Carnes Company v. Stone Creek Mechanic ( 2005 )


Menu:
  •                           In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 04-1244
    CARNES COMPANY,
    Plaintiff-Appellee,
    v.
    STONE CREEK MECHANICAL,
    INCORPORATED,
    Defendant-Appellant.
    ____________
    Appeal from the United States District Court
    for the Western District of Wisconsin.
    No. 02 C 208—Barbara B. Crabb, Chief Judge.
    ____________
    ARGUED NOVEMBER 5, 2004—DECIDED JULY 5, 2005
    ____________
    Before EASTERBROOK, MANION, and SYKES, Circuit Judges.
    SYKES, Circuit Judge. Carnes Company, a Wisconsin-
    based manufacturer of heating, ventilation, and air-condi-
    tioning (“HVAC”) equipment, entered into an agreement to
    sell “energy recovery units” to Stone Creek Mechanical for
    use in a Pennsylvania HVAC project on which Stone Creek
    was the general mechanical contractor. When the parties’
    relationship unraveled, Carnes commenced this breach of
    contract action alleging nonpayment on the part of
    Stone Creek, and Stone Creek counterclaimed for damages
    caused by Carnes’ alleged nonperformance. After a bench
    2                                                No. 04-1244
    trial the district court found that Stone Creek had breached
    the contract and awarded Carnes $401,922 in contract
    damages and $219,614.74 in attorney fees, as provided in
    the agreement. Stone Creek appeals. We affirm.
    I. Background
    In their appellate briefing the parties present very differ-
    ent versions of the pertinent events that combined to doom
    their contractual relationship. Carnes’ statement of facts
    traces the district court’s factual findings; Stone Creek
    essentially ignores the district court findings and tells a
    very different story of the parties’ relationship and course
    of dealing. We view Stone Creek’s approach as largely an
    attempt to retry the case on appeal. This is improper. Find-
    ings of fact entered after trial to the court are reviewed
    under the clearly erroneous standard of review, FED. R. CIV.
    P. 52(a), and an appellate court oversteps its bounds if it
    attempts to duplicate the role of the trial court. Anderson v.
    Bessemer City, 
    470 U.S. 564
    , 573 (1985). The party alleging
    error bears the burden of demonstrating that particular
    factual findings were clearly erroneous. Brunswick Leasing
    Corp. v. Wis. Cent., Ltd., 
    136 F.3d 521
    , 526 (7th Cir. 1998).
    In other words, it is entirely improper for us to “try the case
    de novo on the record.” United States v. Oregon State Med.
    Soc’y, 
    343 U.S. 326
    , 332 (1952); see also Zenith Radio Corp.
    v. Hazeltine Research, Inc., 
    395 U.S. 100
    , 123 (1969) (“In
    applying the clearly erroneous standard to the findings of
    a district court sitting without a jury, appellate courts must
    constantly have in mind that their function is not to decide
    factual issues de novo.”).
    A finding of fact is clearly erroneous only when the
    reviewing court is left with the definite and firm conviction
    that a mistake has been committed. United States v. United
    States Gypsum Co., 
    333 U.S. 364
    , 395 (1948); Bowles v.
    Quantum Chemical Co., 
    266 F.3d 622
    , 630 (7th Cir. 2001).
    No. 04-1244                                                   3
    If there are two permissible views of the evidence, the trial
    court’s choice between them cannot be clearly erroneous.
    Anderson, 
    470 U.S. at 574
    . Where the district court’s
    account of the facts is “plausible in light of the record,” we
    may not reverse it even if we would have decided the case
    differently, and any reasonable doubts we may harbor
    should be resolved in favor of the district court’s ruling “in
    light of its greater immersion in the case.” Cent. States, S.E.
    & S.W. Areas Pension Fund v. Kroger Co., 
    226 F.3d 903
    , 910
    (7th Cir. 2000). We also afford great deference to the trial
    court’s assessment of witness credibility; indeed, we have
    stated that a trial court’s credibility determination “can
    virtually never amount to clear error.” Lac du Flambeau v.
    Stop Treaty Abuse-Wisconsin, Inc., 
    41 F.3d 1190
    , 1194 (7th
    Cir. 1994).
