United States v. Marshall Pecore , 664 F.3d 1125 ( 2011 )


Menu:
  •                             In the
    United States Court of Appeals
    For the Seventh Circuit
    Nos. 10-2676 & 10-3599
    U NITED S TATES OF A MERICA,
    Plaintiff-Appellee,
    v.
    M ARSHALL P ECORE AND
    C ONRAD W ANIGER,
    Defendants-Appellants.
    Appeals from the United States District Court
    for the Eastern District of Wisconsin.
    No. 07-C-316—William C. Griesbach, Judge.
    A RGUED S EPTEMBER 22, 2011—D ECIDED D ECEMBER 30, 2011
    Before B AUER, M ANION, and K ANNE, Circuit Judges.
    K ANNE, Circuit Judge. After a six-year investigation, an
    additional two-and-one-half years of discovery and pre-
    trial posturing, and a nine-day jury trial, Marshall Pecore
    and Conrad Waniger (the “defendants”) prevailed against
    civil charges that they violated the False Claims Act
    (“FCA”). Unsatisfied with just the trial victory and
    perhaps disturbed that the government spent nearly a
    decade chasing about $75,000, the defendants moved for
    2                                  Nos. 10-2676 & 10-3599
    attorney’s fees under the Equal Access to Justice Act
    (“EAJA”), 
    28 U.S.C. § 2412
    (d)(1)(A), or alternatively,
    sanctions under Rule 37(c)(2) of the Federal Rules of
    Civil Procedure. The district court denied both motions.
    Despite our discomfort with what looks like govern-
    ment overreaching, we find that the district court’s
    ruling was not an abuse of discretion and accordingly,
    we affirm.
    I. B ACKGROUND
    The origins of this dispute date back to 2000 when
    Menominee Tribal Enterprises (“Menominee,” “MTE,” or
    the “Tribe”), the principal business arm of the Menominee
    Indian Tribe of Wisconsin, first applied for and received
    federal funding under the Hazardous Fuels Reduction
    program (“HFR”). The federal Bureau of Indian Affairs
    (“BIA”) created HFR as a long-term strategy to grad-
    ually reintroduce the beneficial aspects of fire into fire-
    dependent ecosystems such as densely-wooded forests.
    To obtain HFR funds, an applicant is required to first
    submit a proposal for its planned fire reduction work.
    Unlike previous federal programs, this fire reduction
    program required approved applicants to request BIA
    reimbursement only after incurring project costs.
    In 2000 and again in 2001, Menominee forest manager
    Marshall Pecore, and Menominee fire management officer
    Conrad Waniger, applied for HFR funding on behalf of
    the Tribe. The application sought federal funds to grade
    141 miles of forest roads and to create an additional
    Nos. 10-2676 & 10-3599                                          3
    273 miles of fuel breaks.1 To create these fuel breaks, MTE’s
    application represented that it would remove excess
    vegetation by performing brushing and disking work. As
    its name implies, brushing removes potentially flam-
    mable brush near a forest road. Disking, on the other
    hand, is the process of mixing organic soil with forest
    vegetation to eliminate the continuity of vegetation on
    the forest floor. After obtaining BIA approval, Menominee
    began HFR work in December 2000, and began invoicing
    BIA in 2001. Early MTE invoices requested BIA reim-
    bursement totaling a flat fee of $450 for each mile of fuel-
    break work. As work progressed, MTE abandoned its per-
    mile, fixed-fee invoices in exchange for invoices that
    requested reimbursement for actual costs incurred. The
    purpose of this change was hotly disputed during trial.
    The government claimed that problems with the Tribe
    developed in June 2001, after several MTE staff
    members told Dave Congos, the BIA forester assigned to
    the Tribe, that MTE’s Roads Department budget was
    running a deficit. Menominee employees reported that
    the Tribe purposefully diverted HFR funds to the Roads
    Department as a way to close the budget shortfall.
    Prompted by these reports, Congos and Thomas
    Magnuson, another BIA forester, personally inspected
    some of the work MTE claimed to have completed. Congos
    1
    A fuel break is a strip of land cleared of potentially flammable
    vegetation that runs parallel to a forest road. Among other
    benefits, an effective fuel break provides a defensive area
    for firefighters.
