United States v. Midwest Generation, LLC , 720 F.3d 644 ( 2013 )


Menu:
  •                               In the
    United States Court of Appeals
    For the Seventh Circuit
    Nos. 12-1026 & 12-1051
    U NITED S TATES OF A MERICA and
    S TATE OF ILLINOIS,
    Plaintiffs-Appellants,
    v.
    M IDWEST G ENERATION, LLC,
    E DISON M ISSION E NERGY, and
    C OMMONWEALTH E DISON C OMPANY,
    Defendants-Appellees.
    Appeals from the United States District Court
    for the Northern District of Illinois, Eastern Division.
    No. 09 C 5277—John W. Darrah, Judge.
    A RGUED S EPTEMBER 20, 2012—D ECIDED JULY 8, 2013
    Before E ASTERBROOK , Chief Judge, and M ANION and
    T INDER, Circuit Judges.
    E ASTERBROOK, Chief Judge. Any “major emitting facil-
    ity” built or substantially modified after August 7, 1977,
    in parts of the country subject to the rules about preven-
    tion of significant deterioration (PSD), needs a permit.
    2                                   Nos. 12-1026 & 12-1051
    
    42 U.S.C. §7475
    (a). This construction permit is in addi-
    tion to the operating permits that many facilities
    require under the Clean Air Act and the need to comply
    with state implementation plans. One condition of a
    construction permit is installation of “the best available
    control technology for each pollutant subject to regula-
    tion under” the Act. 
    42 U.S.C. §7475
    (a).
    Between 1994 and 1999 Commonwealth Edison Co.
    modified five of its coal-fired power plants: Crawford
    and Fisk in Chicago; Powerton in Pekin; Waukegan
    Station in Waukegan; and Joliet in Joliet. All five plants
    had been operating on August 7, 1977, and were grand-
    fathered until the modification. We must assume, given
    the posture of this litigation, that the modifications re-
    quired permits under §7475(a). But Commonwealth
    Edison did not obtain permits. The question “how much
    repair or change requires a permit?” has been contentious
    and difficult. See, e.g., Environmental Defense v. Duke
    Energy Corp., 
    549 U.S. 561
     (2007); United States v. Cinergy
    Corp., 
    458 F.3d 705
     (7th Cir. 2006); United States v. Cinergy
    Corp., 
    623 F.3d 455
     (7th Cir. 2010). Commonwealth
    Edison took the position that permits were not required
    and that it therefore was not obliged to install “the
    best available control technology” (called BACT in the
    jargon of environmental law).
    This was a risky strategy because, if someone had
    contested the decision within the statute of limitations
    (five years; see 
    28 U.S.C. §2462
    ), then Commonwealth
    Edison could have needed to undertake a further round
    of modifications to get the permit and might have had
    Nos. 12-1026 & 12-1051                                    3
    to pay hefty penalties for the delay. As it happened,
    however, no one sued until 2009, a decade after the
    last of the modifications had been completed. The district
    court dismissed as untimely the claim based on §7475(a).
    
    694 F. Supp. 2d 999
     (N.D. Ill. 2010), reconsideration
    denied, 
    781 F. Supp. 2d 677
     (2011). Claims concerning
    another plant remain pending, as do claims related to a
    different permit requirement for these five plants and
    the emissions limits for their continued operation. But
    the district court entered a partial final judgment under
    Fed. R. Civ. P. 54(b) so that the claim under §7475(a) could
    proceed to appeal while the parties’ remaining disputes
    were ongoing in the district court.
    After finishing the modifications, Commonwealth
    Edison sold the five plants to Midwest Generation. This
    has introduced some complications. The United States
    and Illinois, the two plaintiffs in this suit, contend that
    Midwest is liable as Commonwealth Edison’s successor,
    and it accuses the district court of allowing a corporate
    restructuring to wipe out liability for ongoing pollu-
    tion. Adding another twist, Midwest and its corporate
    parent Edison Mission Energy filed petitions under
    the Bankruptcy Code after the appeal was argued. The
    parties have agreed that the law-enforcement exception
    to the automatic stay in bankruptcy, 
    11 U.S.C. §362
    (b)(4),
    applies to these proceedings, which therefore need not
    be consigned to limbo. Nor need we worry about
    whether the sale had any effect on liability, and if so who
    would be responsible today. Midwest cannot be
    liable when its predecessor in interest would not have
    been liable had it owned the plants continuously.
    4                                  Nos. 12-1026 & 12-1051
    Commonwealth Edison needed permits before under-
    taking the modifications. By the time this suit com-
    menced, between 10 and 15 years had passed since the
    modifications were finished, at least double the five-year
    period of limitations. Plaintiffs do not contend that the
    time was extended by delay in discovering the modifica-
    tions and, after Gabelli v. SEC, 
    133 S. Ct. 1216
     (2013), no
    such argument would be tenable. (Gabelli holds that
    the time for the United States to sue under §2462 begins
    with the violation, not with a public agency’s discovery
    of the violation.) Gabelli observes that “a claim accrues
    when the plaintiff has a complete and present cause of
    action” (
    133 S. Ct. at 1220
    , quoting from Wallace v. Kato,
    