    The following are the facts as found by the district court
    after trial: Carnes is incorporated and based in Wisconsin
    and manufactures HVAC equipment. Stone Creek is a
    Pennsylvania mechanical contractor.1 In May 2000 Stone
    Creek was awarded a contract for the installation of HVAC
    equipment in three Pennsylvania schools. Stone Creek,
    initially working through an “independent sales representa-
    tive” called Chase & Associates, approached Carnes to de-
    termine whether Carnes could provide 50 “energy recovery
    units” for use in the project. In March 2001 Stone Creek
    sent Carnes a purchase order concerning the manufacture,
    sale, and delivery of the 50 units for a total price of
    $640,000. Carnes did not immediately accept Stone Creek’s
    purchase order. Negotiations continued, and Stone Creek
    asked Carnes to provide warranty information concerning
    the work Carnes was being asked to perform. On April 5,
    2001, Carnes provided Chase with the warranty docu-
    mentation, which in turn was forwarded to Stone Creek.
    1
    Jurisdiction is based upon diversity of citizenship, 
    28 U.S.C. § 1332
    (a), and the parties agree that Wisconsin law applies.
    4                                              No. 04-1244
    The warranty documentation was actually titled “Terms,
    Conditions, and Warranty” and included Carnes’ payment
    terms and conditions: payment must be made within thirty
    days of invoicing; late payment charges and interest in the
    amount of 1.5% per month would be assessed; and in the
    event of nonpayment, Stone Creek would be responsible for
    paying Carnes’ costs of collection, including reasonable
    attorney fees. The documentation further provided that
    these payment conditions would be deemed accepted by
    Stone Creek if there was no objection within five days.
    On June 27, 2001, negotiations between Carnes, Stone
    Creek, and Chase culminated in a letter written that date
    from Carnes to Stone Creek’s president indicating that
    Carnes agreed to perform a portion of the purchase order
    and that it was “assigning” another portion of the work to
    Chase. The letter detailed the aspects of the work Carnes
    would perform and the amount it would charge ($527,000),
    and contained a similar breakdown of the work that Chase
    would perform and the amount that Chase would bill di-
    rectly to Stone Creek ($113,000). The letter asked Stone
    Creek’s authorized representative to sign and return the
    letter as an acknowledgment and acceptance of this ar-
    rangement or, alternatively, to “please advise immediately
    if the aforementioned assignment is not acceptable. . .”
    (emphasis in original).
    Stone Creek did not notify Carnes of any objection to the
    proposed assignment of responsibilities between Carnes and
    Chase. On July 16, 2001, Stone Creek’s president, Richard
    Worth, signed the letter and faxed the signed document to
    Carnes. However, unbeknownst to Carnes, Worth used
    correction fluid to “white out” the dollar amounts allocated
    to Carnes and Chase, respectively. The Carnes employee
    who received the faxed document filed it without noticing
    Worth’s “white-out” deletions.
    The parties thereafter agreed on a production schedule
    under which Carnes would deliver the first 19 units to
    No. 04-1244                                                5
    Stone Creek by August 24, 2001. Carnes’ agreement to this
    delivery schedule was contingent upon Stone Creek’s pay-
    ment of an additional expediting charge reflecting the fact
    that initial negotiations had only contemplated the com-
    pletion of nine units by this time.
    Major stumbling blocks to the amicable completion of the
    parties’ relationship arose almost immediately, and these
    were resolved with a series of agreements that attempted to
    keep the project on track. First, it became apparent early on
    that Chase would be unable to perform all of the tasks it
    had been assigned under the purchase order acknowledg-
    ment. In an attempt to keep the manufacture and delivery
    of the first 19 units on schedule, Worth assumed several of
    Chase’s tasks himself, including ordering the “curbs, coils
    and variable frequency fans” needed for production of
    the units Carnes was manufacturing. Stone Creek also
    assumed the role of guarantor of payments Chase owed to
    component suppliers.
