Ross Bros. Construction Co. v. Markwest Hydrocarbon, Inc. , 196 F. App'x 412 ( 2006 )


Menu:
  •                       NOT RECOMMENDED FOR PUBLICATION
    File Name: 06a0762n.06
    Filed: October 12, 2006
    No. 05-6251
    UNITED STATES COURT OF APPEALS
    FOR THE SIXTH CIRCUIT
    ROSS BROTHERS CONSTRUCTION CO.,
    INC.,
    On Appeal from the United
    Plaintiff-Appellant,                          States District Court for the Eastern
    District of Kentucky
    v.
    MARKWEST HYDROCARBON, INC.,
    Defendant-Appellee.
    /
    BEFORE:      MARTIN and RYAN, Circuit Judges; and MARBLEY, District Judge.*
    RYAN, Circuit Judge.        Ross Brothers Construction Co., Inc., appeals a district
    court decision awarding summary judgment to MarkWest Hydrocarbon, Inc., on a contract
    claim. The district court found that MarkWest was entitled to judgment as a matter of law
    on its defense of accord and satisfaction under Kentucky Revised Statute § 355.3-311.
    We AFFIRM.
    I.
    On November 3, 1999, Ross Brothers Construction contracted with MarkWest to
    upgrade MarkWest’s natural gas processing facility in Siloam, Kentucky, for the price of
    $1,114,944. Over the course of the project, Ross Brothers performed work beyond that
    contemplated in the original contract. Due to time constraints, the parties agreed to
    *
    The Honorable Algenon L. Marbley, United States District Judge for the Southern
    District of Ohio, sitting by designation.
    (No. 05-6251)                                -2-
    “negotiate” and to fix a “hard dollar price” after the project was completed. When the work
    was finished, MarkWest paid Ross Brothers $100,000 on the understanding that more
    would be paid “pending the outcome of cost evaluation discussions planned for a later
    date.”    Ross Brothers determined that the total value of the additional work was
    approximately $1.2 million dollars, but MarkWest submitted its own estimate for the
    additional work, which was less than a third of this amount. The parties were unable to
    agree on a final figure and negotiations broke down.
    Then, on July 10, 2000, MarkWest sent a letter to Ross Brothers and enclosed a
    check payable to Ross in the amount of $449,718, on which was typed “full and final
    payment.” The letter stated, inter alia, that the check was “full and final payment.” Before
    negotiating the check, Ross Brothers struck out the “full and final payment” language on
    the check and wrote “no/under protest.” MarkWest refused to make further payment, and
    on October 26, 2001, Ross Brothers filed suit in Kentucky State Court for breach of
    contract, seeking an additional $734,281.79.
    The case was removed by MarkWest to the United States District Court for the
    Eastern District of Kentucky under 28 U.S.C. § 1441(a) and 28 U.S.C. § 1332. MarkWest
    then filed a motion for summary judgment on February 14, 2002, arguing that Ross
    Brothers’ negotiation of the check bearing the restrictive endorsement “full and final
    payment” resulted in an accord and satisfaction of the claim. Ross Brothers challenged
    this motion, and the motion was denied by the district court on June 3, 2002. Almost three
    years later, on May 6, 2005, after lengthy discovery was completed, MarkWest filed
    another motion for summary judgment on the same theory as the first: accord and
    satisfaction. The district court granted this second motion, after finding that, as matter of
    (No. 05-6251)                                 -3-
    law, the Kentucky requirements for a defense of accord and satisfaction had been met.
    In granting MarkWest’s motion for summary judgment, the district court found that there
    was no genuine issue of material fact as to whether the “payment was tendered in good
    faith in full satisfaction of the . . . claim,” “the amount of the claim was unliquidated or the
    subject of a bona fide dispute,” and “the Plaintiff obtained payment of the instrument.”
    The district court also found both the check and the accompanying letter “‘contained
    a conspicuous statement . . . that the instrument was tendered as full satisfaction of the
    claim’” and that Ross Brothers knew a reasonable time ahead of negotiating the instrument
    that it was “in full satisfaction of the claim.” (Citation omitted.) For this reason, the court
    noted an accord and satisfaction was appropriate under either Ky. Rev. Stat. Ann. §§
    355.3-311(2) or 355.3-311(4). Ross Brothers filed a Fed. R. Civ. P. 59 motion with the
    district court to amend this judgment, but the motion was denied. Ross Brothers has
    appealed.
    II.
    We review a district court’s grant of summary judgment de novo. Kalamazoo
    Acquisitions, LLC v. Westfield Ins. Co., 
    395 F.3d 338
    , 341 (6th Cir. 2005). Under the Erie
    Doctrine, a federal court sitting in diversity applies the law of the state in which it sits.
    Davis v. Sears, Roebuck and Co., 
    873 F.2d 888
    , 892 (6th Cir. 1989). In this case,
    therefore, the substantive law of Kentucky applies.
    Kentucky law sets out several conditions for an accord and satisfaction.
    (1)    If a person against whom a claim is asserted proves that:
    (a)     That person in good faith tendered an instrument to the
    claimant as full satisfaction of the claim;
    (No. 05-6251)                                -4-
    (b)    The amount of the claim was unliquidated or subject to a bona
    fide dispute; and
    (c)    The claimant obtained payment of the instrument[.]
