business MacHines Corp. ( 2006 )


Menu:
  •                 NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
    File Name: 06a0685n.06
    Filed: September 8, 2006
    No. 05-3974, 05-4022
    UNITED STATES COURT OF APPEALS
    FOR THE SIXTH CIRCUIT
    ALPHA TELECOMMUNICATIONS, INC.,
    Plaintiff-Appellant,
    v.                                                   ON APPEAL FROM THE UNITED
    STATES DISTRICT COURT FOR THE
    INTERNATIONAL BUSINESS MACHINES                      NORTHERN DISTRICT OF OHIO
    CORPORATION,
    Defendant-Appellee.
    /
    BEFORE:        MOORE, CLAY, and GRIFFIN, Circuit Judges.
    CLAY, Circuit Judge. Plaintiff, Alpha Telecommunications, Inc. (“Alpha”), appeals a July
    8, 2005 order of the United States District Court for the Northern District of Ohio, denying
    Plaintiff’s motion for summary judgment on its breach of contract and quantum meruit action and
    granting summary judgment sua sponte in favor of Defendant, International Business Machines
    Corp. (“IBM”). IBM cross-appeals the district court’s order, arguing that the district court abused
    its discretion in denying IBM’s motion for sanctions under Rule 11. For the reasons set forth below,
    we AFFIRM the order of the district court.
    No. 05-3974
    I.
    BACKGROUND
    The dispute in this case arises out of a contract between Alpha and IBM, which both parties
    entered into for the purpose of helping IBM obtain service contracts with schools through the federal
    E-Rate program.
    A.     The E-Rate Program
    In February 1996, Congress enacted the Telecommunication Act of 1996, Pub. L. No.104-
    104, 110 Stat. 56, at revising, among other things, the Universal Service System. E-Rate, Federal
    Communications Commission, http://www.fcc.gov/learnnet, (last visited May 25, 2001). Prior to
    1996, the Universal Service System was a program that set below cost rates for telecommunications
    services in under-serviced rural and residential areas, and offset the reduced rates by setting above
    cost rates for telecommunications services in other areas. 
    Id. The 1996
    amendments expanded the
    types of discounted services available through the program, as well as the types of customers eligible
    for relief. 
    Id. In particular,
    the amendments rendered schools and libraries eligible for discounted
    rates on telecommunications and internet services. 
    Id. The schools
    and libraries program is
    commonly referred to as “E-Rate” and is administered by the Universal Service Company
    (“USAC”), under the direction of the Federal Communications Commission (“FCC”). Overview
    of the Schools and Libraries Program, USAC, http://www.universalservice.org/sl/about/overview-
    program.aspx, (last visited May 25, 2006).
    In order for a school or library to participate in E-Rate, the school or library must engage in
    a highly regulated application process. See 
    id. First, the
    school or library must create a “technology
    plan” and have the plan approved by a certified entity. Step 2: Develop a Technology Plan, USAC,
    2
    No. 05-3974
    http://www.universalservice.org/sl/applicants/setp02, (last visited May 25, 2006). Next, the school
    or library must file “Form 470” with the USAC to begin the competitive bidding process. The
    USAC posts the school or library’s request for services online. Step 3: Open a Competitive Bidding
    Process, USAC, http://www.universalservice.org/sl/applicants/step03, (last visited May 25, 2006).
    Thereafter, the school or library must wait 28 days before selecting a service provider. 
    Id. In selecting
    a service provider, schools and libraries must make price the primary selection criteria.
    Step     4:   Select    the    Most      Cost-Effective        Service     Provider,      USAC,
    http://www.universalservice.org/sl/applicants/step04, (last visited May 25, 2006). After selecting
    a provider, applicants must calculate their discount rate by using “Form 471,” and submit Form 471
    to     the    USAC.        Step     5:    Calculate      the    Discount       Level,     USAC,
    http://www.universalservice.org/sl/applicants/step05, (last visited May 25, 2006). The USAC will
    review Form 471 and determine eligibility. Step 7: Submit Application for Support (Form 471),
    USAC, http://www.universalservice.org/sl/applicants/step07, (last visited May 25, 2006).