    Second, several “Invensys controls” and “variable fre-
    quency drives” necessary for Carnes to manufacture and
    ship the 19 units by August 24 did not arrive at Carnes’
    plant in a timely fashion. The parties agreed to resolve this
    dilemma with an agreement that Carnes would ship the
    units without the controls and that Stone Creek would in-
    stall them itself upon delivery. In exchange Carnes agreed
    to cancel the expediting charge that had been negotiated in
    connection with the August 24 delivery date.
    Carnes began shipping the units to Stone Creek on
    August 21, 2001. Invoices sent with the units specified the
    payment terms Carnes had earlier provided to Stone Creek:
    payment due within thirty days; late payment interest
    charges of 1.5% per month; and, in the event of nonpay-
    ment, Stone Creek would be responsible for costs of col-
    lection, including reasonable attorney fees. Each invoice al-
    so contained the following language: “Buyer will be deemed
    6                                               No. 04-1244
    to have assented to these terms and conditions unless Seller
    receives written notice of any objection within 5 days of the
    date Buyer receives this writing[.]”
    In early September 2001 Chase began submitting bills to
    Stone Creek that exceeded the $113,000 allocated to it for
    its work under the purchase order. In light of Chase’s
    shortcomings in performance to that point, Stone Creek was
    not pleased with this development. On September 13, 2001,
    Worth notified Carnes that Stone Creek would not make
    any payments for the units already delivered until he
    received engineering drawings representing the units as
    built (referred to as “as-built submittals”). Carnes sent the
    submittals by overnight mail that very day, and tracking
    information on the package indicated that Worth received
    them on September 14. On October 2, 2001, when no
    payment had been made on any of Carnes’ invoices, Carnes
    notified Stone Creek that it would cease production of the
    remaining units until Stone Creek paid for the completed
    shipments. On October 5, 2001, Stone Creek paid some, but
    not all, of the outstanding invoices. On October 18, Carnes
    notified Stone Creek that it would not ship any more units
    until payment on all outstanding invoices was made.
    On October 24, 2001, in an effort to break the impasse, a
    telephone conference was held between the two principals,
    Worth on behalf of Stone Creek and Gregory Cichon,
    Carnes’ general manager. The following day Worth wrote to
    Cichon memorializing the oral agreement reached on the
    telephone. The letter stated that Stone Creek agreed to pay
    two of Carnes’ outstanding invoices by October 26, 2001,
    and that in exchange, Carnes agreed to expedite the
    pending manufacture of “energy recovery unit #2” for de-
    livery by November 5, 2001. Worth also agreed to pay an
    additional expediting cost in connection with unit #2.
    Worth’s letter also stated that on October 29, 2001, Stone
    Creek “will receive” final approval from the project engineer
    of Carnes’ as-built submittals and that such approval “will
    No. 04-1244                                                 7
    release for payment any invoices . . . over 30 days old.”
    Payment on such invoices, the letter continued, “will be
    made on or before November 17th[,] 2001.” Finally, Worth’s
    letter stated that “all future invoices for materials as
    received by Stone Creek Mechanical, Inc. will be paid net 30
    days as agreed.” The letter made no mention of any agree-
    ment (or even a demand by Stone Creek) to offset the
    invoiced amounts by the cost of the performance deficiencies
    on the part of Chase or for Stone Creek’s purchase and
    installation of component parts on the units. The letter
    closed by noting that Worth would be out of the country and
    unable to communicate with Carnes from October 26 until
    November 11, 2001.
    On October 26, 2001, Carnes received payment on the two
    invoices as promised in the October 25 letter. Carnes
    completed its expedited production of unit #2 and shipped
    it to Stone Creek, together with three other completed
    units. At this point Carnes had shipped a total of 31 units
    to Stone Creek, exactly the number needed by Stone Creek
    to complete the first phase of its contract with the school
    district in Pennsylvania.
    On November 6, 2001, shortly after the units were
    shipped and during the time Worth claimed to be out of the
    country, Worth sent a letter to Carnes’ parent company,
    Venturedyne, stating that no further payments would be
    made to either Carnes or Chase. In the letter Worth
    claimed that Stone Creek never agreed to any assignment
    of a portion of the purchase order to Chase; that Carnes
    (and not Stone Creek) was responsible for paying Chase’s
    invoices; and that Carnes had agreed to assume the costs
    incurred by Stone Creek for purchasing and installing the
    component curbs, coils, rails, and drives on the completed
    units. Attached to this letter were copies of letters purport-
    edly chronicling the history of the parties’ relationship and
    providing support for Stone Creek’s decision to cease
    payment.
