Cichon, Michael C. v. Exelon Generation Co ( 2005 )


Menu:
  •                             In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 03-3724
    MICHAEL C. CICHON,
    Plaintiff-Appellant,
    v.
    EXELON GENERATION COMPANY, L.L.C.,
    Defendant-Appellee.
    ____________
    Appeal from the United States District Court for
    the Northern District of Illinois, Eastern Division.
    No. 02 CV 3441—Charles P. Kocoras, Chief Judge.
    ____________
    ARGUED APRIL 14, 2004—DECIDED MARCH 21, 2005
    ____________
    Before BAUER, COFFEY and KANNE, Circuit Judges.
    COFFEY, Circuit Judge. Michael Cichon was employed as
    a “Unit Supervisor” for Exelon Generation Company at its
    Byron, Illinois, nuclear power plant, until he was removed
    from the position because Exelon believed that he lacked
    the necessary leadership qualities. A few weeks later,
    Cichon applied for a different position with Exelon at their
    Byron plant, as a “Turbine Project Manager,” but was not
    hired because of his lack of leadership skills. Thereafter,
    Cichon filed suit against Exelon under § 215(a)(3) of the
    Fair Labor Standards Act (“FLSA”), 
    29 U.S.C. §§ 201
     et seq.,
    alleging that Exelon had removed him from his Unit
    2                                                    No. 03-3724
    Supervisor position and refused to hire him for the Turbine
    Project Manager position in retaliation for his having filed
    a prior lawsuit against Exelon under the FLSA.1 The dis-
    trict court granted summary judgment to Exelon, finding
    Exelon had offered legitimate, non-retaliatory reasons for
    its decision to remove him as a Unit Supervisor and de-
    clining to hire him as a Turbine Project Manager and went
    on to conclude that Cichon had failed to demonstrate that
    these reasons were pretextual. Cichon appeals, we affirm.
    I. BACKGROUND
    Cichon was employed at Exelon’s Byron plant for fifteen
    years in various non-managerial positions until he trans-
    ferred to a position as a Unit Supervisor in the plant’s
    Operations Department (“OD”) in 1998. As a Unit
    Supervisor, Cichon served as a mid-level manager and also
    assisted in the hands-on operation of the plant’s two nu-
    clear reactors. In January of 2000, management became
    concerned with Cichon’s leadership and supervisory skills,
    and his repeated failure to follow plant procedures. On June
    26, 2001 Cichon gave his supervisors further cause to
    question his leadership abilities and adherence to plant pro-
    cedures when he performed poorly during a reactor shut-
    down. On that date, due to a mechanical malfunction, one
    of the reactors had to be shut down. Once a reactor is shut
    down, the “feedwater” pump2 that supplies feedwater to the
    core of the nuclear reactor temporarily discontinues func-
    1
    Section 215(a)(3) of the FLSA states, in relevant part, that “it
    shall be unlawful for any person . . . to discharge or in any other
    manner discriminate against any employee because such em-
    ployee has filed any complaint or instituted or caused to be
    instituted any proceeding under or related to [the FLSA].”
    2
    The feedwater pump supplies feedwater to the reactor core of a
    nuclear reactor, which the reactor then heats into steam to turn
    the turbine-generator, producing electricity.
    No. 03-3724                                                3
    tioning, requiring the use of an “auxiliary feedwater pump”
    to keep the feedwater flowing into the reactor core in order
    that the steam generator can continue to remove heat from
    the reactor core. When the reactor is brought back on line,
    the auxiliary feedwater pump is manually shut down once
    the main operating pump is functioning normally. Cichon’s
    role in the process of bringing the reactor back on line was
    to order the auxiliary feedwater pump shut down when the
    main feedwater pump was operational. Cichon ordered the
    premature shutdown of an auxiliary pump before the main
    pump was ready to take over, a procedural gaffe that
    caused the auxiliary pump to restart unexpectedly. The
    error was serious enough that Exelon was forced to conduct
    an internal investigation into Cichon’s premature restart of
    the auxiliary feedwater pump and file a report with the
    Nuclear Regulatory Commission. Cichon’s poor performance
    in this critical and potentially hazardous situation resulted
    in his being formally reprimanded for failing to follow
    procedural guidelines and his being warned, in writing, that
    he needed to improve his performance, comply fully with
    Exelon’s procedures and exhibit improved leadership on the
    job or he would be subject to further discipline, up to and
    including termination.
    Because of Cichon’s serious error and other problems at
    the plant caused by OD personnel failing to comply with
    plant procedures, the plant’s upper management moved in
    to rectify the situation and directed a “re-alignment” of the
    OD through a “Leadership Assessment Process” (“LAP”).
    The LAP required all supervisory-level employees in the
    department to successfully complete a series of individual
    interviews in order to retain their positions.
    On September 10, 2001, as part of the LAP Cichon was
    interviewed by an internal panel comprised of upper-level
    supervisors in the OD along with representatives from the
    Byron nuclear plant’s human resources department. During
    the interview Cichon and other managers were asked a
    4                                                   No. 03-3724
    series of questions designed to ascertain whether they
    possessed the necessary leadership and behavioral skills
    that Exelon expected of its management-level employees.
    The questions were framed in a manner designed to gauge
    “competencies”3 in eleven different categories of “fundamen-
    tals.”4 In order for Cichon to retain his position as Unit
    Supervisor, he was required to demonstrate to the inter-
    viewing panel that he was at least “competent” as opposed
    to “developmental” or only developmentally qualified. Upon
    completion of the interviewing process, the LAP panel tallied
    up the scores and determined that Cichon demonstrated the
    required competency in only three of the eleven categories.
