Pioneer Trail Wind Farm, LLC v. Federal Energy Regulatory Commission , 798 F.3d 603 ( 2015 )


Menu:
  •                              In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________________
    Nos. 13-2326, 14-3023
    PIONEER TRAIL WIND FARM, LLC, et al.,
    Petitioners,
    AMERICAN WIND ENERGY ASSOCIATION, et al.,
    Intervening Petitioners,
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    Respondent,
    MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC., et al.,
    Intervening Respondents.
    ____________________
    Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Nos. ER11-3326-001, ER11-3326-002, ER11-3327-001,
    ER11-3327-002, ER11-3330-001, and ER11-3330-002
    ____________________
    ARGUED APRIL 20, 2015 — DECIDED AUGUST 19, 2015
    ____________________
    2                                              Nos. 13-2326, 14-3023
    Before WOOD, Chief Judge, HAMILTON, Circuit Judge, and
    DARRAH, District Judge.*
    WOOD, Chief Judge. Before deciding to build a power
    plant, energy companies and the system operator of an elec-
    trical grid must calculate the anticipated cost of connecting
    the proposed plant to the grid. These determinations occur
    in a highly regulated environment. Not surprisingly, some-
    times the calculations need to be corrected. This case deals
    with who should bear the costs of additional upgrades to the
    grid when the initial studies of the costs of connection con-
    tained an error. Two wind-farm companies argue that the
    Federal Energy Regulatory Commission (FERC or the Com-
    mission) issued unreasoned orders when it assigned the cor-
    rected costs of connection to the wind farms that wanted to
    connect to the grid rather than to the grid’s system operator,
    which was the party that made the mistake. Our task is to
    decide whether the Commission’s decisions to impose the
    costs on the connecting parties and to require a certain
    methodology were arbitrary and capricious under Section
    706(2)(A) of the Administrative Procedure Act, 5 U.S.C.
    § 706(2)(A). We conclude that the Commission’s decisions
    pass muster, and thus we deny the petitions for review.
    I
    Pioneer Trail Wind Farm, LLC (Pioneer), owns and oper-
    ates a 150-megawatt wind-powered electric generation facili-
    ty in Illinois. Settlers Trail Wind Farm, LLC (Settlers), owns a
    similarly sized facility, also in Illinois. Both Pioneer and Set-
    tlers are owned by companies that are in turn owned by a
    *Hon. John W. Darrah of the Northern District of Illinois, sitting by
    designation.
    Nos. 13-2326, 14-3023                                        3
    German company called E.ON SE. (The “SE” stands for “so-
    cietas europaea,” which is the term given to companies that
    register under the European Union’s European Company
    Statute rather than under national law. See EUROPEAN
    COMM’N, The European Company – Your Business Opportunity?,
    http://ec.europa.eu/internal_market/company/societas-
    europaea/index_en.htm, (all websites last visted Aug. 12,
    2015).) According to E.ON’s website, its power companies
    serve 33 million customers worldwide. See E.ON, Who We
    Are. An Overview., http://www.eon.com/en/about-us/profile.
    html. We often refer to Pioneer and Settlers collectively as
    the Generators in this opinion.
    Midcontinent Independent System Operator, Inc. (MISO),
    was formed in 1998 by several independent transmission-
    owning utilities. Since its creation, MISO has linked up the
    transmission lines of the member utilities into a single inter-
    connected grid that stretches across 11 states. The Generators
    wish to be connected to the transmission system of Ameren
    Illinois Company (Ameren), which is run by MISO. Ameren
    oversees 4,500 miles of electric transmission lines and ap-
    proximately 45,400 miles of distribution lines in downstate
    Illinois; it serves roughly 1.2 million customers in Illinois.
