International Production Speci v. Schwing America Incorporated ( 2009 )


Menu:
  •                            In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 07-3632
    INTERNATIONAL P RODUCTION S PECIALISTS, INC.,
    Plaintiff-Appellant,
    v.
    S CHWING A MERICA, INC.,
    Defendant-Appellee.
    Appeal from the United States District Court
    for the Eastern District of Wisconsin.
    No. 05 C 621—Rudolph T. Randa, Chief Judge.
    A RGUED S EPTEMBER 5, 2008—D ECIDED S EPTEMBER 2, 2009
    Before F LAUM, R OVNER and W ILLIAMS, Circuit Judges.
    R OVNER, Circuit Judge. International Production Special-
    ists, Inc. (IPS) entered into a contract with Schwing Amer-
    ica, Inc. (Schwing) to make and install five silos to store
    and treat sludge at a wastewater treatment plant owned
    by the general contractor, North Shore Sanitary District
    (NSSD). Initially IPS’s piece of the process was to take
    about eight months. After several years of delays—some
    attributable to NSSD, some to IPS, and some to events
    2                                               No. 07-3632
    beyond anyone’s control—nearly three-and-a-half years
    after the parties signed the initial purchase order, the
    project still had not been completed. On February 11,
    2005, Schwing notified IPS that it was cancelling the
    contract for cause. IPS responded by suing for breach
    of contract and Schwing countersued. The district court
    ruled in favor of Schwing, awarding damages in the
    amount of $467,140.02. We affirm, but remand in part
    to correct a small error in the calculation of damages.
    I.
    This case comes to this court after a trial in the district
    court. The facts of this case, as determined by the trial
    court, are long and tedious, but necessary for a full under-
    standing of the intricacies of the relationship between
    the parties.
    Schwing and IPS were both subcontractors on a
    larger project to build a wastewater treatment facility. In
    2001, NSSD hired Voest-Alpine Industries, Inc. (VA Tech)
    to work on the construction of its new wastewater treat-
    ment plant in Waukegan, Illinois, agreeing to pay it
    $6.6 million. VA Tech, in turn, entered into a $1.25 million
    subcontract with Schwing to supply and install two
    wet sludge silos, a dry granules silo (conical silos), two
    receiving bins, and other associated equipment for the
    NSSD facility. Pursuant to the terms of the contract
    with VA Tech, Schwing obtained a performance bond.
    Schwing’s operations manager, Nancy Predatsch,
    decided to find a local contractor to fabricate the silos. A
    No. 07-3632                                                       3
    web search turned up IPS, a Wisconsin manufacturer of
    construction equipment, including standard and custom
    built bulk material handling equipment. On August 20,
    2001, IPS and Schwing executed a purchase order in
    which, for payment of $666,372, IPS agreed to manu-
    facture and install at the NSSD Waukegan facility the
    five silos, incorporating the specifications and technical
    supplies from the VA Tech-Schwing contract.
    By attachment, the parties set forth a delivery, installa-
    tion, and payment schedule. (D. Exh. 1004 at p.4)1 . Accord-
    ing to the delivery schedule, IPS was to deliver all of the
    silos (the two receiving bins, the two wet storage, and
    the one dry storage) by December 28, 2001. The installa-
    tion schedule was labeled “approximate” and noted the
    following dates:
    Two (2) Sliding Frame Silos (Receiving Bin), Approxi-
    mately February 1, 2002 2
    Two (2) Sliding Frame Silos (Wet Storage), Approxi-
    mately February 15, 2002
    1
    Exh. References are to district court trial exhibits; D. Exh. to
    the defendant, Schwing’s exhibits and Pl. Exh. to the plaintiff,
    IPS’s exhibits. Tr. references are to pages in the trial transcript.
    2
    The purchase order actually lists these dates as 2001, but it
    seems clear that this is a scrivener’s error and should be 2002.
    Of course the equipment could not be installed until after it
    was delivered. Furthermore, when the parties signed the
    purchase order on September 5, 2001, the February and
    April 2001 dates would have been nine and four months past,
    respectively.
    4                                              No. 07-3632
    One (1) Conical Silo (Dry Storage), Approximately April
    15, 2002
    
    Id. A note
    below the schedule states, “[a]ctual schedule
    will be dictated by progress on the plant construction
    contract. Installation activity will need to be co-
    ordinated with the site contractor.” 
    Id. The delivery
    schedule contains no such approximate language.
    IPS’s Executive Vice President, Jordan Kopac, Jr. man-
    aged IPS’s work directly on site as IPS worked
    through the late summer and fall 2001. Schwing made
    progress payments to IPS totaling $595,692.
    In November 2001, NSSD decided to suspend work
    on the project. Consequently, on November 30, 2001,
    Schwing sent IPS a facsimile directing IPS to cease on-site
    work, but to continue fabricating the two receiving bin
    silos at the shop, as scheduled. Schwing also informed
    IPS that it could continue to deliver materials to the
    site and unload them, but they should not be fabricated
    on site. Schwing estimated that the work stoppage
    would continue for ninety days and asked IPS to
    inform Schwing of any cost changes associated with the
    schedule change.
