Frey v. Environmental Protection Agency , 751 F.3d 461 ( 2014 )


Menu:
  •                                   In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 13-2142
    SARAH E. FREY, KEVIN ENRIGHT, and
    PROTECT OUR WOODS, INC.,
    Plaintiffs-Appellants,
    v.
    ENVIRONMENTAL PROTECTION
    AGENCY and GINA MCCARTHY, AD-
    MINISTRATOR,
    Defendants-Appellees.
    Appeal from the United States District Court for the
    Southern District of Indiana, Indianapolis Division.
    No. 1:00-cv-0660-RLY-TAB — Richard L. Young, Chief Judge.
    ARGUED NOVEMBER 15, 2013 — DECIDED MAY 1, 2014
    Before FLAUM and HAMILTON, Circuit Judges, and KAPALA,
    District Judge.*
    *
    Hon. Frederick J. Kapala, of the Northern District of Illinois, sitting by
    designation.
    2                                                     No. 13-2142
    HAMILTON, Circuit Judge. This environmental dispute stems
    from the contamination and clean-up of several sites near
    Bloomington, Indiana, that have been the subject of two prior
    decisions by this court. See Frey v. Environmental Protection
    Agency, 
    270 F.3d 1129
     (7th Cir. 2001) (“Frey I”); Frey v.
    Environmental Protection Agency, 
    403 F.3d 828
     (7th Cir. 2005)
    (“Frey II”). After our last remand of this citizen suit under the
    Comprehensive Environmental Response Compensation and
    Liability Act (“CERCLA”), see 
    42 U.S.C. § 9659
     (citizen suits
    authorized), the parties filed cross-motions for summary
    judgment. Plaintiffs Sarah E. Frey, Kevin Enright, and Protect
    Our Woods, Inc. also filed a motion to disqualify the district
    judge because of his ruling in a related case.
    The remediation work has been divided into three stages.
    The district court held that § 113(h)(4) of CERCLA, 
    42 U.S.C. § 9613
    (h)(4), deprived it of jurisdiction over the plaintiffs’ claims
    based on the second and third stages because that remedial
    work was ongoing. The court then granted summary judgment
    for the defendants (the Environmental Protection Agency and
    its Administrator) on two of the remaining claims concerning
    the completed first stage of the remedial work and held that
    the third claim was moot. The district judge also denied the
    motion to disqualify him.
    We affirm. The second and third stages of the site clean-ups
    are currently in progress, so § 113(h)(4) prevents the courts
    from reviewing plaintiffs’ claims about those stages. We also
    conclude that § 113(h)(4) does not bar judicial review of
    plaintiffs’ claims about the first remedial stage insofar as they
    are not affected by continuing clean-up efforts at the sites. The
    No. 13-2142                                                               3
    district court correctly granted summary judgment to the EPA
    on plaintiffs’ claims regarding the first remedial stage.
    Plaintiffs also are not prevailing parties on their claim that the
    EPA and its administrator were required to have the court
    enter agreements between parties as consent decrees. Finally,
    Chief Judge Young was not required to recuse himself, and his
    denial of the motion to disqualify did not violate plaintiffs’
    right to due process of law.
    I. Background
    A. Factual Background
    The facts underlying this dispute have been laid out in
    detail in Frey I and Frey II, as well as by the district court in its
    order granting summary judgment, see Frey v. EPA, 
    937 F. Supp. 2d 964
     (S.D. Ind. 2013), so we limit our discussion to the
    facts relevant to this appeal.
    This case arises from the contamination and clean-up of
    three sites in and near Bloomington, Indiana. From the late
    1950s to the early 1970s, CBS (formerly Westinghouse Electric
    Corporation) manufactured electrical capacitors at a plant in
    Bloomington. The capacitors contained insulating fluid made
    up of polychlorinated biphenyls, known as PCBs, which are
    carcinogens that are toxic to both humans and wildlife. See
    United States Environmental Protection
    A g e n c y, “ Po l y c h l o r i n a t e d B ip h e n y l s ( P C B s ) , ”
    www.epa.gov/waste/hazard/wastemin/minimize/factshts/pc
    b-fs.pdf (accessed May 1, 2014); 
    40 C.F.R. § 761.20
     (imple-
    menting the Toxic Substances Control Act, 
    15 U.S.C. §§ 2601
     et
    seq.) (“any exposure of human beings or the environment to
    PCBs … may be significant”). CBS deposited defective
    4                                                    No. 13-2142
    capacitors at local landfills and dumps where PCBs escaped
    from the capacitors and entered the environment. CBS also
    discharged PCB-laden water from its plant to a local sewage
    treatment plant.
    In the late 1970s, PCB contamination was discovered in the
    Bloomington area and traced back to the CBS plant and six
    sites around Bloomington. The United States, the State of
    Indiana, Monroe County, and the City of Bloomington filed
    what we call the enforcement action under CERCLA to make
    CBS clean up the sites. The enforcement action seemed to be
    resolved in 1985 with a consent decree requiring CBS to dig up
    all PCB-contaminated materials at all six sites (down to
    bedrock, if necessary) and to destroy them in a high-
    temperature incinerator. But the Indiana legislature blocked
    construction of the incinerator, forcing the parties back to the
    negotiating table.
    A new agreement proved elusive. The parties eventually