    Accordingly, the panel concluded that although Cichon
    might be an “acceptable candidate [for the] short term
    [because he] has the technical ability to perform the job[, in
    3
    In accordance with the parameters given to the LAP panel,
    “competency” level was rated as either a “strength,” a “mere com-
    petence,” or as a “developmental need.” Concerning employees who
    scored in the “developmental need” range of the evaluation cri-
    teria, Diana Sorfleet, Manager of Employee Relations at Exelon
    testified that “[w]e looked at which [fundamentals] were difficult
    to develop, and based on the improvements that we needed, we
    made decisions to say that if an employee has, you know, two or
    three of these [fundamentals] that all need development, we don’t
    have the time or the money to invest in developing those [fun-
    damentals] when we’re in a turn-around situation.” Therefore, the
    ranking of an employee’s performance in a given area as a
    “developmental need” was the equivalent of a deficient or un-
    satisfactory mark in that given area.
    4
    The eleven categories of “fundamentals” required of Unit
    Supervisors were: 1) “Drives for Results”; 2) “Actively
    Communicates”; 3) “Models our Values”; 4) “Builds Relationships”;
    5) “Provides Direction”; 6) “Develops Others”; 7) “Fosters Team-
    work and Collaboration”; 8) “Motivates and Inspires Passion”; 9)
    “Selects Talent”; 10) “Leverages Resources”; and 11) “Motivational
    Fit.”
    No. 03-3724                                                  5
    the] long-term [he] does not possess the leadership abilities
    that provide a good motivational fit for the position.” On
    October 1, 2001, after all the supervisory-level employees in
    the OD had been interviewed, the LAP panel met and
    rendered its final decisions as to those who qualified to staff
    the Unit Supervisor position. The committee determined
    that because Cichon had failed to meet the minimum
    competency requirements to qualify for a supervisory
    position he should be removed from his Unit Supervisor
    position.
    Prior to the committee’s determination, on September 25,
    2001, Cichon had filed a lawsuit against Exelon under the
    FLSA, challenging the recent changes Exelon had instituted
    in its overtime pay scale for its management-level employ-
    ees.5 On October 23, 2001, Cichon was officially removed as
    a Unit Supervisor. At that time, Cichon was advised that
    his removal was precipitated by several factors; his poor
    performance in his LAP interviews, his failure to follow the
    company’s reactor start-up procedures in June of 2001 and
    his subsequent failure to “demonstrate[] [a] behavior
    change toward embracing and institutionalizing standards
    and fundamentals.”
    After his removal as a Unit Supervisor, Cichon had, in
    accordance with Exelon’s policy, sixty days to find another
    position within the company before he was subject to final
    termination.6 During this time period, Cichon applied for
    the “Turbine Project Manager” position after Mike Kelly,
    the individual in charge of the turbine projects at Exelon’s
    Illinois plants, informed him that the position was open and
    5
    Upper management at the Byron plant were not notified about
    Cichon’s lawsuit until October 2, 2001.
    6
    Cichon continued to receive his previous salary and benefits
    during this 60-day time frame.
    6                                                 No. 03-3724
    even went further and informed Cichon that, in his opinion,
    he felt that he might be a “good fit” for the position.
    Cichon, because of his technical qualifications, was chosen
    as one of the four finalists for the position. However, Exelon’s
    management team sought to staff the position based on
    more than technical skills alone and was looking for can-
    didates with superior leadership, behavioral and manage-
    ment skills. As part of the selection process, the candidates
    had to score well in two interviews before two separate
    panels of interviewers. The panelists were assigned to ask
    each of the interviewees a series of questions and, based
    on the applicants’ responses, determine which one of the
    candidates possessed the superior leadership and behav-
    ioral skills required for the job. Cichon, along with three
    other employees participated in the interviews, and placed
    second out of the four candidates interviewed. Tim Nolan
    received the top score and was accordingly awarded the
    position, rather than Cichon or the other candidates who
    had scored lower.
    Kelly, who had advised Cichon of the Turbine Project
    Manager opening, was one of the panelists who interviewed
    Cichon and the other candidates for the position. The record
    demonstrates that, along with his interviewing partner,
    Kelly scored Cichon lower than did the other team while
    rating him on identical criteria. Kelly stated in deposition
    testimony that although he learned of Cichon’s having filed
    a FLSA lawsuit during the interview with Cichon, that
    knowledge did not affect how Cichon was rated, nor did it
    affect the interviewing teams’ collective final decision to
    hire Nolan. Kelly further stated that Nolan was hired for
    the position rather than Cichon solely because Nolan
    achieved higher scores overall during the interview and rat-
    ing process. Following Cichon’s failure to obtain the Turbine
    Project Manager position, he applied for other positions with
    Exelon, and, on December 12, 2001, accepted a position as
    a dispatcher at a Joliet facility operated by a subsidiary of
    Exelon’s parent company.
    No. 03-3724                                                   7
    On May 13, 2002, Cichon filed his second suit against
    Exelon under the FLSA, alleging that Exelon’s decisions to
    remove him from his Unit Supervisor position and not hire
    him for the Turbine Project Manager position were made in
    retaliation for his filing of the initial FLSA overtime
    pay lawsuit.7 After discovery, Exelon moved for summary
    judgment and also filed a document entitled “Statement of
    Uncontested Material Facts,” as required pursuant to the
    United States District Court for the Northern District of
    Illinois’ Local Rule 56.1. Cichon responded by filing a brief