    In order to put the questions before us in context, some
    background on the interconnection process is essential. In
    layman’s terms, we are talking about the regulatory hoops
    that a power plant must jump through in order to hook up to
    a grid. The Federal Power Act grants FERC jurisdiction to
    oversee “matters relating to generation … and … the trans-
    mission of electric energy in interstate commerce and the
    sale of such energy at wholesale in interstate commerce” be-
    cause Congress has found such oversight to be “necessary in
    4                                        Nos. 13-2326, 14-3023
    the public interest.” 16 U.S.C. § 824(a). In 2003, FERC stand-
    ardized the generation interconnection process, to which we
    reluctantly refer as the GIP, following the industry jargon.
    Under the GIP, the interconnection customers, such as Pio-
    neer and Settlers, submit requests to the grid operator—in
    this case, MISO. MISO then produces studies to assess the
    impact of the projects on the grid. These studies identify
    what additional upgrades are needed to ensure that those
    additional connections do not adversely affect the grid.
    These studies also inform interconnection customers what
    the cost of the upgrades will be. This step is supposed to en-
    able the customers to decide if, in fact, they want to be con-
    nected to the grid or perhaps even build the plants at all. The
    interconnection customers cover the cost of MISO’s studies.
    Each case involves three separate studies. First, the grid
    operator prepares and sends to the interconnection custom-
    ers the “base case,” which gives them an overview of the
    system conditions. Second, the grid operator prepares a
    “system impact study,” which includes a preliminary list
    (with non-binding cost estimates) of network upgrades re-
    quired by the proposed project. At this point, the customers
    may choose whether to proceed. If they go forward, MISO
    performs the third study, called an “interconnection facilities
    study.” This sets out the nature and cost of the necessary
    network upgrades, as well as any information about pending
    upgrades that are entered into MISO’s interconnection
    queue. If another project is entered before the customer’s
    project, then the second customer could end up bearing the
    costs of the earlier project. That is because projects higher in
    the queue are included in the baseline against which the
    lower-queued project is assessed.
    Nos. 13-2326, 14-3023                                       5
    If the interconnection customer chooses to proceed in
    light of these studies, the grid operator provides the custom-
    er and the interconnecting transmission system owner with a
    Generator Interconnection Agreement (Agreement), which
    the parties must execute. The Agreement contains the specif-
    ic upgrades and estimated costs identified in the studies.
    Once the parties execute the Agreement, it is effective under
    Section 205 of the Federal Power Act. See 16 U.S.C. § 824d.
    With that background, we detail the specific process that
    took place here between the interconnection customers—the
    Generators—and the grid’s system operator, MISO. In Feb-
    ruary 2009, MISO and Ameren entered a “study services
    agreement” in which Ameren agreed to perform the studies
    of the impact of the Generators’ interconnection requests.
    Pioneer and Settlers signed their Agreements on February 5,
    2010, with projects scheduled to begin in June and Septem-
    ber of 2011. The Settlers Agreement included roughly $6 mil-
    lion in network upgrades, while Pioneer’s Agreement re-
    quired no network upgrades.
    Everything was apparently proceeding smoothly until
    April 29, 2010, when MISO notified the Generators that the
    studies included a “significant error” that failed to include
    upgrades to a higher-queued project in the vicinity of the
    two companies’ proposed wind farms. The inadvertently
    omitted project was a 30-megawatt upgrade to another wind
    farm in Benton County. MISO told the Generators that some-
    thing had to give: they would either have to agree to fewer
    megawatts (120 megawatts each) or pay for additional net-
    work upgrades estimated to cost $11.5 million. On May 11,
    2010, the Generators informed MISO that they rejected both
    options: the additional network upgrades, they asserted,
    6                                       Nos. 13-2326, 14-3023
    were not their responsibility, and so they claimed they were
    entitled to proceed with their 150-megawatt wind farms.
