Driftless Area Land Conservanc v. Rebecca Valcq ( 2021 )


Menu:
  •      United States Court of Appeals
    For the Seventh Circuit
    ____________________
    No. 20-3325
    DRIFTLESS AREA LAND CONSERVANCY and
    WISCONSIN WILDLIFE FEDERATION,
    Plaintiffs-Appellees,
    v.
    REBECCA VALCQ and TYLER HUEBNER, ∗
    in their official capacities as members of
    the Public Service Commission of Wisconsin,
    Defendants-Appellants,
    and
    AMERICAN TRANSMISSION COMPANY LLC, et al.,
    Intervenor Defendants-Appellants.
    ____________________
    Appeal from the United States District Court
    for the Western District of Wisconsin.
    No. 19-cv-1007 — William M. Conley, Judge.
    ____________________
    ARGUED FEBRUARY 17, 2021 — DECIDED OCTOBER 21, 2021
    ____________________
    ∗ Commissioner Tyler Huebner has been substituted for former Commis-
    sioner Michael Huebsch, who resigned from office. See FED. R. APP.
    P. 43(c)(2).
    2                                                 No. 20-3325
    Before SYKES, Chief Judge, and FLAUM and ROVNER, Circuit
    Judges.
    SYKES, Chief Judge. This appeal is another chapter in con-
    current federal and state litigation challenging the construc-
    tion of a $500 million, 100-mile power line in southwestern
    Wisconsin. In September 2019 the Public Service Commis-
    sion of Wisconsin issued a permit authorizing two transmis-
    sion companies and an electricity cooperative to build and
    operate the line. A few months later, two environmental
    groups filed lawsuits in both federal and state court seeking
    to invalidate the permit. As relevant here, the parallel suits
    allege that two of the three commissioners had disqualifying
    conflicts of interest and should have recused themselves.
    Both suits raise federal due-process claims; the state litiga-
    tion also invokes state recusal law and contests the permit on
    other state-law grounds.
    The case was last here at an early stage of the proceed-
    ings when the district judge rejected the permit holders’
    motion to intervene. We reversed that decision and remand-
    ed with instructions to grant the intervention motion.
    Driftless Area Land Conservancy v. Huebsch (“Driftless I”),
    
    969 F.3d 742
     (7th Cir. 2020). Rulings on dismissal motions
    followed, and the judge significantly narrowed the scope of
    the case. But he denied the commissioners’ motion to dismiss
    based on sovereign immunity. The case returns to us on that
    issue.
    The commissioners have been sued in their official capac-
    ities, so sovereign immunity blocks this suit in its entirety
    unless it falls within the Ex parte Young exception, which
    authorizes a federal suit against state officials for the pur-
    pose of obtaining prospective relief against an ongoing
    No. 20-3325                                                   3
    violation of federal law. The environmental groups seek an
    order vacating the permit or enjoining its enforcement; the
    latter is prospective relief. The harder question is whether
    the suit challenges an ongoing violation of federal law. The
    alleged due-process violation occurred (if at all) in Septem-
    ber 2019 when the commissioners approved the permit. The
    environmental groups contend that the violation is ongoing
    as long as the permit remains in force and effect and the
    commissioners have the power to enforce, modify, or rescind
    it. Though there is little precedent precisely on point for a
    claim like this one, we hold that Ex parte Young applies and
    therefore agree with the judge’s ruling on sovereign immuni-
    ty.
    The commissioners also moved for abstention under
    Colorado River Water Conservation District v. United States,
    
    424 U.S. 800
    , 818 (1976), which authorizes a federal court to
    abstain from exercising jurisdiction and stay a case to await
    the outcome of parallel state litigation when there is a sub-
    stantial likelihood that the state case will resolve the federal
    claim. The judge denied the request, reasoning that the
    federal and state suits are not parallel because the state case
    doesn’t raise a federal due-process claim. That was an error;
    as we’ve noted, both cases raise federal due-process claims.
    Although the abstention ruling is not before us, we may
    raise abstention sua sponte and do so here.
    The state and federal suits are clearly parallel for purpos-
    es of Colorado River. The environmental groups have raised
    materially identical due-process recusal claims in both state
    and federal court. Given the context—this case implicates
    serious state interests regarding the operation of Wisconsin
    administrative law and judicial review of state-agency
    4                                                 No. 20-3325
    proceedings—it’s appropriate to abstain from exercising
    federal jurisdiction to give the state courts an opportunity to
    decide the recusal issue. Litigating the same conflict-of-
    interest questions in both court systems is duplicative and
    wasteful; comity and the sound administration of judicial
    resources warrant abstention under Colorado River. We
    remand with instructions to stay the case pending resolution
    of the state proceedings.
    I. Background
    The underlying administrative proceedings are complex,
    but the details are largely unimportant here. What’s needed
    is a basic understanding of the state regulatory framework
    and the background of the federal and state litigation. We
    assume familiarity with Driftless I and will be as brief as
    possible, but some length cannot be avoided.
    The plaintiffs are two Wisconsin environmental groups,
    Driftless Area Land Conservancy and the Wisconsin Wildlife
    Federation. They sued the Public Service Commission of
    Wisconsin and its three commissioners—Rebecca Valcq,
    Michael Huebsch, and Ellen Nowak. The intervenors are the
    utility companies that hold the permit and will own and
    operate the power line: American Transmission Company
    LLC, ITC Midwest LLC, and Dairyland Power Cooperative
    (we refer to them collectively as “the transmission compa-
    nies”).
    To place the sovereign-immunity and abstention issues in
    context, some background about the regulatory scheme is
    necessary. The Commission “has jurisdiction to supervise
    and regulate every public utility” in Wisconsin. WIS. STAT.
    § 196.02(1). Its three commissioners are appointed by the
    No. 20-3325                                                    5
    governor and confirmed by the state senate. One of the
    Commission’s many duties is to regulate the construction of
    high-voltage electricity transmission lines. Id. § 196.491(1)(e),
    (3). With one irrelevant exception, transmission lines may be
    constructed only if the Commission grants a permit known
    as a “certificate of public convenience and necessity.” Id.
    § 196.491(3)(a)1. Although a permit is a prerequisite for
    projects that require the use of eminent domain, the
    Commission itself does not condemn the land needed for
    construction. Rather, state law transfers the state’s eminent-
    domain power to the utility once the permit has been ap-
    proved. Id. § 32.02. That is, a utility company holding an
    approved permit may use the condemnation power to
    acquire the land needed to complete an approved project.
    The permitting process is complex. The Commission may
    grant a permit only if the transmission line is “in the public
    interest.” Id. § 196.491(3)(d)3. An application commences a
    highly technical inquiry. The Commission must consider a
    multitude of factors such as the reliability of the power
    supply, alternative sources of supply, economic factors,
    engineering obstacles, safety, and environmental impact. Id.
    The Commission’s role continues after it issues a permit. The
    enabling statute is expansive and gives the Commission
    sweeping jurisdiction to “supervise and regulate every
    public utility in this state and to do all things necessary and
    convenient to its jurisdiction.” Id. § 196.02(1). This includes
    the power to file lawsuits, id. § 196.02(12), and to “rescind,
    alter[,] or amend” a permit at any time, id. § 196.39(1).
    The Commission also coordinates with the Midcontinent
    Independent System Operator (“MISO”), a regional trans-
    mission organization that operates interstate electricity grids
    6                                                            No. 20-3325
    on behalf of its constituent utility companies. 1 MISO must
    involve the Commission in all grid-expansion activities. See
    