    On April 11, 2002, VA Tech inspected IPS’s work on
    the silo parts. Representatives from VA Tech, NSSD, IPS,
    and Schwing attended the inspection. The next day, a
    Schwing representative sent out an e-mail identifying
    fifteen problems with the silos including improper
    painting and welding. (Pl. Exh. 17). A VA Tech represen-
    tative also prepared a memorandum noting manu-
    facturing defects , including poor painting and improper
    No. 07-3632                                             5
    welding. (Pl. Exh. 18). At the time of the memorandum,
    90% of the receiving bin silo manufacturing had been
    completed, as had 50% of the wet sludge silos and 40% of
    the dried granules silos. Of course, no installation had
    begun or was yet required. After the inspection, the
    project lay dormant for approximately two years—until
    about February 19, 2004, when VA Tech notified Schwing
    that NSSD had restarted the project at a new site in Zion,
    Illinois and that VA Tech expected Schwing to honor
    its contract. VA Tech did not increase its payment to
    Schwing.
    Schwing, in turn, informed IPS that the project was
    restarting and that Schwing expected IPS to honor its
    contract. Schwing’s project manager asked IPS to inform
    him of any additional expenses that IPS might incur as
    a result of the change of location.
    IPS responded that a “deep silo fabrication lay-down
    area”—in layman’s terms a work area—would be neces-
    sary at the Zion site and would be used to fabricate
    and store the wet sludge silos on site. It provided two
    field service quotations for a total of $210,500.
    In spring 2004, representatives from Schwing, IPS, VA
    Tech, and NSSD met to view the project site, coordinate
    the silo construction site, discuss scheduling, and review
    potential lay down sites where IPS could work on the
    silos. Schwing asked IPS’s vice president, Kopac, to
    identify IPS’s lay-down area preference and to present
    Schwing with a proposal for reimbursement of the addi-
    tional costs for relocating the project and transporting
    materials.
    6                                              No. 07-3632
    After the meeting, IPS’s Kopac called Schwing’s project
    manager, David Miller once, but did not identify his lay-
    down area preference. Miller left a number of unreturned
    messages for Kopac and eventually called IPS’s president,
    Jordan Kopac, Sr., who informed Schwing that IPS
    would not be participating in the project because the
    new site was problematic. IPS maintains that had a
    suitable work area been provided, IPS would have been
    able to complete the project in three to four months. The
    new area, however, was a full-blown construction site
    and IPS believed that the lay down area and roadways
    were insufficient to complete the project.
    Schwing solicited bids from other companies to
    complete IPS’s work, but those bids were high compared
    to Schwing’s contract with VA Tech, factoring in the
    payments Schwing already had made to IPS. Consequently,
    Schwing wrote to IPS on June 10, 2004, asking IPS to
    honor the contract and resume work, or, in the alterna-
    tive, return all payments it received.
    IPS responded that the agreement it had made was for
    the Waukegan site and not the Zion site, stating further,
    IPS stands ready, willing and able to perform per
    its contract with Schwing. We are not willing, however,
    to modify the terms of our contract and commit to
    the performance at a new site that poses potential
    pitfalls and complexities that did not exist with
    respect to the Waukegan site. From a complexity of
    performance standpoint, the Zion site, being a full-
    blown construction project, is substantially more
    complex.
    (Pl. Exh. 4).
    No. 07-3632                                              7
    Notwithstanding IPS’s position, Schwing and IPS
    continued to negotiate. On July 12, 2004, IPS sent a
    quote to Schwing indicating that for approximately
    $264,084, it could complete the project at the Zion site.
    The quote contained three general notes (only note one
    and two are relevant to this appeal).
    GENERAL NOTE #1
    Additional costs from the original 2001 job quota-
    tion in Waukegan based on an August 2004 start
    date with the majority of the main & coned silo
    work expected to be completed by September 30th,
    2004.
    GENERAL NOTE 3:
    IPS has requested and to-date has not received a
    Zion Project time lines [sic] from Schwing, NSSD or
    the General Contractor. Therefore IPS will not be
    responsible for any monetary penalties on this
    project caused by unrealistic milestones, delays
    caused by others or acts of God.
    (D. Exh. 1012, 1017).
    On July 29, 2004, the project manager from Schwing
    e-mailed IPS’s Kopac a proposed change order which
    included nine additional work items with a proposed
    additional payment. IPS increased the change order
    price to $143,630 and noted the outstanding purchase order
    balance of $99,946, for a total price of $243,576. Kopac
    quickly sent a return e-mail back to Schwing proposed
    revisions including that general notes 1-3 of the July 12
    quotation be incorporated. IPS also requested a final
    paragraph that stated:
    8                                              No. 07-3632
    No other changes to this order apply at this time.
    Access to silo installation area infrastructure for
    eventual silo placement into the General Contractor[’]s
    facilities or the use of the General Contractor[’]s
    material handling equipment or requirements for
    the hiring of General Contractors labor personnel
    has not yet been established by Schwing America
    Project Manager and must be established. Additional
    charges may apply if accessibility is delayed or
    limited, and charges from the General Contractor or
    unforeseen issues arise.
    The modifications requested by IPS were incorporated
    into the final change order which was executed on
    August 12, 2004. (D. Exh. 1017)
    That same day, the new Schwing project manager sent
    Kopac a copy of a “classic layout schedule” common on
    large construction sites, scheduling activity at the site.
    The time line contained the following dates:
    activity         early start date    early finish date
    install truck    August 11, 2004     August 12, 2004
    receiving bins
    install wet      December 2, 2004 December 3, 2004
    sludge silos
    install dry      December 6, 2004 December 10, 2004
    granules silos
    (D. Exh. 1013)
    No. 07-3632                                              9
    Schwing made a 30% progress payment of $69,172 on
    August 9, 2004, and then again on August 24, 2009. IPS
    installed the two receiving bin silos on September 8,
    2004. On September 24, 2004, IPS’s Kopac sent Schwing
    an e-mail stating that NSSD had informed IPS that it
    wanted the remainder of the silos the first week of Octo-
    ber. Kopac told Schwing that this was the first he
    had heard of this time frame, and that IPS had been
    planning on delivering the first week of December, refer-
    encing the specific lines in the layout schedule which
    showed a December date for the wet silo installation. On
    October 29, 2004, IPS sent Schwing an invoice for a 20%
    progress payment. Schwing called IPS and noted that
    the underlying work had not been completed. IPS
    agreed, and thus Schwing withheld the payment.