    MISO did not acquiesce in their position. Instead, in No-
    vember 2010, it informed both companies that they would
    need to pay for $10 million in additional network upgrades
    and $1.5 million in common use upgrades before they could
    interconnect. MISO presented superseding Agreements to
    both Pioneer and Settlers. The revised Agreements required
    the companies to pay for both the original and the additional
    network upgrades; they also provided for a Multi-Party Fa-
    cilities Construction Agreement to address the common use
    upgrades. The two companies refused to sign. They asked
    MISO instead to file the superseding Agreements with
    FERC, so that it could resolve the dispute about who had to
    pay for the upgrades. MISO did so on April 8, 2011, and
    April 11, 2011. Before the Commission, the Generators pro-
    tested that they should not be responsible for the cost of the
    additional network upgrades, and Ameren filed an answer,
    claiming it was not the source of the study error. The Com-
    mission found that the Generators should pay for the addi-
    tional network upgrades and denied the companies’ requests
    for rehearing.
    The Generators also contest another aspect of FERC’s de-
    cision. The original Agreements (the ones that failed to ac-
    count for the higher-queued wind farm) included a pricing
    scheme (Option 1), under which the Generators were to fund
    the cost of the network upgrades before construction, MISO
    would refund 100% of the upgrade costs after construction,
    and the Generators would then pay for the upgrades month-
    ly through a “network upgrade charge.” In the course of a
    different FERC proceeding, however, the Commission
    Nos. 13-2326, 14-3023                                        7
    granted MISO’s request to do away with Option 1 pricing
    and replace it with Option 2. Under Option 2 pricing, the
    customer pays for only the unreimbursable cost of the up-
    grades before construction, and the transmission owner re-
    tains the funds. Despite doing away with Option 1 for future
    Agreements, the Commission grandfathered Option 1 pric-
    ing for the original network upgrades and applied Option 2
    pricing only to the upgrades added in light of MISO’s error.
    Pioneer and Settlers filed petitions seeking review of the
    Commission’s decisions to impose the costs of the additional
    upgrades on them and to apply Option 1 pricing to the orig-
    inal upgrades (they would prefer Option 2 pricing across the
    board, for reasons we need not explore). We granted mo-
    tions to intervene as petitioners from the American Wind
    Energy Association (AWEA), a national trade association
    that represents wind power project developers and other
    companies involved in the wind power industry, and Wind
    on the Wires (WOW), a non-profit that collaborates with
    AWEA on wind farm work in the Midwest. Ameren and
    MISO have intervened as respondents.
    II
    The Generators are seeking review of FERC’s decisions
    under Section 313(b) of the Federal Power Act, 16 U.S.C.
    § 824l(b). That statute provides that the Commission’s find-
    ings of fact “if supported by substantial evidence, shall be
    conclusive.” It does not otherwise specify the standard of
    review, and so the applicable standard is found in Section
    706(2)(A) of the Administrative Procedure Act (APA),
    5 U.S.C. § 706(2)(A), which instructs a reviewing court to
    uphold an agency action unless it is “arbitrary, capricious, an
    abuse of discretion, or otherwise not in accordance with
    8                                         Nos. 13-2326, 14-3023
    law.” While deferential, these standards are not toothless.
    We must inquire whether FERC “examined the relevant data
    and articulated a rational connection between the facts
    found and the choice made.” Eastern Ky. Power Co-op, Inc. v.
    FERC, 
    489 F.3d 1299
    , 1306 (D.C. Cir. 2007) (citing Motor Vehi-
    cle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43
    (1983)). The petitioners have the burden of showing “that the
    Commission’s choices are unreasonable and … not within a
    ‘zone of reasonableness.’” ExxonMobil Gas Mktg. Co. v. FERC,
    
    297 F.3d 1071
    , 1084 (D.C. Cir. 2002) (citation omitted).