    8                                               No. 04-1244
    The district court found that at least five of the attached
    letters were fabricated by Worth and never received by
    Carnes. These letters, bearing various dates during July-
    August 2001, ostensibly indicated agreements between the
    parties that Carnes would be responsible for the cost of
    components purchased and installed by Stone Creek; that
    Carnes would be responsible for the payment of state sales
    taxes; and that Stone Creek objected to and rejected the
    payment terms and conditions contained on Carnes’ in-
    voices and warranty verifications. The district court found
    that if these letters had in fact been sent, Carnes never
    would have built a single unit for Stone Creek.
    Carnes received no further payments and shipped no ad-
    ditional units to Stone Creek. Negotiations were attempted
    but Carnes refused to ship any more units unless its out-
    standing invoices were paid and advance payment was
    made for any future shipments. No agreement was ever
    reached and Carnes cancelled the contract on March 7,
    2002.
    On the basis of the foregoing facts, the district court
    concluded that: (1) the payment and collection terms and
    conditions contained in Carnes’ warranty verification and
    invoices formed a part of the parties’ agreement; (2) the
    October 25, 2001, letter from Stone Creek modified the
    existing agreement and committed Stone Creek to pay all
    outstanding invoices without any of the “offsets” it later
    claimed and retrospectively attempted to document via the
    fabricated letters; (3) Stone Creek breached the modified
    agreement when it failed to make payments as agreed in
    the October 25 letter; (4) Carnes acted within its rights
    when it ceased shipping product to Stone Creek after the
    breach; (5) under the modified agreement Carnes had no
    responsibility for the portion of the original purchase order
    assigned to Chase; (6) Carnes did not repudiate the contract
    when it demanded full payment and refused to make
    deductions for cost overruns occasioned by Chase’s failure
    No. 04-1244                                                  9
    to perform its portion of the project; and (7) there was no
    language in the October 25 letter conditioning Stone Creek’s
    liability for payment on approval of Carnes’ engineering
    drawings by the project engineer.
    As a preface to its conclusions on these issues, the district
    court went to great pains to unambiguously declare that
    Worth’s testimony was not credible and that the evidence
    was “irrefutable” that he fabricated the letter attachments
    to his November 6, 2001, letter to Venturedyne. The court
    cited several items of evidence supporting these findings,
    including: (1) discrepancies in fax headings and page
    numbers on the letters; (2) Worth’s surreptitious use of
    correction fluid to delete portions of Carnes’ June 27 letter;
    (3) numerous occasions on which Worth promised payments
    to Carnes that were never forthcoming; (4) Worth’s false
    representation in the October 25 letter that he would be out
    of the country until after the date on which Carnes would
    ship the final four units needed to complete the first phase
    of the project; (5) the fact that he had been preparing the
    November 6 letter to Venturedyne while simultaneously
    assuring Carnes that he would make payments if the final
    four units were shipped; (6) the fact that he did not send
    the November 6 letter until after he was aware that the
    four units had been shipped; and (7) a boast he had made to
    Carnes’ manufacturer’s representative that he “says one
    thing and then does another.” In addition, the district court
    held that Worth testified falsely in a number of respects,
    including denying that Stone Creek had received the
    information about contract terms from Carnes through
    Chase, when the evidence established that Chase had
    forwarded the information.
    The court awarded damages in the amount of
    $231,930.17, plus interest at the rate of 1.5% per month, for
    the units Stone Creek received but never paid for. The court
    also awarded $169,992.19 for units that had been manufac-
    10                                              No. 04-1244
    tured but not shipped and which Carnes could not resell, as
    well as $219,614.74 in attorney fees.