    From this point forward, things began to deteriorate
    rapidly. Schwing’s operations manager began to hear
    reports that IPS was delaying the NSSD project and that,
    with only two workers on site, it was not providing
    adequate staff for the work. VA Tech began calling
    Schwing, threatening to call Schwing’s performance
    bond because the work was not progressing.
    By November 9, 2004, the Zion site was ready for the
    installation of the two wet sludge silos. IPS indicated
    that the two wet sludge silos would be installed by Decem-
    ber 20, 2004. On December 14, however, Schwing’s field
    project manager received a report of welding defects in
    IPS’s work. On December 22, 2004, Schwing asked IPS to
    provide a date for installation of the silos. IPS responded
    that the silos would be on transport trucks by January 21,
    2005, and ready for transportation by January 24.
    10                                            No. 07-3632
    Concerned about the delays, Schwing engaged its
    former project manager, David Miller, as an outside
    consultant to go to the Zion work site for two weeks and
    put matters back on track. Miller testified that the job
    site was in disarray and chaotic, that the two wet sludge
    silos were only fifty percent complete, that the dry
    storage silo had not been assembled, and pieces of it
    were still at the Waukegan site. He testified further that
    IPS had sufficient work space. Miller spent some time
    assisting with welding and fabrication.
    While Miller was on site, IPS’s Kopac raised concerns
    that the road was insufficient to transport the wet sludge
    silos from the lay down area to the building site. Kopac,
    Miller, and a representative from the general contractor,
    J.J. Henderson, walked the site, discussed the road condi-
    tions, and laid out flags indicating where Kopac wanted
    the general contractor to place additional gravel. At
    some point not identified in the record, J.J. Henderson
    put down the fresh gravel.
    On January 25, Schwing paid IPS’s outstanding
    October 29, 2004 invoice. On February 3, IPS sent a
    revised quotation with a cover note that stated “[t]his
    covers the eventualities that the delays in preparing the
    site continue for an unforeseen time” [sic] and proposed
    additional charges of $43,548.30. Schwing believed that
    the additional charges were improper because IPS
    included installation costs which were part of the
    original purchase order and were not removed in the
    change order. IPS believed that the change order did not
    address silo installation at the Zion site and therefore
    No. 07-3632                                               11
    the purchase order only obligated IPS to install at the
    Waukegan site.
    On the same day that IPS sent the revised quote,
    Schwing inspected the paint and noticed obvious un-
    painted stripes of white primer on the undersides of the
    wet sludge silos where they had been laying on the
    trailers when they were painted. The inspection also
    revealed other paint problems. By February 9 e-mail,
    Schwing advised IPS that it would be liable for any
    delay until the paint “is within specifications,” and advised
    IPS of other repairs that had to be made.
    In a February 11, 2005 letter, Schwing terminated IPS’s
    contract citing delays and the increased costs flowing
    therefrom. (D. Exh. 1034). The letter noted that the sched-
    ule required installation of the wet sludge silos by Novem-
    ber 30, 2004, and the dry granules silo by December
    2004. 
    Id. The letter
    also stated that IPS’s failure to
    complete the project within the agreed time frame
    caused delays and thus additional costs to the project
    for which Schwing would hold IPS liable. 
    Id. Schwing hired
    J.J. Henderson, Northeast Water Technol-
    ogies (NWT), and Manta Industrial and Prime Coat
    Corporation to finish the remaining work. Schwing paid
    J.J. Henderson $231,515.65 for labor, equipment, and
    rigging of the wet and dry sludge silos. It paid NWT
    $87,388.78 to complete fabrication of the dry granules silo
    and to transport four remaining sections of the roof and
    other miscellaneous pieces from Waukegan to Zion.
    Schwing paid Manta $202,730 to sandblast and re-paint
    the interior of the silos with coal tar epoxy, and paid
    12                                               No. 07-3632
    $24,826 to Prime Coat to paint the exterior of the three
    silos. (See D. Exh. 1039).
    IPS filed suit alleging that Schwing lacked cause for
    cancelling the contract and that Schwing was liable for
    IPS’s damages. Schwing counterclaimed arguing that it
    justifiably cancelled the contract after IPS breached and
    that IPS was liable for damages incurred by Schwing
    due to IPS’s delays and deficient performance.
    The action was initially filed by IPS in the Circuit Court
    for Racine County, Wisconsin but removed to the district
    court by Schwing as the parties are diverse and the
    amount in controversy exceeds $75,000. 28 U.S.C. § 1332.
    IPS is incorporated in Wisconsin with its principal place
    of business in Wisconsin and Schwing is incorporated
    in Minnesota with its principal place of business in Min-
    nesota. See Pastor v. State Farm Mut. Auto. Ins. Co., 
    487 F.3d 1042
    , 1047-1048 (7th Cir. 2007).
    After a two-day trial, the district court concluded (1) that
    Schwing was justified in cancelling the contract after IPS
    materially breached, (2) Schwing did not breach the
    contract, and (3) that Schwing sustained damages in the
    amount of $467,140.02. We affirm in most part and
    remand for a recalculation of damages.
