Winforge, Inc. v. Coachmen Industries, Inc. , 691 F.3d 856 ( 2012 )


Menu:
  •                                 In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 10-3178
    W INFORGE, INC., et al.,
    Plaintiffs-Appellants,
    v.
    C OACHMEN INDUSTRIES, INC., et al.,
    Defendants-Appellees.
    Appeal from the United States District Court
    for the Southern District of Indiana, Indianapolis Division.
    No. 1:06-CV-619—Sarah Evans Barker, Judge.
    A RGUED O CTOBER 25, 2011—D ECIDED JULY 30, 2012
    Before E ASTERBROOK, Chief Judge, H AMILTON, Circuit
    Judge, and M YERSCOUGH District Judge.Œ
    M YERSCOUGH, District Judge. Winforge, Inc. (“Winforge”),
    and its president, Byron McMahon (“McMahon”),
    brought this diversity suit against Mod-U-Kraf Homes,
    LLC (“Mod-U-Kraf”), All-American Homes, LLC (“All-
    Œ
    Of the Central District of Illinois, sitting by designation.
    2                                               No. 10-3178
    American”), and Coachmen Industries, Inc. (“Coachmen”),
    alleging that the defendants breached the terms of a
    hotel development agreement between the parties.
    Winforge and McMahon claimed that the defendants’
    alleged breach resulted in delay and costs that caused
    the plaintiffs to default on the separate construction loan
    agreement between the parties. The defendants filed a
    cross-complaint alleging that Winforge and McMahon,
    and not the defendants, breached the development agree-
    ment.
    After a bench trial, the district court ruled in favor of
    the defendants and found that the parties had never
    entered into a final, enforceable contract. Additionally,
    the district court found that, if a final contract had
    been formed, the defendants had not breached the con-
    tract. The district court entered final judgment in
    favor of the defendants, entitling them to the funds still
    due and owing on the construction loan as well as
    any and all associated costs and fees. Winforge and
    McMahon appealed. For the following reasons, we affirm.
    BACKGROUND
    The district court provided detailed findings of fact in
    its written decision. See Winforge, Inc., et al. v. Coachmen
    Industries, Inc., et al., No. 1:06-CV-619, 
    2010 WL 3326856
    (S.D. Ind. Aug. 20, 2010). Neither party contends that
    the district court’s recitation of the facts is inaccurate.
    The relevant facts are as follows.
    No. 10-3178                                              3
    1.   The Parties
    Appellant Winforge is a corporation organized under
    the laws of North Carolina, with its principal place of
    business in North Carolina, and has two shareholders.
    Appellant McMahon, a citizen of North Carolina at the
    time the Complaint was filed, holds an 80-percent share
    of Winforge. Donny Thomas, who is not a party in this
    case, owns a 20-percent share of Winforge. McMahon
    and Thomas formed Winforge in 2004 for the purpose
    of developing a large hotel in Pigeon Forge, Tennessee.
    Appellees Mod-U-Kraf and All-American are modular
    manufacturers that build and deliver modular sections
    for use as building components in construction at
    project sites for project developers such as Winforge.
    Mod-U-Kraf is a Virginia corporation with its principal
    place of business in Virginia, and All American is an
    Indiana corporation with its principal place of business
    in Indiana. Appellee Coachmen is an Indiana corpora-
    tion, with its principal place of business in Indiana, and
    acted as the lender in this case.
    2.   Pre-Agreement Developments
    In 2002, Mike Lee, who is not a party in this case, began
    investigating the possibility of developing a large hotel
    constructed with modular units. Lee is an experienced
    developer of hotel projects and the owner of Flagship
    Development, LLC, a hotel development company.
    During his investigation, Lee spoke with Mod-U-Kraf,
    a modular manufacturer that had previously been suc-
    4                                              No. 10-3178
    cessful with modular construction for large building
    projects.
    In fall of 2002, Lee met with Dan Brown, a sales repre-
    sentative of Mod-U-Kraf, and Jeff Powell, Mod-U-Kraf’s
    general manager, at Mod-U-Kraf’s Virginia factory. Lee
    learned about Mod-U-Kraf’s previous experience with
    modular construction and spoke with Brown and Powell
    about a potential modular hotel project. At a second
    visit to Mod-U-Kraf’s Virginia factory, Lee met with
    Steve Kerr, Executive Vice-president of All-American,
    and Joseph Tomczak, Chief Financial Officer of Coachmen.
    Brown made a presentation about the possible ef-
    ficiencies of building a large hotel using modular con-
    struction.
    In November 2002, Lee sent a letter to John Trant,
    a representative of Coachmen, outlining the broad para-
    meters of a potential business relationship. No agree-
    ment was reached, but Coachmen expressed interest in
    entering into such an agreement. Next, Lee sought to
    secure a franchisor for the hotel. Lee contacted Cendant, a
    large hotel franchisor that owns the “Wingate” hotel
    brand.1 Lee explained to Cendant what he had learned
    about the benefits of modular hotel construction. In
    April 2003, Lee sent a letter to Kerr of All American,
    Tomczak of Coachmen, and Powell of Mod-U-Kraf in-
    dicating that Cendant had recommended using Matrix
    Hospitality, LLC, a hotel development company owned
    by McMahon, to develop the contemplated hotel project.
    1
    Cendant is now known as Wyndham Hotel Group.
    No. 10-3178                                            5
    In his April 2003 letter, Lee proposed that the hotel
    would be a Wingate Inn hotel, that Mod-U-Kraf would
    build the modular units, and that Coachmen would
    provide the financing for the project.
    Later, in spring 2003, McMahon and Thomas
    toured Mod-U-Kraf’s factory in Virginia. McMahon was
    impressed with the factory and became convinced
    that modular construction could be better built and more
    cost-effective than traditional construction.
