J.S. Sweet Co. Inc. v. Sika Chemical Corp ( 2005 )


Menu:
  •                              In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 04-2871
    J.S. SWEET COMPANY, INCORPORATED,
    Plaintiff-Appellant,
    v.
    SIKA CHEMICAL CORPORATION, also
    known as SIKA CORPORATION,
    Defendant-Appellee.
    ____________
    Appeal from the United States District Court for the
    Southern District of Indiana, Evansville Division.
    No. 99 C 168—Richard L. Young, Judge.
    ____________
    ARGUED JANUARY 12, 2005—DECIDED MARCH 16, 2005
    ____________
    Before FLAUM, Chief Judge, and EASTERBROOK and WOOD,
    Circuit Judges.
    FLAUM, Chief Judge. J.S. Sweet Company, Inc. (“J.S.
    Sweet”) brought this diversity suit against Sika Chemical
    Corp. (“Sika”), alleging that defendant committed the tort
    of spoliation of evidence by failing to preserve materials rel-
    evant to a lawsuit between J.S. Sweet and one of its cus-
    tomers. Plaintiff also sued for breach of contract. The
    district court granted summary judgment on both counts,
    and Sweet appealed. We hold that Sika had no duty to
    2                                               No. 04-2871
    preserve the evidence in question, that its loss of the
    evidence did not, as a matter of law, harm J.S. Sweet, and
    that Sika did not breach its contract with plaintiff. Accord-
    ingly, we affirm.
    I. Background
    In late 1994, the White County Bridge Commission
    (“WCBC” or “Commission”) requested bids for repair work to
    the surface of the New Harmony Toll Bridge. WCBC named
    the engineering firm of R.W. Armstrong, Inc. (“Armstrong”)
    to review bids, help select a winner, and oversee the con-
    struction work. J.S. Sweet is a general contractor incorpo-
    rated in Indiana. It bid on and won the contract, which
    called for it to remove the top one-quarter inch of concrete
    from the surface of the bridge, extract any faulty concrete,
    fill the resulting holes, and seal the entire surface of the
    bridge with an epoxy overlay. The epoxy would protect the
    underlying concrete and act as a wearing surface.
    Sika is a chemical manufacturing company based in New
    Jersey which produces an epoxy designed for use in con-
    struction projects. J.S. Sweet purchased over $100,000 worth
    of Sika’s product from a third-party distributor and applied
    the epoxy as the overlay on the New Harmony bridge. In
    early 1995, however, the epoxy began to delaminate, or peel
    away, from the surface of the bridge.
    In May 1995, Fraser MacPhee, then a salesman for Sika,
    drove to New Harmony to observe this phenomenon. He was
    accompanied by Michael Magner, the project manager for
    Armstrong. Both MacPhee and Magner took photographs of
    the bridge. MacPhee also may have picked up some loose
    pieces of epoxy from the bridge’s surface, but did not keep
    the fragments or send them to anyone else for analysis. He
    did not conduct any tests or use any special equipment to
    examine the bridge or epoxy, nor does he have any technical
    training or an advanced degree. MacPhee wrote a one-page
    No. 04-2871                                                 3
    memorandum detailing his observations which he forwarded,
    along with his photographs, to his supervisors. J.S. Sweet
    contends that Sika also conducted an analysis based on
    MacPhee’s report, although it is not clear whether this an-
    alysis ever existed or, if so, what it entailed. In July 1995,
    J.S. Sweet employees independently inspected and photo-
    graphed the bridge.
    Because of the problems on the bridge, WCBC refused
    to pay J.S. Sweet for its work. On September 14, 1995,
    J.S. Sweet sued the Commission in Indiana state court for,
    among other things, breach of contract and unjust enrich-
    ment. WCBC counterclaimed, alleging that J.S. Sweet had
    failed to comply with the repair contract’s specifications by
    misapplying the epoxy. At no point during the litigation
    with WCBC, however, did J.S. Sweet subpoena Sika or re-
    quest any of its records. The claims proceeded to a bench
    trial where the court found in favor of J.S. Sweet on its
    breach of contract claim and rejected the Commission’s
    counterclaim. The Court of Appeals of Indiana affirmed the
    judgment, although it remanded for proceedings not rel-
    evant to our discussion. See J.S. Sweet Co. v. White County
    Bridge Comm’n, 
    714 N.E.2d 219
     (Ind. Ct. App. 1999).