    18 C.F.R. § 35.34
    (k)(7). In order to coordinate with MISO, the
    Commission delegates to one commissioner the authority to
    represent it before MISO’s Advisory Committee and the
    Board of the Organization of MISO States, a group that
    represents the interests of state regulators. Commissioner
    Huebsch was the Commission’s designated MISO repre-
    sentative during the relevant period, and he also served as
    secretary of the Organization of MISO States.
    The events giving rise to the parallel state and federal lit-
    igation began in April 2018 when the transmission compa-
    nies applied for a permit to construct a 100-mile, high-
    voltage power line stretching from Dane County in south-
    central Wisconsin to Dubuque County in eastern Iowa. At a
    projected cost of about $500 million, the power line would
    serve the electricity needs of consumers in the southwestern
    quadrant of the state. The application required the Commis-
    sion to convene a class 1 “contested case” proceeding under
    state administrative law. WIS. STAT. § 227.01(3)(a). More than
    50 parties intervened, including Driftless and the Wildlife
    Federation. On behalf of themselves and their members, they
    opposed the project based on environmental and land-use
    impacts.
    After extensive proceedings and submissions, on
    August 20, 2019, the Commission held an open meeting and
    1 A regional transmission organization is a voluntary association of
    utility companies that operates electrical grids on behalf of the utilities.
    See Ill. Com. Comm’n v. Fed. Energy Regul. Comm’n, 
    721 F.3d 764
    , 769 (7th
    Cir. 2013).
    No. 20-3325                                                 7
    unanimously voted to conditionally grant the permit. A
    month later the two environmental groups moved to dis-
    qualify Commissioners Valcq and Huebsch based on alleged
    conflicts of interest. On September 26, 2019, the Commission
    issued a 112-page order finalizing and approving the permit.
    The order addressed and rejected the recusal motion as
    untimely, procedurally improper, and lacking a “factual
    basis to support recusal.”
    On December 11 Driftless and the Wildlife Federation
    sued the Commission and the commissioners in federal
    court in the Western District of Wisconsin seeking to invali-
    date the permit. Two days later they filed two suits in state
    court seeking the same relief under Chapter 227 of the
    Wisconsin Statutes, which authorizes judicial review of state
    administrative proceedings. See 
    id.
     § 227.53. Within days
    they intervened in a third judicial-review lawsuit filed by
    another party. (From now on we refer to the two environ-
    mental groups collectively as “Driftless.”)
    The federal suit raises due-process and takings claims
    under 
    42 U.S.C. § 1983
    . The first two counts center on allega-
    tions that Commissioners Valcq and Huebsch had disquali-
    fying conflicts of interest that required them to recuse
    themselves from the permit proceeding. Count One alleges a
    violation of due process. Count Two, styled as a violation of
    “Due Process and Eminent Domain,” simply repackages the
    due-process claim as an unconstitutional taking of private
    property. This count adds nothing of legal significance;
    allegations of adjudicator bias implicate the Due Process
    Clause, not the Takings Clause, so Count Two can be ig-
    nored. Count Three, a true Takings Clause claim, alleges that
    8                                                 No. 20-3325
    the permit authorizes an unconstitutional taking of private
    property for private use.
    The conflict-of-interest allegations against Commissioner
    Valcq stem from her career in the private sector. Prior to her
    service on the Commission, Valcq was employed as in-house
    and outside counsel for We Energies Corp. The parent
    company of We Energies owns a 60% interest in American
    Transmission Company, one of the permit applicants. The
    conflict-of-interest allegations against Huebsch center on his
    representation of the Commission on MISO, which inter-
    vened in the permit proceedings in support of the project.
    The complaint also accuses him of engaging in ex parte
    communications with MISO representatives and other
    interested parties.
    The state lawsuits—including a fourth judicial-review
    action—were consolidated in Dane County Circuit Court,
    and the combined litigation raises a federal due-process
    claim based on the same conflict-of-interest allegations
    involving Commissioners Valcq and Huebsch. The state
    litigation also invokes the right to an impartial adjudicator
    under state law and raises unrelated violations of state
    administrative and environmental law.
    The opening act in the federal suit involved a disagree-
    ment over the transmission companies’ right to intervene.
    Our August 2020 decision in Driftless I authorized their
    intervention, and on remand the case proceeded to decision
    on a bevy of dismissal arguments. As relevant here, the
    Commission, the commissioners, and the transmission
    companies moved to dismiss the complaint based on sover-
    eign immunity and the failure to state any cognizable consti-
    tutional claim. Alternatively, they urged the judge to abstain
    No. 20-3325                                                    9
    from exercising jurisdiction and stay the case based on the
    ongoing state litigation, citing both Younger v. Harris,
    
