Washington Group v. Bell, Boyd & Lloyd ( 2004 )


Menu:
  •                              In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 03-2389
    WASHINGTON GROUP INTERNATIONAL, INC.,
    Plaintiff-Appellant,
    v.
    BELL, BOYD & LLOYD LLC,
    Defendant-Appellee.
    ____________
    Appeal from the United States District Court
    for the Northern District of Illinois, Eastern Division.
    No. 02 C 8974—James B. Zagel, Judge.
    ____________
    ARGUED OCTOBER 27, 2003—DECIDED SEPTEMBER 9, 2004
    ____________
    Before RIPPLE, DIANE P. WOOD, and EVANS, Circuit
    Judges.
    DIANE P. WOOD, Circuit Judge. While the technical issue
    before us concerns the relation between this litigation and
    an earlier bankruptcy proceeding, the underlying dispute
    alleges that the firm of Bell, Boyd & Lloyd (Bell Boyd) com-
    mitted legal malpractice in conjunction with a mechanic’s
    lien. Washington Group, the successor to Raytheon Engineers
    & Constructors, Inc. (Raytheon), claimed that Bell Boyd
    negligently handled both the drafting of certain liens and
    the litigation related to those liens. In response, Bell Boyd
    claimed that all the issues Raytheon was raising in this
    case had been resolved against it in an adversary proceed-
    2                                                   No. 03-2389
    ing before the Delaware bankruptcy court in a case between
    Raytheon and Acme, a client for whom Raytheon was
    building a plant. The district court agreed with Bell Boyd
    and dismissed all claims. We affirm.
    I
    In 1994, Raytheon entered into a contract with Acme
    Steel Company for the construction of a steel mill. Raytheon
    in turn signed a subcontract with United Steel Erectors,
    Inc. (USE) for construction of the buildings at the steel mill.
    USE enlisted Calumet Construction Corporation (Calumet)
    for the erection of the structural steel for the steel mill build-
    ings. In 1996, Calumet filed a sub-subcontractor’s claim for
    a mechanic’s lien related to its work on the steel mill. It
    followed up on that action with a lawsuit in February 1997
    to enforce its mechanic’s lien against Acme, Raytheon, and
    USE (the Calumet litigation). In March 1997, USE filed its
    own mechanic’s lien and then cross-claimed against
    Raytheon and Acme seeking to enforce that lien.
    Faced with this array of disputes, Raytheon retained Bell
    Boyd to represent it in the Calumet litigation and to protect
    its rights vis-à-vis Acme. Over a year later, in September
    1998, Acme voluntarily filed in the Delaware bankruptcy
    court for Chapter 11 relief. Later, on November 13, 1998,
    Bell Boyd filed a $12,006,799 mechanic’s lien (the Acme
    Lien) on Raytheon’s behalf in connection with its work on
    the steel mill. The property description Bell Boyd used in
    the Raytheon lien was the same description as the one that
    had been used in the Calumet and USE liens. Shortly after
    filing the lien, Bell Boyd withdrew from further representa-
    tion of Raytheon because of a conflict of interest.
    On February 7, 2000, Acme brought an adversary action
    in its bankruptcy proceeding seeking a declaration that
    Raytheon’s Acme Lien was invalid because (1) the property
    description was incorrect; and (2) even if the property de-
    No. 03-2389                                                  3
    scription was acceptable, that the Illinois Mechanic’s Lien
    Act, 770 ILCS 60/6, requires completion of work within three
    years of commencement for a lien to be valid. Raytheon
    vigorously defended the validity of the property description,
    ultimately convincing the bankruptcy court that the
    description was valid. The bankruptcy court determined, as
    a matter of law, that the property description included in
    the November 1998 lien was “ ‘sufficiently correct’ to put
    anyone on notice of [Raytheon’s] claims” and “to effect a lien
    on [Acme’s] Plant.” In re Acme Metals, Inc., 
    257 B.R. 714
    , 720-
    21 (Bankr. D. Del. 2000). Nonetheless, the bankruptcy court
    held the lien invalid because Raytheon had not completed
    the work within three years of commencement. 