    4                                 Nos. 10-2676 & 10-3599
    and Magnuson walked the forest roads and compared
    their observations of work performed to a map prepared
    by MTE that purported to show completed and invoiced
    work. Both Congos and Magnuson concluded that the
    submitted invoices overstated the actual work done.
    In some cases, Congos felt that the work performed
    actually increased the risk of fire. Congos reported his
    findings to his supervisor and discussed the results
    with Waniger, who agreed to rework certain portions
    of the forest.
    Following their initial meeting in 2001, Waniger sub-
    mitted revised maps to Congos that again purported to
    show portions of the forest where HFR fire prevention
    work had been completed and invoiced. In one memoran-
    dum submitted by Waniger documenting 2001 fire reduc-
    tion accomplishments, Wangier claimed that fuel breaks
    were created for 96.2 miles. Of those 96 miles, 54 miles
    were fully completed and the remaining 42 miles were
    95% complete. Maps and memos in hand, Congos in-
    spected Tribal grounds for a second time to determine
    whether the actual work performed reconciled to what
    MTE had billed. Congos’s inspections confirmed his
    belief that the defendants were submitting false invoices
    for work that was never completed or completed in a
    way that did not meet HFR standards. This inspection,
    in part, subsequently served as the basis for the govern-
    ment’s False Claims Act suit.
    In July 2002, Congos and Magnuson contacted
    Joseph Schwartz in the Office of Inspector General
    (“OIG”) for the Department of Interior. Based on
    Nos. 10-2676 & 10-3599                                  5
    Congos’s report, Schwartz initiated an investigation
    into Menominee’s billing practices that included em-
    ployee interviews and a review of subpoenaed records.
    During the investigation, the government also identified
    what it believed were instances of falsified time cards
    relating to HFR funds. Namely, the government alleged
    that Tribe management required certain employees to
    code time worked to fire reduction efforts even though
    these employees were actually working on unrelated
    projects.
    By 2005, the government formally contacted MTE to
    discuss the results of the OIG investigation. Throughout
    the next several months, the parties communicated regu-
    larly and even appeared close to a settlement. But in
    2006, the defendants refused the government’s settle-
    ment offer and broke off negotiations. At that time, the
    defendants maintained their innocence and principally
    argued that the allegations were all one big misunder-
    standing. Had government investigators spent more
    time discussing the allegations with Pecore and Waniger,
    the defendants argue that the protracted litigation
    could have been avoided.
    With a settlement off the table in April 2007, the
    United States filed suit against MTE, Pecore, and Waniger
    alleging violations of the FCA, 
    31 U.S.C. §§ 3729-33
    . MTE,
    Pecore, and Waniger all filed motions to dismiss. The
    district court denied the motions as to Pecore and
    Waniger, but granted MTE’s motion because it was not
    a “person” within the meaning of the FCA. Subsequently,
    the district court rejected the remaining defendants’ and
    the government’s partial motions for summary judgment.
    6                                    Nos. 10-2676 & 10-3599
    At trial, the defendants claimed that the government
    was unclear about the standard fuel-break width it
    would use to evaluate whether MTE complied with HFR
    protocols. The defendants construed this silence and
    subsequent confusion about the fuel-break standard as
    evidence of a simple misunderstanding rather than evi-
    dence that the defendants knowingly submitted false
    invoices. There was further confusion about whether
    Menominee employees were properly recording time to
    HFR projects. The defendants conceded that one em-
    ployee had truly misclassified his time, but this fabrication
    was nothing more than an isolated anomaly. All other
    time-card discrepancies were really a proper internal-
    reporting scheme designed to reclassify time between
    certain departments. Again, had the government investi-
    gators explicitly discussed these discrepancies with the
    Tribe, there would have been no need for litigation.
    The defendants considered their ace-in-the-hole to be
    a 2009 inspection prepared by Ken Sloan, a retired
    forester.2 The defendants hired Sloan to independently
    inspect portions of the forest to determine whether
    2
    The defendants submitted the Sloan report shortly before
    trial, but after the discovery period had closed. The govern-
    ment vigorously argued that the report should be excluded
    from trial on the grounds that the defendants had violated a
    discovery order. The district court noted the violation but
    ultimately accepted the evidence to “ensure a full record
    and protect the Defendants themselves from the arguably
    deficient performance of their attorney.” United States v.