    agreed on modified remedies for three of the six sites but were
    unable to agree on remedies for the remaining three: Lemon
    Lane Landfill, Neal’s Landfill, and Bennett’s Dump. These
    three sites, which had been added to CERCLA’s National
    Priorities List in 1983 and 1984, are the sites at issue in this
    appeal. To resolve their remaining disagreements, the parties
    worked with a special master to approach the clean-up in
    stages. When the parties agreed on remedies for a given stage,
    CBS could begin work on that stage while the parties
    continued to negotiate about further clean-up. Negotiating in
    stages thus made it possible to start cleaning up the sites before
    the parties had resolved all of their differences.
    No. 13-2142                                                      5
    This process eventually resulted in three clean-up stages.
    Stage 1 addressed PCB contamination at the landfills. It
    required CBS to remove sediment from contamination hot
    spots at Lemon Lane Landfill and Neal’s Landfill, and to clean
    all sediment at Bennett’s Dump to “industrial standards.” CBS
    was also required to install a clay landfill cap at all three sites
    that would contain any remaining contaminated sediment.
    Stage 1 was formalized in three slightly different Records of
    Decision, one for each site. The Stage 1 Records of Decision for
    Lemon Lane Landfill and Neal’s Landfill required future
    remedies for groundwater and sediment contamination. The
    Stage 1 Record of Decision for Bennett’s Dump required future
    monitoring to detect any remaining contamination after the
    required total sediment excavation was complete. CBS
    completed work on Stage 1 at all three sites by the end of 2000.
    After CBS completed Stage 1, tests showed that PCBs had
    migrated into the bedrock and were still being released from
    the bedrock into water and sediment. Much of the geology
    around Bloomington consists of limestone karst, which is
    characterized by fissures, fractures, and conduits that can make
    clean-up of contaminated groundwater and bedrock extremely
    difficult.
    CBS and the government parties eventually agreed on
    Stages 2 and 3, which address current and future PCB
    contamination of groundwater and sediment from the sites.
    These two stages require CBS to assume ownership and
    operate a water treatment plant at Lemon Lane Landfill and to
    modify and operate a groundwater collection and treatment
    system at Neal’s Landfill. At Bennett’s Dump, CBS must install
    a passive drain system to decrease water levels in rain-filled
    6                                                    No. 13-2142
    quarry pits, and design, construct, and operate a new water
    treatment plant and collection trench at the site. CBS also
    agreed to sample domestic wells periodically at all three sites
    and to continue all of these activities until the concentration of
    PCBs in the groundwater is equal to or below EPA effluent
    limits for one year. Stages 2 and 3 were formalized in three
    Records of Decision (one per site) in 2006 and 2007. At this
    time, work on Stages 2 and 3 continues.
    In February 2008, the United States filed in the enforcement
    action against CBS an agreed amendment to the 1985 consent
    decree that incorporated all six Records of Decision and
    resolved all claims and counter-claims among the United
    States, CBS, the State of Indiana, Monroe County, and the City
    of Bloomington. See United States v. CBS Corp., No.
    1:81-cv-448-RLY-KPF (S.D. Ind.). A public comment period
    followed, during which plaintiffs in this case submitted
    comments on the proposed amendment. In March 2009, after
    the comment period had ended, the United States moved the
    district court to enter the amendment. Plaintiffs filed a
    statement with the court requesting that it not approve the
    amendment until it had ruled on their case because the two
    cases presented overlapping issues. (Plaintiffs were not parties
    in the enforcement action, but this citizen suit and the
    enforcement action were temporarily consolidated for case
    management purposes, and plaintiffs were permitted to file
    statements in the enforcement action if decisions in that case
    would affect their case.)
    After considering plaintiffs’ public comments and
    statement, the district court approved the agreed amendment
    in the enforcement action. The court found that the agreed
    No. 13-2142                                                            7
    amendment was procedurally and substantively fair, its terms
    were reasonable and adequate, and it was consistent with the
    goals and purposes of CERCLA. In particular, the district court
    found that the EPA had completed the functional equivalent of
    a remedial investigation and feasibility study (“RI/FS”) for each
    site and that the EPA had selected remedial actions that would
    protect human health and the environment. The district court
    entered the agreed amendment in the enforcement action in
    July 2009.
    B. Procedural Background
    Plaintiffs originally filed this separate citizens suit under
    CERCLA in 2000 while work on Stage 1 was continuing.1 The
    district court dismissed the lawsuit on two occasions for lack
    of jurisdiction, citing CERCLA § 113(h)(4)’s bar on citizen suits
    “where a remedial action is to be undertaken at the site.”
    