    in opposition to Exelon’s motion for summary judgment, and
    included with this filing a response to their “Statement of
    Uncontested Material Facts.” In this document, Cichon
    addressed Exelon’s proposed facts line-by-line and admitted
    some of the facts, but denied the accuracy of a large number
    of Exelon’s statements of facts. Our review of Cichon’s re-
    sponse establishes that a great many of Cichon’s written
    attempts in opposition to Exelon’s statement of material
    facts amount to nothing more than conclusory statements,
    unaccompanied by required record citations while others
    contain only cursory analysis with citations to portions of
    the record that failed to support his denials, constituting a
    violation of Local Rule 56.1. In his response, Cichon also set
    forth a number of his own proposed facts, which he con-
    tended required a denial of Exelon’s motion for summary
    judgment. However, Cichon failed to list these “additional
    facts that require the denial of summary judgment” in a
    separate statement of facts document as required under
    Local Rule 56.1. Consequently, when the district court ad-
    dressed Exelon’s motion for summary judgment, the judge
    properly refused to accept a majority of Cichon’s proposed
    facts in light of the fact that he had failed to comply with
    Local Rule 56.1 when he: “(1) [made] new factual assertions
    7
    Cichon’s overtime pay lawsuit was dismissed with prejudice, on
    the plaintiff ’s own motion, on September 12, 2002.
    8                                                No. 03-3724
    in [his] response without filing a Statement of Additional
    Facts in violation of Local Rule 56.1(b)(3)(B); (2) improperly
    den[ied] the accuracy of a large number of Exelon’s facts as
    asserted with evasive responses in violation of Local Rule
    56.1(b)(3)(A); and (3) support[ed] [his] responses with self-
    serving affidavits or unauthenticated documents.”
    Relying primarily on Exelon’s properly submitted facts,
    the court granted summary judgment to Exelon. In con-
    junction with this conclusion the court assumed, for the
    purposes of its analysis, that Cichon had established a
    prima facie case of retaliation. However, the court went on
    to find that Exelon had ultimately carried its burden by
    offering legitimate, non-discriminatory reasons for both re-
    moving Cichon from his Unit Supervisor position and failing
    to subsequently hire him for the Turbine Project Manager
    opening. In doing so Exelon argued that Cichon was removed
    from the Unit Supervisor position because of his failure to
    demonstrate proper supervisory and leadership skills, both
    in his day-to-day job performance and in his responses to
    questions posed to him during the interviews conducted by
    the LAP; and furthermore that Nolan was hired rather than
    Cichon for the Turbine Project Manager position because
    Nolan was rated as the “more qualified” candidate in the
    evaluation proceedings conducted by the interviewing panels.
    The court went on to hold Cichon had failed to demonstrate
    that Exelon’s proffered legitimate business reasons for
    terminating Cichon and subsequently failing to hire him for
    another position at the Byron Plant were pretextual, and
    entered judgment for Exelon. Cichon appeals.
    II. ISSUES
    Cichon contends that the district court abused its dis-
    cretion when it determined that he failed to comply with
    Local Rule 56.1 and discounted a great majority of the facts
    he set forth in response to Exelon’s motion for summary
    No. 03-3724                                                     9
    judgment. Cichon also argues that the district court’s grant-
    ing of summary judgment for the defendant was improper
    because he had demonstrated that the reasons Exelon
    offered for removing him from his Unit Supervisor position
    and then failing to hire him for the Turbine Project Manager
    position were pretextual.
    III. ANALYSIS
    A. Cichon’s Failure to Comply with Local Rule 56.1
    Cichon claims that the district court abused its discretion
    when it determined that he failed to comply with the
    provisions of Local Rule 56.1 by not including a separate
    statement of additional facts and discounted, or refused to
    consider, most of the facts that he submitted in response to
    Exelon’s motion for summary judgment. Cichon posits that
    if the court had accepted his set of proposed “facts,” it would
    have concluded that summary judgment in favor of Exelon
    was not proper.8 We review a district court’s decision
    concerning whether a litigant complied with a local rule,
    such as Local Rule 56.1, for an abuse of discretion. Ammons
    v. Aramark Unif. Servs., Inc., 
    368 F.3d 809
    , 817 (7th Cir.
    2004). Specifically as to Local Rule 56.1, “[w]e have . . .
    repeatedly held that a district court is entitled to expect
    8
    The two “facts” that Cichon contends precluded summary
    judgment are his allegations that: 1) he was “the only [Unit
    Supervisor] discharged as a result of the [LAP]”; and 2) “both
    selecting officials [for the Turbine Project Manager position]
    admitted that [he] was the best qualified candidate for the job.”
    Appellant’s Br. at 20. For the sake of completeness, we have
    examined the record thoroughly and can find no support for these
    allegations aside from Cichon’s own self-serving and unauthenti-
    cated statements, which are insufficient to create a genuine issue
    of material fact. See Rogers v. City of Chicago, 
    320 F.3d 748
    , 751
    (7th Cir. 2003).
    10                                                No. 03-3724
    strict compliance with [Local] Rule 56.1.” 
    Id.
     (citing
    Bordelon v. Chicago Sch. Reform Bd. of Trs., 
    233 F.3d 524
    ,
    527 (7th Cir. 2000) and Waldridge v. American Hoechst
    Corp., 
    24 F.3d 918
    , 922 (7th Cir. 1994)). Local Rule 56.1
    requires specifically that a litigant seeking to oppose a
    motion for summary judgment file a response that contains
    a separate “statement . . . of any additional facts that require
    the denial of summary judgment.” Local Rule 56.1(b)(3)(B);
    see also Ammons, 
    368 F.3d at 817
    ; Smith v. Lamz, 
    321 F.3d 680
    , 682 n.2 (7th Cir. 2003); Midwest Imports, Ltd. v. Coval,
    