    On April 2, 1998, J.S. Sweet sued Armstrong for tortious
    interference with contract, tortious interference with pro-
    spective advantage, and defamation. J.S. Sweet alleged that
    Armstrong had made knowingly false statements to WCBC
    and Sika about J.S. Sweet’s performance in repairing the
    surface of the bridge. Prior to filing suit against Armstrong,
    J.S. Sweet’s counsel interviewed MacPhee (who by then had
    left Sika) and learned that he had taken photographs and
    written a memorandum of his observations on the bridge.
    On March 11, 1998, counsel requested by letter that Sika
    produce the memorandum, photographs, and any related
    correspondence. Sika promptly advised J.S. Sweet that it
    could not find any of the requested materials. On February
    3, 1999, J.S. Sweet subpoenaed Sika and requested again
    4                                                No. 04-2871
    that it hand over the report and related materials. Sika
    reiterated that it could not find the documents or photo-
    graphs. Although it never obtained the requested materials,
    J.S. Sweet deposed MacPhee about his observations,
    recovered the photographs taken by Magners the day of
    MacPhee’s visit, and relied on its own photographs taken of
    the bridge in July 1995. J.S. Sweet’s suit against
    Armstrong, nevertheless, was unsuccessful.
    In November 1995, while the WCBC litigation was still
    pending, J.S. Sweet and Sika signed an agreement pro-
    viding that, in exchange for a $250 enrollment fee, Sika
    would train one of J.S. Sweet’s employees in the use and
    application of Sika’s products. Upon successful completion
    of the training course, Sika would designate J.S. Sweet for
    a period of two years as a “Sika approved contractor.” Sika
    agreed to promote J.S. Sweet to the construction industry
    as capable and experienced in working with Sika products,
    furnish plaintiff with leads to possible construction con-
    tracts, enter a joint advertising campaign, and provide them,
    free of charge, with limited amounts of literature, data books,
    and cured product samples. J.S. Sweet undertook to use
    Sika’s products wherever appropriate. The agreement stated
    expressly that J.S. Sweet would remain an independent
    contractor and that “nothing contained herein shall be con-
    strued as constituting [J.S. Sweet] as the agent, partner, or
    legal representative of Sika.” (Pls.’ App. at 37.) The day the
    parties signed the agreement, Sika gave to J.S. Sweet a
    one-page document entitled “SIKA APPROVED CONTRAC-
    TOR PROGRAM GUIDELINES 1995.” (Id. at 38.) The
    document displays several bullet points that highlight in
    general terms the features of the training program. The
    document does not contain a signature line and was not
    signed by either party.
    On October 13, 1999, J.S. Sweet filed the two-count
    complaint in this case. The first count alleges that Sika
    No. 04-2871                                                 5
    tortiously interfered with the WCBC litigation by spoliating
    evidence. The second count contends that Sika breached the
    approved contractor agreement by failing to explain to J.S.
    Sweet why Sika’s epoxy was delaminating from the bridge.
    The complaint does not include a breach of implied war-
    ranty or products liability claim against Sika arising out of
    the sale of its epoxy. The district court initially denied
    Sika’s motion for summary judgment as to the spoliation
    claim. On a motion to reconsider, however, the court re-
    versed itself and ruled in favor of defendant. The district
    court later granted summary judgment on the breach of
    contract claim as well, and entered judgment in favor of
    Sika. J.S. Sweet appeals.
    II. Discussion
    A district court’s grant of summary judgment is reviewed
    de novo. Carreon v. Ill. Dep’t of Human Servs., 
    395 F.3d 786
    ,
    790 (7th Cir. 2005). Summary judgment is appropriate only
    where “the pleadings, depositions, answers to interrogato-
    ries, and admissions on file, together with the affidavits, if
    any, show that there is no genuine issue as to any material
    fact and that the moving party is entitled to a judgment as
    a matter of law.” Fed. R. Civ. P. 56(c). We draw all reason-
    able inferences and resolve all disputed issues of fact in
    favor of the nonmovant. Carreon, 
    395 F.3d at 790
    .