    Id. at 723.
    While the case was on appeal, Acme and Raytheon settled
    both their adversary proceeding and the Calumet litigation.
    The appeal was dismissed with prejudice on April 22, 2002.
    On December 11, 2002, Raytheon’s successor, the Wash-
    ington Group (an Ohio corporation with its principal place
    of business in Ohio) brought this action under the diversity
    jurisdiction, alleging that Bell Boyd (an Illinois limited
    liability company, none of whose members are citizens of
    Ohio) had committed malpractice. Raytheon claimed that Bell
    Boyd should have discovered the incorrect property descrip-
    tion in the Calumet and USE liens in 1997 and that Bell
    Boyd prepared Raytheon’s 1998 lien negligently because it
    used that same incorrect property description. Raytheon
    also claimed that Bell Boyd was negligent in failing to advise
    Raytheon that the three-year rule might invalidate
    Raytheon’s lien. In addition to damages, Raytheon sought
    reimbursement of the attorneys’ fees it spent litigating the
    bankruptcy and Calumet cases.
    Ruling on Bell Boyd’s 12(b)(6) motion, the district court
    held that the bankruptcy court’s conclusion that the prop-
    erty description was valid barred Raytheon’s claims related
    to the property description. The district court also held that
    Bell Boyd was not negligent in failing to advise Raytheon of
    4                                                No. 03-2389
    the three-year rule. Because Raytheon did not retain Bell
    Boyd until close to the end of the three-year period,
    Raytheon could not have taken any action based on Bell
    Boyd’s advice that would have prevented the application of
    the rule to its lien.
    Before this court, Raytheon makes two principal argu-
    ments: first, that the property description was indeed in-
    valid and that it should not be bound by the bankruptcy
    court’s conclusion on that point; and second, that an Illinois
    court might have interpreted the three-year rule differently
    than the bankruptcy court did, and the possibility of such
    a discrepancy proves Bell Boyd was negligent in not
    informing Raytheon of the rule’s effect. We find it unneces-
    sary to consider the first point in detail, because we con-
    clude that Raytheon was bound by the bankruptcy court’s
    ruling on the three-year rule, and that it is plain on the face
    of the pleadings that nothing Bell Boyd could have done,
    given its late entry into the fray, could have made a differ-
    ence.
    II
    An action for legal malpractice in Illinois requires the
    plaintiff to prove five elements: “(1) an attorney-client rela-
    tionship; (2) a duty arising out of that relationship; (3) a
    breach of that duty; (4) causation; and (5) actual damages.”
    Griffin v. Goldenhersh, 
    752 N.E.2d 1232
    , 1238 (Ill. App.
    2001). Raytheon’s malpractice claims against Bell Boyd
    thus depended upon, among other things, the possibility of
    finding that Bell Boyd’s negligence with respect to the al-
    legedly flawed mechanic’s lien caused some harm to Raytheon.
    Raytheon believes that if Bell Boyd had discovered that the
    property description was incorrect earlier or if Bell Boyd had
    alerted Raytheon to the three-year requirement, Raytheon
    would have prevailed in the Calumet litigation and would
    never have been dragged into bankruptcy court— or at least
    No. 03-2389                                                  5
    not to the degree that it was. Instead, it asserts, Bell Boyd’s
    negligence forced Raytheon to defend itself in the Calumet
    litigation and ultimately to suffer substantial losses.
    Raytheon has argued that the bankruptcy court erred in
    its application of the three-year rule in the Mechanic’s Lien
    Act. Bell Boyd responds that it is too late in the day to
    challenge that ruling, because it is entitled to preclusive
    effect in the present case. Because we are considering what
    effect should be given to the judgment of the Delaware
    bankruptcy court, which is a unit of the district court, see
    28 U.S.C. § 151, we apply the federal common law of issue
    preclusion. Under that law, a party seeking to invoke
    preclusion must show four things:
    1) the issue sought to be precluded must be the same as
    that involved in the prior action, 2) the issue must have
    been actually litigated, 3) the determination of the issue
    must have been essential to the final judgment, and 4)
    the party against whom estoppel is invoked must be
    fully represented in the prior action.