    II.
    The parties dispute the standard by which we review
    various aspects of this case. “The fixing of the boundary
    between questions of law and questions of fact, is a matter
    of federal procedural law and therefore governed by
    No. 07-3632                                                  13
    federal rather than state law in diversity as in other
    federal suits.” Dilworth v. Dudley, 
    75 F.3d 307
    , 309 (7th
    Cir. 1996); Tax Track Sys. Corp. v. New Investor World, Inc.
    
    478 F.3d 783
    , 789 (7th Cir. 2007) (in a diversity suit when
    the judge acts as a fact finder the federal standard of
    review applies). Although the interpretation of an estab-
    lished written contract is generally a question of law for
    the court (Holmes v. Potter, 
    552 F.3d 536
    , 538 (7th Cir.
    2008), the question of whether or not a particular breach
    of a contract is material is a question of fact. ABM
    Marking, Inc. v. Zanasi Fratelli, S.R.L., 
    353 F.3d 541
    , 544 (7th
    Cir. 2003). Thus, we interpret the contract de novo but
    review the district court’s determination of whether IPS
    materially breached the contract for clear error. See
    United States v. Lake, 
    500 F.3d 629
    , 632 (7th Cir. 2007)
    (questions of law reviewed de novo; findings of fact
    for clear error).
    A. Breach of Contract
    The district court concluded, and the parties do not
    contest, that Wisconsin law applies to the agreement in
    this case. Under Wisconsin law, a material breach of
    contract releases the non-breaching party from perfor-
    mance of the contract. Mgmt. Computer Servs., Inc. v.
    Hawkins, Ash, Baptie & Co., 
    557 N.W.2d 67
    , 77 (Wis. 1996).
    A breach is material if it destroys the essential object of
    the agreement or deprives the non-breaching party of a
    benefit that the party reasonably expected. Ranes v. Am.
    Family Mut. Ins. Co., 
    580 N.W.2d 197
    , 200 (Wis. 1998);
    Mgmt. Computer Servs., 
    Inc., 557 N.W.2d at 77-78
    . In this
    14                                              No. 07-3632
    case, Schwing terminated the contract due to IPS’s failure
    to complete work satisfactorily within particular time
    frames. Consequently, the district court’s task was to
    determine whether fabrication and installation by a
    particular date was a benefit that Schwing reasonably
    expected and whether the delays and the claimed defects
    in performance destroyed the essential object of the
    contract.
    The first step in such a determination is identifying
    the contract and what it required. The district court
    determined that the September 5, 2001 purchase order,
    and the August 12, 2004 change order together formed
    the contract between the parties. (R. 32 at p.23). The
    question before this court is interpreting what, if
    anything, those orders say about performance standards
    and deadlines.
    When a contract is silent on the time for performance, a
    reasonable time is implied. Delap v. Inst. of Am., Inc., 
    143 N.W.2d 476
    , 478 (Wis. 1966); Wis. Stat. § 402.309(1). IPS
    argues that the contract here was such a “reasonable
    time” contract. We think the better interpretation is that
    the contract did indeed set forth specific dates for per-
    formance. As we ultimately conclude, however, whether
    the contract was one demanding performance within “a
    reasonable time,” or by a date certain, IPS failed to
    meet the requirement.
    The original 2001 purchase order clearly identified a
    time frame for performance, requiring delivery by Decem-
    ber 28, 2001, and installation by the approximate dates
    of February 1, 2002, for the two receiving bins, February 15
    No. 07-3632                                              15
    for the two wet storage silos, and April 15 for the dry
    storage bins. (D. Exh. 1004, Attachment A at p.4). Of
    course, these dates were later modified by the parties;
    first, by a November 30, 2001 fax, in which Schwing
    directed IPS to continue shop fabrication, but to cease on-
    site fabrication until further notice (D. Exh. 1005), and
    later by the August 12, 2004 change order (to which we
    will turn our attention momentarily). These initial dates
    indicate that Schwing and IPS had a meeting of the
    minds that the project would be completed within a
    particular time frame—an approximately eight-month
    period, with installation occurring just one month from
    the delivery date for receiving bins, forty-nine days from
    delivery for the wet sludge silos, and three-and-a-half
    months from delivery for the dry granules silo. In sum,
    the initial contract contemplated a short time frame and
    a quick turn around time from delivery to installation.
    Nothing in the language of the change order alters
    those expectations or modifies the contract from one
    requiring specific dates to one requiring only a rea-
    sonable time for performance. In fact, the change order
    specifically states that other than the changes
    specifically iterated in the change order, “no other changes
    to this order apply.” (D. Exh. 1017 at p.2). We know, of
    course, that it was the intent of the parties to alter the
    delivery and installation dates from the original purchase
    order. Clearly, Schwing altered the contract deadlines
    when it sent the fax directing IPS to cease all on-site
    fabrication as of November 30, 2001, and later when it
    agreed to a change order. To what date, then, did the
    parties alter the original deadlines?
    16                                                 No. 07-3632
    General Note One to the change order states that “the
    majority of the main & coned silo work [is] expected to
    be completed by September 30th, 2004.” (D. Exh. 1017,
    1012)3 . The main silo work refers to the wet sludge silos
    and the coned silo refers to the dry granules silos (see
    D. Exh. 1004), thus leaving only a smaller project—the
    truck receiving bins—to complete after September 30,
    2004 4 . In fact, the receiving bins were installed on Septem-
    ber 8, 2004, well before the September 30 deadline. This
    express language sets forth some clear expectations
    regarding timing. September 30 came and went without
    completion of the majority of the main and coned silo
    work.
