Checkers Eight v. Hawkins, La-Van ( 2001 )


Menu:
  • In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 00-2704
    Checkers Eight Limited Partnership, et al.,
    Plaintiffs-Appellees,
    v.
    La-Van Hawkins, et al.,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the Northern District of Illinois, Eastern Division.
    No. 95 C 7708--John F. Grady, Judge.
    Argued January 24, 2001--Decided February 20, 2001
    Before Flaum, Chief Judge, and Evans and Williams,
    Circuit Judges.
    Flaum, Chief Judge. Defendants La-Van Hawkins and
    his associated corporations appeal the amount of
    damages entered under an agreed order. They claim
    that a provision requiring them to pay an
    additional $150,000 if their scheduled payments
    under the order were tardy is an unenforceable
    penalty clause. The defendants also argue that
    plaintiffs Checkers Eight Limited Partnership
    ("Checkers") and associated persons,
    partnerships, and corporations waived strict
    compliance with the payment schedule. For the
    reasons stated herein, we reverse and remand.
    I.   Background
    The facts underlying this lengthy commercial
    litigation are complicated and generally not
    relevant to the legal issues presented in this
    case and so will receive only a concise summary.
    In 1995, Checkers, Thomas W. Lonergan, James T.
    Lonergan, Thomas W. Lonergan Trust No. 1, and
    Tower Food Services, Inc. (the general partner of
    Checkers) filed suit against La-Van Hawkins,
    Hawkins Two, Inc., Hawkins Four, Inc., Hawkins
    Five, Inc., and Hawkins Eight, Inc. Count I of
    the amended complaint alleged that the defendants
    owed money to Checkers under a partnership
    agreement signed by each of the defendants, and
    Count II alleged that payments from the
    defendants were owed to another partnership. The
    plaintiffs sought $350,747.68 on Count I and
    $214,597.58 on Count II. The basis of federal
    jurisdiction was (and is) diversity, since the
    plaintiffs and the limited partners of Checkers
    were either citizens of or were incorporated and
    had their primary places of business in Illinois,
    New York, or Ohio, while the original defendants
    were either citizens of or were incorporated and
    had their primary places of business in Georgia.
    The litigation developed with the plaintiffs
    filing motions for summary judgment. In a June 3,
    1997 opinion, the court denied one of these
    motions but found as substantially uncontroverted
    facts under Fed.R.Civ.P. 56(d) that the
    defendants owed at least $181,303.68 on Count I
    and at least $200,162.58 on Count II. In
    September, 1997, after being granted leave by the
    court, the defendants filed a counterclaim
    seeking reimbursement for expenses the defendants
    allegedly paid on behalf of the partnerships. The
    counterclaim stated only that the defendants
    sought more than $50,000 in damages, but the
    defendants’ documented expenses totaled
    $1,153,484.85.
    In February, 1999, the parties settled the case
    and had the district court enter an order
    memorializing their resolution. This order
    dismissed the defendants’ counterclaim with
    prejudice and provided that if the defendants
    paid the plaintiffs a total of $250,000 in a
    timely manner the complaint would be dismissed
    with prejudice as well. This $250,000 was to be
    paid in an initial lump sum and then monthly
    installments, with the installment amounts due
    near the end of each month from March, 1999 to
    January, 2000. The order also stated that if the
    payments were not made in a timely manner,
    judgment for $400,000 minus any settlement
    payments would be entered against the defendants
    who were parties to the original partnership
    dispute as well as other associated entities,/1
    which collectively form the defendants in this
    case.