    Menominee Tribal Enters., No. 07-C-316, 
    2010 WL 2465505
    , at *4
    (E.D. Wis. June 15, 2010).
    Nos. 10-2676 & 10-3599                                         7
    Menominee had actually conducted appropriate brushing
    and disking work between 2000-2002. In response, the
    government conducted its own reinvestigation in
    October 2009. Congos testified at trial that the Sloan
    photographs showed some evidence of cutting, but that
    it was not evidence of cutting related to the HFR pro-
    gram. Additionally, Congos testified that other locations
    evaluated by Sloan continued to show no signs of any fire
    prevention work.
    At the close of the government’s evidence, the defen-
    dants moved for judgment as a matter of law, which
    the district court denied. After a nine-day trial, the defen-
    dants’ theory prevailed. Following their trial victory, the
    defendants moved for attorney’s fees under EAJA or
    alternatively, sanctions under Rule 37(c)(2). The district
    court denied both motions, and the defendants filed
    this timely appeal.3
    3
    Ten days before oral argument, the defendants requested
    that we take judicial notice of various letters and memoranda
    that purportedly illustrate Congos’s bias against defendants
    Pecore and Waniger. The defendants interpret this bias as the
    real reason the government brought suit. Although we are
    skeptical that documents defense counsel inadvertently failed
    to include in the record are the proper subject of judicial
    notice, we offer no opinion on this matter because these docu-
    ments do not change our conclusion that the district court
    did not abuse its discretion in finding substantial justification
    for the government’s position.
    8                                  Nos. 10-2676 & 10-3599
    II. A NALYSIS
    Pecore and Waniger present two related issues for
    our review. The defendants first contend that the district
    court erred by rejecting their post-trial motion for EAJA
    attorney’s fees. Similarly, Pecore and Waniger challenge
    the district court’s refusal to impose Rule 37 sanctions
    against the government. We review both of the district
    court’s decisions for an abuse of discretion. Pierce v.
    Underwood, 
    487 U.S. 552
    , 559-60 (1988) (reasoning that
    in EAJA cases, “the district court may have insights not
    conveyed by the record, into such matters as whether
    particular evidence was worthy of being relied upon, or
    whether critical facts could easily have been verified by
    the Government.”); Johnson v. Kakvand, 
    192 F.3d 656
    ,
    661 (7th Cir. 1999) (finding that Rule 37 decisions are
    reviewed deferentially because “[d]istrict courts possess
    wide latitude in fashioning appropriate sanctions and
    evaluating the reasonableness of the attorneys’ fees re-
    quested”).
    A. EAJA Attorney’s Fees
    The defendants principally contend that the district
    court abused its discretion by rejecting their motion for
    EAJA attorney’s fees. A district court may award such
    fees where “(1) the claimant is a prevailing party; (2) the
    government was not substantially justified in its position;
    (3) no special circumstances make an award unjust; and
    (4) the fee application is timely and supported by an
    itemized statement.” Conrad v. Barnhart, 
    434 F.3d 987
    , 989
    (7th Cir. 2006) (quotation marks omitted); 28 U.S.C.
    Nos. 10-2676 & 10-3599                                    9
    § 2412(d)(1)(A). Here, the defendants only challenge the
    district court’s finding related to the second element:
    whether the government was substantially justified in
    bringing the FCA action. The government bears the
    burden of proving that its position was substantially
    justified, and to do so, it must show: “(1) a reasonable
    basis in truth for the facts alleged; (2) a reasonable basis
    in law for the theory propounded; and (3) a reasonable
    connection between the facts alleged and the theory
    propounded.” Conrad, 
    434 F.3d at 990
    ; see also
    Golembiewski v. Barnhart, 
    382 F.3d 721
    , 724 (7th Cir.
    2004). In evaluating the government’s position, we
    review the claim in its entirety rather than the
    individual positions the government may have taken
    throughout different phases of litigation. Comm’r, I.N.S.
    v. Jean, 
    496 U.S. 154
    , 161-62 (1990).