    71 F.3d 1311
    , 1312 (7th Cir. 1995). A district court does not
    abuse its discretion when, in imposing a penalty for a
    litigant’s non-compliance with Local Rule 56.1, the court
    chooses to ignore and not consider the additional facts that
    a litigant has proposed. Midwest Imports, 
    71 F.3d at 1316
    .
    Indeed, as we have stated on a number of occasions, “[a] local
    rule of a federal district court is written by and for district
    judges to deal with the special problems of their court, and
    we are disposed therefore to give a district judge’s interpreta-
    tion of his court’s local rules . . . considerable weight.” 
    Id.
    Cichon failed to file a statement of additional facts in op-
    posing Exelon’s motion for summary judgment, and admits
    in his brief that he only identified his proposed facts “in
    [his] response to [Exelon’s] statement of facts” rather than
    filing a separate statement of proposed facts. In defense of
    his failure to submit his own statement of additional facts,
    Cichon mistakenly takes the position that “[t]here was no
    need to make such a submission,” because the Northern
    District of Illinois’ Local Rule 56.1 does not require him to
    do so. However, as we have noted above, Local Rule 56.1 does
    require that he make such a submission, that is, as long as
    he wants the court to consider his proposed “facts” when
    determining whether a dispute over facts material to the
    case exists that requires a denial of summary judgment.
    Because Cichon failed to comply with Rule 56.1 which re-
    quires that a litigant file a separate statement of additional
    No. 03-3724                                                11
    facts, we hold that it was not an abuse of discretion for the
    district court to ignore most of Cichon’s proposed “facts”
    when ruling on Exelon’s motion for summary judgment. 
    Id.
    Accordingly, for the purposes of this appeal we will consider
    only those facts that the trial judge found not to be excluded
    under Rule 56.1 when addressing the remainder of Cichon’s
    claims. 
    Id. at 1312
    .
    B. Cichon’s Retaliation Claims
    Cichon next argues that it was improper for the trial
    judge to grant summary judgment in Exelon’s favor because
    he successfully demonstrated that the reasons Exelon offered
    for removing him from his Unit Supervisor position and
    then refusing to hire him for the Turbine Project Manager
    position were pretextual. We review de novo the district
    court’s grant of summary judgment to Exelon. Sphere Drake
    Ins. Ltd. v. Am. Gen. Life Ins. Co., 
    376 F.3d 664
    , 668 (7th
    Cir. 2004). To establish a claim under § 215(a)(3) of the
    FLSA, Cichon has the burden of demonstrating that Exelon
    engaged in retaliatory conduct, either through the direct or
    indirect method of proof. See Scott v. Sunrise Healthcare
    Corp., 
    195 F.3d 938
    , 940 (7th Cir. 1999). Cichon concedes
    that he has no direct evidence that Exelon removed him
    from the Unit Supervisor position and failed to hire him for
    the Turbine Project Manager position simply because he
    filed a lawsuit against Exelon under the FLSA. Thus,
    Cichon frames his argument according to the indirect
    method of proof under the familiar burden-shifting frame-
    work prescribed by the Supreme Court in McDonnell
    Douglas, as adapted for use in the context of retaliation
    claims. Stone v. City of Indianapolis Pub. Utils. Div., 
    281 F.3d 640
    , 644 (7th Cir. 2002); see McDonnell Douglas Corp.
    v. Green, 
    411 U.S. 792
     (1973).
    12                                               No. 03-3724
    1. Removal from the Unit Supervisor Position
    Cichon argues that the court improperly granted summary
    judgment to Exelon on his allegation that he was retaliated
    against when removed from the Unit Supervisor position
    and asserts that he produced sufficient evidence of dis-
    crimination to demonstrate a disputed issue of fact as to
    whether Exelon’s proffered reason for removing him from
    the position was pretextual. In order to reach the pretext
    stage of the McDonnell Douglas analysis, Cichon was ini-
    tially required to present a prima facie case of retaliation by
    demonstrating, among other things, that “he was per-
    forming his job in a satisfactory manner.” Stone, 
    281 F.3d at 644
    . Although the district court assumed that Cichon met
    this requirement, after review of the record we are forced to
    disagree and are convinced that Cichon was not performing
    his job in a satisfactory manner at the time he was termi-
    nated from his position at Exelon, and thus failed to clear
    the initial hurdle of making out a prima facie case of
    discrimination.
    Beginning in January of 2000, Cichon’s supervisors started
    to question his leadership and supervisory skills, and be-
    came aware that Cichon had often failed to follow required
    safety procedures at Exelon’s Byron plant. Indeed, in
    June 2001, Cichon’s failure to adhere to plant procedures
    caused a very serious problem when he improperly shut
    down the reactor’s auxiliary feedwater pump, and caused an
    undesirable chain of events that ended in Exelon’s filing of
    a report with the Nuclear Regulatory Commission. See
    supra pp. 2-3. And, perhaps more damaging to Cichon’s case,
    were the results of the interviews that he participated in as
    part of Exelon’s department-wide LAP evaluations during
    September of 2001, where he performed so poorly that the
    interviewing panel rated him as “developmental,” or
    No. 03-3724                                                   13
    deficient9 in eight of the eleven categories selected by
    Exelon to evaluate leadership and behavior skills. As a re-
    sult, the interviewing panel determined that Cichon failed
    to “possess the leadership abilities that provide a good
    motivational fit for the [Unit Supervisor] position.”
    Cichon’s error during the restart of the reactor and
    Exelon’s poor LAP evaluation of Cichon occurred prior to
    the company receiving notice of Cichon’s lawsuit and were
    certainly indicative of Cichon’s inability to perform his job
    in a satisfactory manner and ipso facto justified Exelon’s
    decision to remove him as a Unit Supervisor. Accordingly,
    Cichon’s attempt to rely merely on a “suspicious timing”
    theory falls far short of creating any logical or reasonable
    inference that Exelon’s complaints about his unsatisfactory
    job performance were not based in fact, but instead were
    trumped-up charges invented by Exelon merely to cloak
    their clandestine retaliatory motive for removing him as a
    Unit Supervisor. See Lang v. Ill. Dep’t of Children & Family
    Servs., 
    361 F.3d 416
    , 419-20 (7th Cir. 2004); Sitar v. Ind.
    Dep’t of Transp., 
    344 F.3d 720
    , 728-29 (7th Cir. 2003); Ajayi
    v. Aramark Bus. Servs., Inc., 
    336 F.3d 520
    , 533-34 (7th Cir.
    2003). In spite of the fact that Exelon did not inform Cichon
    of its decision to remove him from the position until after he
    filed his FLSA suit, the record clearly establishes that
    Exelon had been “contemplating [Cichon’s removal] before
    it learned of the suit [and] [e]mployers need not suspend
    previously planned [employment actions] upon discovering
    that [an FLSA] suit has been filed, and their proceeding
    along lines previously contemplated . . . is no evidence
    9
    As Exelon’s Manager of Employee Relations, Diana Sorfleet
    explained: “ ‘needs development,’ and too many ‘developmental’
    scores means that the employee is so deficient (in Exelon’s opin-
    ion) that he is not worth the time, money and effort it would take
    to properly develop these deficiencies to the point where he is
    ‘competent’ in fundamental areas.” See supra note 3.
    14                                               No. 03-3724
    whatever of causality.” Clark County Sch. Dist. v. Breeden,
    