    401 U.S. 37
     (1971), and Colorado River.
    In November 2020 the judge issued a lengthy decision
    dismissing the case in part and substantially trimming its
    scope. First, he dismissed the case against the Commission
    itself, explaining that state agencies, as arms of the state,
    enjoy sovereign immunity from suit in federal court under
    the Eleventh Amendment. Indeed, Driftless conceded its
    mistake in suing the Commission and agreed that it must be
    dismissed from the suit. The commissioners’ immunity
    claim, however, was another matter; it was hotly contested.
    State officials may be sued in federal court in their official
    capacities notwithstanding the state’s sovereign immunity if
    the Ex parte Young exception applies. Under that doctrine a
    plaintiff may proceed in federal court against a state official
    for the limited purpose of obtaining prospective relief
    against an ongoing violation of federal law. The judge
    concluded that Ex parte Young applies and declined to dis-
    miss the suit against the commissioners on immunity
    grounds.
    The judge also denied the abstention request, ruling that
    Younger abstention is inapplicable because the state case
    doesn’t fit within the limited categories of cases covered by
    the doctrine. He also ruled out Colorado River abstention. He
    reasoned that the federal and state cases are not parallel in
    the sense meant by Colorado River because the state litigation
    does not raise a federal constitutional claim (or so he
    thought, mistakenly).
    10                                                No. 20-3325
    Moving on to the arguments on the merits, the judge
    dismissed Count Three—the takings claim—for failure to
    state a claim. Under the broad contours of the Supreme
    Court’s Takings Clause cases, see, e.g., Kelo v. City of New
    London, 
    545 U.S. 469
    , 478–82 (2005), that claim is not remote-
    ly plausible. As the judge explained, construction of a power
    line is universally recognized as a constitutionally permissi-
    ble public purpose for using eminent domain.
    That left only the due-process claim based on the conflict-
    of-interest allegations involving Commissioners Valcq and
    Huebsch. The judge concluded that the conflict allegations
    against them cleared the plausibility bar under the due-
    process standard announced in Caperton v. A.T. Massey Coal
    Co., 
    556 U.S. 868
     (2009). But nothing in the complaint sug-
    gests that Commissioner Nowak had a conflict of interest, so
    the judge dismissed the case against her.
    The judge’s sovereign-immunity ruling precipitated this
    appeal. An order denying a claim of sovereign immunity is
    immediately appealable, Richman v. Sheahan, 
    270 F.3d 430
    ,
    434 (7th Cir. 2001), so Valcq and Huebsch—the remaining
    defendants—appealed the denial of their motion to dismiss
    on immunity grounds. A stay is customary in this situation,
    Allman v. Smith, 
    764 F.3d 682
    , 684 (7th Cir. 2014), so we
    stayed the proceedings in the district court while the im-
    munity appeal is pending. On August 26, 2021, Driftless
    moved to partially lift the stay. We address that motion
    below.
    II. Discussion
    We begin with an oddity in the case that complicates the
    analysis of sovereign immunity and the Ex parte Young
    No. 20-3325                                                  11
    exception. Huebsch resigned from the Commission in
    February 2020, shortly after the suit was filed and long
    before the judge ruled on the motion to dismiss. Inexplica-
    bly, he remains a defendant in this official-capacity suit even
    though he is out of office and no relief can be ordered
    against him. Under Rule 25(d) of the Federal Rules of Civil
    Procedure, when a public officer is sued in his official capac-
    ity and resigns from office while the suit is pending, his
    successor is automatically substituted. Tyler Huebner suc-
    ceeded Heubsch in March 2020, but the substitution did not
    occur.
    As the case comes to us, then, Valcq is the only defendant
    against whom an injunction could possibly issue. And that
    raises an anomaly in the district court’s Ex parte Young
    analysis. An injunction against Valcq—one member of a
    three-member commission—would be pointless. We can fix
    the problem by applying Rule 43(c)(2) of the Federal Rules of
    Appellate Procedure, which like Rule 25(d) requires the
    substitution of the current officeholder. We therefore substi-
    tute Commissioner Huebner for Huebsch.
    But that’s not the only complication. There are notable
    gaps in the information we’ve received from the parties
    about the status of the concurrent state proceedings. While
    this appeal has been pending, significant developments have
    occurred in the state litigation. The parties alerted us to this
    information only very recently in their briefs supporting and
    opposing the August 26 motion to partially lift the stay. Even
    then, however, they omitted some important details.
    Here’s what we’ve pieced together from the public record
    and the parties’ filings on the motion to lift the stay. On
    January 21, 2021—a month before this appeal was argued—
    12                                                No. 20-3325
    the judge presiding in the consolidated judicial-review
    proceedings in Dane County held a lengthy hearing and
    ruled that Commissioner Valcq’s prior representation of We
    Energies was not a disqualifying conflict of interest and did
    not trigger a due-process duty to recuse. The judge accord-
    ingly rejected Driftless’s request for discovery on those
    allegations and said he was “throwing out any challenge to
    Commissioner Valcq.” Hearing Transcript (Jan. 21, 2021),
    Affidavit of Brian H. Potts in Response to Motion to Lift Stay,
    Ex. 2 at 77, No. 20-3325, ECF No. 64-2. The judge reached the
    opposite conclusion regarding Huebsch, ruling that the
    conflict-of-interest allegations against him were enough to
    state a prima facie case of an appearance of improper bias.
    
    Id.
     at 77–79. The judge therefore authorized discovery on the
    recusal question involving Huebsch and directed the parties
    to propose a discovery plan. They did so. On May 25 the
    judge issued a written order memorializing his oral rulings
    and setting a discovery schedule. County of Dane v. Pub. Serv.
    Comm’n of Wis., No. 2019CV003418 (Wis. Cir. Ct. Dane Cnty.
    May 25, 2021) (decision and order).
    Some procedural skirmishes ensued, and by July the liti-
    gation over Huebsch’s alleged conflict of interest had moved
    to the court of appeals. More procedural maneuvering
    followed, and by the end of the summer, the case landed at
    the Wisconsin Supreme Court’s doorstep. On September 21
    the state high court granted Huebsch’s petition for expedited
    review and set a briefing schedule. County of Dane v. Pub.
    Serv. Comm’n of Wis., No. 2021AP1321-LV (Wis. Sept. 21,
    2021) (order granting expedited review). The petition raises
    threshold procedural questions and several substantive
    questions about the legal standards for evaluating recusal
    issues under Caperton and state law and the proper applica-
    No. 20-3325                                                                13
    tion of those standards to the allegations involving Huebsch.
    The Dane County proceedings are stayed while the case is
    pending before the state supreme court. 2
    There is more. On June 28 the transmission companies
    returned to the Commission and asked it to reopen the
    permit proceedings on its own motion to rescind and recon-
    sider the permit based on the conflict-of-interest allegations
    regarding Heubsch. On July 1 the Commission issued a
    notice of intent to rescind the permit and invited comments
    by July 19. Notice of Intent and Request for Comments,
    Cardinal-Hickory Creek Project, Pub. Serv. Comm’n of Wis.,
    No. 5-CE-146, Ref# 415003 (July 1, 2021), https://apps.psc.
    wi.gov/ERF/ERFview/viewdoc.aspx?docid=415003. A hear-
    ing was held on July 29; the minutes reflect that the Com-
    mission discussed the matter but took no action. 
    Id.,
     Minutes
    and Informal Instructions of the Open Meeting of Thursday,
    July 29, 2021, Ref# 418174 (Aug. 5, 2021), https://apps.psc.wi.
    gov/ERF/ERFview/viewdoc.aspx?docid=418174.
    As best we can tell, that’s where things stand in the state
    courts and before the Commission. These important devel-
    opments inform the abstention inquiry, to which we’ll turn
    in a moment. But sovereign immunity is our first issue. It is a
    2 Yesterday Driftless notified us of additional events in the state case. On
    October 8 Driftless filed an emergency motion for injunctive relief
    blocking construction activity—the same relief it wanted to pursue in the
    district court if its motion to lift the stay in this case were successful. On
    October 12 the Dane County judge stayed the proceedings pending a
    decision by the Wisconsin Supreme Court, but on October 18 he nonethe-
    less held a telephonic hearing on the emergency motion and orally
    granted it. The docket reflects that he is currently considering a motion
    to stay his order pending appeal.
    14                                                    No. 20-3325
    jurisdictional defense. See, e.g., Gorka v. Sullivan, 
    82 F.3d 772
    ,
    774 (7th Cir. 1996) (describing sovereign immunity as a
    “jurisdictional bar”); Crosetto v. State Bar of Wis., 
    12 F.3d 1396
    ,
    1400 (7th Cir. 1993) (labeling “state sovereign immunity” as
    “one of the Constitution[’s] unavoidable jurisdictional
    hurdles”).
    A. Sovereign Immunity
    “Sovereign immunity is the privilege of the sovereign not
    to be sued without its consent” and is secured to the states
    by the Eleventh Amendment. Va. Off. for Prot. & Advoc. v.
    Stewart, 
    563 U.S. 247
    , 253 (2011). As the Supreme Court has
    explained, the Eleventh Amendment “confirm[s] the struc-
    tural understanding that States entered the Union with their
    sovereign immunity intact, unlimited by Article III’s juris-
    dictional grant.” 
    Id.
    The text of the Amendment provides: “The Judicial pow-
    er of the United States shall not be construed to extend to
    any suit in law or equity, commenced or prosecuted against
    one of the United States by Citizens of another State.”
    U.S. CONST. amend. XI. Although this language does not “by
    its terms … bar suits against a State by its own citizens,” the
    Supreme Court “has consistently held that an unconsenting
    State is immune from suits brought in federal courts by her
    own citizens as well as by citizens of another State.” Edelman
    v. Jordan, 
    415 U.S. 651
    , 662–63 (1974). “[I]f properly raised,
    the [A]mendment bars actions in federal court against a
    state, state agencies, or state officials acting in their official
    capacities.” Council 31 Am. Fed’n of State, Cnty. & Mun. Emps.
    v. Quinn, 
    680 F.3d 875
    , 881 (7th Cir. 2012) (quotation marks
    omitted).
    No. 20-3325                                                    15
    But “sovereign immunity is not absolute immunity.” 
    Id. at 882
    . The doctrine of Ex parte Young, 
    209 U.S. 123
     (1908),
    creates an exception to state sovereign immunity “by assert-
    ing that a suit challenging the constitutionality of a state
    official’s action in enforcing state law is not one against the
    State.” Green v. Mansour, 
    474 U.S. 64
    , 68 (1985). The doctrine
    is “accepted as necessary to permit the federal courts to
    vindicate federal rights.” Stewart, 
    563 U.S. at
    254–55 (quota-
    tion marks omitted). “It rests on the premise—less delicately
    called a ‘fiction’—that when a federal court commands a
    state official to do nothing more than refrain from violating
    federal law, he is not the State for sovereign-immunity
    purposes.” 
    Id. at 255
     (cleaned up).
    But Ex parte Young is “limited to that precise situation.”
    