    II. Discussion
    A. Carnes’ Terms and Conditions
    Stone Creek argues that the district court erred in finding
    that Carnes’ payment and collection terms (including the
    interest and attorney fees provision) were incorporated into
    the parties’ agreement. The district court held that the
    terms were binding on Stone Creek because Stone Creek
    had been fully apprised of and accepted (by failing to object
    to) these terms prior to Carnes’ formal acceptance of the
    purchase order in its letter of June 27. As noted above,
    Carnes sent Stone Creek its “Terms, Conditions, and
    Warranty”on April 5, 2001, and this document stated in
    relevant part:
    This writing constitutes the complete and exclusive
    statement of the terms and conditions of sale of the
    products and/or services described herein, and Seller’s
    obligation to sell is expressly conditioned upon assent
    to these terms and conditions. Buyer will be deemed to
    have assented to these terms and conditions unless
    Seller receives written notice of any objection within 5
    days of the date Buyer receives this writing . . . .
    Stone Creek argues that because this document was
    provided to Chase, not Stone Creek, the district court’s
    finding that Stone Creek was aware of Carnes’ terms was
    clearly erroneous. We disagree. First, Stone Creek, not
    Chase, requested Carnes’ warranty information. Indeed,
    Carnes’ warranty verification was required by Stone Creek
    under the terms of the purchase order, and Stone Creek’s
    request for the information was prompted by a demand for
    it from the project engineer. The document was passed from
    Carnes to Chase with the understanding that it would be
    No. 04-1244                                                    11
    forwarded to Stone Creek in compliance with the latter’s
    request, and the district court specifically discredited
    Worth’s testimony that Stone Creek had not received
    information that Carnes transmitted to it through Chase.
    In addition, there is no evidence that Stone Creek was
    forced to make a second request for warranty verification.
    Finally, one of the letters the district court found to have
    been fabricated by Worth included a statement to the effect
    that Stone Creek did not accept Carnes’ “Terms, Conditions
    and Warranty2.” If Stone Creek had never received the
    terms-and-conditions document, Worth would not have
    attempted to disclaim it, even in a letter prepared sometime
    after its purported date of mailing. The fact that this letter
    sought to affirmatively disavow any acceptance of Carnes’
    payment terms is evidence that Stone Creek considered
    itself bound in the absence of a falsified document rejecting
    the conditions.
    Stone Creek also argues that it is not “reasonable” to hold
    it to Carnes’ payment terms because the “Terms, Condi-
    tions, and Warranty” document was provided in response to
    Stone Creek’s request for warranty verification alone. Stone
    Creek offers no authority for the proposition that a contrac-
    tual term cannot be incorporated into an agreement in this
    way. In any event, the district court properly held that
    Carnes’ payment terms and conditions are among those
    “additional terms” that are customarily included in invoices
    and considered incorporated in the parties’ contract unless
    certain exceptions, not applicable here, apply. See WIS.
    STAT. § 402.207; Advance Concrete Forms, Inc. v. McCann
    Constr. Specialties Co., 
    916 F.2d 412
    , 415 (7th Cir. 1990)
    (applying Wisconsin law); Mid-State Contracting, Inc. v.
    Superior Floor Co., 
    655 N.W.2d 142
    , 145 (Wis. App. 2002).
    2
    This letter was dated July 10, 2001, and Stone Creek has not
    taken issue with the district court’s conclusion that Worth fabri-
    cated this letter after the fact.
    12                                              No. 04-1244
    B. Modification of the Contract
    Stone Creek next contends that the district court erred in
    finding that the parties’ agreement was modified by Worth’s
    October 25, 2001, letter. Whether a contract has been
    modified is a question of fact subject to the clearly errone-
    ous standard of review. Am. Suzuki Motor Corp. v. Bill
    Kummer, Inc., 
    65 F.3d 1381
    , 1386 (7th Cir. 1995) (applying
    Wisconsin law); Kohlenberg v. Am. Plumbing Supply Co.,
    
    263 N.W.2d 496
    , 500 (Wis. 1978). The existence of an
    agreement modifying a previous contract is “established in
    the same way as any other contract.” Kohlenberg, 263
    N.W.2d at 500. The acts relied upon to modify a prior con-
    tract must be unequivocal in character, and acts that are
    ambiguous as to whether a modification was intended are
    not sufficient to establish a modification. Am. Suzuki, 
    65 F.3d at
    1386 (citing Nelsen v. Farmers Mut. Auto Ins. Co.,
    
    90 N.W.2d 123
    , 134 (Wis. 1958)). While the effect of a
    modification may be the creation of a new contract, that
    contract consists of not only the new terms agreed upon but
    those terms of the original contract which were not modi-
    fied. Estreen v. Bluhm, 
    255 N.W.2d 473
    , 479 (Wis. 1977).