    B.      IBM’s Contract with Alpha
    On May 25, 1999, IBM and Alpha entered into a CSA, which was to govern the terms of their
    relationship. The CSA specified that Alpha would provide “deliverables” and “services” to IBM and
    that such “deliverables” and “services” would be defined in a future SOW. The CSA also contained
    termination provisions both for the CSA itself and SOW or Work Authorizations (“WA”). The
    CSA’s termination provision for SOWs reads as follows:
    3.3    Termination of a SOW or WA
    3
    No. 05-3974
    [IBM] may terminate a SOW or WA with Cause effective immediately or without
    Cause on sixty (60) days written notice. Upon termination, in accordance with
    [IBM]’s written direction, [Alpha] will immediately: (I) cease work; (ii) prepare and
    submit to [IBM] an itemization of all completed and partially completed Deliverables
    and Services; (iii) deliver to [IBM] Deliverables satisfactorily completed up to the
    date of termination at the agreed upon Prices in the relevant SOW; and (iv) deliver
    upon request any work in progress. In the event [IBM] terminates without Cause,
    [IBM] will compensate [Alpha] for the actual and reasonable expenses incurred by
    [Alpha] for work in process up to and including the date of termination provided
    [Alpha] uses reasonable efforts to mitigate [IBM]’s liability under this Subsection by,
    among other actions, accepting the return of, returning to its suppliers, selling to
    others, or otherwise using the canceled Deliverables (including raw materials or work
    in process) provided such expenses do not exceed the Prices.
    (J.A. at 63.)
    The particular SOW at issue in this case was entered into on January 7, 2002. The SOW
    specified that Alpha would help IBM prepare bids on request for services from school districts in
    IBM’s Western and Southwestern regions. In particular it specified that Alpha would review school
    districts’ requests and determine the applicable rates and discounts under the E-Rate program
    allowing IBM to properly price its bids. The SOW further specified an estimated schedule for
    Alpha’s work, stating:
    1.5 Estimated Schedule
    Alpha Telecommunications, Inc., will perform services in this Statement of Work as
    required to meet customer requirements. For this Statement of Work the Start Date
    will be December 1, 2001, and the Termination Date shall be December 1, 2003.
    (J.A. at 17-18.)
    Finally, the SOW sets forth fees. The fees provision provided that Alpha would be entitled
    to a percentage of IBM’s fees from the school districts provided those districts were funded by the
    School and Libraries Division (“SLD”) of the USAC. The payment schedule includes the following
    4
    No. 05-3974
    statements reiterating the conditional nature of Alpha’s entitlement to payment: (1) “Total fees wills
    will apply only to school districts which are funded by the Schools & Libraries Division (SLD),” and
    (2) “If portions of the [SOW] are not funded or cannot be completed due to delayed release of funds,
    Alpha Telecommunications , Inc. [sic] payment will be delayed until funding occurs or reduced
    accordingly.” (J.A. at 18.) Finally, the Key Assumptions section of the SOW also states that the
    SOW is “contingent on funding confirmation from the Schools and Libraries Division (SLD) of the
    [USAC].” (J.A. at 16.)
    C.      The Dispute
    Alpha started work under the SOW in January 2002. Alpha’s work consisted of assisting
    IBM in preparing bids on request for services for the following sixteen school districts:
    Albuquerque; Boor Hill; Canntillo; Clint; Dallas; Donna; El Paso; Forth Worth; Galena Park;
    Gallup; Houston; NETC; New Orleans; Oakland; OK City; and Ysleta. In particular, Alpha would
    review the districts’ request forms (Form 470) and applications for funding (Form 471) and
    determine which services were eligible for funding. It is unclear from the record which of these
    school districts subsequently accepted IBM’s bids and applied to the SLD for funding. It is clear,
    however, that the SLD denied funding to all of the districts that applied. See In re Request for
    Review of the Decision of the Universal Service Administrator by Ysleta Independent School
    District, 18 F.C.C.R. 26407 (2003). The districts and IBM appealed the denials to the FCC. 
    Id. On December
    8, 2003, the FCC issued an order affirming the SLD’s denial of funding. 
    Id. On February
    25, 2004, IBM employee, Mike Pratt, called Alpha’s attorney, Nathaniel
    Hawthorne, and informed Hawthorne that the SOW had expired at the end of December 2003 and
    5
    No. 05-3974
    that IBM would not be renewing it. In response, Alpha sent IBM an invoice for $16,135,053.97 for
    worked performed under the SOW. Alpha allegedly performed 90% of the work called for the SOW.