    Id.
     It applies only when a plaintiff seeks prospective relief
    against an ongoing violation of federal law. Idaho v. Coeur
    d’Alene Tribe of Idaho, 
    521 U.S. 261
    , 281 (1997). Accordingly,
    our task is to “conduct a straightforward inquiry into
    whether [the plaintiffs’] complaint alleges an ongoing viola-
    tion of federal law and seeks relief properly characterized as
    prospective.” Verizon Md., Inc. v. Pub. Serv. Comm’n of Md.,
    
    535 U.S. 635
    , 645 (2002) (quotation marks omitted).
    1. Prospective Relief
    Analyzing the form of relief is the simpler part of the in-
    quiry. Injunctive relief is prospective relief. See Coeur d’Alene,
    
    521 U.S. at 277
     (“[W]e have consistently allowed suits seek-
    ing prospective injunctive relief based on federal violations
    to proceed.”); Hutto v. Finney, 
    437 U.S. 678
    , 690 (1978)
    (“[S]tate officers are not immune from prospective injunctive
    relief.”); Edelman, 
    415 U.S. at 664
     (“[T]he relief awarded in Ex
    parte Young was prospective only; the Attorney General of
    16                                                 No. 20-3325
    Minnesota was enjoined to conform his future conduct of
    that office to the requirement of the Fourteenth Amend-
    ment.”). It’s usually easy to separate suits for prospective
    relief from those that seek retroactive remedies; the latter
    primarily take the form of monetary damages to remedy
    past harms. See McDonough Assocs. v. Grunloh, 
    722 F.3d 1043
    ,
    1050–51 (7th Cir. 2013) (explaining that courts cannot “direct
    a state to make payments … to remedy a past injury to a
    private party”); MSA Realty Corp. v. Illinois, 
    990 F.2d 288
    , 291
    (7th Cir. 1993) (“The [E]leventh [A]mendment bar extends to
    suits for money damages against state officials sued in their
    official capacities … .”).
    Here, Driftless seeks (1) a declaration that Valcq and
    Huebsch had a due-process duty to recuse themselves from
    the permit proceeding; (2) a declaration that the permit is
    void as a matter of law; (3) an order vacating the permit; and
    (4) an injunction barring the enforcement of the permit.
    Declaratory and injunctive relief are paradigmatic examples
    of prospective relief. See Alden v. Maine, 
    527 U.S. 706
    , 747
    (1999) (recognizing that Ex parte Young allows “certain suits
    for declaratory or injunctive relief against state officers” to
    proceed in federal court). But vacatur of the permit is retro-
    spective. Although an injunction and vacatur have similar
    real-world effects in that each will prevent construction of
    the power line, the two forms of relief have different legal
    consequences.
    A federal injunction does not erase an unconstitutional
    state law from existence; federal courts cannot repeal state
    laws. See Borden v. United States, 
    141 S. Ct. 1817
    , 1835 (2021)
    (Thomas, J., concurring) (“Courts have no authority to ‘strike
    down’ statutory text.” (cleaned up)); Skilling v. United States,
    No. 20-3325                                                  17
    