    Not even Schwing, however, seems to be arguing that
    IPS breached by missing the September 30, 2004 deadline
    from the change order. Schwing argues instead that the
    new deadlines came from the layout schedule—an eight-
    page, 399-line spreadsheet used to coordinate all of the
    projects on the site. General Note Three to the change
    order states, “IPS has requested and to-date has not
    received a Zion Project time lines [sic] from Schwing, NSSD
    or the General Contractor. Therefore IPS will not be
    3
    The change order (D. Exh. 1017) incorporated by reference
    three general notes from IPS estimate #1520 (D. Exh. 1012),
    drafted by IPS.
    4
    The initial purchase order contemplated delivery of all of the
    parts on December 28, 2001, and installation of the truck
    receiving bins just a mere 31 days later, so we may assume
    that this was the fastest of the projects.
    No. 07-3632                                               17
    responsible for any monetary penalties on this project
    caused by unrealistic milestones, delays caused by
    others or acts of God.” (D. Exh. 1017 at p.2; Exh. 1012 at
    p.4). This language contemplates that the timelines will
    be guided by the layout schedule. In fact, IPS’s
    language indicates that without such a timeline, “all
    bets are off.” Clearly this is not a contract that antici-
    pated that the parties would perform in a “reasonable
    time.” The project at hand was complex and involved
    coordination of many different subcontractors. The
    layout schedule contained approximately 400 lines of
    activities that were to be completed over the course of
    eighteen months—each activity carefully scheduled to
    coordinate with the project as a whole. Even IPS relied
    upon the layout schedule for its deadlines. IPS’s senior
    vice president stated in an e-mail to Schwing, “They are
    actually looking for the remainder of the silos in the first
    week of October. This is also the first I have heard this and
    was planning/scheduling to be ready the first week in
    December [as described in the attached layout schedule]
    Line #s 1810 and 1990.” (D. Exh. 1022). In sum, this
    appears to be a contract containing specific deadlines and
    one that was referring to the layout schedule to provide
    them.
    In arguing that the layout schedule did not establish
    deadlines, IPS raises some noteworthy points. First, IPS
    argues that the parties could not have intended to in-
    corporate some of the layout schedule deadlines in their
    contract. For example, the layout schedule states an early
    finish date of August 12, 2004 for installation of the truck
    receiving bins. The parties, however, did not execute the
    18                                              No. 07-3632
    change order until August 12, 2004. IPS argues that it
    certainly did not intend to execute a contract that it was
    in breach of before it had any opportunity to perform.
    IPS, however, puts too fine a point on these exact dates.
    After the lengthy delay while the project sat on hold, and
    after some mildly contentious correspondence, on July 10,
    2004, the parties began negotiating to resume the
    project under revised terms. On July 12, 2004, IPS sent
    Schwing a Field Service Quotation which eventually led
    to the final change order which the parties signed on
    August 12, 2004. On July 12, when Schwing drafted the
    field service quotation that would become the final
    change order, the August 12 deadline certainly was
    feasible. It is quite possible that the parties contemplated
    beginning work or perhaps did begin work before the
    ultimate change order agreement was finalized and
    signed. In fact, the receiving bins were installed on Septem-
    ber 8, only twenty-seven days after the parties signed
    the change order. Moreover, the fact that some of the
    dates were either unrealistic or inaccurate does not eviscer-
    ate the import of the general framework of the layout
    schedule to the project. Of course, as IPS points out,
    one expects some amount of delay and revision in the
    scheduling of construction projects. And although
    “[w]hen performance is due . . . anything short of full
    performance is a breach” (Steele v. Pacesetter Motor Cars,
    Inc., 
    672 N.W.2d 141
    , 144 (Wis. Ct. App. 2003) (internal
    citations omitted)), a relatively minor breach does not
    excuse the other party from its contractual performance.
    Mgmt 
    Comp., 557 N.W.2d at 77-78
    .
    No. 07-3632                                                 19
    Even if we were to determine that the parties did not
    intend to incorporate the layout schedule into the
    contract, we would arrive at the same conclusion re-
    garding the question of a material breach. If the contract
    contained no time for performance, the law will imply
    a reasonable time. 
    Delap, 143 N.W.2d at 478
    . What consti-
    tutes a reasonable time for performance given the facts
    of the case is again a question of fact to which we defer to
    the district court. Klockner, Inc. v. Fed. Wire Mill Corp., 
    663 F.2d 1370
    , 1380 (7th Cir. 1981). And how would a court
    determine what a reasonable time for performance is in
    a complex construction project such as this? The logical
    place to begin is by looking at the highly detailed docu-
    ment that sets forth all of the various time frames for the
    project—the layout schedule. It is true, as IPS points
    out, that the layout schedule speaks not of deadlines, but
    of “early start” and “early finish” dates. Once again,
    however, the layout schedule is the beginning, and not
    the end of the consideration. In determining materiality
    of breach and the parties’ reasonable expectations, a court
    would look not only at the construction schedule, but
    would also consider the circumstances as a whole,
    bearing in mind normal delays of construction, whether
    Schwing or other contractors or subcontractors bore
    responsibility for the delays, and the benefit Schwing
    could reasonably expect. In short, whether we conclude,
    as the district court did, that the layout schedule was
    part of the contract, or whether we find that IPS had
    a “reasonable time” to perform, the determination of
    whether IPS materially breached the contract must be
    made by looking initially to the time frames set forth in
    the purchase orders and layout schedule.