    With that, we turn to the defendants’ argument on
    appeal, which cites three sets of uncontested facts that
    purportedly prove that the government’s case lacked
    substantial justification. First, the defendants suggest
    that the government’s position had no reasonable basis
    in the law. Similarly, the defendants next argue that
    the government’s position was not reasonably based on
    the facts. And third, Pecore and Waniger argue that the
    government failed to adequately investigate the defen-
    dants’ evidence. Each set of facts standing alone, the
    defendants assert, is enough to show that the govern-
    ment’s position was not substantially justified. Like the
    district court before us, we’ll evaluate each of these al-
    legations individually.
    10                                      Nos. 10-2676 & 10-3599
    1.   The Government’s Position Was Reasonably Based On
    The Law 4
    The defendants first contend that two legal errors
    prevented the government from ever establishing a
    substantially justified claim. First, the BIA failed to
    follow its own internal policies before the government
    filed suit. Second, the government’s FCA suit was really
    a poorly disguised breach of contract suit. The govern-
    ment’s failure to select the proper cause of action pre-
    cluded it from developing a substantially justified
    FCA claim. Both arguments are baseless.
    First, the defendants argue that the government
    violated the internal BIA policy manual and the Midwest
    Regional Office Handbook, both of which require the
    government to consult with Tribe personnel before
    taking federal action. Had the government obeyed the
    two internal consultation policies, the Tribe could have
    explained away the confusion about its fire reduction
    work, the rationale for its complex billing practice, and
    4
    On appeal, the defendants argue for the first time that
    sovereign immunity protects tribal employees such as Pecore
    and Waniger from FCA suits, and as such, the government’s
    position lacked substantial legal justification. Although the
    defendants made a similar sovereign immunity argument in
    their merits brief supporting summary judgment, which the
    district court rejected, the defendants did not raise this issue
    in their post-trial brief for EAJA attorney’s fees. Accordingly,
    the defendants waived this argument as to EAJA attorney’s
    fees, and we will not consider it. Fednav Int’l Ltd. v. Cont’l Ins.
    Co., 
    624 F.3d 834
    , 841 (7th Cir. 2010).
    Nos. 10-2676 & 10-3599                                      11
    whether the width of its fuel breaks complied with
    HFR standards. According to the defendants, had these
    conversations occurred, both parties could have avoided
    trial. But, as a threshold matter, a government agency’s
    internal policies and procedures (as opposed to duly
    enacted regulations) do not have the force of law. See
    Krasilych v. Holder, 
    583 F.3d 962
    , 966 (7th Cir. 2009) (noting,
    for example, that the “Attorney General’s guidelines are
    internal rules that have no legal force”). In this case, the
    clue as to the status of the BIA policy is located on the
    very first page of the Government-to-Government Con-
    sultation Policy, where it plainly states that the policy
    “illustrates the guidelines that the Bureau of Indian
    Affairs will follow for consultation with tribal govern-
    ments.” Bureau of Indian Affairs, Government-to-Gov-
    ernment Consultation Policy 1 (2000) (emphasis added).
    Certainly agency guidelines do not carry the weight of
    law, and thus, any alleged violation can serve only as
    probative evidence that the government failed to file
    suit in good faith.
    The seven cases cited by the defendants in support of
    their policies and procedures argument do not bolster
    their claim. Instead, each case only suggests the possi-
    bility for EAJA attorney’s fees when the government
    violates a law, an agency regulation, or clear judicial
    precedent. See, e.g., Stewart v. Astrue, 
    561 F.3d 679
    , 684
    (7th Cir. 2009) (awarding EAJA attorney’s fees “because
    the ALJ contravened longstanding agency regulations, as
    well as judicial precedent”); Golembiewski, 
    382 F.3d at 724
    (awarding EAJA attorney’s fees because “the ALJ and
    Commissioner violated clear and long judicial precedent
    12                                 Nos. 10-2676 & 10-3599
    and violated the Commissioner’s own Ruling and Reg-
    ulations”); Or. Natural Res. Council v. Madigan, 
    980 F.2d 1330
    , 1332 (9th Cir. 1992) (awarding attorney’s fees
    after the agency failed to issue regulations demanded by
    clear statutory language). Because the defendants allege
    only that the government violated internal policy guide-
    lines, we reject their first legal argument.