    IBM refused to pay on the ground that SLD had not approved the funding, and therefore, IBM did
    not owe Alpha any fees under the SOW.
    On March 11, 2004, Alpha filed suit in federal district court, alleging that IBM breached the
    CSA by terminating the SOW without cause. IBM denied that it terminated the SOW, and argued
    that the SOW expired on December 1, 2003, as set forth in the SOW’s estimated schedule.
    Additionally, IBM moved for sanction under Rule 11 on the ground that even if it had breached the
    SOW, Alpha was not entitled to damages under the SOW and thus Alpha’s suit was frivolous. In
    response, Alpha argues that the SOW did not expire because the FCC extended the SLD’s funding
    period for E-Rate grants, or “project year,” from December 8, 2003 until April 23, 2004. Alpha
    contends that the FCC’s extension of the funding period altered the SOW’s termination date.
    The district court assumed that IBM had terminated the SOW for the purposes of this action
    and granted summary judgment in favor of IBM on the ground that Alpha had not demonstrated it
    was entitled to damages under the SOW. According to the district court, SLD funding was a
    condition precedent to payment under the SOW, and IBM never received such funding. Alpha
    appeals this determination, arguing that the district court misconstrued its claim; Alpha states that
    it is not claiming the right to payment under the SOW but damages under the CSA for IBM’s
    without-cause-termination of the SOW. IBM cross appeals the district court’s order denying Rule
    11 sanctions.
    6
    No. 05-3974
    II.
    DISCUSSION
    A.     Summary Judgment
    1.      Standard of Review
    This appeal arises both in the context of a grant of summary judgment in favor of IBM and
    a denial of a motion for summary judgment in favor of Alpha. A district court’s decision to grant
    summary judgment is reviewed de novo, whereas a district court’s decision to deny summary
    judgment is reviewed for abuse of discretion. Wojcik v. City of Romulus, 
    257 F.3d 600
    , 608 (6th Cir.
    2001). In this case, the differing standards of review are not dispositive to our resolution of the
    issues before us because the issues in this appeal are purely legal, contract interpretation. See
    GenCorp Inc. v. Am. Int’l Underwriters, 
    178 F.3d 804
    , 817-18 (6th Cir. 1999) (insurance contract).
    Inasmuch as a district court has no discretion to grant summary judgment on the basis of an incorrect
    interpretation of law, see In re Brown, 
    342 F.3d 620
    , 633 (6th Cir. 2003) (citation omitted), we
    review all the issues in this case de novo.
    2.      Analysis
    To prevail on a breach of contract claim under Ohio law, a plaintiff must establish the
    following four elements: (1) the existence of a contract; (2) performance by the plaintiff; (3) a breach
    by the defendant; and (4) damage or loss to the plaintiff. Doner v. Snapp, 
    649 N.E.2d 42
    , 44 (Ohio
    App. 1994). The district court granted summary judgment in favor of IBM and denied summary
    judgment in favor of Alpha on the ground that Alpha had failed to establish any entitlement to
    damages under the contract. Although we disagree with the district court’s holding on damages, we
    7
    No. 05-3974
    nonetheless affirm the order of the district court on the ground that Alpha failed to establish that IBM
    breached the contract in question.
    a.      Damages
    The CSA expressly requires IBM to compensate Alpha for work completed under an SOW
    when IBM terminates a SOW without cause. It states:
    In the event [IBM] terminates without Cause, [IBM] will compensate [Alpha] for the
    actual and reasonable expenses incurred by [Alpha] for work in process up to and
    including the date of termination provided [Alpha] uses reasonable efforts to mitigate
    [IBM]’s liability under this Subsection by, among other actions, accepting the return
    of, returning to its suppliers, selling to others, or otherwise using the canceled
    Deliverables (including raw materials or work in process) and provided such
    expenses do not exceed the Prices.
    (J.A. at 63). Thus, Alpha is clearly entitled to be compensated for its work in the event of a breach.