    20                                              No. 07-3632
    The district court found that IPS had materially
    breached the terms of the contract and the record
    certainly supports such a determination. The original
    purchase order required delivery less than five months
    from the date the order was signed and then antici-
    pated approximate installation dates one month from
    the delivery date for the receiving bins, forty-nine days
    from delivery for the wet storage silos, and three-and-a-
    half months from delivery for the dry storage bin (conical
    silos). The notice to cease work at the site specifically
    instructed IPS to continue shop fabrication. Thus, by the
    time the change order negotiations occurred in July and
    August 2004, a significant amount of work had or
    should have already occurred in the shop. It was not
    unreasonable, therefore, for the contract to contemplate
    “an August 2004 start date with the majority of the main
    & coned silo work expected to be completed by Septem-
    ber 30th, 2004,” as stated in General Note One. (D. Exh.
    1012 at p.4). Nor was it unreasonable for the agree-
    ment (via the layout schedule) to contemplate installa-
    tion of the wet and dry storage silos by the even later
    dates in early December. (D. Exh. 1013, line 1810 and 1990).
    Of course, IPS argued that the new site presented far
    greater logistical challenges than the previous site. Even
    so, as of February 11, 2005, long after any of the contem-
    plated due dates, the project had not been completed.
    The district court did not err by determining that IPS
    materially breached the contract by failing to meet
    Schwing’s reasonable expectations.
    Nor did the district court err in finding that IPS’s
    reliance upon an allegedly insufficient lay-down area as
    an excuse for its delayed performance was not con-
    No. 07-3632                                               21
    sistent with the evidence. The district court determined
    that persuasive, overwhelming, and credible evidence
    established that the Zion site provided sufficient space
    and roads for IPS to complete its work, and that IPS
    did not devote a sufficient number of workers to the
    project.
    Finally, we need not address IPS’s argument that expert
    testimony as to “reasonable time” was required, as that
    argument was waived when IPS failed to raise it in the
    district court. See Skywalker Communications of Ind., Inc. v.
    Skywalker Communications, Inc., 
    333 F.3d 829
    , 831 (7th
    Cir. 2003).
    B. Damages
    Having determined both that IPS materially breached
    the agreement, and that the breach damaged Schwing,
    the district court turned to its calculation of damages.
    We review the calculation of an award of damages for
    clear error (Trs. of Chicago Painters and Decorators Pension,
    Health and Welfare, and Deferred Sav. Plan Trust Funds v.
    Royal Intern. Drywall and Decorating, Inc., 
    493 F.3d 782
    , 789
    (7th Cir. 2007)), but review the propriety of awarding
    damages de novo. See Morley-Murphy Co. v. Zenith Elec.
    Corp., 
    142 F.3d 373
    , 378 (7th Cir. 1998).
    The district court determined that Schwing was
    entitled to damages to compensate it for losses it
    incurred by IPS’s breach. In a breach of contract action,
    the fundamental idea is to put the injured party in as
    satisfactory a position as the party would have been in
    had the contract been performed. Thorp Sales Corp. v. Gyuro
    22                                              No. 07-3632
    Grading Co., 
    331 N.W.2d 342
    , 346 (Wis. 1983). Once the
    district court concluded that IPS breached, it properly
    determined that Schwing was entitled to damages to
    rectify the loss.
    IPS objects to the district court’s characterization of the
    damages as “incidental damages.” See (R. 32 at p.31). The
    district court noted that they could also be characterized
    as “cover.” 
    Id. We need
    not quibble over the terms. Pro-
    vided Schwing properly mitigated its damages as
    required, it is entitled to be placed in the position it
    would have been had IPS properly performed. (Peterson
    v. Cornerstone Prop. Dev., LLC, 
    720 N.W.2d 716
    , 731
    (Wis. App. 2006)). Under that general concept, the
    injured party is entitled to damages that flow directly
    and necessarily from the breach of contract, and that
    were reasonably foreseeable to or contemplated by the
    parties at the time the contract was made. 
    Id. at 730.
    A
    party is not entitled, however, to be placed in a better
    position than it would have been if the contract had
    been performed. 
    Id. Our task
    then, is to determine
    whether the district court clearly erred in calculating
    which payments were necessary to put Schwing in the
    position it would have been in had IPS performed, allow-
    ing for reasonably foreseeable additional damages, but
    ensuring that Schwing did not come out ahead.
    1.   Silo installation
    IPS argues first that it had no obligation to install silos
    at the Zion site, claiming that, because IPS did not have
    No. 07-3632                                              23
    available sufficient information to quote installation
    costs at the time it signed the change order, the change
    order did not address silo installation at all. The
    district court did not address the matter directly, but
    by allowing damages for silo installation, inherently
    found that the contract obligated IPS to install the silos
    at the Zion site. The interpretation of an established
    written contract is generally a question of law for the
    court, and thus we review this question de novo. Holmes
    v. Potter, 
    552 F.3d 536
    , 538 (7th Cir. 2008).
    IPS argues that the final paragraph of the change
    order indicates that “issues relating to silo area infra-
    structure access, material handling equipment and labor
    requirements had not been established at the time the
    order was signed.” IPS Brief at 21. That final paragraph
    of the change order states:
    No other changes to this order apply at this time.
    Access to silo installation area infrastructure for
    eventual silo placement into the General Contractors
    facilities or the use of General Contractors material
    handling equipment or requirements for the hiring
    of General Contractor labor personnel has not yet
    been established by Schwing America Project Manager
    and must be established. Additional charges may
    apply if accessibility is delayed or limited, and charges
    from the General Contractor or unforeseen issues arise.