    Even if the BIA’s policies had the force and effect of
    law, the record belies the defendants’ claim that they
    were not adequately consulted before the government
    brought suit. For example, Congos testified that he
    spoke with Waniger in 2001 about the work deficiencies
    Congos identified during his initial forest inspection, and
    Waniger promised to rework the identified areas. During
    the remainder of 2001 and 2002, Congos, Waniger, and
    Pecore communicated through written memoranda and
    work-completion maps about the status of the Tribe’s
    HFR work. In 2005, the government contacted the Tribe
    to formally discuss the results of the OIG investigation.
    And, during much of 2006, the parties engaged in signifi-
    cant settlement negotiations. Each discussion occurred
    before the government brought suit in 2007. As a
    simple question of fact, the record reveals that the de-
    fendants had several years to eliminate any misunder-
    standings about its work. Ultimately, the defendants’
    internal-policies argument is baseless.
    The defendants’ second legal objection to the district
    court’s ruling is that the court failed to recognize that
    the government’s suit was more akin to a breach-of-con-
    tract action than an FCA action. According to the defen-
    Nos. 10-2676 & 10-3599                                   13
    dants, if the government misused the FCA statute, then
    surely it could not have been substantially justified
    in bringing such a suit. As a result, the defendants
    claim the breach-of-contract action should have been
    governed by the Indian Self-Determination Education
    and Assistance Act (“ISDEAA”).
    We need not spend much time discussing the merits
    of the defendants’ claim because the district court right-
    fully concluded that a case involving contract performance
    does not necessarily foreclose FCA liability. Menominee
    Tribal Enters., 
    2010 WL 2465505
    , at *6 (citing United States
    ex rel. Davis v. Dyna Corp., 
    17 F.3d 397
     (9th Cir. 1994)
    (unpublished table decision)). It is perfectly logical for a
    contracting party to knowingly submit a false invoice
    purportedly pursuant to a valid contract. As we will
    discuss shortly, the government had reasonable grounds
    for believing that the defendants knowingly submitted
    false invoices, and as such, the government’s claim fit
    neatly into the FCA.
    Because the defendants’ legal objections are without
    merit, we find that the government had substantial
    legal justification for bringing an FCA claim.
    2.   The Government’s Position Was Reasonably Based On
    The Facts
    The defendants next contend that the government’s
    position was not substantially justified because the gov-
    ernment failed to prove its factual allegations at trial.
    Here, the defendants argue that an FCA claim requires
    the government to prove the defendants submitted a
    14                                  Nos. 10-2676 & 10-3599
    false statement, see Hindo v. Univ. of Health Scis./The
    Chicago Med. Sch., 
    65 F.3d 608
    , 613 (7th Cir. 1995), but
    the government could never prove that the defendants
    lied. In the absence of a lie, the government’s position
    had no substantial factual justification.
    Before reviewing the record, it is first important to
    recall that the substantial justification standard does not
    require the government to have won at trial. In fact, the
    government’s position need not even be correct. Pierce,
    
    487 U.S. at
    566 n.2 (“[A] position can be justified even
    though it is not correct, and we believe it can be sub-
    stantially (i.e., for the most part) justified if a rea-
    sonable person could think it correct.”). Rather, sub-
    stantial justification only requires the position to have
    “a reasonable basis in law and fact.” Conrad, 
    434 F.3d at 990
    ; Pierce, 
    487 U.S. at 565
     (a position need only be “justi-
    fied to a degree that could satisfy a reasonable per-
    son”). Here, the defendants broad assertions that “[t]he
    government’s [motive] theory collapsed at trial” and “the
    Government failed to prove that either Pecore or
    Waniger lied,” only suggest that the jury sided with the
    defendants, not that their opponent’s position was
    never substantially justified. Therefore, we generally
    ignore what the jury believed or did not believe at trial,
    and instead focus on whether the government’s position
    as a whole could satisfy a reasonable person. See Jean,
    
    496 U.S. at 161-62
    .