    The defendants were tardy making some of the
    payments. The payment of the first late sum,
    which was due on May 28, 1999 according to the
    agreed order, was delayed with the permission of
    the plaintiffs until June 4. However, the
    defendants did not obtain explicit permission
    from the plaintiffs for the remaining late
    payments, the next of which was the September 30
    payment, which was made one day late on October
    1. The sum due October 30 was not produced until
    November 9, with the plaintiffs filing a motion
    for entry of judgment on November 5, which was
    withdrawn when they received the payment. The
    monies due on December 31 were also late and the
    plaintiffs filed a motion to enter judgment for
    $400,000 in their favor on January 7, 2000. The
    defendants made this payment on January 11 and
    paid the last sum on January 20, which was eleven
    days early. At that point, the defendants had
    paid $250,000. However, the plaintiffs did not
    withdraw their motion for entry of judgment under
    the agreed order and the district court held a
    hearing. After listening to argument from both
    sides, the court granted the motion and ordered
    the defendants to pay an additional $150,000.
    II.   Discussion
    The defendants argue that the extra $150,000
    they were required to produce for not making
    timely payments is an unenforceable penalty
    clause. They claim that this sum has no relation
    to the damages caused by the late payments and
    that these damages are easily estimated by using
    prevailing interest rates. They further contend
    that the only purpose of this provision of the
    order was to secure performance of the contract
    and that the amount is insensitive to the gravity
    of their breach. The plaintiffs claim that the
    provision in question is a perfectly acceptable
    liquidated damages clause.
    We begin by making explicit a few assumptions
    relied on by the parties. The first of these is
    that state law, rather than federal, applies to
    the construction of agreed orders entered by a
    federal court sitting in diversity. In their
    briefs, both parties cite only Illinois law and
    Seventh Circuit and Illinois district court cases
    interpreting Illinois law. Most of the circuits
    that have considered the issue have held that
    questions of the validity or interpretation of an
    agreed order resolving state law claims are
    governed by state law, see, e.g., Bamerilease
    Capital Corp. v. Nearburg, 
    958 F.2d 150
    , 152 (6th
    Cir. 1992); Alumax Mill Prods., Inc. v. Congress
    Fin. Corp., 
    912 F.2d 996
    , 1007 (8th Cir. 1990);
    White Farm Equip. Co. v. Kupcho, 
    792 F.2d 526
    ,
    529 (5th Cir. 1986). Thus, we will assume with
    the parties that state law applies, though we
    need not make a definitive ruling on this
    question since the issue is not contested. The
    second assumption is that Illinois law, rather
    than the law of some other state, applies. Since
    the parties cite only cases interpreting Illinois
    law, we will assume that Illinois law governs
    their dispute. See Coleman v. Ramada Hotel
    Operating Co., 
    933 F.2d 470
    , 473 (7th Cir. 1991).
    The third premise is that Illinois applies its
    penalty clause jurisprudence to consensual orders
    approved by courts. The plaintiffs implicitly
    assume this in their briefs by arguing only that
    the provision of the agreed order at issue in
    this case does not constitute a penalty clause,
    but at oral argument questioned whether part of
    a court order could ever be considered a penalty.
    Even if we were to consider the plaintiffs’ late
    argument that under Illinois law no part of a
    settlement agreement approved by a court can be
    a penalty,/2 they cite no case law to that
    effect and we previously have found that under
    Illinois law portions of court-approved
    agreements can constitute unenforceable
    penalties. See South Suburban Hous. Ctr. v.
    Berry, 
    186 F.3d 851
    , 856 (7th Cir. 1999).
    Having established these preliminary points, we
    now move to the merits of the penalty clause
    argument. In interpreting contract provisions
    that specify damages, Illinois law draws a
    distinction between liquidated damages, which are
    enforceable, and penalties, which are not. See
    Lake River Corp. v. Carborundum Co., 
    769 F.2d 1284
    , 1289 (7th Cir. 1985). A clause is a
    liquidated damages provision if: (1) the actual
    damages from a breach are difficult to measure at
    the time the contract was made; and (2) the
    specified amount of damages is reasonable in
    light of the anticipated or actual loss caused by
    the breach. See American Nat’l Bank & Trust Co.
    of Chicago v. Regional Transp. Auth., 
    125 F.3d 420
    , 440 (7th Cir. 1997); Lake 
    River, 769 F.2d at 1289-90
    . In addition, when the sole purpose of
    the clause is to secure performance of the
    contract, the provision is an unenforceable
    penalty. See American Nat’l Bank & 
    Trust, 125 F.3d at 440
    ; MedPlus Neck & Back Pain Ctr., S.C.
    v. Noffsinger, 
    726 N.E.2d 687
    , 693 (Ill. App.