    A. Spoliation of Evidence
    J.S. Sweet contends that MacPhee’s report, photographs,
    and Sika’s internal analysis of the report would have pro-
    vided strong evidence that WCBC’s counterclaim for breach
    of contract was unfounded. Although J.S. Sweet ultimately
    prevailed on that claim, it argues that the materials in
    Sika’s possession, if introduced at trial, would have brought
    the WCBC litigation swiftly to an end. Plaintiff contends
    6                                                 No. 04-2871
    that, instead, it was dragged through extended litigation
    and forced to incur unnecessary legal fees. J.S. Sweet as-
    serts that Sika is liable to it for the harm caused by Sika’s
    failure to maintain and produce this evidence.
    Sika rejoins that, absent a subpoena or other discovery
    request, it had no duty to preserve the documents. It points
    out that the materials sought by J.S. Sweet were misplaced
    (or according to plaintiff, intentionally destroyed) long
    before it ever received a subpoena. Defendant asserts,
    moreover, that the loss or destruction of the materials could
    not have harmed J.S. Sweet because all of the information
    contained therein was available to plaintiff through other
    avenues.
    The parties agree that Indiana law governs. Indiana
    courts define spoliation as “[t]he intentional destruction,
    mutilation, alteration, or concealment of evidence, usually
    a document.” Cahoon v. Cummings, 
    734 N.E.2d 535
    , 545
    (Ind. 2000) (quoting Black’s Law Dictionary 1409 (7th ed.
    1999)). The concept of spoliation has at least two distinct
    applications. The first is as a permissive evidentiary in-
    ference. See, e.g., Morris v. Buchanan, 
    44 N.E.2d 166
    , 169
    (Ind. 1942). That is, if there is reason to believe that a party
    to a lawsuit has suppressed evidence within its peculiar
    possession, the trial court has discretion to instruct jurors
    that they may infer that, had the evidence been produced,
    it would have been unfavorable to that party’s case. See Ind.
    Pattern Jury Instruction (Civil) 3.11 (2003); Cahoon, 734
    N.E.2d at 545.
    The second application—at issue in this case—is where
    spoliation is alleged as an independent tort. Indiana is one
    of few jurisdictions that recognizes the tort, which is an-
    alyzed either as a species of negligence or under the rubric
    of intentional interference with prospective or actual civil
    litigation. See Murphy v. Target Prods., 
    580 N.E.2d 687
    ,
    688-90 (Ind. Ct. App. 3d Dist. 1991). Negligent or inten-
    No. 04-2871                                                7
    tional spoliation is actionable as a tort only if the party
    alleged to have lost or suppressed the evidence owed a duty
    to the person bringing the spoliation claim to have preserved
    the material. 
    Id. at 690
    ; see also Levinson v. Citizens Nat’l
    Bank of Evansville, 
    644 N.E.2d 1264
    , 1268 (Ind. Ct. App.
    5th Dist. 1994). Plaintiff must also show that the duty was
    breached and that it was harmed as a result. Thompson v.
    Owensby, 
    704 N.E.2d 134
    , 140 (Ind. Ct. App. 1998).
    1. Duty
    Whether a duty exists is a question of law decided by the
    court after balancing three factors: “1) the relationship be-
    tween the parties, 2) the reasonable foreseeability of the
    type of harm to the type of plaintiff at issue, and 3) the
    public policy promoted by recognizing an enforceable duty.”
    
    Id. at 136
    ; see also Webb v. Jarvis, 
    575 N.E.2d 992
    , 995
    (Ind. 1991). The Indiana courts have refused to recognize a
    duty to preserve evidence absent “an independent tort,
    contract, agreement, or special relationship.” Murphy, 
    580 N.E.2d at 690
    .