    561 U.S. 358
    , 424 (2010) (Scalia, J., concurring in part) (“I
    continue to doubt whether ‘striking down’ a statute is ever
    an appropriate exercise of our Article III power.”). Rather, a
    federal injunction prevents state officials from enforcing the
    challenged statute, regulation, or agency action in the future
    based on its incompatibility with federal law. An injunction
    operates on the enjoined officials; the law, regulation, or
    agency action remains on the books, and if the injunction is
    lifted by the issuing court, overturned by a higher court, or
    superseded by federal law, it resumes effect. See generally
    Jonathan F. Mitchell, The Writ-of-Erasure Fallacy, 104 VA. L.
    REV. 933 (2018).
    Vacatur, in contrast, retroactively undoes or expunges a
    past state action. Vacatur is “[t]he act of annulling or setting
    aside.” BLACK’S LAW DICTIONARY (11th ed. 2019). Unlike an
    injunction, which merely blocks enforcement, vacatur un-
    winds the challenged agency action. Ex parte Young does not
    encompass retroactive remedies like vacatur—and for good
    reason: the federal judiciary is not an oversight board over
    state agencies and has no power to vacate the actions of state
    agencies. That power belongs to the state courts, WIS. STAT.
    § 227.57(5), or the agency itself.
    Still, the complaint’s request for injunctive relief brings
    this case within Ex parte Young—provided, however, that
    Driftless has plausibly alleged an ongoing violation of
    federal law.
    2. Ongoing Violation
    The more challenging aspect of Ex parte Young analysis is
    the proviso that the suit must seek relief against an “ongo-
    ing” violation of federal law. An ongoing violation of federal
    18                                                  No. 20-3325
    law is one that is “continuing.” Green, 474 U.S. at 68. Because
    Ex parte Young is limited to federal-court orders “granting
    prospective injunctive relief to prevent a continuing viola-
    tion of federal law,” the doctrine does not apply when
    “federal law has been violated [only] at one time or over a
    period of time in the past.” Papasan v. Allain, 
    478 U.S. 265
    ,
    277–78 (1986). This part of the inquiry may seem simple at
    first, but “the difference between the type of relief barred by
    the Eleventh Amendment and that permitted under Ex parte
    Young will not in many instances be that between day and
    night.” Edelman, 
    415 U.S. at 667
    .
    This case lies in that twilight zone. It presents a difficult
    question of first impression: Is there an ongoing violation of
    federal law when the alleged violation is a procedural error
    committed by a state actor at a discrete point in time? The
    commissioners argue that the due-process violation (if there
    was one) was complete when the permit was approved and
    thus cannot be considered “ongoing” for purposes of Ex
    parte Young. Driftless insists that the violation is ongoing so
    long as the permit remains in force and effect and the
    Commission continues to exercise jurisdiction over the
    transmission companies in the present by virtue of its power
    to enforce, amend, or rescind the permit.
    Three cases are instructive here, although none is precise-
    ly on point. The first is Verizon v. Public Service Commission of
    Maryland. There, the telecommunications carrier Verizon
    negotiated an interconnection agreement with its competitor
    WorldCom as required by federal law. The state agency with
    jurisdiction over the matter approved the agreement, but a
    few months later, WorldCom filed a complaint with the
    agency accusing Verizon of violating the agreement. The
    No. 20-3325                                                     19
    agency ruled in favor of WorldCom on grounds pertaining
    to state contract law. Verizon then filed a federal lawsuit
    against the agency’s commissioners in their official capaci-
    ties alleging that the agency’s order was preempted by the
    Telecommunications Act of 1996 and a recent FCC ruling.
    Verizon, 
    535 U.S. at
    639–40. The Supreme Court held that the
    Eleventh Amendment did not bar Verizon’s suit. 
    Id. at 635
    .
    Verizon’s prayer for injunctive relief asked the federal court
    to enjoin the state officials “from enforcing the order in
    contravention of controlling federal law.” 
    Id. at 645
    . That
    was sufficient to bring the case within Ex parte Young. 
    Id.
    The second relevant precedent is MCI Telecommunications
    Corp. v. Illinois Bell Telephone Co., 
    222 F.3d 323
     (7th Cir. 2000),
    another telecommunications case, though one from this
    court. There, the Illinois and Wisconsin utility commissions
    arbitrated several interconnection agreements between
    telecommunications companies. One of them sued the
    commissioners in their official capacities claiming that the
    approved agreements violated the Telecommunications Act.
    The commissioners raised sovereign immunity, arguing that
    “if any violations occurred, they occurred in the past,” so Ex
    parte Young did not apply. 
    Id. at 345
    . We disagreed, observ-
    ing that the “challenged determinations are still in place, and
    the [plaintiffs] seek to have the commissioners conform their
    future actions, including their continuing enforcement of the
    challenged determinations, with federal law.” 
    Id.
    The final case is Town of Barnstable v. O’Connor, 
    786 F.3d 130
     (1st Cir. 2015), which involved a challenge to a state
    agency’s energy policy. A Massachusetts utility commission
    approved a merger between two electricity companies. The
    Town of Barnstable, joined by an environmental group and
    20                                                 No. 20-3325
    several other plaintiffs, filed a federal suit alleging that the
    merger was incompatible with the Federal Power Act and
    also violated the dormant Commerce Clause. Citing Verizon,
    the First Circuit rejected the commissioners’ claim of sover-
    eign immunity. The court held in relevant part that “the
    continued enforceability of the [merger agreement] repre-
    sents an ongoing violation of federal law because [it] binds
    the parties to abide by the [agreement’s] allegedly unconsti-
    tutional terms.” Id. at 139.
    At first glance these cases seem closely analogous to this
    one. But there is a distinction. Each of these cases raised a
    substantive violation of federal law: the challenged state-
    agency determinations authorized the regulated parties to
    conduct their ongoing activities in violation of an FCC order,
    the Telecommunication Act, and the Federal Power Act and
    Commerce Clause, respectively. In contrast, this case raises a
    discrete procedural violation: the alleged due-process error
    occurred when commissioners with disqualifying conflicts of
    interest approved the power-line permit. In other words,
    Driftless does not assert that the permit substantively violates
    federal law (at least not in this suit); it challenges only the
    process by which the permit was issued.
    In the end, we’re not convinced that the difference be-
    tween substance and procedure is decisive. As the First
    Circuit observed in Town of Barnstable, the “continued en-
    forceability” of an unlawful state-agency decision can
    amount to an ongoing violation of federal law. Nothing in
    Ex parte Young or its successors suggests that the distinction
    between substantive and procedural violations makes a
    difference, so we hesitate to draw that line here. The relevant
    inquiry is whether the suit seeks prospective relief against an
    No. 20-3325                                                   21
    ongoing violation of federal law. A permit issued in viola-
    tion of due process remains unlawful as long as it is in force
    and effect.
    The commissioners point to Sonnleitner v. York, 
    304 F.3d 704
     (7th Cir. 2002), which has surface similarity to this case—
    it too involved a due-process claim—but on close review is
    distinguishable. Sonnleitner involved a suit by a state em-
    ployee who was demoted without a predisciplinary hearing.
    He later prevailed at a postdeprivation hearing but was not
    reinstated, in part due to his own procedural missteps. He
    then sued his supervisors in federal court seeking an injunc-
    tion reinstating him to his position. He alleged that the
    denial of a predisciplinary hearing violated his right to due
    process. We held that the claim was barred by sovereign
    immunity. 
    Id. at 718
    . Because the plaintiff was “eventually
    given an opportunity to tell his side of the story” at the
    postdeprivation hearing, we concluded that his due-process
    claim concerned “at most, a past rather than an ongoing
    violation of federal law.” 
    Id.
    Our holding in Sonnleitner turned on the fact that the
    plaintiff had received a postdeprivation hearing that com-
    plied with due-process requirements. After the postdepriva-
    tion hearing, the alleged error in the predeprivation process
    could not be characterized as “ongoing.” The due-process
    violation at issue here is different. Driftless contends that the
    Commission’s approval of the permit was tainted by adjudi-
    cator bias in violation of the Due Process Clause.
    Finally, the commissioners argue that if this case is al-
    lowed to proceed under Ex parte Young, then all manner of
    final state-agency rulings will suddenly become reviewable
    in federal court based on allegations of adjudicator bias. This
    22                                                 No. 20-3325
    would complicate state judicial review of agency rulings and
    erode state sovereign immunity. It could also open the
    floodgates to federal suits by parties complaining about
    biased state administrative adjudicators.
    We are sensitive to these concerns. Federal courts are not
    oversight boards designed to police the final actions of state
    agencies. Cf. River Park, Inc. v. City of Highland Park, 
    23 F.3d 164
    , 165 (7th Cir. 1994) (“Federal courts are not boards of
    zoning appeals.”). Challenges to state administrative actions
    usually belong in state courts, which are interested in and
    fully capable of ensuring that state agencies comply with
    federal due-process requirements. See Coeur d’Alene, 
    521 U.S. at 276
     (“Where, as here, the parties invoke federal principles
    to challenge state administrative action, the courts of the
    State have a strong interest in integrating those sources of
    law within their own system for the proper judicial control
    of state officials.”).
    At bottom, these concerns rest on federalism principles.
    State sovereign immunity is, of course, rooted in the anchor-
    ing structure of our system of federalism. So too, however, is
    abstention doctrine. The commissioners’ arguments about
    federalism and comity are valid, but we think they are better
    addressed by abstention doctrine. For the foregoing reasons,
    we conclude that the due-process claim against them satis-
    fies the requirements of Ex parte Young and now move to the
    abstention question.
    B. Abstention
    The commissioners also asked the district judge to ab-
    stain and stay this case to await the outcome of the state
    litigation, citing both Younger and Colorado River abstention.
    No. 20-3325                                                  23
    The judge denied the request. We see no flaw in the judge’s
    analysis of Younger, but his Colorado River ruling rests on a
    misunderstanding of the claims in the state litigation, which
    in turn led him to mistakenly conclude that the federal and
    state cases are not parallel within the meaning of the doc-
    trine.
    1. Raising Abstention Sua Sponte
    The abstention issue is not formally before us, but the
    Supreme Court has held that a reviewing court may raise
    abstention sua sponte in an appropriate case. See Bellotti v.
    Baird, 
    428 U.S. 132
    , 143 n.10 (1976) (“[T]he fact that the full
    arguments in favor of abstention may not have been asserted
    in the District Court does not bar this Court’s consideration
    of the issue.”). We have done so at least twice before, though
    the cases are a bit dated.
    We raised abstention sua sponte in Waldron v. McAtee,
    