    42 U.S.C. § 9613
    (h)(4). We reversed on both occasions, finding
    that at those times any plans for future remedial action were
    too tentative to trigger § 113(h)(4). See Frey I, 
    270 F.3d at 1133-34
    ; Frey II, 
    403 F.3d at 829
    .
    Plaintiffs filed their Third Amended Complaint—now the
    operative complaint in this case—in July 2009. They allege that
    the EPA failed to complete an RI/FS or its functional equivalent
    prior to selecting Stages 1, 2, and 3 as required by CERCLA.
    Plaintiffs also claim that the EPA violated CERCLA’s mandate
    to protect human health and the environment by adopting the
    1
    In 1988, Frey had filed an earlier suit that was dismissed for lack of
    jurisdiction pursuant to CERCLA § 113(h)(4). We affirmed the district
    court’s dismissal. See Schalk v. Reilly, 
    900 F.2d 1091
     (7th Cir. 1990).
    8                                                           No. 13-2142
    remedial plans in Stages 1, 2, and 3. Finally, the complaint
    alleges that the EPA violated CERCLA’s mandate that
    settlement agreements be entered as consent decrees. The
    parties filed cross-motions for summary judgment. Plaintiffs
    also moved to disqualify the district judge because he had
    ruled in the related enforcement action.
    The district court held that it lacked jurisdiction over claims
    pertaining to Stages 2 and 3, reasoning that work on those
    stages was continuing, so § 113(h)(4)’s bar applied. The court
    then granted summary judgment for the EPA on all claims
    regarding Stage 1, holding that the EPA had completed the
    functional equivalent of an RI/FS for Stage 1 and had selected
    remedies for Stage 1 that were protective of human health and
    the environment. The court also held that plaintiffs’ claim that
    the EPA violated CERCLA’s consent decree requirement was
    moot because the consent decree had by then been amended.
    Finally, the judge declined to recuse himself because his prior
    ruling in the enforcement case did not stem from an
    extrajudicial source and thus was not a ground for recusal.
    II. Discussion
    Plaintiffs argue on appeal that § 113(h)(4)’s prohibition on
    judicial review does not apply to any of their claims and that
    the district court should have ruled on their claims regarding
    Stages 2 and 3. They also ask us to order summary judgment
    in their favor on all Stage 1 claims.2 Plaintiffs claim that, on the
    2
    Plaintiffs argue in their reply brief that summary judgment for EPA
    should be denied on plaintiffs’ Stage 1 claims because disputes of material
    (continued...)
    No. 13-2142                                                                 9
    undisputed facts, the EPA did not complete the functional
    equivalent of an RI/FS prior to selecting Stage 1; Stage 1
    violated CERCLA’s mandate that remedies protect human
    health and the environment; and the EPA violated CERCLA’s
    requirement that all settlement agreements be entered as
    consent decrees. Plaintiffs contend that their claim about the
    consent decree requirement is not moot. Rather, they seek to be
    declared prevailing parties on that claim because their lawsuit
    spurred the EPA to modify the consent decree. Finally,
    plaintiffs maintain that the district judge should have recused
    himself.3
    A. Scope of Review
    We begin by determining the scope of our jurisdiction.
    Although neither party challenges our jurisdiction, we must
    satisfy ourselves as to our jurisdiction over a case. E.g.,
    Wernsing v. Thompson, 
    423 F.3d 732
    , 743 (7th Cir. 2005). Section
    113(h)(4) of CERCLA states in relevant part: “No Federal court
    shall have jurisdiction … to review any challenges to removal
    or remedial action selected under section 9604 of this title, or to
    review any order issued under section 9606(a) of this title, in
    any action except … (4) An action under section 9659 of this
    title (relating to citizens suits) alleging that the removal or
    2
    (...continued)
    fact exist. The argument was waived both because it appeared for the first
    time in the reply brief and because it was too cursory for us to consider. See
    Puffer v. Allstate Ins. Co., 
    675 F.3d 709
    , 718 (7th Cir. 2012).
    3
    Counsel for plaintiffs informed us at oral argument that plaintiff Sarah E.
    Frey had recently passed away. The appeal continues on behalf of the other
    plaintiffs.
    10                                                    No. 13-2142
    remedial action taken under section 9604 of this title or secured