    532 U.S. 268
    , 272 (2001).
    Exelon has every reason to expect that each of its Unit
    Supervisors possess and exhibit the necessary leadership
    and supervisory skills, and follow the procedures required
    to ensure the safe operation of its nuclear power plants. The
    record demonstrates that Cichon fell far short of meeting
    Exelon’s expectations as evidenced by his failure to follow
    the approved reactor start-up and shut-down safety proce-
    dures and his poor showing in the LAP interviews, when he
    was rated “developmental” or deficient10 in all but three out
    of the eleven categories in which his leadership and behav-
    ior skills were rated. Cichon does not argue that Exelon’s
    expectations were unreasonable or not bona fide. See Robin
    v. Espo Eng’g Corp., 
    200 F.3d 1081
    , 1090 (7th Cir. 2000).
    Since Cichon has failed to demonstrate that “he was
    performing his [Unit Supervisor] job in a satisfactory
    manner” and meeting his employer’s legitimate business ex-
    pectations that its management-level employees possess
    and demonstrate the requisite leadership and behavioral
    skills, he has failed to establish a prima facie case of re-
    taliation in regards to his removal from this position. Stone,
    
    281 F.3d at 644
    .
    Even assuming arguendo that Cichon had established a
    prima facie case of retaliation, his claim would still ulti-
    mately fail due to the fact that he has failed to present any
    evidence that would establish that Exelon’s proffered
    reasons for removing him were pretextual. In error Cichon
    asserts that he was the only Unit Supervisor removed as a
    result of the LAP; a contention which is devoid of any sup-
    port in the record. To the contrary, at least two other
    individuals were removed due to poor performance in the
    LAP evaluations. Furthermore, because Cichon failed to
    10
    See supra notes 3, 9.
    No. 03-3724                                                 15
    present any evidence that Exelon relied on anything other
    than his poor work performance and negative LAP evalua-
    tions when it removed him, we need not inquire any further
    into the wisdom of its employment decisions. Appelbaum v.
    Milwaukee Metro. Sewerage Dist., 
    340 F.3d 573
    , 579 (7th
    Cir. 2003). We conclude that the district court’s grant of
    summary judgment to Exelon on Cichon’s claim of retalia-
    tion in his removal from the Unit Supervisor position was
    proper.
    2. Failure to Hire for the Turbine Project Manager
    Position
    Cichon argues that summary judgment was improper on
    his claim that Exelon retaliated against him when not hir-
    ing him for the Turbine Project Manager position, and con-
    tends that he produced sufficient evidence to demonstrate
    a disputed issue of fact as to whether Exelon’s proffered
    reason for not hiring him for the position was pretextual.
    We agree with the district court’s determination that Cichon
    produced sufficient evidence to make out a prima facie case
    on the failure to hire portion of his retaliation claim when he
    demonstrated that: 1) he engaged in a statutorily protected
    activity by filing an FLSA lawsuit, see Sapperstein v. Hager,
    