    The fact that Alpha’s entitlement to payment under the SOW is conditioned on IBM’s receipt
    of SLD funding does not render Alpha’s right to damages in the event of breach conditional on such
    funding. The district court’s conclusion to the contrary, which is adopted by the concurrence,
    misconceives the nature of conditions precedent. Conditions precedent render a party’s performance
    conditional; conditions precedent do not grant a party the right to repudiate a contract prior to the
    occurrence of the condition. Corbin on Contracts § 959 (interim ed. 2002) (discussing anticipatory
    repudiation). When a party repudiates a contract before the occurrence of a condition precedent to
    the party’s performance, the adverse party may “treat the entire contract as broken and sue for breach
    of contract, and there is no necessity in such cases for . . . compliance with conditions precedent.”
    Livi Steel, Inc. v. Bank One, Youngstown, N.A., 
    584 N.E.2d 1267
    , 1270 (Ohio App. 1989); see also
    Corbin on Contracts § 959 (“It is now the generally prevailing rule in both England and the United
    8
    No. 05-3974
    States that a definite and unconditional repudiation of the contract by a party thereto, communicated
    to the other, is a breach of the contract, creating an immediate right of action and other legal effects,
    even though it takes place long before the time prescribed for the promised performance and before
    conditions specified in the promise have ever occurred”). In this case, Alpha argues that IBM
    repudiated the SOW prior to the occurrence of the relevant condition – SLD funding – and
    accordingly, Alpha need not establish that condition precedent contained in the SOW has occurred.
    
    Id. Although, as
    will be discussed in the next section, Alpha’s contention that IBM repudiated the
    contract is incorrect, if IBM had repudiated the contract, the traditional principles of contract law
    espoused by Ohio would entitle Alpha to damages.
    Similarly, IBM’s argument that the CSA itself limits Alpha’s recovery is incorrect.
    According to IBM, the CSA limits Alpha’s right to recovery in the event of breach by limiting
    damages to the “Prices” set forth in the SOW. IBM interprets the SOW to set the “Price” at 0 in the
    event that IBM does not receive SLD funding. As IBM never received SLD funding, it contends that
    the CSA entitles Alpha’s to “0” damages. The problem with IBM’s argument, however, is that it
    confuses the concept of Price with the concept of right to payment. The prices set forth in the SOW
    are the actual numerical values attached to Alpha’s work – in this case 7%-10% of various contracts
    – whereas SLD funding is a condition precedent to payment, not a part of the “Price.”
    To interpret “Price” otherwise would render the SOW termination clause set forth in the CSA
    meaningless. The CSA damages provision contemplates IBM terminating an SOW before the parties
    complete their performance under the contract, and conceivably before conditions precedent to
    payment are fulfilled. In fact, the entire purpose of the CSA damages provision is to compensate
    9
    No. 05-3974
    parties in such cases. Thus, to hold that despite IBM’s termination without cause, Alpha is not
    entitled to damages would be illogical.
    b.     Breach
    Nonetheless, Alpha is not entitled to damages under the CSA’s damages provisions because
    IBM did not repudiate the SOW in issue. Alpha alleges that IBM’s February 25, 2004 phone call,
    in which Mike Pratt instructed Alpha to stop work under the SOW, constituted an anticipatory
    repudiation of the terms of the SOW. At the time of the phone call, however, the SOW had already
    expired according to its own terms on December 1, 2003. The SOW reads:
    1.5 Estimated Schedule
    Alpha Telecommunications, Inc., will perform services in this Statement of Work as
    required to meet customer requirements. For this Statement of Work the Start Date
    will be December 1, 2001, and the Termination Date shall be December 1, 2003.
    (J.A. at 18 (emphasis added).) Consequently, in February 2004, the SOW had already expired, and
    IBM could not have repudiated or terminated the SOW.
    Alpha’s contention that the SOW did not terminate of its own accord on December 1, 2003
    because the termination deadline was extended is meritless. According to Alpha, the FCC’s
    December 8, 2003 order altered the actual termination date by extending the regulatory funding year
    for E-Rate contracts (“project year”). As proof of its position, Alpha submits evidence that Alpha
    and IBM entered into another SOW, the Syracuse SOW, and the Syracuse SOW has not yet been
    terminated, ostensibly due to the FCC’s order.
    There are numerous problems with Alpha’s argument. First, the FCC’s alteration of its
    project year is irrelevant to the SOW’s termination date. A project year is simply the year which a
    10
    No. 05-3974
    school’s plan must cover, and for which time period the FCC will supply a school with funding.