    under section 9606 of this title was in violation of any
    requirement of this chapter. Such an action may not be brought
    with regard to a removal where a remedial action is to be undertaken
    at the site.” 
    42 U.S.C. § 9613
    (h)(4) (emphasis added).
    Our cases interpreting § 113(h)(4) are in tension as to
    whether its prohibition is jurisdictional or not. Frey I concluded
    that § 113(h)(4) is substantive rather than jurisdictional, 
    270 F.3d at
    1132–33, but did not discuss our circuit’s prior holding
    in North Shore Gas Co. v. Environmental Protection Agency that
    § 113(h)(4) effects “the blunt withdrawal of federal
    jurisdiction.” 
    930 F.2d 1239
    , 1244 (7th Cir. 1991). Later cases in
    this circuit have followed North Shore Gas and interpreted §
    113(h)(4) as jurisdictional. See Pollack v. U.S. Department of
    Defense, 
    507 F.3d 522
    , 524–25 (7th Cir. 2007) (adopting the North
    Shore Gas interpretation of § 113(h)(4) without discussing Frey
    I); Village of DePue v. Exxon Mobil Corp., 
    537 F.3d 775
    , 784 (7th
    Cir. 2008) (same); Adkins v. VIM Recycling, Inc., 
    644 F.3d 483
    ,
    493–94 (7th Cir. 2011) (§ 113(h) “expressly limits federal courts’
    subject matter jurisdiction”).
    Also, since Frey I was decided, a series of Supreme Court
    decisions that have generally narrowed the issues that federal
    courts treat as affecting subject matter jurisdiction have
    directed courts to take a statute at its word when it speaks in
    terms of jurisdiction, as § 113(h)(4) does. E.g., Arbaugh v. Y & H
    Corp., 
    546 U.S. 500
    , 515–16 (2006); see also Reed Elsevier Inc. v.
    Muchnick, 
    559 U.S. 154
    , 160–163 (2010); Henderson v. Shinseki,
    562 U.S. ___, 
    131 S. Ct. 1197
    , 1204–05 (2011). These cases
    strongly suggest that § 113(h)(4) should be deemed
    No. 13-2142                                                     11
    jurisdictional rather than substantive. See Pakootas v. Teck
    Cominco Metals, Ltd., 
    646 F.3d 1214
    , 1219–20 (9th Cir. 2011)
    (declining to follow Frey I and holding that § 113(h)(4) is
    jurisdictional based on intervening Supreme Court precedent).
    Having previously held in this same case that § 113(h)(4) is
    not jurisdictional, see Frey I, 
    270 F.3d at
    1132–33, we hesitate to
    reverse course now and hold that § 113(h)(4) is jurisdictional
    after all. The distinction does not make a practical difference in
    this case since there is no issue as to waiver, whether the trier
    of fact should be a judge or jury, or whether the district court’s
    decision would have preclusive effects. Whether jurisdictional
    or substantive, § 113(h)(4) bars judicial review of claims
    regarding ongoing site clean-ups, either because we lack
    jurisdiction over those claims or because they are premature.
    If plaintiffs’ claims address ongoing clean-up at the sites,
    § 113(h)(4) bars review of them under either interpretation. For
    now we therefore follow Frey I in treating § 113(h)(4) as
    substantive rather than jurisdictional and proceed to determine
    which of plaintiffs’ claims are barred by § 113(h)(4).
    Section 113(h)(4) prevents court consideration of citizen
    suits under CERCLA until a remedial action is complete.
    Schalk v. Reilly, 
    900 F.2d 1091
    , 1095 (7th Cir. 1990) (“The
    obvious meaning of this statute is that when a remedy has been
    selected, no challenge to the cleanup may occur prior to the
    completion of the remedy.”); see also North Shore Gas, 
    930 F.2d at 1244
    . Environmental remediation is a complex endeavor that
    often proceeds in stages. Frey II, 
    403 F.3d at 834
    . Accordingly,
    § 113(h)(4) prevents us from reviewing a finished stage of a
    broader remediation plan if the execution of the plan itself is
    12                                                             No. 13-2142
    not yet complete. Frey I, 
    270 F.3d at 1134
    . On the other hand,
    extended monitoring and indefinite plans for future action do
    not suffice to trigger the bar of § 113(h)(4). Id. at 1133-34; Frey
    II, 
    403 F.3d at 834-35
    . For § 113(h)(4) to protect the EPA from
    citizen suits, the EPA must adopt an “objective referent” or
    “objective indicator” that future work is planned. Frey II, 
    403 F.3d at 834-35
    . A Record of Decision would certainly qualify as
    an objective referent or indicator, but less could also suffice. 
    Id. at 834
    .
    In Frey II, we concluded that the EPA had not provided an
    objective indicator that further work was planned at the sites.
    