    188 F.3d 852
    , 857 (7th Cir. 1999); 2) he applied and had the
    technical qualifications required for the Turbine Project
    Manager position; 3) he was not hired for the position; and
    4) a similarly situated individual who did not file a com-
    plaint under the FLSA was hired for the position (Tim
    Nolan). Volovsek v. Wis. Dep’t of Agric., Trade, & Consumer
    Prot., 
    344 F.3d 680
    , 692 (7th Cir. 2003); Stone, 
    281 F.3d at 644
    . Thus, the burden shifted to Exelon to offer a legitimate,
    non-retaliatory reason for not hiring Cichon for the Turbine
    Project Manager position. Millbrook v. IBP, Inc., 
    280 F.3d 1169
    , 1175 (7th Cir. 2002). We hold that Exelon did fulfill
    this burden by pointing out and providing evidence that
    16                                               No. 03-3724
    Cichon was not hired because the candidate selected, Tim
    Nolan, demonstrated that he was more qualified and
    possessed better overall leadership and behavioral skills
    when he achieved better scores than Cichon during the
    interview and rating process. Further, Tim Kelly, one of the
    individuals who interviewed both Cichon and Nolan for the
    position, stated that Nolan was hired instead of Cichon
    simply because of his higher score, and not because Cichon
    had filed an FLSA lawsuit against Exelon (Kelly explained
    that he had no knowledge of a lawsuit being filed until
    Cichon offered the information during the interview). In
    order for Cichon’s claim to advance beyond the summary
    judgment stage, it was his responsibility to offer the district
    court evidence that created “an issue of material fact as to
    whether [Exelon’s] proffered reasons [for not hiring him
    were] merely pretext for unlawful discrimination or retalia-
    tion,” Hudson v. Chicago Transit Auth., 
    375 F.3d 552
    , 561
    (7th Cir. 2004), which he has failed to do. “To demonstrate
    pretext, [Cichon] must demonstrate that [Exelon’s] articu-
    lated reason for [not hiring him] either: 1) had no basis in
    fact; 2) did not actually motivate its decision; or 3) was
    insufficient to motivate its decision.” Grayson v. O’Neill, 
    308 F.3d 808
    , 820 (7th Cir. 2002).
    Cichon did not directly attack Exelon’s proffered reason
    for choosing Nolan as the more qualified candidate, i.e., that
    Nolan exhibited superior overall leadership and behavioral
    skills during the interviewing process. If Cichon had
    advanced such an argument, he would be facing an uphill
    battle in attempting to discredit Exelon’s statement that it
    hired Nolan because he was better qualified than Cichon as
    pretextual, even when considering that Exelon’s evaluation
    of the two applicants was based on subjective evaluation
    criterion such as the candidates’ “leadership and behavioral
    skills.” This is because “where an employer’s proffered non-
    discriminatory reason for its employment decision is that it
    selected the most qualified candidate, evidence of the
    No. 03-3724                                                17
    applicants’ competing qualifications does not constitute
    evidence of pretext ‘unless [the plaintiff’s case demonstrates
    that those qualifications] are so favorable to the plaintiff
    that there can be no dispute among reasonable persons of
    impartial judgment that the plaintiff was clearly better
    qualified for the position at issue.’ ” Millbrook, 
    280 F.3d at 1180
     (quoting Deines v. Texas Dep’t of Protective & Regula-
    tory Servs., 
    164 F.3d 277
    , 279 (5th Cir. 1999)) (emphasis
    added). Cichon failed to present any evidence that directly
    called into question the veracity of Exelon’s reason for
    hiring Nolan instead of himself.
    Instead, Cichon mounted an indirect attack on the integ-
    rity of the interviewing panel and its process that resulted
    in Nolan’s selection, by accusing one of his interviewers,
    Kelly, of manipulating his evaluation of Cichon in order that
    Nolan would be awarded the position. Without a scintilla of
    proof, evidence or substantiation of any kind to support his
    claim, Cichon alleges that Kelly, who had told Cichon before
    the interviewing process began that Cichon might be a
    “good fit” for the job, did an about-face after learning of
    Cichon’s FLSA lawsuit against Exelon and purposely gave
    him (Cichon) a lower score than Nolan to sabotage his
    prospects of being selected for the position. Cichon posits
    that such an allegation was sufficient to create a disputed
    issue of fact as to whether Exelon’s proffered reason for
    hiring Nolan was pretextual. We disagree.
    First of all, Kelly’s having told Cichon prior to the inter-
    viewing process that he was a “good fit” for the job does not
    ipso facto create an inference that Kelly’s assessment of
    Cichon following the interview was prompted by a retalia-
    tory animus instead of Kelly’s forthright evaluation of
    Cichon’s leadership and behavioral skills. Kelly’s pre-
    interview comment noting that Cichon was well-suited for
    the job was based on his knowledge of Cichon’s technical
    qualifications, but the interviewing process was designed to
    sort through the more technically-qualified candidates to
    18                                                No. 03-3724
    find the applicant who possessed the superior leadership as
    well as behavioral skills. Cichon’s “mere qualification [for the
    position] does not mean that [he] must get the job . . . .
    [a]nd in choosing between different candidates, all of whom
    are qualified, an employer may legitimately use subjective
    qualifications.” Perfetti v. First Nat’l Bank of Chicago, 
    950 F.2d 449
    , 458 (7th Cir. 1991). The opinion of one person in
    isolation that Cichon would be a “good fit” for the job is not
    persuasive evidence that Cichon was the most qualified
    person for the position, much less the person that would be