    723 F.2d 1348
     (7th Cir. 1983), citing Bellotti and noting that a
    reviewing court has “the power and in an appropriate case
    the duty to order abstention, if necessary for the first time at
    the appellate level, even though no party is asking for it.” 
    Id. at 1351
    . We explained that abstention doctrines do not exist
    “to protect the rights of one of the parties” but instead to
    “promote a harmonious federal system.” 
    Id.
     We later charac-
    terized Waldron as recognizing a clear rule that “appellate
    courts are free to raise and resolve the abstention issue sua
    sponte.” Gen. Ry. Signal Co. v. Corcoran, 
    921 F.2d 700
    , 708 (7th
    Cir. 1991) (citing Waldron, 
    723 F.2d at 1351
    ).
    We also raised abstention sua sponte in In re Complaint of
    McCarthy Brothers Co., 
    83 F.3d 821
     (7th Cir. 1996), a compli-
    cated admiralty action involving an ironworker who was
    24                                                  No. 20-3325
    injured while working on a barge on the Mississippi River.
    Admiralty law has its own arcane abstention doctrine
    known as Langnes abstention, which advises federal courts to
    “permit[] proceedings in state court to go forward on the
    question of liability and retain[] jurisdiction over any ques-
    tion that might arise as to the shipowner’s right to limit his
    liability.” 
    Id. at 828
     (describing Langnes v. Green, 
    282 U.S. 531
    (1931)). Though no one argued the point, we decided “to
    raise the issue of abstention sua sponte,” explaining that
    reversal for application of Langnes abstention was necessary
    to correct the district court’s error and facilitate the “opera-
    tion of the complicated admiralty jurisdictional rules.” Id. at
    826.
    This too is an appropriate case in which to raise absten-
    tion sua sponte. The error in the judge’s Colorado River ruling
    is plain, and our concerns about federal interference in
    ongoing state litigation justify taking this step. In so doing
    we follow the lead of our colleagues in the First Circuit. See
    Jiménez v. Rodríguez-Pagán, 
    597 F.3d 18
    , 27 n.4 (1st Cir. 2010)
    (“As with other forms of abstention, our decision to decline
    jurisdiction under Colorado River may be sua sponte.”).
    2. Colorado River Abstention
    We begin with first principles. Although abstention “is
    the exception, not the rule,” Colorado River, 
    424 U.S. at 813
    , “a
    federal court may, and often must, decline to exercise its
    jurisdiction where doing so would intrude upon the inde-
    pendence of the state courts and their ability to resolve the
    cases before them,” SKS & Assocs., Inc. v. Dart, 
    619 F.3d 674
    ,
    677 (7th Cir. 2010). The main categories of abstention are
    known by the names of the Supreme Court cases that creat-
    No. 20-3325                                                              25
    ed them: Pullman, Burford, Younger, and Colorado River. 3
    These categories are not rigid, however. The animating force
    of the Court’s abstention cases is that “they all implicate (in
    one way or another and to different degrees) underlying
    principles of equity, comity, and federalism foundational to
    our federal constitutional structure.” J.B. v. Woodard, 
    997 F.3d 714
    , 722 (7th Cir. 2021).
    Under the doctrine announced in Colorado River, a federal
    court may abstain and stay or dismiss a suit in deference to
    parallel state proceedings in exceptional circumstances
    where abstention would promote “wise judicial administra-
    tion.” 
    424 U.S. at 818
    . Several prudential principles are
    embedded in this highly generalized statement of the doc-
    trine. Among them are the interest in conserving judicial
    resources, the desirability of avoiding duplicative litigation
    and the risk of conflicting rulings, and the benefits of pro-
    moting a comprehensive disposition of the parties’ dispute
    in a single judicial forum. 
    Id.
    We have found it useful to approach Colorado River ab-
    stention in two steps. DePuy Synthes Sales, Inc. v. OrthoLA,
    Inc., 
    953 F.3d 469
    , 477 (7th Cir. 2020). “The first question is
    whether the concurrent state and federal actions are actually
    parallel. If so, the second question is whether the necessary
    exceptional circumstances exist to support” abstention. 
    Id.
    (cleaned up).
    “Two suits are considered parallel when substantially the
    same parties are contemporaneously litigating substantially
    3R.R. Comm’n of Tex. v. Pullman Co., 
    312 U.S. 496
     (1941); Burford v. Sun Oil
    Co., 
    319 U.S. 315
     (1943); Younger v. Harris, 
    401 U.S. 37
     (1971); Colo. River
    Water Conservation Dist. v. United States, 
    424 U.S. 800
     (1976).
    26                                                    No. 20-3325
    the same issues in another forum. Formal symmetry is
    unnecessary, as long as there is a substantial likelihood that
    the state litigation will dispose of all claims presented in the
    federal case.” 
    Id.
     at 477–78 (cleaned up). On this understand-
    ing, there is no doubt that the state and federal suits here are
    parallel.
    True, the suits are not completely identical: the state litiga-
    tion raises state-law issues in addition to the duplicative
    due-process claim. But perfect symmetry isn’t necessary. The
    cases are parallel in all the ways that matter under Colorado
    River. The due-process recusal claims “involve the same
    parties, the same facts, and the same issues.” Id. at 478.
    Indeed, the claims are materially identical: they will “be
    resolved by examining largely the same evidence,” Huon v.
    Johnson & Bell, Ltd., 
    657 F.3d 641
    , 647 (7th Cir. 2011), and are
    governed by the legal standard announced in Caperton. So
    it’s not just “substantially likely” that the state litigation will
    dispose of the federal case—it is nearly certain that it will do
    so.
    The second step in the framework is to determine wheth-
    er exceptional circumstances justify abstention. A plethora of
    nonexclusive, unweighted factors can inform this question,
    including:
    1.   Whether the case concerns rights in prop-
    erty, and if so, whether the state has as-
    sumed jurisdiction over that property;
    2.   The inconvenience of the federal forum;
    3.   The desirability of consolidating litigation
    in one place (put otherwise, the value in
    avoiding “piecemeal” or broken-up pro-
    ceedings);
    No. 20-3325                                                 27
    4.    The order in which jurisdiction was ob-
    tained in the concurrent fora;
    5.    The source of governing law—federal or
    state;
    6.    The adequacy of the state-court action to
    protect the federal plaintiff’s rights;
    7.    The relative progress of the state and fed-
    eral proceedings;
    8.    The presence or absence of concurrent ju-
    risdiction;
    9.   The availability of removal; and
    10.   Whether the federal action is vexatious or
    contrived.
    DePuy, 953 F.3d at 477. We have cautioned that this overa-
    bundant list of factors “is designed to be helpful, not a
    straitjacket. Different considerations may be more pertinent
    to some cases, and one or more of these factors will be
    irrelevant in other cases.” Loughran v. Wells Fargo Bank, N.A.,
    