    On June 24, 2003, McMahon and Powell signed a letter
    of intent outlining a preliminary understanding be-
    tween Matrix Hospitality, Mod-U-Kraf, and Coachmen
    with regard to the construction of a modular hotel in
    Pigeon Forge, Tennessee. On August 19, 2003, McMahon
    hired Lee as project manager for the Pigeon Forge pro-
    ject. On September 28, 2003, McMahon, on behalf of
    Winforge, signed a franchise agreement with Wingate
    Inn, which secured the Wingate hotel brand for the
    Pigeon Forge hotel.
    3.   The Parties Sign the Development Agreement and Loan
    Agreement
    On April 13, 2004, Mod-U-Kraf and Winforge executed
    a Development Agreement (“Agreement”) regarding the
    development of a Wingate Inn Hotel in Pigeon Forge,
    Tennessee (the “Project”). According to the Agreement,
    Winforge sought to “utilize modular construction for
    the buildings which will comprise a portion of the Pro-
    ject.” For that purpose, “Winforge [sought] to purchase
    6                                               No. 10-3178
    from [Mod-U-Kraf] the modular sections for the
    buildings to be incorporated into the Project and also to
    engage [Mod-U-Kraf] to provide the setting of the
    modular buildings.” The Agreement also provided that
    Flagship Development, Lee’s company, would be the
    project manager for the Project, contracted by Winforge.
    Winforge and Flagship Development were to “prepare
    the site” and select a general contractor for the Project
    that was to be approved by Coachmen.
    Attached to the Agreement as Exhibit A was the “Pre-
    liminary Scope of Work” provision, which described the
    functions and work to be performed by Mod-U-Kraf,
    Winforge, and the general contractor.2 The Preliminary
    Scope of Work provision is the primary subject of the
    parties’ dispute in this case. The April 13, 2004 Pre-
    liminary Scope of the Work provided, in pertinent part:
    1.0 General
    1.1 The following document shall set out the specifica-
    tions, scope of work, drawings, and pricing as pre-
    pared by Mod-U-Kraf Homes LLC. The document
    further serves to set out the responsibilities of
    each of the following parties: Coachmen Industries,
    Inc. (COA), Lender; Winforge, Inc., Owner/Buyer
    (Winforge), Mod-U-Kraf Homes, LLC (MUK), Modular
    manufacturer.
    1.2 Mod-U-Kraf shall manufacture modular units
    at the Mod-U-Kraf manufacturing facilities in accor-
    2
    The “Preliminary Scope of Work” provision was incorporated
    into the Agreement at Section 1 of the Agreement.
    No. 10-3178                                                 7
    dance with the approved Specifications and Drawings.
    Drawings to meet local, state, 3rd party and franchisor
    requirements. To include only materials and on-site
    services specified as supplied by MUK.
    1.3 MUK shall provide modular units and material
    noted on plans for installation and completion of
    a Wingate Inn. This will include all architectural
    drawings, structural calculations for modular unit
    construction, mechanical, electrical systems for
    modulars, and sprinkler system.
    1.4 WINFORGE will be responsible for overseeing
    the completion of the modular units tie-in and com-
    ponents such as the following to complete the
    Wingate Inn on-site:
    •   Plumbing connections between levels
    •   Plumbing connections to city sewer & water
    •   Electrical connections and equipment as noted on
    plans
    •   Elevator
    •   Roof Façade (Completion of Parapet Wall)
    •   Finish Decor at all common areas, drop ceiling,
    HVAC 3 System, Lights, Finish Floor, Drywall &
    Finish as shown, Entry Doors, FF&E materials, etc.
    •   For additional material and task, reference to
    plans[.]
    3
    “HVAC” is an abbreviation for “heating, ventilation, and air
    conditioning.”
    8                                              No. 10-3178
    Pursuant to Section 4 (“Foundation”) of the Pre-
    liminary Scope of Work, Mod-U-Kraf was responsible for
    “provid[ing] architectural drawings and foundation
    footprint . . . and receiv[ing] all state, local and county
    approvals,” and the general contractor was “responsible
    for the engineering of the foundation.” The Preliminary
    Scope of Work also enumerated other responsi-
    bilities relating to the transport of the modular units
    from Mod-U-Kraf’s factory to the project site as well
    as work to be completed on the project site.
    Throughout 2003 and early 2004, the parties’
    pre-agreement negotiations focused on the provisions
    of the Scope of Work, and the Scope of Work attach-
    ment was revised at least ten times before being attached
    to the April 13, 2004 Agreement as the “Preliminary” Scope
    of Work. After signing the Agreement, the parties con-
    tinued to negotiate the terms of the Scope of Work. In
    July 2004, Mod-U-Kraf sent a proposal for a final version
    of the Scope of Work to Lee. Lee testified that he did not
    review it because it was not “red-lined” to highlight
    the proposed changes and did not indicate changes in
    pricing. In September 2004, Powell sent another draft of
    the Scope of Work to Lee but, for the same reasons, Lee
    did not review the draft.
    The parties dispute the finality of the Preliminary
    Scope of Work. Winforge contends that the April 13, 2004
    version was final and controlled the parties’ responsi-
    bilities, but the defendants contend that the parties never
    reached a final agreement regarding the Scope of Work.
    The district court noted that, during a January 25, 2005
    No. 10-3178                                             9
    conference call between the parties, Lee stated that he
    thought the Preliminary Scope of Work had been modi-
    fied or was open to modification. However, McMahon
    expressed his belief and hope that the parties would
    continue to honor the Preliminary Scope of Work as final.
    Separate from the Agreement, Winforge and Coach-
    men entered a loan agreement on April 14, 2004 (“Loan
    Agreement”), under which Coachmen agreed to provide
    financing for the Project for a term of 150 days.