    2000). If the amount of damages is invariant to
    the gravity of the breach, the clause is probably
    not a reasonable attempt to estimate actual
    damages and thus is likely a penalty. See Raffel
    v. Medallion Kitchens of Minn., Inc., 
    139 F.3d 1142
    , 1146 (7th Cir. 1998); Lake 
    River, 769 F.2d at 1290
    . Whether a provision is a penalty clause
    is an issue of law that we review de novo. See
    American Nat’l Bank & 
    Trust, 125 F.3d at 439
    .
    Given these legal principles, the provision of
    the parties’ agreed order requiring the
    defendants to pay an additional $150,000 if the
    installments are not paid in a timely fashion is
    an unenforceable penalty clause. Absent
    exceptional circumstances, actual damages caused
    by monetary payments being late are not difficult
    to measure because interest rates can be used to
    estimate the time value of money. See Lawyers
    Title Ins. Corp. v. Dearborn Title Corp., 
    118 F.3d 1157
    , 1161 (7th Cir. 1997); United Order of
    Am. Bricklayers & Stone Masons Union No. 21 v.
    Thorleif Larsen & Son, Inc., 
    519 F.2d 331
    , 335
    (7th Cir. 1975). The interest that would have
    accrued on the late payments of the defendants is
    minimal, probably less than one hundred dollars.
    The amount of $150,000 is unreasonable and
    excessive compared to the actual damages as
    estimated by using interest rates. The amount of
    damages under the agreed order also is
    insensitive to the magnitude of the defendants’
    breach. Regardless of whether the defendants were
    a day late in making the last payment or had
    refused to perform at all, they would have been
    required to pay $150,000 to the plaintiffs.
    Finally, the extra $150,000 in damages appears to
    have no purpose other than ensuring that the
    defendants made the installment payments on time.
    Each factor considered by the Illinois courts
    points to the conclusion that the provision in
    the agreed order is a penalty./3
    The plaintiffs’ principal argument is that
    requiring the defendants to pay a total of
    $400,000 adequately measures the damages caused
    to the plaintiffs because of the defendants’
    breach of the timeliness requirement of the
    agreed order. They base this contention on the
    district court’s findings in its June 3, 1997
    order that the defendants owed at least
    $381,466.26 and the possibility that the
    defendants could have been liable for as much as
    $565,345.26. The plaintiffs’ argument is
    unpersuasive. The amount of $400,000 might have
    been a reasonable estimate of the damages caused
    by the alleged breach of the partnership
    agreement, though this is neither certain/4 nor
    pertinent. The issue before this court is not
    what remedy would adequately compensate the
    plaintiffs for the alleged breach of the
    partnership agreement, but rather what remedy is
    reasonable for the breach of the agreed order.
    This latter breach, the only relevant one for
    purposes of this opinion, was caused by the
    tardiness of some of the defendants’ installment
    payments. For the reasons explained above,
    requiring the defendants to pay an additional
    $150,000 is not a reasonable estimate of the
    damages caused by these late payments.
    The plaintiffs also argue that courts should
    respect contracts between two sophisticated
    parties and not reform such agreements so as to
    give one party a bargain to which the other did
    not agree. This claim amounts to a generalized
    assertion that contract provisions between
    commercially experienced parties should never
    constitute penalty clauses because the parties
    are of roughly equal bargaining strength. While
    we have noted similar criticisms in this
    circuit’s opinions discussing Illinois penalty
    clause jurisprudence, see Lawyers 
    Title, 118 F.3d at 1160-61
    , Lake 
    River, 769 F.2d at 1288-90
    ,
    Illinois continues to invalidate damages
    provisions in contracts that fail the test
    outlined above even if both parties are
    economically sophisticated, see, e.g., Telenois,
    Inc. v. Village of Schaumburg, 
    628 N.E.2d 581
    ,
    584-85 (Ill. App. 1993); Grossinger Motorcorp,
    Inc. v. American Nat’l Bank & Trust Co., 
    607 N.E.2d 1337
    , 1345-46 (Ill. App. 1992). The
    plaintiffs’ argument would prove too much if
    accepted, because then no damages clause between
    commercially experienced parties could be
    considered a penalty, which clearly contradicts
    actual Illinois law. Since, as aforementioned, we
    apply Illinois law in this case, we must reject
    the plaintiffs’ argument.