    2 F.4th 640
    , 647 (7th Cir. 2021). Nor does the list “preclude
    the district court from taking into account a special charac-
    teristic of the case before it.” DePuy, 953 F.3d at 477.
    More generally, the decision to abstain “does not rest on
    a mechanical checklist, but on a careful balancing of the
    important factors.” Moses H. Cone Mem’l Hosp. v. Mercury
    Constr. Corp., 
    460 U.S. 1
    , 16 (1983). In short, abstention law
    doesn’t demand an exact fit with the precise parameters of a
    doctrinal category. J.B., 997 F.3d at 723–24. Instead, the
    abstention inquiry is flexible and requires a practical judg-
    ment informed by principles of comity, federalism, and
    sound judicial administration.
    28                                                  No. 20-3325
    With these principles in mind, we find it neither neces-
    sary nor helpful to march through our 10-factor “test” and
    decide which factors support abstention and which do not.
    DePuy, 953 F.3d at 479 (explaining that the factors in a multi-
    factor, unweighted test often point in different directions);
    see also United States v. Mayfield, 
    771 F.3d 417
    , 435 (7th Cir.
    2014) (en banc) (“Multifactor tests are common in our law
    but they can be cryptic when unattached to a substantive
    legal standard, as this one is. Knowing what factors to look
    at is useless unless one knows what to look for.”).
    Several compelling considerations justify abstention in
    this case, and all can be loosely keyed to the factors on the
    list. The first is the desirability of avoiding piecemeal litiga-
    tion over the legality of the power-line permit. Multi-
    jurisdictional legal challenges involving the same subject
    matter are costly, disruptive, and run the risk of a collision of
    conflicting rulings. A related consideration is the wholly
    duplicative nature of this suit. The takings claim was
    doomed from the start and can fairly be characterized as
    contrived, and there is no good reason to litigate identical
    due-process recusal claims in state and federal court. See
    Interstate Material Corp. v. City of Chicago, 
    847 F.2d 1285
    , 1289
    (7th Cir. 1988) (holding that a federal lawsuit “could be
    considered” contrived when the plaintiff files parallel suits
    “seeking substantially the same relief from substantially the
    same parties”).
    Needless to say, the state courts routinely apply federal
    constitutional standards, as they must under the Supremacy
    Clause. More to the point here, Wisconsin courts are fully
    capable of applying Caperton and have begun to do so. See In
    re Paternity of B.J.M., 
    944 N.W.2d 542
    , 549 (Wis. 2020). And
    No. 20-3325                                                   29
    they have long applied federal due-process standards to
    recusal questions involving administrative adjudicators. See
    Guthrie v. Wis. Emp. Rels. Comm’n, 
    331 N.W.2d 331
    , 336 (Wis.
    1983). So there is nothing about this particular legal context
    that cautions against abstention. To the contrary, it appears
    that Driftless simply wants two bites at the apple. And that
    weighs heavily in favor of abstention.
    What’s more, the state case has advanced toward a reso-
    lution of the due-process claim. As we’ve explained, the
    Dane County judge already ruled against Driftless on its
    allegations against Valcq. The allegations involving Huebsch
    remain, but the case is now before the Wisconsin Supreme
    Court on that issue. The petition for review raises substan-
    tive questions about the application of Caperton—both in
    general and in light of the specific allegations involving
    Huebsch. Under these circumstances, the use of federal
    judicial resources to decide the same questions cannot be
    justified. “The principal purpose of a stay under Colorado
    River is judicial economy … .” Schneider Nat’l Carriers, Inc. v.
    Carr, 
    903 F.2d 1154
    , 1157 (7th Cir. 1990). There is “no reason
    for identical suits to be proceeding in different courts.”
    U.S.O. Corp. v. Mizuho Holding Co., 
    547 F.3d 749
    , 750 (7th Cir.
    2008). Judicial economy strongly favors abstention.
    That brings us to a final consideration, and it is far from
    the least important one. Although Colorado River abstention
    is primarily concerned with judicial economy, it also imple-
    ments the fundamental federalism principles that animate all
    abstention categories. See, e.g., Adkins v. VIM Recycling, Inc.,
    