    In the face of its burden to demonstrate clear error, Stone
    Creek argues only that the October 25 letter “merely set
    forth the parties’ agreement regarding payment of the
    invoices Carnes’ asserted were past due, and nothing more.”
    But the evidence supports the conclusion that the letter was
    intended as far more. At the time, Carnes was accusing
    Stone Creek of breaching the agreement and was with-
    holding shipments based upon nonpayment. Stone Creek
    needed four additional units to complete the first phase of
    its contract with the school district and was required to
    make concessions in order to break the parties’ impasse and
    induce Carnes to ship the additional units. The agreements
    memorialized in the October 25 letter specified that Stone
    Creek would pay Carnes for the two oldest invoices immedi-
    ately, get current on other outstanding invoices within a
    No. 04-1244                                                 13
    few weeks, and pay invoices on additional units to be
    shipped on the original thirty-day terms, in exchange for
    Carnes’ promise to expedite the manufacture of unit #2 and
    ship it on or before November 5, 2001.
    The district court properly concluded that Carnes’ agree-
    ment to permit Stone Creek to pay in this manner and to
    expedite the manufacture of unit #2 in exchange for Stone
    Creek’s promise to adhere to the specified payment sche-
    dule was a modification of the contract. Stone Creek has not
    demonstrated that this finding was clearly erroneous.
    C. Breach and Repudiation
    Stone Creek takes issue with the district court’s conclu-
    sion that it breached the terms of the modified contract
    when it refused to make any payments after October 26,
    2001. Whether Stone Creek breached the terms of the modi-
    fied contract requires an interpretation of the modified
    contract, which is a question of law that we review de novo.
    Designer Direct, Inc. v. DeForest Redevelopment, 
    313 F.3d 1036
    , 1041 (7th Cir. 2002) (applying Wisconsin law). Stone
    Creek’s argument flows from language in the October 25
    letter stating that “Stone Creek . . . will receive on 10/29/01
    final approval of the submittal information[.] The approval
    of this information will release for payment any invoices . . .
    over 30 days old. Payment for these invoices will be made
    on or before November 17th[,] 2001.”
    Based on this language, Stone Creek argues that it did
    not breach the modified contract because it only promised
    to pay if and when the project engineer approved Carnes’
    submittals. Apparently the project engineer never actually
    gave such approvals, although the record does not elaborate
    as to why this is so. The district court examined the
    language of the October 25 letter and concluded that there
    was no such condition attached to Stone Creek’s promise to
    pay, and we agree with this interpretation. The letter pre-
    14                                              No. 04-1244
    sents the approvals as a fait accompli, not as a condition
    that may or may not occur and upon which Stone Creek’s
    obligation to pay depends. The letter presents the approval
    issue as an assurance to Carnes that payment will be
    forthcoming very soon, and even promises a date certain by
    which payment will be made. The district court correctly
    concluded that Stone Creek breached the modified contract.
    Stone Creek argues that Carnes engaged in an anticipa-
    tory repudiation of the contract when Cichon notified Worth
    that Carnes was not responsible for cost overruns associ-
    ated with Chase’s nonperformance and that Carnes was not
    responsible for tasks assigned to Chase under the purchase
    order. Anticipatory repudiation of a contract occurs “when
    either party repudiates the contract with respect to a
    performance not yet due, the loss of which will substantially
    impair the value of the contract to the other.” WIS. STATS.
    § 402.610 (UCC 2-610). In order to constitute an anticipa-
    tory repudiation of a contract, there must be a definite and
    unequivocal manifestation of intention on the part of the
    repudiator that he will not render the promised perfor-
    mance when the time fixed for it in the contract arrives.
    Wis. Dairy Fresh, Inc. v. Steel & Tube Prods. Co., 
    122 N.W.2d 361
    , 367 (Wis. 1963).