    4.   Winforge and Mod-U-Kraf Begin Development of the
    Project
    From April 13, 2004 to June 23, 2004, Mod-U-Kraf acted
    as the modular manufacturer under the Agreement. On
    June 23, 2004, Mod-U-Kraf, with Winforge’s agreement,
    passed all of its rights and responsibilities under the
    Agreement to All American.
    Prior to All American’s assumption of those rights
    and responsibilities, Mod-U-Kraf had begun to perform
    its part of the Agreement. On April 22, 2004, Cendant, the
    franchisor, acknowledged that Mod-U-Kraf’s architec-
    tural plans for the modular units were “100% complete.”
    Cendant informed Winforge of this fact. However, other
    aspects of the planning for the Project, separate from the
    modular unit designs, remained incomplete and were
    required for State approval. These aspects included a
    number of Mod-U-Kraf’s obligations, such as the designs
    10                                           No. 10-3178
    for the PTAC 4 (air conditioning) units and the sprinkler
    system, and a number of Winforge’s obligations, such as
    the designs for the elevator, plumbing, HVAC, electrical,
    and mechanical systems.
    Upon learning that the modular plans were 100%
    complete, Winforge began on-site work in Pigeon Forge.
    Winforge hired a site supervisor and retained an on-site
    engineering firm and a foundation-engineering firm.
    At this time, as the district court described in its
    findings, the Project “proceeded in fits and starts.”
    Mod-U-Kraf did not prepare or submit a finished plan
    for State approval because Mod-U-Kraf believed that
    Winforge was required to provide Mod-U-Kraf with
    design information for a number of aspects of the
    Project, including the elevator, plumbing, HVAC, elec-
    trical, and mechanical systems, before Mod-U-Kraf could
    submit its plans for State approval. Further, Winforge
    instructed Mod-U-Kraf not to complete certain tasks
    that were originally Mod-U-Kraf’s responsibility under
    the Preliminary Scope of Work.
    Specifically, in June 2004, Winforge instructed
    Mod-U-Kraf not to proceed with the development and
    design of the sprinkler system, which had been de-
    signated Mod-U-Kraf’s responsibility under the Prelimi-
    nary Scope of Work. By agreement of the parties,
    Winforge assumed responsibility for the design and
    approval of the sprinkler system. Winforge also verbally
    4
    “PTAC” is an abbreviation for “packaged terminal air
    conditioner.”
    No. 10-3178                                               11
    agreed to take over responsibility for providing plans
    for the PTAC units, EPDM roof membrane, parapet wall
    removal, and fire alarm system, all of which were
    initially Mod-U-Kraf’s responsibility under the Prelim-
    inary Scope of Work.5 Mod-U-Kraf, believing that Mod-U-
    Kraf required Winforge’s approval on these portions of
    the Project, never developed designs or entered into
    sub-contracts for these portions of the Project.
    On June 22, 2004, Mod-U-Kraf submitted its plans for
    approval by the State of Tennessee’s third-party adminis-
    trator, T.R. Arnold and Associates (“T.R. Arnold”). T.R.
    Arnold is a review agency approved by the State to con-
    duct design review and approval on behalf of the State.
    After reviewing submitted plans, T.R. Arnold commonly
    issues a “deviation report” that identifies “deviations,” or
    failures to comply with Tennessee State Code. Mod-U-Kraf
    submitted its plans in June 2004, knowing that the
    plans were a work in progress, in order to generate a
    deviation report that would allow Mod-U-Kraf to refine
    the plans while it awaited other designs from Winforge.
    Mod-U-Kraf hoped that being aware of what issues
    needed to be addressed, sooner rather than later, would
    expedite the construction process.
    T.R. Arnold returned a deviation report that listed
    twenty-three deviations. The deviations related to the
    sprinkler design, elevator design, mechanical and
    electrical plan design, fire alarm design, and insulation
    5
    In exchange for Winforge’s assumption of these duties, Mod-
    U-Kraf was to receive reduced payment from Winforge.
    12                                              No. 10-3178
    design. T.R. Arnold representative Ray Helmer testified
    that such deviation reports are commonly issued and
    are to be expected for modular designs.
    5.   All-American Assumes Mod-U-Kraf’s Rights and Responsi-
    bilities Under the Agreement
    On June 23, 2004, all of Mod-U-Kraf’s rights and obliga-
    tions under the Agreement passed to All-American.
    Mod-U-Kraf informed Winforge that the substitution
    had become necessary due to delays in the design pro-
    cess. Winforge agreed to the transfer of responsibility.
    Between June and October 2004, Winforge obtained
    designs of the sprinkler system and elevator, the need for
    which had been identified in the June 2004 deviation
    report issued by T.R. Arnold. After incorporating the
    newly acquired designs, All American submitted revised
    plans to T.R. Arnold in September 2004. This time, T.R.
    Arnold issued a new deviation report that identified
    only two items. The first item was a minor issue that All
    American corrected quickly. The second item was a
    more substantial deviation that called for the com-
    pleted design of the mechanical and electrical plan for
    the Project. Resolution of this item required the assistance
    of professionals yet to be hired by Winforge. Although
    overall approval of the plans still required the develop-
    ment of the mechanical and electrical plan identified in
    the deviation report, in October 2004, T.R. Arnold ap-
    proved the modular portion of the plans, certifying
    them as fully compliant with the Tennessee State Code.
    No. 10-3178                                                   13
    Final approval by the State required the additional step
    of submitting the plans to the State, which receives and
    reviews plans approved by the third party administrator.