    J.S. Sweet contends that its purchase of over $100,000
    worth of Sika’s epoxy and its status as a Sika approved
    contractor establish a special relationship between the par-
    ties. It argues, furthermore, that Sika knew or reasonably
    could have foreseen that the MacPhee report, photos, and
    Sika’s internal analysis of the report were critical to the
    WCBC litigation, and that the loss or destruction of those
    materials would have harmed J.S. Sweet. It asserts that
    imposing a duty in this case would enhance motorists’ safety
    by preserving evidence that will expose those at fault when
    public works projects go awry.
    We decline to recognize a duty under these circumstances.
    First, we disagree with plaintiff’s contention that a special
    relationship exists between the parties. J.S. Sweet pur-
    chased Sika’s epoxy through a third-party distributor in an
    8                                                    No. 04-2871
    arm’s-length transaction in the same way as any of Sika’s
    other customers. An arrangement as ordinary as this cannot
    be considered special. Nor does the approved contractor
    agreement help J.S. Sweet’s argument. Plaintiff concedes
    that the agreement does not expressly obligate Sika to pre-
    serve evidence. Moreover, the contract forecloses the possi-
    bility that it creates a special relationship by implication:
    “[J.S. Sweet] is, and in all events shall be, an independent
    Contractor and nothing contained herein shall be construed
    as constituting [J.S. Sweet] as the agent, partner, or legal
    representative of Sika or [sic] any purpose whatsoever.”
    (Pls.’ App. at 37.)
    Second, Sika could not reasonably have foreseen that its
    failure to maintain the evidence would harm J.S. Sweet.
    MacPhee’s report was merely a summary of what an inter-
    ested layperson observed on the bridge. His photographs
    were equally commonplace. Sika could anticipate reasonably
    that J.S. Sweet would do its own investigation, make its own
    observations, and take its own photographs. (And as it
    turned out, plaintiff did.) Plaintiff emphasizes, however,
    that it was damaged by the loss or intentional destruction
    of Sika’s internal analysis of the report, rather than by the
    disappearance of the report itself, and that Sika should have
    foreseen this harm. We find this argument unpersuasive.
    By plaintiff’s allegations, the internal analysis relied on
    observations made in the MacPhee report, which were readily
    available to Sweet. Sika could justifiably expect Sweet to do
    its own homework and come to its own conclusions.1
    1
    J.S. Sweet heavily emphasizes evidence that, in 1996, Sika’s
    corporate counsel informed one of plaintiff ’s employees that he
    had “the Sweet file” on his desk. Plaintiff claims that this demon-
    strates that Sika had conducted an internal analysis of MacPhee’s
    observations and knew that its analysis would be important to
    J.S. Sweet in the WCBC litigation. There is no indication, how-
    (continued...)
    No. 04-2871                                                      9
    Third, public policy considerations counsel strongly
    against recognizing a duty under these circumstances. A
    ruling in favor of J.S. Sweet would impose a significant
    but undefined burden on an unpredictable class of persons.
    Plaintiff has not proposed, nor can we divine, any principled
    way to decide which records should be maintained, for how
    long, or by whom. A rule of such uncertain scope appears
    especially ill-advised given that J.S. Sweet had the option of
    subpoenaing Sika, thereby putting it on notice that it
    possessed evidence relevant to the WCBC litigation. See
    Ind. Trial P. R. 34(C) (allowing for the subpoena of non-
    parties); see also Murphy, 
    580 N.E.2d at 690
     (“Prior to
    receiving a request as contemplated under [Rule 34(C)], the
    non-party ought to have no legal concerns about potential
    evidence in his possession, absent any promises, contracts,
    statutes or special circumstances.”). What we can say with
    certainty is that any holding in favor of plaintiff would
    require us to expand the spoliation tort vastly beyond where
    the Indiana courts have been willing to go. See, e.g., 
    id.
    (refusing to impose a duty on an employer to preserve
    evidence relevant to its employee’s lawsuit against a third
    party); Levinson, 664 N.E.2d at 1268-69 (holding that the
    tort of spoliation does not include a duty to avoid causing a
    mistrial); Loomis v. Ameritech Corp., 
    764 N.E.2d 658
    , 663-
    64 (Ind. Ct. App. 2002) (spoliation tort does not apply to
    testimonial evidence).