    We find no merit to Stone Creek’s anticipatory repudia-
    tion argument for several reasons. First, the evidence does
    not support Stone Creek’s position that Carnes had ac-
    cepted responsibility for the cost overruns attributable to
    Chase under the original purchase agreement, much less
    the agreement as modified in the October 25 letter. From
    the very beginning of the parties’ relationship, Stone Creek
    assumed duties that had been assigned to Chase under the
    original purchase agreement, such as ordering the “curbs,
    coils and variable frequency fans” and guaranteeing Chase’s
    payments to suppliers. Prior to the shipment of the final
    four units needed to complete phase one of the project,
    Stone Creek never suggested to Carnes that these tasks,
    No. 04-1244                                               15
    assigned to Chase, were actually Carnes’ responsibility. Not
    once did Stone Creek apprise Carnes of the costs it was
    incurring as a result of Chase’s inability to perform its as-
    signed tasks. Not once did Stone Creek suggest to Carnes
    that it would be claiming an offset against Carnes’ invoices
    for cost overruns incurred by Chase or for costs incurred by
    Stone Creek for having to assume Chase’s responsibilities.
    To the contrary, the evidence supports the conclusion that
    it was not until November 6, 2001, after he had unam-
    biguously promised full payment and after Carnes shipped
    the four units in compliance with the modified agreement
    that Worth first indicated that he considered Carnes
    responsible for these costs and would make no further
    payments to Carnes as a result. Indeed, the district court
    held that Worth’s November 6 letter attempted to prove an
    understanding between the parties as to Carnes’ responsi-
    bility for Chase’s nonperformance only by resorting to
    falsified documents ostensibly evidencing that this was the
    agreement all along. In short, the evidence fully supports
    the conclusion that Worth placated Carnes with promises
    of full payment until he had gotten what he needed, and
    only then did he raise the issue of offsets by resorting to
    fabricated documents.
    Stone Creek’s second basis for arguing that Carnes either
    breached or repudiated the contract is that after Worth sent
    the November 6 letter indicating that no future payments
    would be forthcoming, Carnes refused to ship any more
    product in the absence of the payment promised in the
    October 25 letter as well as advance payment for any future
    shipments. We agree with the district court’s conclusion
    that far from being a repudiation of the contract by Carnes,
    the refusal to ship was a legally justifiable response to
    Stone Creek’s repudiation of the contract in its November
    6 letter.
    First, there can be little doubt that Worth’s November 6
    letter, coming directly on the heels of the October 25 letter
    16                                               No. 04-1244
    setting forth the modified payment-and-delivery schedule,
    was a repudiation of the contract by Stone Creek. The
    November 6 letter unequivocally states that “[n]o further
    payments of any kind will be made to Carnes Company”
    until Carnes picked up the cost of Chase’s deficient per-
    formance. This plainly is a manifestation of Stone Creek’s
    intention not to perform. Wis. Dairy Fresh, 122 N.W.2d at
    367. At this point Carnes could properly treat the contract
    as having been repudiated. In addition, Carnes’ response to
    the November 6 letter was consistent with its rights under
    WIS. STATS. § 402.609(1) (UCC 2-609):
    When reasonable grounds for insecurity arise with re-
    spect to the performance of either party the other may
    in writing demand adequate assurance of due perfor-
    mance and until the demanding party receives such
    assurance may if commercially reasonable suspend any
    performance for which the demanding party had not
    already received the agreed return.
    When Carnes received the November 6 letter indicating
    that no payments would be made, it had more than ample
    grounds for insecurity as to Stone Creek’s performance un-
    der the terms of the modified agreement. Carnes’ response,
    to suspend any performance until adequate assurances of
    performance were forthcoming, was commercially reason-
    able in light of the history of the parties leading up to that
    point.
    Accordingly, the evidence supports the district court’s
    conclusion that Stone Creek—not Carnes—breached the
    parties’ modified agreement. The judgment of the district
    court is AFFIRMED.
    No. 04-1244                                        17
    A true Copy:
    Teste:
    ________________________________
    Clerk of the United States Court of
    Appeals for the Seventh Circuit
    USCA-02-C-0072—7-5-05