    (D. Exh. 1017 at p.2). Under the plain language of this
    paragraph, the parties anticipated that IPS would install
    the silo at the Zion site and that additional charges
    might apply, but only if IPS’s access to the site was
    24                                               No. 07-3632
    delayed or limited or other unforeseen issues arose. The
    only unresolved installation issues, therefore, were ques-
    tions regarding access to the site, use of the general con-
    tractor’s materials and labor, and possible unforeseen
    issues. The final note assumes that the contract covers
    installation at the Zion site.
    IPS’s vice president Kopac testified that installation
    was not included in the change order. Schwing’s opera-
    tions manager, Predatsch, testified to the contrary. Al-
    though the district court did not make an explicit
    factual finding, by granting Schwing damages for silo
    installation, it determined that the change order
    included installation of the silos at the Zion site. Such a
    determination makes sense to the narrative of this case.
    Recall that after Schwing asked IPS to honor the original
    agreement, IPS responded that the agreement it had
    made was for the Waukegan site and not the Zion site.
    Negotiations continued and after several exchanges, the
    parties signed the change order and IPS resumed its
    work at the Zion site. Not only does the plain language
    of the change order demonstrate an agreement to install
    at the Zion site, but the parties’ actions demonstrate an
    agreement that IPS would continue performing and
    install the silos at the Zion site.
    2.   Painting and coating
    Each party in this case presented evidence regarding
    the sufficiency of the coating and painting of the silos, both
    inside and out. After hearing the evidence, the district
    court determined that Schwing had met its burden of
    No. 07-3632                                                25
    proving damages attributable to IPS’s breach of perfor-
    mance. Our review of the record reveals no clear error.
    See, e.g., D. Exhs. 1027, 1032, 1033, 1042; Tr. pps. 138-39,
    155, 233-35, 237, 247-48, 255-56, 259-62, 275). IPS argues
    that Schwing failed to prove that the drips and runs,
    which are obvious from photographic and documentary
    evidence in the record, were not permitted by the
    contract specifications, and did not require complete re-
    coating as a remedy. The district court, in awarding
    damages for re-coating, disagreed and the record
    supports such a conclusion. See 
    id. IPS also
    argues that IPS
    remedied the paint thickness problem by re-coating the
    silos prior to termination. The district court was well
    within its bounds to determine that this eve-of-termination
    remedy either came too late or was insufficient to
    resolve the problem. Nevertheless, even if the coat thick-
    ness had been resolved, the drips and runs had not,
    and the district court did not clearly err by determining
    that Schwing was entitled to re-paint.
    3.    The warranty
    IPS further claims that Schwing waived any claim for
    defective workmanship by failing to present a warranty
    claim to IPS as IPS claims was required by the contract.
    Paragraph K of the contract stated,
    K. Warranty: One year parts and labor. One year
    commences upon acceptance by owner. I.P.S. shall
    be responsible for replacement or repair resulting from
    defective workmanship or non-conformance to
    Schwing-furnished designs, approved shop drawings
    26                                                  No. 07-3632
    or standard fabrication procedures. Warranty is to
    be performed by I.P.S. others authorized by I.P.S.
    (D. Exh. 1004).
    In short, IPS argues that Schwing had a contractual duty
    to give IPS the first stab at repairing any defects or dam-
    age. The parties engage in much back and forth
    over whether either of the parties waived this issue by
    failing to raise it below. IPS raised it below, at least nomi-
    nally, by claiming in its post-trial brief that “Schwing is
    not entitled to any damages because . . . it did not comply
    with the requirements of paragraph K of Attachment A
    to the original purchase order which required that any
    warranty claim work be performed by IPS.” (R. at 24
    at p.8). See Oscar Gruss and Son v. First State Bank of Eldo-
    rado, 
    582 F.2d 424
    , 433 (7th Cir. 1978) (noting without
    discussing that a party had raised a claim below by
    asserting it in a post-trial brief); See also Quest Med., Inc. v.
    Apprill, 
    90 F.3d 1080
    , 1087 (5th Cir. 1996) (“an issue first
    presented to the district court in a post-trial brief is prop-
    erly raised below when the district court exercises
    its discretion to consider the issue”). IPS did not discuss
    the issue further, but nevertheless, the statement is
    clear, albeit perfunctory, in its claim. Not surprisingly,
    Schwing failed to reply to this needle of a claim hidden
    in a haystack of issues in this case. It is also not
    surprising because each party filed its post-trial brief on
    the same day, limiting the opportunity of both parties to
    respond. Of course, a party may always move a court for
    the opportunity to reply (see, e.g., Wright v. United States,
    
    139 F.3d 551
    , 553 (7th Cir. 1998) (allowing party to file
    an additional brief where opposing party articulated
    No. 07-3632                                                  27
    new theory)), but because the argument was so trun-
    cated, Schwing may not have identified it as a new
    or separate argument.
    In any event, there is no question that, at trial, the parties
    had the opportunity to present evidence as to whether
    IPS had a fair chance to correct defects or damage, and
    the district court considered this matter in the course of
    arriving at its holding. The district court noted that
    Schwing gave notice of its dissatisfaction with IPS’s
    work by its repeated requests for an installation date
    for the wet sludge silos and its complaints about the
    painting and welding of the silos. (R. at 32 at p.27). See
    also (D. Exhs. 1027, 1029, 1032, 1033, 1043) (Tr. pps. 72, 123-
    124, 132-145, 207-209, 233-235, 251, 253-55, 274). The
    district court did not err by determining that this was
    sufficient notice to IPS of Schwing’s dissatisfaction.