    644 F.3d 483
    , 486 (7th Cir. 2011) (describing Colorado River as
    a “federalism doctrine”); Black Sea Inv., Ltd. v. United Heritage
    Corp., 
    204 F.3d 647
    , 650 (5th Cir. 2000) (“The Colorado River
    30                                                 No. 20-3325
    abstention doctrine is based on principles of federalism,
    comity, and conservation of judicial resources.”).
    Federalism concerns loom large here. This case impli-
    cates Wisconsin’s sovereign interest in the proper function-
    ing of its administrative law and procedure and the role of
    the state courts in reviewing the decisions of administrative
    agencies. Wisconsin has created an elaborate permitting
    regime for important public-utility projects like this one, and
    aggrieved persons are entitled to judicial review in the state
    courts. See generally WIS. STAT. § 227.53. Only the state courts
    can review the agency’s work for compliance with the
    procedural and substantive requirements of state law. And
    the state courts alone have the authority to vacate the permit
    and order the Commission to conduct a new hearing—
    whether as a remedy for a violation of state law or as a
    remedy for a violation of the federal constitutional guarantee
    of due process.
    Conversely, there is no significant federal interest at
    stake here that necessitates or even encourages federal-court
    review of the procedural regularity of the permit proceeding
    before the agency. A foundational premise of our federalism
    is “the assumption that state courts are co-equal to the
    federal courts and are fully capable of respecting and pro-
    tecting” federal constitutional rights. Courthouse News Serv.
    v. Brown, 
    908 F.3d 1063
    , 1074 (7th Cir. 2018). “Principles of
    comity entitle the states to make their own decisions, on
    federal issues as well as state issues, unless there is some
    urgent need for federal intervention.” Nicole K. ex rel. Linda
    R. v. Stigdon, 
    990 F.3d 534
    , 537–38 (7th Cir. 2021). The federal
    courts have no institutional superiority in ruling on Caperton
    No. 20-3325                                                                 31
    claims. 4 Accordingly, “[e]xercising federal jurisdiction over
    [this] claim[] would reflect a lack of respect for the state’s
    ability to resolve the[] issues properly before its courts.” J.B.,
    997 F.3d at 722 (quotation marks omitted).
    Finally, the recent developments before the agency are
    worth mentioning. As we’ve noted, the Commission recently
    reopened its proceedings to determine whether to rescind
    and reconsider the permit based on the conflict-of-interest
    allegations involving Huebsch. Of course, we cannot predict
    what it will do. But if the Wisconsin Supreme Court rules in
    favor of Driftless and allows the due-process claim to move
    forward in Dane County Circuit Court, remedial steps by the
    Commission would not be surprising.
    In short, abstention under Colorado River is amply justi-
    fied. The judge was wrong to conclude otherwise.
    III. Conclusion
    For the foregoing reasons, the judge correctly denied the
    commissioners’ motion to dismiss based on sovereign
    immunity. But he incorrectly denied the motion for Colorado
    4 By our count, we have addressed Caperton claims in just five reported
    cases: Gacho v. Wills, 
    986 F.3d 1067
    , 1071–76 (7th Cir. 2021); United States v.
    Williams, 
    949 F.3d 1056
    , 1061–63 (7th Cir. 2020); Wozniak v. Adesida,
    
    932 F.3d 1008
    , 1011 (7th Cir. 2019); Alston v. Smith, 
    840 F.3d 363
    , 368–69
    (7th Cir. 2016); and Suh v. Pierce, 
    630 F.3d 685
    , 691–92 (7th Cir. 2011).
    Another four make passing reference to Caperton: Trustmark Ins. Co. v.
    John Hancock Life Ins. Co., 
    631 F.3d 869
    , 872 (7th Cir. 2011); Bauer v.
    Shepard, 
    620 F.3d 704
    , 712 (7th Cir. 2010); Siefert v. Alexander, 
    608 F.3d 974
    ,
    980 (7th Cir. 2010); and Chen v. Holder, 
    607 F.3d 511
    , 513 (7th Cir. 2010).
    Not that case counts matter. The Wisconsin Supreme Court is equally
    capable of applying Caperton, even if it has done so less frequently than
    this court.
    32                                                No. 20-3325
    River abstention. We therefore REVERSE and REMAND with
    instructions to stay this case pending dispositive develop-
    ments in the state litigation. The motion to partially lift the
    stay pending appeal is denied as moot.
    

Document Info

Docket Number: 20-3325

Judges: Sykes

Filed Date: 10/21/2021

Precedential Status: Precedential

Modified Date: 10/21/2021

Authorities (31)

SKS & Associates, Inc. v. Dart , 619 F.3d 674 ( 2010 )

general-railway-signal-company-v-james-p-corcoran-superintendent-of , 921 F.2d 700 ( 1991 )

shelley-gorka-a-minor-by-next-friend-her-mother-sauncey-gorka-v-cheryl , 82 F.3d 772 ( 1996 )

marcella-richman-individually-and-as-special-administrator-of-the-estate , 270 F.3d 430 ( 2001 )

mci-telecommunications-corporation-a-delaware-corporation-and-mci-metro , 222 F.3d 323 ( 2000 )

Papasan v. Allain , 106 S. Ct. 2932 ( 1986 )

Interstate Material Corporation, an Illinois Corporation, ... , 847 F.2d 1285 ( 1988 )

Xiu Qin Chen v. Holder , 607 F.3d 511 ( 2010 )

River Park, Inc., and Country Club Estates, Ltd. v. City of ... , 23 F.3d 164 ( 1994 )

Schneider National Carriers, Inc. v. David M. Carr , 903 F.2d 1154 ( 1990 )

in-the-matter-of-the-complaint-of-mccarthy-brothers-companyclark-bridge , 83 F.3d 821 ( 1996 )

msa-realty-corporation-v-state-of-illinois-jim-edgar-as-governor-of-the , 990 F.2d 288 ( 1993 )

Younger v. Harris , 91 S. Ct. 746 ( 1971 )

Caperton v. A. T. Massey Coal Co., Inc. , 129 S. Ct. 2252 ( 2009 )

Adkins v. VIM Recycling, Inc. , 644 F.3d 483 ( 2011 )

Langnes v. Green , 51 S. Ct. 243 ( 1931 )

U.S.O. Corp. v. Mizuho Holding Co. , 547 F.3d 749 ( 2008 )

Huon v. Johnson & Bell, Ltd. , 657 F.3d 641 ( 2011 )

Bauer v. Shepard , 620 F.3d 704 ( 2010 )

Bellotti v. Baird , 96 S. Ct. 2857 ( 1976 )

View All Authorities »