    549 U.S. 384
    , 388 (2007)) and that the statute of limita-
    tions begins to run when the claim accrues. That
    occurred as early as 1994 for one plant and no later
    than 1999 for any of the five.
    Plaintiffs concede all of this but reply that failure to
    obtain a construction permit is a continuing violation. The
    phrase “continuing violation” is ambiguous. It may
    mean any of at least three things: (1) ongoing discrete
    violations; (2) acts that add up to one violation only
    when repeated; and (3) lingering injury from a com-
    pleted violation. Analysis will be easier if we call the
    first situation a continuing violation, the second a cum-
    ulative violation, and the third a continuing-injury situa-
    tion. See Turley v. Rednour, No. 11-1491 (7th Cir. July 3,
    2013) (concurring opinion). Plaintiffs make arguments
    of both the continuing-violation and continuing-injury
    stripes.
    Nos. 12-1026 & 12-1051                                     5
    The continuing-violation argument is that every day a
    plant operates without a §7475 permit is a fresh violation
    of the Clean Air Act. Congress sometimes writes regula-
    tory statutes that way, but §7475 is not among them.
    Section 7475 bears the caption “Preconstruction require-
    ments” and begins this way: “No major emitting facility
    on which construction is commenced after August 7,
    1977, may be constructed in any area to which this part
    applies unless—”. The rest of §7475(a) spells out the
    conditions that must be met before the permit will issue.
    See also 
    40 C.F.R. §52.21
    (r)(1). The text bears out the
    caption: it specifies a step the operator must take
    before constructing or modifying a “major emitting
    facility”. The violation is complete when construction
    commences without a permit in hand. Nothing in the
    text of §7475 even hints at the possibility that a fresh
    violation occurs every day until the end of the universe
    if an owner that lacks a construction permit operates a
    completed facility. Gabelli tells us not to read statutes in
    a way that would abolish effective time constraints on
    litigation.
    Two other courts of appeals have considered whether
    operating a new or modified plant, despite failure to
    obtain a construction permit, is a new violation of
    §7475(a). Both have held that it is not. Sierra Club v. Otter
    Tail Power Co., 
    615 F.3d 1008
     (8th Cir. 2010); National
    Parks and Conservation Association Inc. v. Tennessee Valley
    Authority, 
    502 F.3d 1316
     (11th Cir. 2007). We agree with
    those decisions. Although plaintiffs insist that the con-
    struction permit has “an operational component,” they
    6                                   Nos. 12-1026 & 12-1051
    mean only that under §7475(a)(4) the operator must
    install the best available control technology. Section
    7475(a)(4) specifies what must be built, not how the
    source operates after construction. If the owners ripped
    out or deactivated the best available control technology
    after finishing construction that would not violate
    §7475—though it might well violate some other statute,
    regulation, or implementation plan prescribing how
    polluters run their facilities.
    Plaintiffs stress that §7475(a)(4) says that newly built
    or modified sources are “subject to” the need for the
    best available control technology. That obligation,
    they insist, continues after the construction work is done,
    which leads them to say that National Parks and Conserva-
    tion Association Inc. v. Tennessee Valley Authority, 
    480 F.3d 410
     (6th Cir. 2007), disagrees with the eighth and
    eleventh circuits. Yet the sixth circuit’s decision rests on
    Tennessee statutes and implementation plans that
    require certain sources to use the best available control
    technology, while §7475 deals only with conditions prec-
    edent to construction or modification. Perhaps an Illinois
    statute, regulation, or implementation plan provides
    that any plant “subject to” BACT by virtue of §7475(a)(4)
    must use it in operation, but any claim of that sort
    remains pending in the district court. What BACT entails
    is plant-specific. 
    40 C.F.R. §52.21
    (b)(12). All we have
    for decision is a claim directly under §7475.
    Plaintiffs maintain that 415 ILCS 5/9.1(d)(2) works the
    same way as the Tennessee requirements that the sixth
    circuit considered. To the extent that this contention is
    Nos. 12-1026 & 12-1051                                     7
    independent of §7475, we leave it to the district judge
    in the first instance. To the extent that plaintiffs maintain
    that Commonwealth Edison has violated §5/9.1(d)(2)
    because it earlier violated §7475, the argument is wrong.
    Section 5/9.1(d)(2) provides that no one shall “modify or
    operate” a point source “except in compliance with the
    requirements of such Sections [of the Clean Air Act] and
    federal regulations adopted pursuant thereto”. Plaintiffs
    point to “or operate”, which is missing from §7475(a).
    This gets us nowhere, however; no one can operate a
    plant except in compliance with federal law with or
    without §5/9.1(d)(2). We have already concluded that
    §7475 deals with getting permission for construction, not
    with a plant’s operations; it follows that Commonwealth
    Edison’s violations of §7475 during the 1990s do not
    make its current operations a violation of federal law,
    so they do not derivatively violate §5/9.1(d)(2).
    Plaintiffs’ contention that a continuing injury from
    failure to get a preconstruction permit (really, from failure
    to use BACT) makes this suit timely is unavailing. What
    these plants emit today is subject to ongoing regulation
    under rules other than §7475. Today’s emissions cannot
    be called unlawful just because of acts that occurred
    more than five years before the suit began. Once the
    statute of limitations expired, Commonwealth Edison
    was entitled to proceed as if it possessed all required
    construction permits. That’s the point of decisions such
    as United Air Lines, Inc. v. McMann, 
    434 U.S. 192
     (1977),
    and Ledbetter v. Goodyear Tire & Rubber Co., 
    550 U.S. 618
    (2007), which hold that enduring consequences of acts
    8                                  Nos. 12-1026 & 12-1051
    that precede the statute of limitations are not independ-
    ently wrongful.
    A FFIRMED
    7-8-13