    III.   Conclusion
    Because the damages clause is an unenforceable
    penalty under Illinois law, the plaintiffs are
    entitled only to the actual damages caused by the
    defendants’ late payments, as measured by an
    appropriate interest rate. For the reasons stated
    herein, we Reverse and Remand for further proceedings
    consistent with this opinion.
    /1 The parties who are the defendants in the instant
    dispute are La-Van Hawkins, Hawkins One, Inc.,
    Hawkins Two, Inc., Hawkins Four, Inc., Hawkins
    Five, Inc., Hawkins Eight, Inc., The La-Van
    Hawkins Group, Inc., Windy City Construction,
    Inc., Inner City Foods Company, and La-Van
    Hawkins & Assoc. of Chicago, Inc. At least two of
    the entities included in this group but who were
    not originally defendants, namely, Inner City
    Foods Company and La-Van Hawkins & Assoc. of
    Chicago, Inc., are incorporated and have their
    principal places of business in Illinois, and
    thus are not diverse from the plaintiffs.
    However, since the parties were completely
    diverse when the action was commenced and these
    two entities are not indispensable parties, their
    subsequent addition does not deprive this court
    of jurisdiction. See Freeport-McMoRan, Inc. v. K
    N Energy, Inc., 
    498 U.S. 426
    (1991).
    /2 Claims raised for the first time at oral argument
    are normally considered waived. See Berens v.
    Ludwig, 
    160 F.3d 1144
    , 1148 (7th Cir. 1998).
    /3 Because we accept the defendants’ penalty clause
    argument, we need not address their contentions
    regarding waiver.
    /4 Despite the district court’s finding that their
    claims were worth at least $381,466.26, the
    plaintiffs quite possibly could have netted much
    less than $400,000, or even $250,000, if they had
    continued to litigate. This course would have
    required the plaintiffs to expend further
    resources on preparing and conducting a jury
    trial and would have also exposed them to the
    possibility of being found liable on the
    defendants’ counterclaim. If these expenses were
    sufficiently large, a reasonable estimate of the
    expected value of the plaintiffs’ suit on the
    date that they settled could have been $250,000
    or less.
    EVANS, Circuit Judge, concurring. I can’t agree
    that the court-approved settlement order, which
    increased Hawkins’ obligation to $400,000 if he
    failed to make timely payments, is an
    unenforceable penalty clause. In fact, it seems
    to me that this sort of carrot-and-stick
    settlement agreement, blessed by a court in an
    order, is fairly routine. Surely, Checkers and
    Hawkins could have agreed to the entry of a
    judgment for $400,000, dischargeable as fully
    satisfied upon Hawkins paying $250,000 over 10
    months. The court order here, in substance, isn’t
    any different. It is wrong, I submit, to
    characterize this agreement as one involving
    "damages." It’s not. It involves an alternative
    entitlement if certain conditions are not met.
    And there is nothing wrong with that, especially
    here where we are dealing with big boys who ought
    to be able to freely agree on any mechanism for
    resolving what the court correctly describes as
    complicated and "lengthy commercial litigation."
    But that said, I join the court’s opinion
    because I think Checkers, by waiting to spring
    its $150,000 kicker until after it got all its
    money, waived its right to insist on strict
    compliance with the order’s timely payment
    provisions. So the court, in my view, is correct
    in rejecting Checkers’ claim (except for a
    pittance of interest), although I would do so for
    a different reason.