    If the State approves the plans, the State issues a Letter
    of Filing, which constitutes final State approval of the
    plans. On October 19, 2004, the State of Tennessee’s
    Code Enforcement Division found that T.R. Arnold had
    performed a substandard review of the plans. On
    October 21, 2004, the State sent a letter to T.R. Arnold
    setting forth a list of areas in which the plans failed to
    comply with the Tennessee Code. These areas included:
    (1) failure to clearly identify whether All American or
    Mod-U-Kraf was responsible for the modular construc-
    tion; (2) failure to affix certain engineering seals; (3) failure
    to complete HVAC, plumbing, and mechanical designs.
    None of the deviations listed by the State related to
    the design of the modular units themselves. Rather, the
    deviations related only to other aspects of the Project. In
    December 2004, T.R. Arnold issued another deviation
    report to All American, reiterating the same issues identi-
    fied by the State.
    Because of the stated deviations, the State refused to
    issue a Letter of Filing. Under state law, All American
    could not begin construction of the modular units
    without a Letter of Filing. Helmer, T.R. Arnold’s represen-
    tative, testified that the State’s decision to reject the
    plans was “very unusual” and “contrary to the standard
    way of doing business in the State of Tennessee.” Helmer
    testified that, based on his experience, the State’s Letter
    of Filing ordinarily related only to the modular unit
    designs and not designs related to site work. Here, the
    14                                                 No. 10-3178
    modular units had been deemed fully compliant and
    complete, but the State rejected the plans based on devia-
    tions related to site work.
    6. Coachmen Denies Further Draws on the Construction Loan
    In February 2005, Coachmen denied Winforge’s request
    for a further draw on the construction loan under the
    Loan Agreement and informed Lee that money would
    be withheld until Winforge proceeded with its obliga-
    tions to develop the Project. Up to this point, Coachmen
    had provided Winforge with significant funding from
    the construction loan. Despite receiving these funds,
    Winforge had not hired a general contractor, as it was
    required to do under the Agreement. Instead, Winforge
    had chosen to assign Lee and McMahon to the role of
    general contractor at various points. The defendants
    believed that neither McMahon nor Lee was qualified
    to perform those duties.
    7. The State of Tennessee Issues the Letter of Filing
    On March 3, 2005, Winforge finally completed the
    design of the mechanical and electrical plans. All
    American incorporated those designs into the plans
    and submitted revised plans to T.R. Arnold, which re-
    sponded with a new deviation list. All American then
    incorporated the necessary changes indicated in the
    deviation report and submitted revised plans in
    May 2005. T.R. Arnold approved the May 2005 plans
    and forwarded those plans to the State.
    No. 10-3178                                            15
    On May 13, 2005, the State responded with a list of
    forty-eight deviations relating to three key substantive
    design issues: a faulty sprinkler design, an inadequate
    fire alarm design, and a faulty smoke egress design for
    the lobby area. Again, none of the deviations related to
    the modular plans themselves.
    In August 2005, Winforge successfully produced a
    code-compliant sprinkler design. In the same month, the
    parties also resolved the lobby egress issue. After in-
    corporating the necessary changes, All American resub-
    mitted the plans to T.R. Arnold, which once again ap-
    proved the plans and forwarded them to the State. On
    August 30, 2005, the State issued a Letter of Filing for
    the Project, finally authorizing All American to begin
    construction of the modular units.
    8.   The City of Pigeon Forge Rejects the Building Permit
    Application for the Project
    Before All American could commence construction of
    the modular units, however, a building permit had to be
    obtained from the City of Pigeon Forge. Winforge was
    supposed to obtain that permit. Although Winforge
    produced a “Building Permit Application,” Winforge
    never completed or submitted the document, leaving
    certain items on the form blank or marked “TBD” (to be
    determined). Because Winforge had not yet secured the
    building permit and had still not hired a general contrac-
    tor, All American hired a general contractor, D.F. Chase,
    to seek the building permit. D.F. Chase filed a building
    permit application with the City of Pigeon Forge. However,
    16                                              No. 10-3178
    on February 13, 2006, the City of Pigeon Forge rejected
    the application because the City’s sewer system lacked
    capacity to handle the Project. The rejection letter clearly
    indicated that an earlier application would have likely
    been approved because the sewer issue had not arisen
    until just before D.F. Chase had applied for the permit.
    This letter strongly suggested that the permit would
    likely have been approved if Winforge had submitted
    the permit application on time.
    Without a building permit, the Project was at a perma-
    nent standstill. Therefore, All American never began
    manufacturing the modular units, concluding that the
    units could never be incorporated into the Project due
    to the lack of a building permit.
    On February 23, 2006, Coachmen notified Winforge
    that it was in default on the Loan Agreement. During
    the course of the development of the Project, Lee and
    McMahon had obtained draws on the construction
    loan amounting to more than forty percent of the total
    projected cost of the Project, paying themselves and
    the entities they had employed on the Project approxi-
    mately $1.2 million. However, neither Mod-U-Kraf nor
    All-American had received any payment from the funds
    obtained through the construction loan.
    On March 24, 2006, Coachmen notified Winforge that
    Coachmen intended to institute foreclosure proceedings
    and attached a Note of Foreclosure stating that the prop-
    erty was to be sold on April 21, 2006. On November 15,
    2006, the real estate was sold. Coachmen held the highest
    bid and purchased the property for $1.8 million. On
    No. 10-3178                                            17
    January 30, 2007, Coachmen auctioned the personal
    property that it held as collateral pursuant to a Security
    Agreement between the parties. The net proceeds of
    $283,142.79 were paid to Coachmen and applied against
    the loan deficit.
    9. Winforge and McMahon Bring Suit in District Court
    Winforge and McMahon brought suit against Mod-U-
    Kraf, All-American, and Coachmen, believing that the
    defendants were at fault for the losses incurred and had
    caused the loan default. Winforge and McMahon sought
    to defeat the foreclosure and hold Mod-U-Kraf, All Ameri-
    can, and Coachmen responsible for breach of contract.