    Its dates do not correspond with any agreement between Alpha and IBM. As IBM correctly notes,
    the SOW does not state that its termination date is based on the FCC’s project year, and Alpha fails
    to explain why the dates of the project year would have any bearing on the SOW’s termination date.
    Notably, the original project year dates never matched the termination date, making any inference
    that the dates needed to correspond untenable. Second, the Syracuse SOW is not comparable to the
    SOW at issue in this case. The Syracuse SOW does not state a termination date. Therefore, to
    argue that because the Syracuse SOW has not terminated that this SOW has not terminated makes
    no sense. Finally, there is no relationship between the FCC’s altered project year and the fact that
    Syracuse SOW has not yet terminated. The FCC’s altered project year applied only to a limited
    number of school districts, those school districts covered by the SOW at issue in this case, but not
    those covered by the Syracuse SOW. See In Re Request for Review of the Universal Service
    Administrator by Ysleta Independent School District, 18 F.C.R. at 26407. Thus, the non-termination
    of the Syracuse SOW does not indicate that the FCC’s order altered any termination date.
    The only plausible argument that supports Alpha’s position that the December 1, 2003
    termination date was only an “estimated” termination date is the heading of the termination clause
    itself. The heading reads “Estimated Schedule.” (J.A. at 18.) One could infer from the heading that
    the termination date itself, which was a part of the schedule, was also estimated.
    Despite the plausibility of this interpretation, however, we nonetheless hold that the SOW
    expired on December 1, 2003.       Assuming that the December 1, 2003 was an “estimate” and
    therefore subject to change, Alpha has offered this Court no reason to believe the date was actually
    11
    No. 05-3974
    changed. As explained above, Alpha’s theory that the FCC order altered the date is without merit.
    Inasmuch as Alpha offers no evidence that December 1, 2003 was not the termination date, there is
    no reason for this Court to assume that it was not.
    B.     Sanctions
    1.      Standard of Review
    This Court reviews a district court order denying sanctions under Rule 11 for abuse of
    discretion. Andretti v. Borla Performance Indus., Inc., 
    426 F.3d 824
    , 833 (6th Cir. 2005). “A court
    necessarily abuses its discretion if it bases its ruling on an erroneous view of the law or a clearly
    erroneous assessment of the evidence.” Ridder v. City of Springfield, 
    109 F.3d 288
    , 293 (6th Cir.
    1997) (citing Cooter & Gell v. Hartmarx Corp., 
    496 U.S. 384
    , 405 (1990)).
    2.      Analysis
    IBM filed a motion for sanctions alleging that Alpha violated Rule 11 by: (1) filing an
    objectively meritless complaint; (2) moving for summary judgment; and (3) selectively quoting
    passages from the contract to the district court. The district court denied the motion, finding Alpha’s
    conduct was not objectively unreasonable because the SOW termination date was not clear from the
    face of the SOW. On appeal, IBM argues that the district court abused its discretion in denying the
    motion because, according to the plain language of both contracts, Alpha was not entitled to damages
    regardless of whether IBM terminated the agreement. Additionally, IBM argues that the district court
    abused its discretion in failing to consider that Alpha had selectively quoted from the contract.
    Section (b) of Rule 11 prohibits attorneys from filing any “pleading, written motion, or other
    paper,” unless “to the best of that attorney’s knowledge, information, and belief, formed after an
    12
    No. 05-3974
    inquiry reasonable under the circumstances . . . the claims, defenses, and other legal contentions
    therein are warranted by existing law or by a nonfrivolous argument for the extension, modification,
    or reversal of existing law or the establishment of new law.” Fed R. Civ. P. 11(b). In this Circuit,
    the test for whether sanctions under Rule 11 are warranted is whether the conduct for which
    sanctions are sought was “reasonable under the circumstances.” Ridder v. City of Springfield, 
    109 F.3d 288
    , 293 (6th Cir. 1997); Runfola & Assoc., Inc. v. Spectrum II, Inc., 
    88 F.3d 368
    , 372 (6th Cir.
    1996). The district court exercises wide discretion in determining whether an attorney’s conduct is
    reasonable. 