    Id. at 830
    . Plaintiffs were therefore entitled to judicial review of
    their claims about Stage 1, which was at that time the only
    concrete action planned at the site. Id.4 Since that remand,
    however, the EPA has filed Records of Decision for Stages 2
    and 3, and work on those stages is ongoing. We must therefore
    confront a new question: how does § 113(h)(4) apply if, after a
    judicial determination that no future action was planned (so
    that § 113(h)(4) did not bar consideration of the citizen suit),
    the EPA then makes new, concrete plans to conduct further
    remediation at a site?
    4
    The EPA does not seem to have argued in Frey II that the Stage 1 Records
    of Decision explicitly committed the EPA to conduct water and sediment
    remediation at the site and therefore were “objective indicators” of future
    action sufficient to trigger the bar of § 113(h)(4). Since Frey II, the EPA has
    filed Records of Decision for Stages 2 and 3, so we need not resolve whether
    the statements in the Stage 1 Records of Decision would have sufficed to
    trigger § 113(h)(4).
    No. 13-2142                                                     13
    There are several possible answers to this question, which
    the text of § 113(h)(4) itself does not answer. First, we might
    say that the moment the EPA finalizes its new plans,
    § 113(h)(4) bars review of any prior remediation at the site.
    That interpretation, however, would have the unsettling effect
    of allowing a citizen suit to proceed while the EPA is
    considering further action but then requiring its dismissal the
    moment the EPA decides to act. We should avoid this winking
    in and out of claims if possible. This reading would also risk
    constraining the scope of judicial review under § 113(h)(4) to
    the point of rendering it almost a nullity: the EPA would be
    able to delay citizen suits indefinitely by proposing minor
    “further actions” whenever a citizen files suit, regardless of
    whether the further action affects the work already completed
    at the site. As we have said before, we should avoid converting
    § 113(h)(4) into “a silent prohibition on judicial review.” Frey I,
    