    Mod-U-Kraf, All American, and Coachmen filed a counter-
    claim against Winforge and McMahon, also alleging
    breach of contract. The parties filed cross-motions for
    summary judgment. The district court denied Winforge
    and McMahon’s motion and granted in part and denied
    in part the defendants’ motion. The defendants then
    filed a motion to compel arbitration under the arbitra-
    tion clause found in the Agreement. The district court
    denied the motion, finding that the defendants had
    already implicitly agreed to have the district court
    resolve their legal dispute.
    After a four-day bench trial, the district court entered
    judgment in favor of the defendants, finding that no final
    contract was ever formed and that, even if there were
    a contract, the defendants had not breached it. Winforge
    and McMahon appealed, challenging both findings.
    18                                                No. 10-3178
    DISCUSSION
    Initially, we must determine whether we have subject-
    matter jurisdiction. See Carroll v. Stryker Corp., 
    658 F.3d 675
     (7th Cir. 2011) (“[W]e have an independent obliga-
    tion to satisfy ourselves that jurisdiction is secure before
    proceeding to the merits.”). Winforge and McMahon
    rely on diversity of citizenship for federal jurisdiction
    under 
    28 U.S.C. § 1332
    . At oral argument, we questioned
    the parties as to whether the requirements of diversity
    of citizenship under § 1332 was satisfied. Winforge is a
    North Carolina corporation with its principal place of
    business in North Carolina. Coachmen and All American
    are Indiana corporations with their principal place of
    business in Indiana, and Mod-U-Kraf is a Virginia corpora-
    tion with its principal place of business in Virginia.
    McMahon’s citizenship, however, was not clear from
    the parties’ jurisdictional statements. The complaint
    stated that McMahon was a “resident” of North Carolina,
    but the district court’s written opinion states that
    McMahon is a “resident” of Athens, Greece. The plain-
    tiffs’ docketing statement filed with this Court states
    that McMahon is a resident of North Carolina. Both
    the plaintiffs’ supplemental statement of jurisdiction
    and the jurisdictional section of the plaintiffs’ brief assert
    that McMahon is a citizen of North Carolina.
    An allegation of residence is not sufficient to estab-
    lish citizenship, which requires domicile. See Heinen v.
    Northrop Grumman Corp., 
    671 F.3d 669
    , 670 (7th Cir.
    2012) (citing Gilbert v. David, 
    235 U.S. 561
    , 
    35 S. Ct. 164
    , 
    59 L. Ed. 360
     (1915); Steigleder v. McQuesten, 
    198 U.S. 141
    , 25
    No. 10-3178                                                 
    19 S. Ct. 616
    , 
    49 L. Ed. 986
     (1905); Denny v. Pironi, 
    141 U.S. 121
    , 
    11 S. Ct. 966
    , 
    35 L. Ed. 657
     (1891); Robertson v. Cease,
    
    97 U.S. 646
    , 
    24 L. Ed. 1057
     (1878)). Further, a United States
    citizen who establishes domicile in a foreign country is
    no longer a citizen of any State of the United States and
    destroys complete diversity under 
    28 U.S.C. § 1332
    .
    Newman-Green, Inc. v. Alfonzo-Larrain, 
    490 U.S. 826
    , 828, 
    109 S. Ct. 2218
    , 2220-21 (1989).
    At oral argument, we directed the parties to file addi-
    tional jurisdictional statements to clarify McMahon’s
    citizenship. The parties’ amended jurisdictional state-
    ments indicate that McMahon was a citizen of the United
    States residing and domiciled in North Carolina on
    April 17, 2006, the date on which the complaint was
    filed. McMahon moved to Athens, Greece about two
    years later. Because we determine jurisdiction based on
    citizenship at the time the case was filed, we conclude
    that McMahon is a citizen of North Carolina for pur-
    poses of diversity jurisdiction in this case. See Hukic v.
    Aurora Loan Servs., 
    588 F.3d 420
    , 427 (7th Cir. 2009) (citing
    Grupo Dataflux v. Atlas Global Grp., L.P., 
    541 U.S. 567
    , 
    124 S. Ct. 1920
    , 
    158 L. Ed. 2d 866
     (2004)). Accordingly, we
    find that the requirements of diversity jurisdiction are
    satisfied.
    I.    Standard of Review
    In an appeal from a bench trial, we review the district
    court’s findings of fact and applications of law to those
    findings of fact for clear error. Trustees of Chi. Painters and
    20                                                No. 10-3178
    Decorators Funds v. Royal Int’l Drywall and Decorating, Inc.,
    
    493 F.3d 782
    , 785 (7th Cir. 2007) (quoting Keach v. United
    States Trust Co., 
    419 F.3d 626
    , 634 (7th Cir. 2005)). “A
    finding is ‘clearly erroneous’ when although there is
    evidence to support it, the reviewing court on the entire
    evidence is left with the definite and firm conviction that
    a mistake has been committed.” United States v. United
    States Gypsum Co., 
    333 U.S. 364
    , 395, 
    68 S. Ct. 525
    , 542, 
    92 L. Ed. 746
     (1948). “The party alleging error bears the burden
    of demonstrating that particular factual findings were
    clearly erroneous.” Carnes Co. v. Stone Creek Mech., Inc., 
    412 F.3d 845
    , 847 (7th Cir. 2005). We review the district court’s
    conclusions of law de novo. Platinum Tech., Inc. v. Fed. Ins.
    Co., 
    282 F.3d 927
    , 930-31 (7th Cir. 2002).
    A. This Court Reviews the District Court’s Determination that
    No Contract Existed for Clear Error.