    We have located only one reported case where an Indiana
    court has recognized a duty to preserve evidence under the
    1
    (...continued)
    ever, that “the Sweet file” contained an analysis of the MacPhee
    report. Assuming that it did, corporate counsel’s statement that
    he possessed the file establishes at most that he had a copy of the
    analysis as late as 1996. It says nothing about the content of the
    analysis. Thus, it does not undermine our conclusion that Sika
    would have been reasonable to expect J.S. Sweet to conduct its
    own investigation.
    10                                               No. 04-2871
    tort of spoliation. See Thompson, 
    704 N.E.2d at 139
    . The
    plaintiffs in Thompson were the parents of a young girl who
    had been mauled by a dog after it broke free of its chain.
    The parents sued the chain manufacturer, the dog’s owners,
    and the owners’ landlords. The landlords’ insurance com-
    pany took possession of the allegedly defective chain before
    anyone had an opportunity to examine it. When the insur-
    ance company lost the chain, the parents sued it, claiming
    that its failure to preserve the evidence undermined the
    parents’ case against the chain manufacturer, dog owners,
    and landlords. The appellate court reversed the trial court’s
    dismissal of the spoliation claim and held that the insur-
    ance company had a duty to preserve the evidence.
    Thompson is plainly distinguishable from this case. In
    Thompson, the party alleged to have spoliated the evidence
    had a direct financial stake in the outcome of the under-
    lying litigation. Had the landlords been found liable, the
    insurance company would have had to indemnify them. And
    if the key evidence implicating the landlords disappeared,
    but for spoliation liability, the insurer would have been off
    the hook. We have no similar reason to be suspicious of
    Sika’s motives because WCBC’s counterclaim could have
    been resolved on a number of grounds that would not have
    impacted Sika financially. Moreover, the broken dog chain
    was obviously critical to the plaintiffs’ case in Thompson,
    and the insurance company’s decision to take exclusive pos-
    session of the chain shows that it recognized that fact. By
    contrast, Sika could have expected J.S. Sweet to obtain the
    information found in MacPhee’s report elsewhere. Given our
    reluctance as a court sitting in diversity to expand state
    law, see, e.g., King v. Damiron Corp., 
    113 F.3d 93
    , 97 (7th
    Cir. 1997), we refuse to recognize a duty in this case.
    2. Harm
    Even if Sika had a duty to preserve the evidence, J.S. Sweet
    No. 04-2871                                                 11
    would also have to show that the duty was breached, that
    it was harmed by the breach, “and that the harm resulted
    in damages that can be proven with reasonable specificity.”
    Thompson, 
    704 N.E.2d at 140
    . A spoliation claim is viable
    only if the party who allegedly failed to preserve the evi-
    dence possessed it exclusively. Loomis, 
    764 N.E.2d at 663
    .
    Many of the considerations that informed our duty an-
    alysis also lead us to conclude that the destruction or loss
    of the report and related materials did not, as a matter of
    law, harm Sweet. Anything MacPhee observed on the bridge
    could have been (and likely was) observed by J.S. Sweet.
    There is no indication that the conditions on the bridge
    changed between MacPhee’s visit in May 1995 and plaintiff     ’s
    arrival two months later. Even if things had changed, J.S.
    Sweet deposed MacPhee and asked him about his recollec-
    tions. Moreover, plaintiff obtained photographs taken the
    same day as MacPhee’s visit. None of the allegedly
    spoliated evidence, therefore, was in Sika’s exclusive
    possession. See 
    id.
     Nor could the loss or suppression of Sika’s
    internal analysis have harmed J.S. Sweet. As explained
    above, that analysis was based on observations that plaintiff
    could have made. J. S. Sweet also had the opportunity to
    depose Sika employees about what conclusions, if any, they
    drew from MacPhee’s report. The district court held cor-
    rectly that J.S. Sweet failed, as a matter of law, to establish
    that it was harmed by the loss of this evidence.