    A
    We begin with the Generators’ primary challenge, which
    is to the Commission’s decision to allocate to them the cost
    of system upgrades that are necessary to accommodate their
    new 150-megawatt facilities. In so doing, FERC was follow-
    ing FERC Order No. 2003, in which it takes the position that
    when an interconnection customer (typically a generator
    such as Pioneer or Settlers) is the “but-for cause” of network
    upgrades, it is appropriate to have that customer assume the
    costs of the necessary upgrades. Consistently with that poli-
    cy, the order allows regional system operators to implement
    participant funding, under which the costs of network up-
    grades fall on the interconnecting customer. MISO did this
    in 2006.
    Not surprisingly, modifications to the grid are often
    made to accommodate the change in power transmission
    brought about by new plants. “To the extent that a utility
    benefits from the costs of new facilities, it may be said to
    have ‘caused’ a part of those costs to be incurred, as without
    the expectation of its contributions the facilities might not
    have been built, or might have been delayed.” Ill. Commerce
    Nos. 13-2326, 14-3023                                         9
    Comm’n v. FERC, 
    576 F.3d 470
    , 476 (7th Cir. 2009). While the
    Commission is “not authorized to approve a pricing scheme
    that requires a group of utilities to pay for facilities from
    which its members derive no benefits,” 
    id., here the
    Genera-
    tors are the primary utilities that stand to benefit from being
    connected to the grid. See Old Dominion Elec. Co-op., Inc. v.
    FERC, 
    518 F.3d 43
    , 51 (D.C. Cir. 2008) (upholding FERC’s cost
    allocations of interconnection facilities to the interconnection
    customers “when facilities would not have been built but for
    the interconnection request”). The parties acknowledge that
    the additional upgrades, first neglected and later noticed by
    MISO, are required.
    In administering the regulatory process of updating an
    electrical grid, FERC needs a way to handle inevitable mis-
    takes of fact. The question is how to think about this prob-
    lem. The Generators argue that the legal framework within
    which we should answer the question is that of contract:
    they each had one Agreement; it was premised on a mistake
    of fact; and now a new Agreement is needed. FERC rejects
    the contract model and contends that the proper model is
    regulatory. We think that FERC has the better of this debate.
    It is true that the Generator Interconnection Agreements run
    between the interconnection customer (a generator), a
    transmission owner, and a transmission provider (MISO),
    but that is not the end of the matter. The parties are not free
    to contract as they wish; instead, they must structure their
    relationship within the elaborate regulatory regime that
    FERC has created. This case illustrates the point well: Pio-
    neer and Settlers refused to sign the revised Agreements.
    They asked MISO instead to refer the matter to FERC, which
    MISO did. After proceedings in which everyone was heard,
    FERC decided that the cost should fall on the Generators.
    10                                         Nos. 13-2326, 14-3023
    This was a regulatory decision. Indeed, every step leading to
    an Agreement is dictated by regulations: MISO must connect
    new power plants to the grid in accordance with the Federal
    Power Act and its implementing regulations; it must conduct
    (or contract for) the three types of studies described above;
    and it must accept the interconnection terms FERC dictates,
    when FERC has to become involved.
    Even if we were to focus on the contract-like aspects of
    the relationship, the Generators have problems. The record
    fails to show that they relied on the original, mistaken stud-
    ies. There is no evidence that the added cost of the corrected
    upgrades was a dealbreaker for either Pioneer or Settlers’s
    project. MISO gave them the opportunity to avoid the extra
    cost for the additional upgrades and instead reduce the out-
    put (to 120 megawatts) of the wind farms so as to not over-
    load the system. They did not show why this would have
    made their farms economically unsustainable. They also had
    an exit option. The results of the system impact and inter-
    connection facilities studies are designed to give companies
    the opportunity to withdraw from a proposal; the Genera-
    tors could have opted to do so once they learned of the addi-
    tional upgrades that were necessary to avoid overloading the
    existing electrical grid. Finally, they always understood (or
    should have understood) that upgrades required by another
    project in the queue could cause exactly the kind of problem
    that occurred here. (We note that the Generators apparently
    went ahead and built their wind farms despite this dispute.