    Winforge argues that we should apply de novo review
    to the district court’s determination that no contract
    existed. Winforge contends that under both federal law
    and Virginia law, the existence of a contract is a question
    of law that should be reviewed de novo where, as
    argued here, the facts surrounding contract formation
    are undisputed.
    In this Court, “[t]he fixing of the boundary between
    questions of law and questions of fact, is a matter of
    federal procedural law and therefore governed by federal
    rather than state law in diversity as in other federal suits.”
    Dilworth v. Dudley, 
    75 F.3d 307
    , 309 (7th Cir. 1996). Under
    No. 10-3178                                                  21
    federal procedural law, the existence of a contract is a
    mixed question of law and fact that is subject to clear error
    review. E.C. Styberg Eng’g Co., 
    492 F.3d 912
    , 917 (7th Cir.
    2007).
    In this case, the facts were in dispute. The district court
    considered the facts surrounding contract formation,
    particularly the parties’ words and actions, and deter-
    mined, as a matter of fact, that the parties never
    intended to be bound by the Agreement and attached
    Preliminary Scope of Work signed on April 13, 2004.
    Based on its findings of fact, the district court concluded
    that the Agreement was not an enforceable contract
    because the parties never achieved mutuality of assent
    to the central terms of the Agreement. Accordingly,
    we review the district court’s determination that no
    contract existed for clear error. See E.C. Styberg Eng’g Co.,
    
    492 F.3d at 917
    ; see also Thomas v. Gen. Motors Acceptance
    Corp., 
    288 F.3d 305
    , 307 (7th Cir. 2002)).
    B. This Court Reviews the District Court’s Determination
    Regarding Breach of Contract for Clear Error.
    “Although the interpretation of an established written
    contract is generally a question of law for the court, the
    question of whether or not a particular breach of a
    contract is material is a question of fact.” Int. Prod. Special-
    ists, Inc. v. Schwing Am., Inc., 
    580 F.3d 587
    , 594 (7th Cir.
    2009) (citations omitted). Therefore, we interpret the
    contract de novo and review the district court’s determina-
    tion of whether the contract was materially breached
    for clear error. 
    Id. at 594-95
    .
    22                                                   No. 10-3178
    II. The District Court’s Determination that No Contract
    Existed Was Not Clear Error.
    The district court found that the parties never
    achieved a “distinct intention common to both” as to the
    central aspects of the contract. Winforge, 
    2010 WL 3326856
    ,
    at *9 (citing Moorman v. Blackstock, Inc., 
    276 Va. 64
    , 75,
    
    661 S.E.2d 404
    , 409 (Va. 2008)). Therefore, the district
    court found that the contract lacked mutuality of assent
    as to essential terms and that no contract ever existed.
    Winforge, 
    2010 WL 3326856
    , at *9. On appeal, Winforge
    urges this Court to find the Agreement enforceable
    because (1) the parties thoroughly negotiated and signed
    the Agreement and (2) the defendants waived objection
    to the validity of the contract by acknowledging its
    validity before and after the district court’s entry of
    judgment.6
    6
    In its brief, Winforge also contends, without citing to any
    authority, that the Agreement is a valid contract because the
    parties mutually undertook to perform according to the terms
    of the Agreement for a period of 20 months after signing the
    Agreement. However, in its reply brief, Winforge clarifies
    that “Winforge’s reliance on the parties’ conduct is not
    intended to establish, but rather to explain, the terms of the
    agreement.” Based on this clarification, we need not discuss
    Winforge’s initial argument that the Agreement should be
    enforced based on the parties’ course of dealing. Moreover,
    we note that examination of the parties’ performance after
    signing the Agreement certainly does not help Winforge’s
    case. In its findings of fact, the district court determined that
    (continued...)
    No. 10-3178                                               23
    A. The District Court Did Not Clearly Err in Its Determina-
    tion that the Agreement Lacked Mutuality of Assent and,
    Therefore, Was Not a Valid Contract.
    We first address Winforge’s argument that the district
    court should have found the Agreement enforceable
    because the parties thoroughly negotiated and signed it.
    Winforge argues that the district court erred in finding
    that subsequent drafts of the Scope of Work indicated
    lack of assent to the original Agreement signed on April 13,
    2004 and that the district court erred in failing to
    consider the “legal presumption of assent that arises
    under Virginia law when an agreement is written and
    signed.” Appellants’ Brief 20 (citing Browne v. Kline
    Tysons Imp., Inc., 
    190 F. Supp. 2d 827
    , 830 (E.D. Va. 2002)).
    In support, Winforge draws our attention to the fact
    that, prior to signing the Agreement, the parties
    negotiated the terms of the Agreement and Preliminary
    Scope of Work for almost ten months and exchanged
    at least ten drafts of the Scope of Work. Winforge also
    argues that the fact that the Agreement required that any
    change to the Agreement or Scope of Work be done by a
    written change order further establishes that the Agree-
    ment was final.
    6
    (...continued)
    Winforge failed to perform a number of tasks clearly assigned
    to it under the Agreement, including hiring a general con-
    tractor. Winforge also failed to timely complete the designs
    of the elevator, mechanical and electrical system, HVAC
    system, and plumbing system and failed to secure the neces-
    sary building permit from the City of Pigeon Forge.
    24                                              No. 10-3178
    We find no error in the district court’s conclusion that
    the Agreement, although negotiated and signed, was not
    an enforceable contract. The parties are in agreement that,
    pursuant to the terms of the Agreement, Virginia law
    applies to the resolution of all contractual disputes be-
    tween the parties. Under Virginia law, Winforge and
    McMahon, as the parties seeking to enforce the contract,
    bore the burden of proving the existence of the contract.