    270 F.3d at 1134
    ; see also Frey II, 
    403 F.3d at 836
    ; North Shore
    Gas, 
    930 F.2d at 1245
    .
    We might instead say that the prior action remains subject
    to judicial review regardless of the EPA’s new clean-up plans,
    but that would also create problems. If the EPA’s new action is
    not fully distinct from the old one but rather builds upon and
    supplements it, we would then lack a meaningful way to
    review the completed action without also reviewing the new
    action, which § 113(h)(4) would bar until the new action were
    complete. That would make it difficult to escape the conclusion
    that despite the EPA’s delay, there would be no complete
    action for us to review and § 113(h)(4)’s bar would apply.
    Under those circumstances, the prior action would seem more
    like a completed stage in a broader remediation plan than a
    14                                                 No. 13-2142
    stand-alone plan ready for judicial review. See Frey I, 
    270 F.3d at 1134
     (we cannot review a stage in a clean-up until the whole
    clean-up is complete). So, we cannot categorically conclude
    that the new plan does not affect judicial review of the old one
    because that approach would present problems if the two
    plans overlapped.
    We think the best approach is to chart a middle path. If the
    EPA adopts a new remediation plan after an old plan is
    complete, a court remains able to review citizens’ claims about
    the old plan that are not directly affected by the new plan. For
    example, when the new plan targets a different area, pollutant,
    or polluted medium than the old plan, a court should still be
    able to review most claims regarding the old plan because the
    two plans are largely distinct from one another. If the plans
    overlap, however, § 113(h)(4) prevents us from resolving
    claims about the old plan that are directly affected by the new
    plan, that is, claims about aspects of the old plan that fall
    within the plans’ overlap. Otherwise, we would in effect be
    reviewing the new plan before it was complete, which we
    cannot do. In other words, adoption of the new plan does not
    affect judicial review of claims about the old plan unless the
    two plans overlap, and only to the extent that they do so.
    For example, if the old remedial plan addressed soil and
    water contamination at a site and the new plan addressed only
    soil contamination at the same site, a court would be able to
    review claims pertaining to the old plan’s water remedies but
    would not be able to review claims about the old plan’s soil
    remedies. If the old plan addressed soil contamination and the
    new plan addressed water contamination, then we should be
    able to examine claims about the old plan’s soil remedies
    No. 13-2142                                                    15
    without worrying about the new plan at all. Finally, if the old
    plan addressed soil contamination and the new plan addressed
    soil and water contamination, then we could not review any
    claims about the old plan’s soil remedies because the new plan
    also addressed soil contamination.
    We recognize that these lines may turn out to be difficult to
    draw in practice. But there is no entirely satisfactory solution
    to the problem of later remedial actions supplementing prior
    work at a site, especially one that preserves an appropriate and
    effective role for judicial review through citizen suits. We think
    this approach creates the most workable solution. It is
    consistent with the language of § 113(h)(4) and our past
    decisions interpreting that language. It also strikes a reasonable
    balance between citizens’ right to meaningful judicial review
    of their claims and the EPA’s interest in being able to clean up
    sites without being delayed by citizen suits.
    Turning to the facts before us, the district court correctly
    concluded that it could not review the ongoing work of Stages
    2 and 3 but could review at least some claims about Stage 1.
    The remedial work of Stages 2 and 3 is ongoing, so § 113(h)(4)
    bars review at this time. The delay in reviewing plaintiffs’
    claims about Stages 2 and 3 is a necessary consequence of the
    § 113(h)(4) bar on judicial review of a remedial action until that
    action is complete. The district court correctly declined to
    consider plaintiffs’ claims regarding Stages 2 and 3, and we do
    not discuss those claims further.
    B. Stage 1
    The remedial work of Stage 1, on the other hand, is
    complete, so we can review plaintiffs’ claims about Stage 1 that
    16                                                    No. 13-2142
    are not directly affected by Stages 2 and 3. Plaintiffs raise three
    such claims about Stage 1 on appeal. First, they argue that the
    EPA failed to prepare the functional equivalent of a remedial
    investigation and feasibility study (“RI/FS”) before selecting
    the Stage 1 remedies as required by CERCLA because the EPA
    did not consider whether Stage 1 would stop all PCB releases
    into the environment. Second, plaintiffs argue that selecting
    Stage 1 violated CERCLA’s mandate to protect human health
    and the environment because Stage 1 did not stop all releases
    of PCBs into the environment. Finally, plaintiffs argue that the
    EPA violated CERCLA’s mandate that all agreements with
    parties be entered as consent decrees in the district court
    because the EPA did not modify the consent decree before
    implementing Stage 1.
    Our review of the EPA’s actions is limited. What is now
    § 310 of CERCLA permits citizen suits against the EPA only if
    they allege a failure to perform an act or duty under CERCLA
    “which is not discretionary.” 
    42 U.S.C. § 9659
    (a)(2). The
    Supreme Court has interpreted identical language in the
    Endangered Species Act citizen suit provision to allow review
    only of whether the EPA followed required decision-making
    procedures. See Bennett v. Spear, 
    520 U.S. 154
    , 172 (1997); see
    also Scott v. City of Hammond, 
    741 F.2d 992
    , 995 (7th Cir. 1984)
    (interpreting identical language in the Clean Water Act the
    same way). The substance of the EPA’s decisions, on the other
    hand, is at least partly discretionary, and therefore beyond the
    scope of these citizen suit provisions. Scott, 
    741 F.2d at 995
    (applying citizen suit provision of Clean Water Act). The scope
    of judicial review under these provisions is therefore much
    narrower than the scope of judicial review under the
    No. 13-2142                                                    17
    Administrative Procedure Act, which allows judicial review of
    the substance of an agency’s action under a deferential abuse-
    of-discretion standard. See Scott, 
    741 F.2d at 995
    ; Little Company
    of Mary Hospital v. Sebelius, 
    587 F.3d 849
    , 853 (7th Cir. 2009)
    (discussing the deferential standard of review under the
    Administrative Procedure Act).
    Plaintiffs have not argued that § 310(a)(2) should be
    interpreted differently from the citizen suit provisions in the
    Endangered Species Act and Clean Water Act, and we see no
    reason to do so. We thus read CERCLA’s citizen suit provision
    to allow review of claims regarding whether the EPA complied
    with required procedures under CERCLA, but not claims
    regarding the substance of the EPA’s decisions, which is a
    matter of discretion for the agency.
    Given these constraints on our review, we must make sure
    that plaintiffs’ claims are within the scope of § 310(a)(2) before
    analyzing them further. We agree with plaintiffs that the EPA
    had a non-discretionary duty to prepare the functional
    equivalent of an RI/FS for Stage 1. See 
    42 U.S.C. § 9616
    (requiring commencement of RI/FS for pre-1986 National
    Priorities List sites); 
    40 C.F.R. § 300.430
     (detailed requirements
    of an RI/FS); see also Frey v. Environmental Protection Agency,
    