    That fact has no effect on our analysis.)
    We do not deny that the amount of money at issue, $11.5
    million, is significant. It is also possible, in another case, that
    a more developed record might demand a different ap-
    Nos. 13-2326, 14-3023                                        11
    proach. For instance, had there been evidence in the record
    about the cost of a proposed wind farm, the Commission ini-
    tially, and now our court, would have had a better sense of
    how much the additional upgrades drove up the cost of con-
    struction. Our case is devoid of such evidence, and so we
    lack a benchmark against which to measure the cost of the
    mistake. If the record before FERC had demonstrated that
    the difference in the interconnection costs turned a profitable
    enterprise into a losing one for both companies, it is possible
    that FERC would have entered a different order. If it had en-
    tered the same order, there might have been a stronger ar-
    gument for the proposition that the order was arbitrary. This
    is all speculation, however. We see nothing in evidence sug-
    gesting that the facts FERC found are not supported by sub-
    stantial evidence, nor do we see the kind of legal error that
    requires us to set aside its order.
    We find further support for this conclusion in another
    point the Commission makes. It observes that there is noth-
    ing in the regulations that suggests it cannot modify agree-
    ments even if one party does not consent and the parties had
    not contemplated who would bear the cost of an error in the
    studies. That puts the Generators in a difficult spot, because
    they cannot point to something in the Agreements or FERC
    precedent that suggests they cannot be held liable for those
    costs. Article 11.3.1 of the Agreement lists aspects of the sys-
    tem configuration for which the system operator (MISO) is
    entitled to change the tariff without FERC’s approval. Article
    30.11, “the reservation of rights” section of the Agreement,
    allows MISO or Ameren “to make a unilateral filing with
    FERC to modify this [Agreement] with respect to any rates,
    terms, and conditions, classifications of service, rule or regu-
    lation under Section 205 of the Federal Power Act”; it also
    12                                         Nos. 13-2326, 14-3023
    allows Pioneer and Settlers “to make a unilateral filing with
    FERC to modify this [Agreement] pursuant to Section 206 or
    any other applicable provision of the Federal Power Act and
    FERC’s rules and regulations thereunder.” The phrase “a
    unilateral filing with FERC” appears to be a clumsy way of
    saying that MISO or Ameren can go back to FERC and seek
    the agency’s modification of the Agreement. If they do so,
    the end result is still a regulatory order, not an arms-length
    agreement.
    Finally, the Generators contend that FERC’s decision to
    impose the costs of the mistake on them violates the filed
    rate doctrine. The filed rate doctrine, as the name suggests,
    requires utilities to charge the rate that is on file with the rel-
    evant regulatory agency. See Arkansas Louisiana Gas Co. v.
    Hall, 
    453 U.S. 571
    , 577 (1981) (defining the doctrine as one
    that “forbids a regulated entity to charge rates for its services
    other than those properly filed with the appropriate federal
    regulatory authority”). In order to evaluate the Generators’
    argument, it is helpful to recall why the doctrine exists: “[to]
    preserv[e] the agency’s primary jurisdiction over reasona-
    bleness of rates,” “to insure that regulated companies charge
    only those rates of which the agency has been made cogni-
    zant,” and to “prevent[] the Commission itself from impos-
    ing a rate increase for [electricity] already sold.” 
    Id. at 577–
    78. The filed rate doctrine is intended to bind both the par-
    ties and the agency (here, FERC) to the rate on file.
    Nothing that happened in this case imperiled FERC’s
    primary jurisdiction, hid information from FERC, or im-
    posed a retroactive fee on electricity already sold. Instead,
    what happened was an ex ante decision about cost allocation,
    untainted by fraud or discrimination. In a different line of
    Nos. 13-2326, 14-3023                                           13
    cases involving preemption of state regulation, the Supreme
    Court repeatedly has protected FERC’s discretion to modify
    cost allocations in this way. See, e.g., Entergy Louisiana, Inc. v.