    B. Breach of Contract
    J.S. Sweet relies on the approved contractor agreement,
    not only to support its argument that a special relationship
    existed between the parties, but also as the basis for its
    breach of contract claim. Plaintiff contends that Sika vio-
    lated the agreement by failing to provide it with technical
    12                                                   No. 04-2871
    support.2 “The primary and overriding purpose of contract
    law is to ascertain and give effect to the intentions of the
    parties.” Indiana-American Water Co. v. Town of Seelyville,
    
    698 N.E.2d 1255
    , 1259 (Ind. Ct. App. 1998). “In interpreting
    a written contract, the court should attempt to determine
    the intent of the parties at the time the contract was made
    as discovered by the language used to express their rights
    and duties.” 
    Id.
     (internal citations omitted). “When the
    language of a written contract is not ambiguous . . . its
    meaning is a question of law ‘for which summary judgment
    is particularly appropriate.’ ” Hyperbaric Oxygen Therapy
    Sys., Inc. v. St. Joseph Med. Ctr. of Ft. Wayne, Inc., 
    683 N.E.2d 243
    , 247 (Ind. Ct. App. 1997) (quoting Fetz v. Phillips,
    
    591 N.E.2d 644
    , 647 (Ind. Ct. App. 1992)).
    Although not entirely clear from its papers, J.S. Sweet
    appears to argue that the obligation to provide technical
    support requires that Sika explain to it why the epoxy was
    peeling away from the surface of the New Harmony bridge.
    As support for this argument, plaintiff points not to the
    terms of the approved contractor agreement, but to the
    following language from the one-page flyer distributed by
    Sika:
    - ANNUAL CONTRACTOR REVIEW TO BE HELD
    WITH EACH SIKA APPROVED CONTRACTOR
    COVERING:
    ....
    2
    Plaintiff also alleges that Sika breached the contract by failing
    to enter a joint advertising campaign and provide it with cured
    product samples. These arguments were not developed in J.S.
    Sweet’s lead brief and, although discussed in its reply, are for-
    feited. See Employers Ins. of Wausau v. Browner, 
    52 F.3d 656
    ,
    665-66 (7th Cir. 1995) (arguments pressed before the district court
    but not raised in appellant’s opening brief are forfeited even if
    developed in reply brief).
    No. 04-2871                                                 13
    - DISCUSSION OF CONTRACTOR NEEDS (TRAIN-
    ING, PRODUCTS INFORMATION, FIELD SUPPORT,
    ETC.).
    (Pls.’ App. at 38.)
    This argument suffers from numerous flaws. First, there
    is no indication from the face of either the approved contrac-
    tor agreement or the flyer that the flyer modifies the
    contract between the parties. The flyer is not signed, and
    neither instrument explicitly incorporates the other.
    Second, assuming that the flyer comprises a portion of the
    contract, it mentions only “field support”; neither document
    refers to “technical support.” Nevertheless, J.S. Sweet
    points to the deposition testimony of one of its employees
    stating that he thought the flyer guaranteed technical
    support. Plaintiff argues that summary judgment was
    improper because a jury must decide whether the em-
    ployee’s interpretation was correct. But the employee’s
    misapprehension about what the flyer says cannot be used
    to rewrite the terms of the document or create an issue of
    fact for trial. See, e.g., Heredia v. Sandler, 
    605 N.E.2d 1212
    ,
    1216 (Ind. Ct. App. 5th Dist. 1993) (“[T]his court will not
    rely on, nor are we bound by, an erroneous construction
    placed upon the contract by a party.”).
    Third, even if “field support” means “technical support,”
    the flyer does not obligate Sika to provide this service.
    Rather, it merely contemplates that Sika’s annual review
    with Sweet will “COVER[ ]” a “DISCUSSION OF CON-
    TRACTOR NEEDS,” including the need for field support.
    Although plaintiff asserts that the flyer is ambiguous and
    therefore must be construed against Sika, its drafter, we
    hold that the document cannot reasonably be interpreted as
    obligating Sika to explain the problems on the bridge.
    Accordingly, the district court properly granted summary
    judgment in favor of defendant on the breach of contract
    claim.
    14                                          No. 04-2871
    III. Conclusion
    For the reasons stated herein, we AFFIRM the district
    court’s grant of summary judgment.
    A true Copy:
    Teste:
    ________________________________
    Clerk of the United States Court of
    Appeals for the Seventh Circuit
    USCA-02-C-0072—3-16-05