    Ky. Rev. Stat. Ann. § 355.3-311(1). If these conditions are met:
    the claim is discharged if the person against whom the claim is asserted
    proves that the instrument or an accompanying written communication
    contained a conspicuous statement to the effect that the instrument was
    tendered as full satisfaction of the claim.
    Ky. Rev. Stat. Ann. § 355.3-311(2). Alternatively, the claim can be discharged:
    if the person against whom the claim is asserted proves that within a
    reasonable time before collection of the instrument was initiated, the
    claimant, or an agent of the claimant having direct responsibility with respect
    to the disputed obligation, knew that the instrument was tendered in full
    satisfaction of the claim.
    Ky. Rev. Stat. Ann. § 355.3-311(4).
    III.
    Ross Brothers argues that the district court committed several errors that require
    vacating its decision. First, Ross Brothers claims that the district court applied too narrow
    an interpretation of case law because it did not consider the “facts surrounding . . .
    performance of the underlying contract” when it considered “good faith.” Ross Brothers
    argues that the entire contractual relationship between the parties was rife with bad faith
    acts and omissions by MarkWest, and that such bad faith extended to the tender of the
    check in an amount substantially less than the disputed claim. This argument, however,
    is without merit. We note, first of all, that the statute itself requires only that the person
    claiming the defense show that he “in good faith tendered an instrument to the claimant as
    full satisfaction of the claim,” not that good faith be shown throughout the course of the
    contract. Ky. Rev. Stat. Ann. § 355.3-311(1)(a). Further, in Kentucky, “good faith” is
    (No. 05-6251)                                -5-
    defined to “mean[] honesty in fact in the conduct or transaction concerned.” Ky. Rev. Stat.
    Ann. § 355.1-201(19) (emphasis added). See Star Bank, Kenton County, Inc. v. Parnell,
    
    992 S.W.2d 189
    , 192 (Ky. Ct. App. 1998). Clearly, the “transaction concerned” in section
    355.3-311(1)(a) is the tender, not the overall contract.
    Other states with similar statutes have also limited the “good faith” requirement to
    the actual tender. See Ex parte Meztista, 
    845 So. 2d 795
    (Ala. 2001) (interpreting Ala.
    Code 1975 § 7-3-311(a)); and Webb Bus. Promotions, Inc. v. Am. Electronics & Entm’t
    Corp., 
    617 N.W.2d 67
    (Minn. 2000) (interpreting Minn. Stat. Ann. § 336.3-311(a)). As we
    read Kentucky law, a tender made in good faith to settle a dispute should not be denied
    legal status as an accord and satisfaction simply because earlier in the contractual
    proceedings the tendering party may not have acted in good faith.
    Second, Ross Brothers argues that the district court should not have excluded the
    proposed expert opinion testimony of David Boggs. Ross Brothers admits that Boggs
    offered opinion testimony on the ultimate issue in the case, but argues that Fed. R. Evid.
    704 “permits a witness to testify in the form of an opinion or inference to an ‘ultimate issue
    to be decided by the trier of fact.’” But Ross Brothers focuses on the wrong rule of
    evidence. The district court did not exclude Boggs’s opinion testimony on the theory that
    it violated Fed. R. Evid. 704; it was excluded because the testimony contained numerous
    conclusions of law rather than fact.       For example, Boggs proposed to testify that
    “MarkWest’s tender of partial payment of the invoiced amount[] was not made in good
    faith, [and] did not have a good faith basis.” This is not a factual conclusion within the
    expert’s competence; it is a legal conclusion. This circuit has held that a district judge has
    discretion—and the duty—to exclude “legal opinion” it deems improper, and this stands
    (No. 05-6251)                                 -6-
    independent of Fed. R. Evid. 704. Stoler v. Penn Cent. Transp. Co., 
    583 F.2d 896
    , 899
    (6th Cir. 1978).
    Ross Brothers also claims there was no meeting of the minds for the tender
    because it was not clear what MarkWest was offering the “full and final payment” for and,
    in addition, that the district court invaded the province of the jury by holding that a bona fide
    or unliquidated dispute existed as to the amount owed. But we hold that it is apparent from
    the check, the text of the accompanying letter, and from the fact that Ross Brothers struck
    out “full and final payment” on the check that the parties knew the check was tendered as
    full and final payment. We agree with the district court’s alternative findings. The check
    and letter together contained the “conspicuous statement” required by Ky. Rev. Stat. Ann.
    § 355.3-311(2) and, in addition, Ross Brothers “knew that the instrument was tendered in
    full satisfaction of the claim,” as required by Ky. Rev. Stat. Ann. § 355.3-311(4). It is also
    clear that the debt was unliquidated, as the record shows that the Construction Change
    Requests were not a “hard dollar price” and the final price “could be higher or lower.”
    Finally, Ross Brothers argues that the district court improperly “looked at the
    evidence in a light most favorable to MarkWest.” Whether it did or did not is of no moment.
    This court has reviewed Ross Brothers’ claims de novo, considered the evidence in the
    light most favorable to Ross Brothers, and has concluded that summary judgment for
    MarkWest is appropriate under the defense of accord and satisfaction in Kentucky.
    IV.
    For the above reasons, we AFFIRM the district court’s judgment granting summary
    judgment to MarkWest.