    Louisiana Pub. Serv. Comm’n, 
    539 U.S. 39
    , 50 (2003) (“We see
    no reason to create an exception to the filed rate doctrine for
    tariffs of this type that would substantially limit FERC’s flex-
    ibility in approving cost allocation arrangements.”); Missis-
    sippi Power & Light Co. v. Mississippi ex rel. Moore, 
    487 U.S. 354
    , 372 (1988). In fact, “[i]gnorance or misquotation of rates
    is not an excuse for paying or charging either less or more
    than the rate filed.” Louisville & Nashville R.R. Co. v. Maxwell,
    
    237 U.S. 94
    , 97 (1915). The filed rate doctrine protects parties
    not from misquoted rates, but from discriminatory or fraud-
    ulent ones. It is of no help to the Generators here.
    The Generators also complain that to allow FERC to allo-
    cate the costs as it has would create a bad precedent. The
    Commission responds, without data to back it up, that its
    decision was highly fact-specific and that, in any event, these
    cases are rare. That is unsatisfying, particularly if we accept
    for the sake of argument intervenor AWEA’s contention that
    such a decision makes investments less predictable. From
    our perspective, however, cases must be decided on the basis
    of their record. We do not know what FERC would have
    done if a utility had sunk significant money based on rea-
    sonable expectations about the costs of a regulated project
    and then was told that it had to bear additional, unforeseen
    costs. Much less do we know how we would evaluate an
    agency decision that was adverse to the utility in such a case.
    Federal courts do not decide hypothetical cases for a good
    reason; we leave these questions for another day, when they
    are properly before us.
    14                                     Nos. 13-2326, 14-3023
    To sum up, the interconnection process at issue here in-
    cludes three studies that give the affected parties multiple
    opportunities to choose to pursue or to abandon an inter-
    connection agreement. There was an error in the original cal-
    culation of the costs that the new capacity proposed by the
    Generators would entail, and at the Generators’ request,
    FERC resolved the question who should bear those addi-
    tional costs. The Generators had the option of connecting to
    the grid at the 120-megawatt level, paying, or walking away.
    They did not like those options, but FERC’s conclusion was
    based on substantial evidence and was not arbitrary.
    “[W]hen entities before FERC present intensely practical dif-
    ficulties that demand a solution, FERC must be given the lat-
    itude to balance the competing considerations and decide on
    the best resolution.” NRG Power Mktg., LLC v. FERC, 
    718 F.3d 947
    , 955–56 (D.C. Cir. 2013) (quotations and citation omit-
    ted).
    B
    We now turn to the Generators’ second challenge to the
    Commission’s orders. This one relates to FERC’s decision to
    apply Option 1 pricing for reimbursing the system operator
    the cost of the original network upgrades and Option 2 pric-
    ing for the additional upgrades that were deemed necessary
    after the mistake was discovered. They argue that Option 2
    pricing should apply to the entire package. Recall that under
    Option 1 pricing, the interconnection customer funds the en-
    tire cost of the network upgrades before construction, the
    transmission owner then refunds 100% of the upgrade costs
    after construction, and the customer then pays for the up-
    grades monthly, through a “network upgrade charge.” Un-
    der Option 2 pricing, the customer pays for the unreimburs-
    Nos. 13-2326, 14-3023                                        15
    able costs of the upgrades before construction, and the
    transmission owner retains the funds.
    It is not hard to imagine why the Generators prefer Op-
    tion 2. Under Option 1, the transmission owner (MISO) re-
    pays the full amount of the cost of the network upgrades to
    the interconnection customer, but the customer (i.e., Pioneer
    and Settlers) must then charge a monthly amount to recover
    the costs of the upgrades. Under Option 2, Pioneer and Set-
    tlers pay the nonrefundable amount for the interconnection
    and then do not have to pay monthly charges to MISO. Once
    again, the standard of review is deferential. As the D.C. Cir-
    cuit put it, “we defer to FERC’s decisions in remedial mat-
    ters, respecting that the difficult problem of balancing com-
    peting equities and interests has been given by Congress to
    the Commission with full knowledge that this judgment re-
    quires a great deal of discretion.” Koch Gateway Pipeline Co. v.