    hired. In addition, Kelly’s statement does not controvert
    Cichon’s poor performance in the other stages of the inter-
    view process. The decision that Nolan was a more attractive
    candidate than Cichon came at the end of a collaborative
    interview process that included input from a number of in-
    terviewers other than Kelly, and as this court has reiterated
    time and time again, “[w]e do not sit as a superpersonnel
    department that reexamines an entity’s business decision
    and reviews the propriety of that decision.” Stewart v.
    Henderson, 
    207 F.3d 374
    , 378 (7th Cir. 2000) (citation
    removed).
    Second, Cichon failed to present evidence from which a
    rational decisionmaker could logically infer that, based on
    the fact that Kelly knew about Cichon’s FLSA lawsuit, Kelly
    was motivated by a retaliatory animus when he determined
    that Cichon did not possess the necessary leadership and
    behavioral skills to merit a higher score than Nolan in the
    interviewing process. See Eiland v. Trinity Hosp., 
    150 F.3d 747
    , 753 (7th Cir. 1998); Kearney v. Town of Wareham, 
    316 F.3d 18
    , 23 (1st Cir. 2002). Cichon gave no logical explana-
    tion or reason as to why Kelly, who like Cichon was a man-
    agement-level employee at Exelon, would take such umbrage
    to Cichon’s having filed an FLSA lawsuit against Exelon—
    protesting the company’s decision to cut overtime pay for
    management-level employees—that he would take it upon
    himself to sabotage Cichon’s chances of being awarded the
    No. 03-3724                                                 19
    Turbine Project Manager position. Indeed, accepting Cichon’s
    speculative theory that Kelly harbored a retaliatory motive
    when he interviewed him, and essentially acted as a pawn
    in Exelon’s alleged nefarious scheme, see Eiland, 
    150 F.3d at 752
    , would require us to also implicate some or all of the
    other three individuals who interviewed him in a conspiracy
    designed to thwart Cichon’s prospects of obtaining the
    Turbine Project Manager position. “We have typically been
    wary of allegations based on nothing [more than a bold
    statement in] an attempt to come up with a conspiracy
    theory and in particular where there is not a scintilla of evi-
    dence in the record before us to support [Cichon’s] theory.”
    Wells v. Unisource Worldwide, Inc., 
    289 F.3d 1001
    , 1007
    (7th Cir. 2002); see also Perfetti, 950 F.2d at 453. And we
    are even more skeptical of Cichon’s conspiratorial retalia-
    tion allegations because he himself engineered this scenario
    by informing Kelly during the interviewing process that he
    had filed an FLSA lawsuit against Exelon—recall that before
    interviewing Cichon, Kelly had no knowledge of Cichon’s
    lawsuit and only learned about it when Cichon volunteered
    the information.
    Cichon has provided no evidence other than bald, self-
    serving assertions that would allow us to rationally infer
    that Kelly was motivated by a retaliatory animus to redirect
    the selection process for the Turbine Project Manager
    position to exclude Cichon. Indeed, there is no reason to
    believe Kelly’s evaluation of Cichon during the interviewing
    process was based on anything besides a fair and well-rea-
    soned assessment of Cichon’s leadership and behavioral
    skills. Kelly flatly denied that his knowledge of Cichon’s law-
    suit had any affect on his decisions during the interviewing
    process. Thus, the only way in which Cichon could prevail
    on his allegation of pretext would be to demonstrate that
    Kelly was not being truthful when he made this statement.
    Perfetti, 950 F.2d at 456. However, because Cichon has the
    ultimate burden of proof to demonstrate that Exelon engaged
    20                                                No. 03-3724
    in retaliatory conduct, see David v. Caterpillar, Inc., 
    324 F.3d 851
    , 858 (7th Cir. 2003), he cannot create a triable dispute
    of fact “ ‘if his only ‘evidence’ [is that Exelon’s] witnesses
    [are] not worthy of belief. That would [be] a no-evidence
    case, and such a case [Cichon] must lose, because he has the
    burden of proof.’ ” Millbrook, 
    280 F.3d at 1181
     (quoting
    EEOC v. G-K-G, Inc., 
    39 F.3d 740
    , 746 (7th Cir. 1994)). Put
    differently, it is impossible for Cichon to meet his burden of
    proof and demonstrate retaliatory conduct “by relying
    on the hope that the jury will not trust the credibility of
    [Exelon’s] witnesses.” Perfetti, 950 F.2d at 456. Without
    some shred of affirmative evidence to call into question
    Kelly’s credibility, Cichon must lose. Id.; see also Massey v.
    Blue Cross-Blue Shield of Illinois, 
    226 F.3d 922
    , 926 (7th
    Cir. 2000). As demonstrated above, Cichon has presented no
    such evidence. Accordingly “what this case really comes
    down to is . . . deciding which applicant is more qualified,”
    a decision that we leave to the employer. Millbrook, 
    280 F.3d at 1183
    . Filing a lawsuit under the FLSA does not im-
    munize an employee from adverse employment actions, or
    prevent “the employer from exercising its business judg-
    ment.” Blackie v. Maine, 
    75 F.3d 716
    , 723 (1st Cir. 1996).
    Cichon’s indirect, insubstantial evidence fell far short of
    demonstrating that Exelon’s proffered reason for hiring
    Nolan was pretextual. See Perfetti, 950 F.2d at 452. We thus
    conclude that the district court’s grant of summary judg-
    ment to Exelon on Cichon’s claim that he was not hired for
    the Turbine Project Manager position in retaliation for
    filing an FLSA lawsuit was proper.
    IV. CONCLUSION
    The decision of the district court is
    AFFIRMED.
    No. 03-3724                                         21
    A true Copy:
    Teste:
    ________________________________
    Clerk of the United States Court of
    Appeals for the Seventh Circuit
    USCA-02-C-0072—3-21-05
    