    2006 WL 2849715
    , at *3–*5 (S.D. Ind. Sept. 29, 2006) (the RI/FS
    is the functional equivalent of the Environmental Impact
    Statement required by NEPA, so the RI/FS must be
    mandatory). We therefore can review whether the EPA
    18                                                          No. 13-2142
    completed the necessary components of an RI/FS.5 We also
    agree with plaintiffs that the EPA had a non-discretionary duty
    to select remedial actions that are protective of human health
    and the environment, 
    42 U.S.C. § 9621
    (b)(1), but again, we can
    review only whether the EPA determined that, in its
    estimation, Stage 1 was protective of human health and the
    environment. Finally, the EPA has a non-discretionary duty to
    enter party agreements as consent decrees in the district court,
    
    42 U.S.C. § 9622
    (d)(1)(A), so we are free to review whether it
    did so.
    We proceed to this limited review of the merits. We agree
    with the district court that the undisputed facts show that the
    EPA completed the functional equivalent of an RI/FS prior to
    selecting Stage 1. Contrary to plaintiffs’ assertions, the EPA did
    consider whether Stage 1, standing alone, would stop all PCB
    releases from the sites into the environment. It concluded that
    Stage 1 would significantly improve soil quality at the sites but
    that further remediation of the contaminated groundwater and
    sediment would be needed. In other words, the EPA
    considered Stage 1 to be a good first step toward preventing all
    PCB releases into the environment from the sites and explained
    5
    The EPA argues that it did not have to prepare the functional equivalent
    of an RI/FS for Stage 1 because the 1985 consent decree was adopted before
    the RI/FS requirement was added to the statute. However, Stage 1 was
    selected and the amendment to the consent decree was approved long after
    the RI/FS requirement was added in 1986. CERCLA subjects clean-up sites
    to the RI/FS requirement even if they were added to the National Priorities
    List before the requirement was enacted, see 
    42 U.S.C. § 9616
    (d), so the
    Bloomington sites were not somehow grandfathered out of the RI/FS
    requirement.
    No. 13-2142                                                   19
    that future steps would be needed to solve the problem fully.
    The RI/FS regulations did not require more. See 
    40 C.F.R. § 300.430
    ; Frey II, 
    403 F.3d at 834
     (recognizing that site clean-up
    often proceeds in stages).
    The EPA also determined that Stage 1 was protective of
    human health and the environment. Again, our review of that
    determination is deferential. It is clear that the EPA made the
    required determination. Here, the EPA concluded that Stage 1
    was protective of human health and the environment because
    it would reduce PCB contamination at the sites. That
    determination is sufficient to comply with CERCLA’s mandate,
    and plaintiffs’ challenge accordingly fails. To the extent that
    plaintiffs argue that the EPA did not protect human health and
    the environment because it did not select the most protective
    remedy, we note that the EPA is not required to do so. In fact,
    the EPA is explicitly directed to consider other factors,
    including cost, when selecting a remedy. 
    42 U.S.C. § 9621
    (b)(1).
    Finally, plaintiffs’ claim that the EPA violated CERCLA’s
    consent decree requirement is moot. Plaintiffs’ complaint asked
    the court to make the EPA amend the 1985 consent decree. The
    EPA has now filed and the district court has approved an
    amendment to the consent decree that incorporates all of the
    Records of Decision for each site. The court could no longer
    provide meaningful relief, so plaintiffs’ claim is moot. See
    Cornucopia Institute v. U.S. Department of Agriculture, 
    560 F.3d 673
    , 676 (7th Cir. 2009).
    Plaintiffs argue that rather than declaring their claim moot,
    we should find them to be prevailing parties and award
    attorney fees because the EPA amended the consent decree in
    20                                                    No. 13-2142
    response to their lawsuit. However, the Supreme Court has
    rejected this “catalyst theory” for most federal statutes that
    award attorney fees to prevailing parties. Buckhannon Board and
    Care Home, Inc. v. West Virginia Department of Health and Human
    Resources, 
    532 U.S. 598
    , 605 (2001); Walker v. Calumet City, 
    565 F.3d 1031
    , 1033–34 (7th Cir. 2009). Buckhannon held that a
    plaintiff does not become a prevailing party when her lawsuit
    brings about a voluntary change in the defendant’s conduct
    without a court order that materially alters the legal
    relationship between the parties. 
    Id.
    This circuit has adopted “a strong presumption that
    Buckhannon applies to each fee-shifting statute that awards fees
    to ‘prevailing parties.’” T.D. v. LaGrange School District No. 102,
    