    Moving to the facts, the defendants first argue with
    some force that the government could never articulate a
    reasonable motive theory. After all, why would two men
    Nos. 10-2676 & 10-3599                                       15
    risk criminal and civil sanctions when they never
    received any benefits in return? Without a motive theory,
    the defendants contend that the government could not
    prove a lie or false claim, and without a lie, an FCA claim
    necessarily fails.5 Hindo, 
    65 F.3d at 613
    . Although the
    defendants attempt to construe the motive question
    as uncontested, this issue was subject to conflicting evi-
    dence and testimony such that a reasonable person
    could have accepted either version of events, which is
    all we require. Pierce, 
    487 U.S. at 565
    . For example, the
    government maintained throughout trial that Congos
    and Pecore were looking for a source of funds to keep
    the Menominee Roads Department in the black. The
    district court heard testimony to this effect. On the
    other hand, the defendants claim that the government’s
    “key” motive witness unknowingly contradicted the
    government’s theory by suggesting that additional
    Roads Department funds were only spent three years
    after they were requested. The defendants construed
    this testimony as proof that the Roads Department
    never had an urgent need for additional funding, and
    thus, Pecore and Waniger were never motivated to
    falsify government invoices to obtain additional funding.
    In pointing to the version of events that the jury ap-
    parently believed, the defendants ignore the legitimate
    5
    Motive is not an element for an FCA claim. See Hindo, 
    65 F.3d at 613
    . Rather, the defendants appear to only highlight the
    lack of motive as evidence that defendants did not knowingly
    submit a false statement.
    16                                  Nos. 10-2676 & 10-3599
    factual dispute that existed throughout the litigation.
    Instead, the defendants seem to simply rely on their
    trial victory. But this is not enough. Furthermore, even
    if we completely accept as true the defendants’ version
    of motive, it still does not directly contradict or disprove
    the government’s position that the Roads Department
    faced serious budget difficulties. Accordingly, the
    district court did not abuse its discretion in finding
    that the government’s motive theory was substantially
    justified, even though it apparently failed at trial.
    The defendants’ second factual dispute highlights the
    miscommunication between the parties about Tribal
    billing practices. Here, the defendants claim that they
    never billed the government on a per-mile basis, but
    rather, only submitted bills for actual fire prevention
    costs incurred. Moreover, the bills detailing actual costs
    represented an accurate snapshot of MTE’s legitimate
    costs. The defendants also contend that the maps sub-
    mitted to Congos were never supposed to accurately
    represent the precise amount of work MTE had com-
    pleted. Instead, the maps were only to be used as a
    general guide to their work. Accordingly, the de-
    fendants argue that government confusion was the
    reason for the charges against Pecore and Waniger, and
    thus, the government could never prove that Pecore
    or Waniger submitted a false claim.
    As was the case for the factual dispute about the de-
    fendants’ motive, the government offered evidence to
    counter the defendants’ theory. First, the government
    offered testimony suggesting that MTE had submitted a
    Nos. 10-2676 & 10-3599                                  17
    handful of invoices on a per-mile basis. Only after
    Congos’s initial inspection did the Tribe change to cost-
    based invoicing. Next, the government offered a 2001
    accomplishments memorandum prepared by Waniger
    stating that fuel breaks were created for 96.2 miles and
    that work was at least 95% completed. The government
    also offered testimony indicating that Waniger sub-
    mitted a second completion map to Congos after MTE
    rework was completed. Finally, the government offered
    Congos’s testimony about his 2001 and 2002 inspections
    as well as his brief 2009 reinspection following the
    Ken Sloan report. On appeal, our review of the record
    confirms the district court’s finding that there was
    ample confusion associated with the Tribe’s invoices.
    We also agree with the district court’s finding that “even
    if the Defendants’ expense-based view of its billing
    was entirely correct, that did not entitle it to list areas
    of work done (by mileage) if those areas were not
    actually done.” Menominee Tribal Enters., 
    2010 WL 2465505
    ,
    at *3. Ultimately, the intense nature of this debate
    suggests to us that either party’s position could be ac-
    cepted as true by a reasonable person.