    People Who Care v. Rockford Bd. of Educ., 
    68 F.3d 172
    , 178
    (7th Cir. 1995); La Preferida, Inc. v. Cerveceria Modelo, S.A.,
    
    914 F.2d 900
    , 905-06 (7th Cir. 1990). Raytheon challenges
    only the first requirement—that the issue sought to be pre-
    cluded in the present case is not the same as that decided
    in the bankruptcy court. (When Bell Boyd responded to the
    motion under Rule 12(b)(6) with a claim of collateral estop-
    pel, Raytheon responded with arguments on the merits of
    that point. It did not assert that Bell Boyd needed to plead
    preclusion as an affirmative defense under Fed. R. Civ. P.
    8(c), and thus we attach no weight to the procedural short-
    cut that occurred here. We do, however, construe the facts
    in the light most favorable to Raytheon, as is normal in
    reviewing a decision under Rule 12(b)(6).)
    In order to resolve this element of issue preclusion, we
    examine first what was before the bankruptcy court, and
    6                                                No. 03-2389
    then what was before the district court. Raytheon filed two
    secured proofs of claim in the bankruptcy proceeding, each
    in the amount of $8,820,252. It asserted that its original
    mechanic’s lien secured these claims. Acme responded that
    Raytheon’s claims actually were unsecured because
    Raytheon filed the lien improperly. Acme offered three ar-
    guments in support of this position, one of which was that
    the lien was invalid because it failed to meet the three-year
    requirement of the Illinois Mechanic’s Lien Act, 770 ILCS
    60/6.
    Section 6 of the Illinois Mechanic’s Lien Act requires com-
    pletion of work within three years of commencement in order
    for a mechanic’s lien to be valid. The question whether the
    Raytheon liens complied with this rule was precisely the
    issue presented to the bankruptcy court. Indeed, this is the
    reason why the bankruptcy court ultimately ruled that the
    lien was invalid. 
    See 257 B.R. at 722
    . The bankruptcy court
    pointed out that the parties entered into the contract at
    issue in July 1994, and the contract specified a guaranteed
    completion date of June 16, 1997. 
    Id. The contract
    was not
    in fact completed by that date, nor were either of
    Raytheon’s mechanic’s liens filed within four months of the
    completion date. 
    Id. (In fact,
    as we noted earlier, Bell Boyd
    did not file the lien until November 13, 1998, well outside
    the three-year period.)
    Raytheon has already had its day in court with respect to
    the question whether the lien complied with the three-year
    rule, and it lost. That much is therefore established for
    purposes of the liens at issue here. The only remaining
    issue is whether Raytheon has stated a claim against Bell
    Boyd for negligently failing to counsel it about the effects of
    the three-year rule. The district court pointed out that
    Raytheon did not even hire Bell Boyd until more than two
    years of the contract had passed. Raytheon failed to allege
    any facts suggesting that construction would be completed
    by the statutory three-year deadline, or that, had Bell Boyd
    No. 03-2389                                                   7
    alerted it to that rule earlier, it could have sped up con-
    struction. Because Raytheon could take no action to stave
    off the effects of the three-year rule even had Bell Boyd told
    it about the rule, Bell Boyd’s failure to do so could not have
    caused any damage to Raytheon.
    III
    We cannot improve on the conclusion that the district
    court succinctly stated: “. . . [A]ll of the elements of collat-
    eral estoppel are clearly met here, and there is no showing
    that the defendant’s actions were the proximate cause of
    any damage to Raytheon . . . .” The same reasons are
    enough to defeat Raytheon’s request for attorneys’ fees it
    paid allegedly because Bell Boyd was negligent. Finally, we
    deny Raytheon’s motion to certify these issues to the Illinois
    Supreme Court, as we see no issues that meet that court’s
    standards for certification. See Ill. S. Ct. R. 20(a). We
    AFFIRM the judgment of the district court.
    A true Copy:
    Teste:
    ________________________________
    Clerk of the United States Court of
    Appeals for the Seventh Circuit
    USCA-02-C-0072—9-9-04