    Id. The district
    court did not abuse its discretion in denying IBM’s motion for sanctions pursuant
    to Rule 11. The termination date set forth in the SOW arguably was ambiguous. As discussed
    above, the clause’s heading stated “Estimated Schedule,” thereby allowing the inference that the
    termination date listed below was also estimated. Accordingly, the district court’s determination that
    Alpha’s position was not objectively unreasonable was within its discretion.
    Furthermore, we decline to hold that IBM’s remaining arguments merit a contrary result.
    First, IBM’s primary argument – that the ambiguity of the termination clause is irrelevant because
    Alpha was not entitled to damages regardless of whether IBM terminated the contract – is incorrect
    as a matter of law as discussed in the previous section. Next, IBM’s second argument – that Alpha
    selectively quoted passages – is waived. IBM failed to point to any specific instances in which
    Alpha selectively quoted passages. In addition to having a duty to develop arguments, see United
    States v. Layne, 
    192 F.3d 556
    , 566 (6th Cir. 1997), IBM has a duty to cite to the record in its brief
    on appeal, Fed. R. App. P. 28. Inasmuch as IBM has done neither with regard to its second
    13
    No. 05-3974
    argument, we deem this argument waived. See Bush v. Dictaphone Corp., 
    161 F.3d 363
    , 366 (6th
    Cir. 1998); 
    Layne, 192 F.3d at 566
    . Consequently, we hold that the district court did not abuse its
    discretion in denying IBM’s motion for Rule 11 sanctions and affirm the district court’s order.
    III.
    CONCLUSION
    For the reasons set forth above, we AFFIRM the order of the district court.
    14
    Nos. 05-3974 / 4022, Alpha Telecommunications v. IBM Corp.
    GRIFFIN, Circuit Judge, concurring.
    I concur in the result reached by the majority, but would do so for the reasons set forth by the
    district court.   The district court found dispositive the section of the SOW entitled “Key
    Assumptions,” and I agree. The relevant “Key Assumptions” provide:
    2. This Statement of Work is contingent on funding confirmation from the Schools
    and Libraries Division (SLD) of the Universal Service Administrative Corporation.
    Funding confirmation shall occur when the SLD posts funding on the SLD website.
    3. Alpha Telecommunications, Inc. will receive payment from IBM for services
    provided pursuant to the appropriate SOW . . . upon IBM [sic] receipt of payment
    from the federal government.
    The district court interpreted these “Key Assumptions” as conditions precedent to the
    performance of IBM’s payment obligations, and I find no reason to disturb that holding. Ohio law
    requires that “[a]n entire contract must be considered when determining whether a condition
    precedent exists.” Kaufman v. Byers, 
    823 N.E.2d 530
    , 537 (Ohio App. 2004) (citations omitted).
    Generally, whether a particular provision is a condition precedent “is a question of intent; and the
    intention will be ascertained by considering the language not only of the particular provision, but of
    the whole contract and its subject-matter.” 
    Id. (citation omitted).
    Here, the SOW unambiguously
    provides that the SOW was contingent upon SLD funding, that Alpha was only entitled to payment
    after IBM’s receipt of federal funds, and Alpha’s payment (if any) was based on a percentage of the
    federal funds that IBM received.
    Alpha’s remaining arguments–that the FCC’s ruling modified the time period of the SOW
    and that IBM breached the contract before the condition precedent could occur–are equally without
    merit. First, as IBM points out, the district court’s grant of summary judgment was entirely based
    15
    Nos. 05-3974 / 4022, Alpha Telecommunications v. IBM Corp.
    on the failure of a condition precedent; therefore, it is irrelevant whether the FCC ruling extended
    the contract window. Most importantly, Alpha has not alleged that the condition precedent – that
    the school districts and, in turn, IBM, would receive federal funding – did occur, or would have
    occurred, within the extended time period. Notably, the applications for federal funding were
    submitted by the school districts, not IBM. Thus, even if Alpha were alleging a frustration-of-
    purpose defense to execution of the condition precedent, the school districts were responsible for
    submitting new bids, not IBM. To this effect, five of the school districts did submit new bids, yet,
    nevertheless, IBM did not receive any federal funds. Alpha has not alleged any evidence to the
    contrary, but merely contends that the CSA provision controls the contract’s termination.
    For these reasons, I would affirm the ruling of the district court with respect to Alpha’s
    breach of contract claims. I join in Section II.B. of the majority opinion affirming the district court’s
    order denying sanctions.
    16