    Two final points about the defendants’ factual dis-
    putes bear mentioning. First, the defendants ignore the
    objective, although not necessarily conclusive, evidence
    that the government’s complaint survived both a motion
    to dismiss and a motion for summary judgment. United
    States v. Thouvenot, Wade & Moerschen, Inc., 
    596 F.3d 378
    ,
    382 (7th Cir. 2010) (“[T]here is a [rebuttable] presumption
    that a government case strong enough to survive both
    a motion to dismiss and a motion for summary judg-
    18                                      Nos. 10-2676 & 10-3599
    ment is substantially justified.”). 6 This objective evi-
    dence combined with the intensity of the factual
    disputes between the parties illustrates that the govern-
    ment had a substantial fact-based justification for
    bringing suit. The second, and perhaps more important,
    concluding thought is that our review is limited to a
    discussion of whether the district court abused its dis-
    cretion. Conrad, 
    434 F.3d at 990
    . Although our own
    review of the record shows that the government’s
    position was substantially justified, we must again ac-
    knowledge the district court’s unique position to
    6
    The defendants criticize Thouvenot because it supposedly shifts
    the government’s statutory burden of proof to the prevailing
    defendant by creating a presumption of substantial justifica-
    tion if a case survives both a motion to dismiss and summary
    judgment. This is wrong. Thouvenot only construes a motion
    to dismiss or summary judgment victory as objective and
    perhaps compelling evidence of substantial justification. Pierce,
    
    487 U.S. at 568
     (finding that objective factors are relevant).
    Notably, Thouvenot left the door open for an attorney’s fees
    award in those cases where something emerges at trial proving
    that the government never had a case or in those cases where
    the district court judge has new evidence to show that she
    “erred grievously in refusing to grant the defendant’s motion
    to dismiss or motion for summary judgment.” Thouvenot, 
    596 F.3d at 382
    . But, even if Thouvenot was somehow improperly
    decided, the district court in this case expressly stated that
    Thouvenot was only a second, independent ground for
    rejecting the defendants’ EAJA motion. In other words, even
    if Thouvenot did not exist, the government’s position was
    still substantially justified.
    Nos. 10-2676 & 10-3599                                   19
    observe and weigh the evidence over two-and-one-
    half years of an intensely factual litigation. Pierce, 
    487 U.S. at 560
     (“[S]ome of the elements that bear upon
    whether the Government’s position ‘was substantially
    justified’ may be known only to the district court.”).
    Ultimately, the defendants have not offered anything
    to cast doubt on the district court’s well-reasoned sixteen-
    page opinion.
    For the preceding reasons, we find the district court
    did not abuse its discretion in concluding that the gov-
    ernment’s position had a substantial factual justification.
    3.   The Government Properly Investigated The Defendants’
    Evidence
    Finally, the defendants argue that the government
    failed to properly investigate its own FCA claim, in
    violation of 
    31 U.S.C. § 3730
    (a) (“The Attorney General
    diligently shall investigate a violation under section
    3729.”). Such a failure to investigate, according to the
    defendants, is further evidence that the government’s
    position was never substantially justified. Pecore and
    Waniger assert that the government’s reliance on
    stale Congos inspections instead of the more recent
    Sloan report exculpating the defendants is proof that
    the government failed to investigate. We disagree.
    As a threshold matter and as the district court noted,
    the loose grasp the government supposedly had on the
    facts might have more to do with the defendants’ border-
    line discovery abuses rather than the government’s
    20                                 Nos. 10-2676 & 10-3599
    failure to investigate to the defendants’ liking. See
    Menominee Tribal Enters., 
    2010 WL 2465505
    , at *4. We
    lend little credence to the defendants’ argument that
    the government should have dropped its suit after
    reading the Sloan report when that report was not pro-
    duced until the eve of trial. Second, there is no support
    for the defendants’ apparent position that the govern-
    ment must give greater deference to the defendants’
    expert rather than rely on its own forester’s inspec-
    tions. Instead, trial litigation routinely boils down to
    a battle of experts, and a dispute between experts “tends
    to show a good faith dispute,” Chicago Dist. Council of
    Carpenters Pension Fund v. Reinke Insulation Co., 
    464 F.3d 651
    , 656 (7th Cir. 2006), which is another way to
    say that both parties’ claims were substantially justified.
    Third, the defendants’ contention that Congos’s inspec-
    tions were stale as compared to the Sloan report is, at
    best, irrelevant. To the contrary, a reasonable person
    could have found that the Congos inspections were
    more reliable because they occurred closer in time to
    when the fire reduction work was supposedly com-
    pleted. Finally, Congos testified at trial that the govern-
    ment conducted its own reinspection in October 2009
    following the belated Sloan inspection. According to
    Congos, the Sloan photos showed some evidence of
    cutting unrelated to the HFR program, but other por-
    tions of the forest continued to show no signs of any fire
    prevention work. Ultimately, the defendants’ contention
    that its inspection is better than the others is similar to
    the other fact-intensive disputes the defendants have
    highlighted on appeal. Like this other conflicting evi-
    Nos. 10-2676 & 10-3599                                   21
    dence, the parties’ debate about the validity of the in-
    spections says little about substantial justification.