    FERC, 
    136 F.3d 810
    , 816 (D.C. Cir. 1998) (quotations and cita-
    tion omitted).
    The Generators contend that the Commission’s finding
    that Option 1 may be used on the original network upgrades
    is contrary to its prior decisions. They rely heavily on West
    Deptford Energy, LLC v. FERC, 
    766 F.3d 10
    (D.C. Cir. 2014), in
    which the D.C. Circuit granted an energy company’s petition
    for review and vacated FERC’s order on the ground that the
    Commission needed to provide a better explanation for why
    certain tariff rates governed that company’s interconnection
    request. In our view, however, West Deptford strengthens the
    Commission’s position here. The Commission did not apply
    Option 1 pricing to the additional upgrades required to con-
    nect Pioneer and Settlers’s windfarms. It chose to stay the
    course for the original upgrades, preserving the same pric-
    16                                      Nos. 13-2326, 14-3023
    ing scheme that it originally had approved. It provided rea-
    sons for its decision to do so, explaining that grandfathering
    the existing pricing scheme provided regulatory certainty
    and was easier to administer. The Commission also dis-
    cussed how its decision serves the Federal Power Act’s pur-
    pose of preserving the expectations of parties.
    The Generators object that the Commission is being in-
    consistent, insofar as it rejects a reliance argument for pur-
    poses of cost allocation for the mistake and it embraces a re-
    liance argument for this purpose. But we have explained
    why the reliance argument is at best weak for purposes of
    cost allocation. And it is hard to complain on the basis of re-
    liance that the Commission did not change the pricing
    scheme for the original parts of the Agreement. We have no
    reason to think that the Commission misinterpreted its own
    orders when it decided to bifurcate the pricing options. See
    NRG Power 
    Mktg., 718 F.3d at 957
    (“[W]e afford FERC sub-
    stantial deference in its interpretation of its own orders.”).
    As with their first challenge, the Generators also argue
    that the Commission’s decision to apply Option 2 pricing on-
    ly for the additional upgrades violated the filed rate doc-
    trine. But this argument founders on the fact that “[t]he filed
    rate doctrine simply does not extend to cases in which buy-
    ers are on adequate notice that resolution of some specific
    issue may cause a later adjustment to the rate being collected
    at the time of service.” Natural Gas Clearinghouse v. FERC, 
    965 F.2d 1066
    , 1075 (D.C. Cir. 1992). Once MISO and Ameren
    filed the amended Agreements with the Commission, both
    Pioneer and Settlers were on notice. Compare Shetek Wind
    Inc. v. MISO, 138 FERC ¶ 61,250 (2012) (requiring that
    changes to terms and conditions of service laid out in the tar-
    Nos. 13-2326, 14-3023                                      17
    iff be filed with FERC). After FERC handed down its No-
    vember 2011 decision, both companies knew that the addi-
    tional network upgrades could be priced under Option 1 or 2.
    Pioneer and Settlers would have to pay for the upgrades un-
    der either pricing scheme, and the agency has the discretion
    to apply the 2011 order accordingly.
    Given the standard of review, the choice to grandfather
    Option 1 was FERC’s to make. FERC has the authority to de-
    cide to apply one reimbursement scheme for the original
    upgrades, and a different reimbursement scheme consistent
    with the regulatory scheme for the additional upgrades. The
    Commission reasonably interpreted its original order for the
    approximately $6 million worth of work and the later order
    for $11.5 million as two different instruments. It did not act
    arbitrarily in deciding to do so.
    III
    We DENY Pioneer and Settlers’s petitions for review of the
    Commission’s orders.