    Brown v. Brown, 
    53 Va. App. 723
    , 728, 
    674 S.E.2d 597
    ,
    599 (2009). Winforge was required to establish mutuality
    of assent, or “the meeting of the minds” of the parties,
    which is an essential element of any contract. Moorman, 276
    Va. at 75, 661 S.E.2d at 409 (citing Phillips v. Mazyck, 
    273 Va. 630
    , 636, 
    643 S.E.2d 172
    , 175 (2007)). “Until the parties
    have a distinct intention common to both . . . there is a
    lack of mutual assent and, therefore, no contract.” 
    Id.
    Mutual assent is determined “exclusively from those
    expressions of [the parties’] intentions which are com-
    municated between them.” Lucy v. Zehmer, 
    196 Va. 493
    ,
    503, 
    84 S.E.2d 516
    , 522 (1954) (citations and internal
    quotation marks omitted); see also Phillips, 273 Va. at 636,
    
    643 S.E.2d at 175
     (stating that courts are to determine
    mutual assent from the parties’ words or acts). Winforge
    and McMahon also had the burden of proving that the
    Agreement contained essential terms. McKay Consulting
    v. Rockingham Mem’l Hosp., No. 5:09-CV-00054, 
    2010 WL 3200061
    , at *9 (W.D. Va. Aug. 11, 2010). In Virginia, the
    essential terms of an agreement for services include “the
    nature and extent of service to be performed, the place
    where and the person to whom it is to be rendered, and
    the compensation to be paid.” Reid v. Boyle, 
    259 Va. 356
    ,
    No. 10-3178                                               25
    370, 
    527 S.E.2d 137
    , 145 (2000) (quoting Mullins v. Mingo
    Lime & Lumber Co., 
    176 Va. 44
    , 
    10 S.E.2d 492
    , 494 (1940)).
    An agreement lacking these terms will not be enforced.
    Mullins, 176 Va. at 50, 10 S.E.2d at 494.
    The district court’s conclusion that the Agreement
    lacked mutuality of assent is supported by the evidence.
    In reaching its conclusion, the district court cited evidence
    that the parties continued to exchange new drafts of
    the Scope of Work even after they had signed the Agree-
    ment on April 13, 2004. The court noted that, in July 2004,
    Mod-U-Kraf sent a proposed final draft of the Scope of
    Work to Lee, who was working on behalf of Winforge.
    Lee did not review the July 2004 draft and, instead, re-
    quested that Mod-U-Kraf provide a “red-lined” version
    of the Scope of Work that would highlight the changes
    and describe how the newly proposed terms would
    affect the pricing of the Project. In September 2004, Mod-U-
    Kraf sent another proposed draft of the Scope of Work
    to Lee, but Lee again did not review the draft because
    it was not red-lined to highlight changes. The district
    court noted that “[n]othing in the record indicates that
    Lee declined to review these proposed revisions because
    he believed the negotiations were already complete.”
    Winforge, 
    2010 WL 3326856
    , at *9. The district court consid-
    ered these facts to be evidence that the terms of the
    Scope of Work remained under negotiation and were not
    agreed upon well into the summer of 2004. The district
    court also cited evidence that Lee and McMahon had
    different views regarding the finality of the Preliminary
    Scope of Work. During a January 25, 2005 conference
    call between the parties, Lee stated that he thought
    26                                              No. 10-3178
    the Preliminary Scope of Work had been modified or was
    open to modification, but McMahon expressed his
    belief and hope that the parties would continue to
    honor the Preliminary Scope of Work as binding.
    Based on Lee’s and McMahon’s statements, evidence
    that the parties continued to negotiate the Scope of Work
    long after they had signed it, and the fact that no final
    version of the Scope of Work had been agreed upon, the
    district court concluded that the Agreement, with the
    attached Preliminary Scope of Work, was preliminary
    and not final. The district court concluded as follows:
    Given these clear indications by the parties that
    the Scope of Work accompanying the Develop-
    ment Agreement was ‘Preliminary,’ as well as signifi-
    cant evidence that the parties continued to negotiate
    the Scope of Work well after the date they signed the
    Development Agreement and that no final version of
    the Scope of Work was ever agreed upon, it is obvious
    that the parties’ initial ‘preliminary’ agreement as to
    these key performance terms was not, in fact, final.
    Thus, because the essence of the parties’ dispute in
    this litigation regards different interpretations and
    understandings of the terms contained in that Pre-
    liminary Scope of Work, the parties never achieved a
    ‘distinct intention common to both’ as to central
    aspects of the contract. Moorman, 661 S.E.2d at 409.
    Accordingly, the contract between the parties lacked
    mutuality of assent as to essential terms; indeed, no
    contract ever, in fact, existed. Id.
    Winforge, 
    2010 WL 3326856
    , at *9.
    No. 10-3178                                              27
    Winforge argues that the district court erred in con-
    sidering facts related to Mod-U-Kraf’s July 2004 draft of
    the Scope of the Work to be an indication that the Agree-
    ment remained under negotiation. Winforge contends
    that Mod-U-Kraf’s July 2004 draft of the Scope of Work
    was a “request to modify” the existing contract rather
    than an indication that no contract existed. According
    to Winforge, Mod-U-Kraf’s proposed revision could not
    have reached “back in time” to invalidate an agreement
    that had already been negotiated and signed and “con-
    tained all necessary material terms.” Winforge contends
    that Lee’s decision not to review the July 2004 draft
    was evidence of Lee’s lack of assent to the new pro-
    posed terms but not lack of assent to the already formed
    contract. Winforge additionally argues that the fact that
    changes were proposed does not mean that the parties
    lacked assent to the original Agreement because the
    original Agreement contemplated changes, which were
    required to be in writing pursuant to Section 14 of the
    Agreement.