    Rather, the intensity of the dispute, both at trial and on
    appeal, shows that a reasonable person could have been
    satisfied by either party’s theory. Pierce, 
    487 U.S. at 565
    .
    Defendants’ reliance on Phil Smidt & Son, Inc. v. NLRB,
    
    810 F.2d 638
     (7th Cir. 1987), is misplaced. There,
    we reversed the district court’s refusal to impose EAJA
    attorney’s fees against the government in part because
    of the strong contradictory evidence presented by the
    defendant. We chided the government for not making
    “any attempt to independently corroborate [its] allega-
    tion.” 
    Id. at 643
     (emphasis added). In this case, however,
    the record reveals that the government investigated the
    Sloan report, reinspected portions of the forest, and
    concluded that Congos’s inspections were more reliable.
    This is not a case where the government completely
    abdicated its duty to diligently investigate its claims
    against Pecore and Waniger.
    Because the government’s position throughout trial
    was substantially justified, the district court did not
    abuse its discretion in denying defendants’ EAJA motion.
    B. Rule 37(c)(2) Sanctions
    The defendants allege that the district court also abused
    its discretion in denying its Rule 37 motion. Federal Rule
    of Civil Procedure 37(c)(2) provides that a district court
    must impose reasonable expenses including attorney’s
    fees on a party that fails to properly admit the genuine-
    22                                  Nos. 10-2676 & 10-3599
    ness of a document pursuant to a Rule 36 request for
    admission. Fed. R. Civ. P. 37(c)(2); Hicklin Engineering,
    L.C. v. Bartell, 
    439 F.3d 346
    , 351 (7th Cir. 2006). But, this
    rule provides an escape hatch for those parties that “had
    a reasonable ground to believe that it might prevail on
    the matter.” Fed. R. Civ. P. 37(c)(2)(C). The district court
    found that the government fit into this exception, and
    thus, it denied the defendants’ request for sanctions.
    We agree.
    In its motion for sanctions and again on appeal, the
    defendants identify two types of Rule 36 requests that
    the government should have admitted. The first type
    was a request like Request 21, which asked the govern-
    ment to admit that the defendants incurred $8,707.50
    in expenses related to invoice 200. The government
    denied knowledge sufficient to admit or deny the re-
    quest. The second type of Rule 36 request asked
    the government to admit that work related to invoice
    200, for example, had been substantially completed. The
    government unambiguously denied this type of request
    as it was the government’s position all along that
    Pecore and Waniger submitted invoices for work that was
    incomplete, deficient, or both. The defendants served
    identical requests for several different invoices.
    We need not spend much time disposing of the defen-
    dants’ argument because we have already covered much
    of this ground in our EAJA analysis. There, we held
    that there was reasonable confusion surrounding MTE’s
    invoices, completion maps, and accomplishment memo-
    randa such that either party’s position was “justified to a
    Nos. 10-2676 & 10-3599                                   23
    degree that could satisfy a reasonable person.” Pierce,
    
    487 U.S. at 565
    . Rule 37(c)(2) incorporates a standard
    that is strikingly similar to Pierce. The 1970 Advisory
    Committee notes provide that “the true test under
    Rule 37(c) is not whether a party prevailed at trial but
    whether he acted reasonably in believing that he might
    prevail.” Fed. R. Civ. P. 37 advisory committee’s note;
    see Mut. Serv. Ins. Co. v. Frit Indus., Inc., 
    358 F.3d 1312
    ,
    1326 (11th Cir. 2004). Based on our EAJA analysis, we
    find that the government reasonably believed it might
    prevail on the invoice and map issue for the same
    reasons we found the government’s position to be sub-
    stantially justified. Therefore, we find that the dis-
    trict court did not abuse its discretion in rejecting the
    defendants’ request for Rule 37 sanctions.
    III. C ONCLUSION
    We hold that the district court did not abuse its dis-
    cretion and accordingly, we A FFIRM its decision denying
    defendants’ motions for attorney’s fees under either
    EAJA or Rule 37(c)(2).
    12-30-11