Document Info

Docket Number: 03-3724

Judges: Per Curiam

Filed Date: 3/21/2005

Precedential Status: Precedential

Modified Date: 9/24/2015

Authorities (30)

Marshall T. Stewart, Jr. And Isiah Williams v. William ... , 207 F.3d 374 ( 2000 )

Anna D. Wells v. Unisource Worldwide, Inc. , 289 F.3d 1001 ( 2002 )

Gary Millbrook v. Ibp, Inc. , 280 F.3d 1169 ( 2002 )

Clark County School District v. Breeden , 121 S. Ct. 1508 ( 2001 )

Stephanie A. Massey v. Blue Cross-Blue Shield of Illinois , 226 F.3d 922 ( 2000 )

Sandra L. Waldridge v. American Hoechst Corp. , 24 F.3d 918 ( 1994 )

Clyde Ammons v. Aramark Uniform Services, Inc. , 368 F.3d 809 ( 2004 )

Dana Blackie v. State of Maine , 75 F.3d 716 ( 1996 )

McDonnell Douglas Corp. v. Green , 93 S. Ct. 1817 ( 1973 )

Judith Volovsek v. Wisconsin Department of Agriculture, ... , 344 F.3d 680 ( 2003 )

William Sapperstein v. Robert Hager and Patricia Hager ... , 188 F.3d 852 ( 1999 )

Alfred L. Stone v. City of Indianapolis Public Utilities ... , 281 F.3d 640 ( 2002 )

Kearney v. Town of Wareham , 316 F.3d 18 ( 2002 )

equal-employment-opportunity-commission-v-g-k-g-incorporated-bernard , 39 F.3d 740 ( 1994 )

Merlee EILAND, Plaintiff-Appellant, v. TRINITY HOSPITAL, ... , 150 F.3d 747 ( 1998 )

Sandra M. Scott v. Sunrise Healthcare Corporation, a ... , 195 F.3d 938 ( 1999 )

Patricia Rogers v. City of Chicago, an Illinois Municipal ... , 320 F.3d 748 ( 2003 )

Ralph L. Grayson v. Paul O'neill, Secretary, United States ... , 308 F.3d 808 ( 2002 )

Caroline M. Sitar v. Indiana Department of Transportation , 344 F.3d 720 ( 2003 )

Midwest Imports, Ltd. v. Les Coval and Joseph Pieciak & Co.,... , 71 F.3d 1311 ( 1995 )

View All Authorities »