    IPS argues, in the alternative, that Schwing com-
    plained only of drips and runs and the thickness of the
    exterior shell coatings on the wet sludge silos and that,
    even if it did give sufficient notice for these items, such
    notice did not relieve Schwing of the duty to tender
    warranty claims for other work before contracting with
    others. The district court concluded, however, that
    Schwing gave IPS sufficient notice of its dissatisfaction,
    not only with the quality of the work, but also with IPS’s
    tardiness in completing the project. It was this failure to
    perform on both fronts—timeliness and quality—that
    allowed Schwing to repudiate the contract and mitigate
    its damages by retaining other companies to either com-
    plete the unfinished work or redo the non-conforming
    work as appropriate. (See R. at 32 at p.27).
    28                                                   No. 07-3632
    4.     Amount of damages
    As to the amount of damages, a matter we review for
    clear error (Gaffney v. Riverboat Servs. of Ind., Inc., 
    451 F.3d 424
    , 461 (7th Cir. 2006)), we agree with the district court’s
    assessment that Schwing met its burden of proving to
    a reasonable degree of certainty that the following dam-
    ages were attributable to IPS’s breach:
    (1) $68,500.00 to Northeast Water Technologies (NWT)
    for completion of fabrication work (March 5, 2005);
    (2) $75,250.00 to J.J. Henderson for labor, equipment,
    and rigging of the wet sludge silos into place. (Febru-
    ary 14, 2005);
    (3) $45,054.00 to J.J. Henderson for labor, equipment,
    and rigging of the dry granules silo into place (May 10,
    2005);
    (4) $18,888.78 to NWT for documented additional
    work items including meetings, inspections, repairing
    manufacturing defects, and supplies (September 1,
    2005);
    (5) $13,891.32 to J.J. Henderson (December 19, 2005)5 ;
    (6) $42,826.02 to Prime Coat for painting the exteriors
    of two wet sludge silos and the dry granules silo
    (December 28, 2005); and
    5
    These numbers differ from Schwing’s charges incurred
    (see infra at section I and D. Exh. at 1039), as not all of the
    payments to J.J. Henderson were attributable to IPS’s breach
    (see Tr. at 156-58).
    No. 07-3632                                                  29
    (7) $202,730.00 to Manta for repainting the interior
    of the two wet sludge silos and the dry granules
    silo with coal tar epoxy (December 20, 2005).
    (R. at 32 at p.33) (see also D. Exh. 1044).
    We do, however, find one small error. At the time of
    the breach, Schwing had not yet paid IPS $46,116 dollars
    that would have been owed had IPS completed the con-
    tract. By failing to deduct this money from the
    damage award, Schwing was placed in a better position
    than it would have been in had IPS performed. Schwing
    received damages to cover its costs for completing the
    work, but also was absolved of its requirement to pay the
    remaining $46,116 of the contract. In essence, Schwing
    was rewarded twice for the breach. Schwing is incorrect
    that IPS waived this argument. In its post-trial brief to
    the district court, IPS argued that the damage “sum must
    be reduced by $46,114, the final 20% installment under
    the change order that Schwing did not pay.” (R. at 24 at
    p.9). IPS raised the issue and identified the amount at
    pages 12 and 30 of its brief before this court. Apparently,
    Schwing agrees that the unpaid balance of the change
    order amounted to $46,116, and argues only that IPS
    waived the argument (a contention we just debunked) or
    that, in some nebulous way, the trial court’s findings
    were plausible in light of the record and should be af-
    firmed. 6 We remand for the limited purposes of
    6
    In calculating the amount of the unpaid balance of the change
    order, Schwing twice correctly calculates the number as $46,116.
    (continued...)
    30                                                 No. 07-3632
    deducting this $46,116 unpaid balance from the total
    damage award calculated by the district court.
    Finally, the district court concluded that Schwing
    owed IPS $2,000 for moving two power pacs from
    Waukegan to Zion. The district court concluded that the
    work was not part of the parties’ contract, but based on
    Schwing’s stipulation at trial that $2,000 in compensation
    for these services was acceptable, the district court con-
    cluded that Schwing should reimburse IPS for these
    costs. IPS seems to have viewed this concession as an
    opportunity to get the rest of the camel under the tent.
    Toward that end, it argues not just that Schwing and IPS
    had a separate agreement to transport two power pacs
    from Waukegan to Zion, but that the parties had an
    entire oral contract regarding installation of the silos (a
    matter, we have already concluded was included in the
    written contract). The existence of an oral agreement is
    a question of fact that warrants deference to the district
    court. Podolsky v. Alma Energy Corp., 
    143 F.3d 364
    , 369 (7th
    Cir. 1998). In this case, the district court determined
    (largely because of Schwing’s agent’s concession at trial)
    that the parties had a separate agreement for “mobilization
    of two power pacs from Waukegan to Zion,” but not, as
    IPS states, that they had an agreement for all of the
    6
    (...continued)
    See Schwing brief at 35, n.12. In a parenthetical explaining the
    calculations, however, Schwing mis-typed that number as
    $44,166. According to both Schwing and IPS’s calculations, the
    correct number is $46,116.
    No. 07-3632                                              31
    costs IPS would incur in assisting Schwing’s installation
    of silos at the Zion site.
    For the foregoing reasons, the district court is A FFIRMED
    in part, and R EVERSED in part with instructions to
    correct damages in a manner consistent with this opin-
    ion. IPS shall bear the cost of this appeal.
    9-2-09