    349 F.3d 469
    , 475 (7th Cir. 2003). For Buckhannon not to apply,
    the text, structure or legislative history of a particular statute
    must clearly indicate a different definition of “prevailing
    party.” 
    Id.
     Nothing in the text, structure, or legislative history
    of CERCLA clearly indicates that we should interpret its fee-
    shifting provision differently from that in Buckhannon, so we
    see no reason why it should not apply here. See City of
    Waukesha v. PDQ Food Stores, Inc., 
    500 F. Supp. 2d 1119
    , 1122
    (E.D. Wisc. 2007) (applying Buckhannon to CERCLA’s fee-
    shifting provision); Lucia A. Silecchia, The Catalyst Calamity:
    Post-Buckhannon Fee-Shifting in Environmental Litigation and
    a Proposal for Congressional Action, 
    29 Colum. J. Envtl. L. 1
    (2004) (assuming Buckhannon applies to fee-shifting under
    CERCLA and calling for legislation).
    Applying the Buckhannon definition of “prevailing party,”
    plaintiffs’ claim for attorney fees fails. Plaintiffs’ lawsuit did
    No. 13-2142                                                       21
    not result in a court-ordered change in the legal relationship
    between the plaintiffs and the EPA. Even if we accept plaintiffs’
    contention that the EPA amended the 1985 consent decree in
    response to their lawsuit, plaintiffs were not parties to the
    enforcement action, so the decree did not change their legal
    relationship with the EPA. Plaintiffs’ claim regarding the
    consent decree is therefore moot, and they are not prevailing
    parties on that claim.
    C. Recusal
    Finally, plaintiffs argue that the district judge should have
    recused himself from this citizen suit because he had ruled on
    similar issues in the enforcement action and was therefore
    biased against them. The argument has no merit. For starters,
    the enforcement action addressed similar issues because
    plaintiffs inserted those issues into the enforcement action
    through both the public comment process and their statement
    to the court. Plaintiffs’ attempts to cast their participation in the
    public comment period and enforcement action and the judge’s
    consideration of their views in resolving the enforcement
    action as a due process violation are not at all persuasive.
    Second, and more fundamental, information a judge has
    gleaned from prior judicial proceedings is not considered
    extrajudicial and simply does not require recusal. See United
    States v. Barnes, 
    909 F.2d 1059
    , 1072 (7th Cir. 1990) (alleged bias
    caused by past cases involving the judge and moving party
    were not grounds for recusal); United States v. Sammons, 
    918 F.2d 592
    , 599 (6th Cir. 1990) (extrajudicial bias cannot come
    from the judge’s prior involvement in related cases).
    22                                                    No. 13-2142
    Judges frequently preside over related cases, including
    successive appeals and remands between the same parties. This
    common practice does not violate the Due Process Clauses of
    the Fifth or Fourteenth Amendments. See, e.g., Withrow v.
    Larkin, 
    421 U.S. 35
    , 48–49 (1975), quoting FTC v. Cement
    Institute, 
    333 U.S. 683
    , 702–03 (1948). Finally, plaintiffs point to
    no evidence that the district judge displayed “deep-seated bias
    or antagonism that would make fair judgment impossible,” as
    required to justify recusal for bias under 
    28 U.S.C. § 455
    .
    Liteky v. United States, 
    510 U.S. 540
    , 555 (1994). Simply put,
    there is no reason the district judge should have recused
    himself from this case. His decision not to do so did not deny
    plaintiffs due process of law.
    The judgment of the district court dismissing this action is
    AFFIRMED in all respects.
    

Document Info

Docket Number: 13-2142

Citation Numbers: 751 F.3d 461, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20102, 78 ERC (BNA) 1473, 2014 U.S. App. LEXIS 8238, 2014 WL 1713409

Judges: Flaum, Hamilton, Kapala

Filed Date: 5/1/2014

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (23)

Sarah E. Frey, Kevin Enright, and Protect Our Woods, Inc. v.... , 270 F.3d 1129 ( 2001 )

United States v. Michael Lee Sammons , 918 F.2d 592 ( 1990 )

City of Waukesha v. PDQ Food Stores, Inc. , 500 F. Supp. 2d 1119 ( 2007 )

david-schalk-and-ronald-t-smith-v-william-k-reilly-administrator-us , 900 F.2d 1091 ( 1990 )

Jenny Wernsing, Charles Bingaman and Troy Cannon v. Odell ... , 423 F.3d 732 ( 2005 )

Withrow v. Larkin , 95 S. Ct. 1456 ( 1975 )

sarah-e-frey-kevin-enright-and-protect-our-woods-inc-v-environmental , 403 F.3d 828 ( 2005 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

Liteky v. United States , 114 S. Ct. 1147 ( 1994 )

T.D. v. Lagrange School District No. 102 , 3 A.L.R. Fed. 2d 755 ( 2003 )

Cornucopia Institute v. United States Department of ... , 560 F.3d 673 ( 2009 )

Walker v. CALUMET CITY, ILL. , 565 F.3d 1031 ( 2009 )

Pollack v. United States Department of Defense , 507 F.3d 522 ( 2007 )

North Shore Gas Company v. Environmental Protection Agency , 930 F.2d 1239 ( 1991 )

Village of DePue, Ill. v. Exxon Mobil Corp. , 537 F.3d 775 ( 2008 )

Henderson v. Shinseki , 131 S. Ct. 1197 ( 2011 )

William J. Scott, on His Own Behalf and on Behalf of All ... , 741 F.2d 992 ( 1984 )

Reed Elsevier, Inc. v. Muchnick , 130 S. Ct. 1237 ( 2010 )

Arbaugh v. Y & H Corp. , 126 S. Ct. 1235 ( 2006 )

Little Company of Mary Hospital v. Sebelius , 587 F.3d 849 ( 2009 )

View All Authorities »