    We find no clear error in the district court’s conclusion
    that Mod-U-Kraf’s July and September 2004 drafts of the
    Scope of Work, coupled with Lee’s responses to those
    drafts, indicated that the parties had not mutually as-
    sented to the April 2004 Preliminary Scope of Work. We
    conclude that the district court’s findings that the parties
    continued to exchange drafts of the Scope of the Work
    long after signing the Agreement, that no final Scope of
    Work had been agreed upon, and that Lee and McMahon
    had different views regarding the finality of the document
    provide substantial and sufficient support for the court’s
    28                                              No. 10-3178
    conclusion that the parties never reached mutuality
    of assent as to the Agreement.
    Winforge further argues that the district court, in
    finding that the Agreement lacked mutual assent, failed
    to consider the legal presumption of assent that arises
    under Virginia law when an agreement is written and
    signed. Winforge cites Browne, 
    190 F. Supp. 2d at 830
    ,
    for the proposition that “[o]ne who signs a contract is
    presumed to know and assent to the terms contained
    therein.” However, even a signed writing is not a con-
    tract if there is no mutual assent or “distinct intention
    common to both,” which is essential to any contract.
    Moorman, 276 Va. at 75, 661 S.E.2d at 409 (citing Phillips,
    273 Va. at 636, 
    643 S.E.2d at 175
    ). Here, the district court
    found, and we agree, that the parties never agreed as to
    the essential terms of the Agreement. In Browne, the
    court considered whether a consumer had agreed to
    submit all claims to arbitration when he signed a Buyer’s
    Order consummating the sale of a used car, where the
    back of the Buyer’s Order stated that the claim would
    be resolved by binding arbitration. 
    190 F. Supp. 2d at 830
    .
    The court found that the consumer’s intent to submit
    all claims to arbitration was shown through his signature
    on the Buyer’s Order because “[o]ne who signs a con-
    tract is presumed to know and assent to the terms con-
    tained therein.” 
    Id. at 830
    . In Browne, the issue of whether
    the parties had mutually assented to the contract was not
    before the court. In the present case, by contrast, the
    issue is not whether the parties were aware of the terms
    in the Agreement when they signed it; rather, the issue
    is whether the parties mutually assented to the terms
    No. 10-3178                                           29
    necessary to form a contract. The district court con-
    cluded that no contract had been formed because the
    parties never mutually assented to the essential terms.
    We find no clear error in that finding.
    Finally, Winforge asks this Court to determine as a
    matter of law that the Agreement contained all terms
    necessary for formation. Specifically, Winforge con-
    tends that Mod-U-Kraf’s obligations were clearly set
    forth in sections 1.2, 1.3, 4.1, and 10.4 of the Scope of
    Work. Winforge also contends that the Agreement set
    forth the timing for the completion of the obligations
    and set forth the contract price pursuant to exhibits to
    the Agreement.
    The district court did not make specific conclusions as
    to whether essential terms were lacking from the con-
    tract. Instead, the court held that the contract lacked
    mutual assent as to essential terms. Because we have
    already concluded that the district court did not clearly
    err in finding that the contract lacked mutual assent as
    to essential terms, we need not decide the question
    of whether the contract lacked specific essential terms.
    B. Defendants Have Not Waived Their Challenge to the
    Validity of the Agreement
    Winforge argues that the defendants should be pre-
    cluded from contesting the validity of the Agreement
    because they “consistently and repeatedly reaffirmed” the
    validity of the Agreement in pleadings before and after
    the district court’s entry of judgment. Winforge first
    30                                              No. 10-3178
    claims that the defendants acknowledged the validity of
    the Agreement because they did not challenge its validity
    in their Answer. We disagree. We first note that con-
    testing the validity of an alleged contract is not an enumer-
    ated affirmative defense that is waived if not included
    in an answer. See Fed. R. Civ. P. 8(c). This Court has
    previously noted that the appropriate analysis for deter-
    mining whether a defense is an affirmative defense
    when not specifically listed in Rule 8(c) “is not well
    settled, especially in diversity cases.” Brunswick Leasing
    Corp. v. Wis. Cent., Ltd., 
    136 F.3d 521
    , 530 (7th Cir. 1998).
    This Court has identified two approaches for deter-
    mining whether a defense not specifically enumerated in
    Rule 8(c) is an affirmative defense: a defense is an affirma-
    tive defense (a) “if the defendant bears the burden of
    proof” under state law or (b) “if it [does] not controvert
    the plaintiff’s proof.” Brunswick Leasing Corp., 
    136 F.3d at 530
    . Under either approach, contesting the validity of
    the contract in a breach of contract action is not an af-
    firmative defense because, under Virginia law, the exis-
    tence of the contract is an issue on which the plaintiff
    bears the burden of proof. See Brown, 
    53 Va. App. at 728
    ,
    
    674 S.E.2d at 599
    . The defendants did not bear the
    burden of proving that the Agreement was not a
    valid contract.
    Winforge next argues that Defendants have waived
    their challenge to the validity of the Agreement because,
    at trial, Powell (Mod-U-Kraf’s general manager) testified
    regarding the negotiation and execution of the Agree-
    ment but never suggested that it was not a valid contract.
    However, admitting that the Agreement was negotiated
    and signed certainly does not amount to an admission
    No. 10-3178                                                31
    that the Agreement was a valid contract. As we stated
    above, even a signed, written contract is not enforceable
    if it lacks mutual assent, as was the case here. Moorman,
    276 Va. at 75, 661 S.E.2d at 409. Further, it is well-estab-
    lished that waiver only applies when there has been
    “ ‘the voluntary or intentional relinquishment of a known
    right.’ ” Vershaw v. Northwestern Nat’l Life Ins. Co., 
    979 F.2d 557
    , 560 (7th Cir. 1992) (citation omitted). The trial
    transcript shows that Powell never voluntarily or inten-
    tionally relinquished the defendants’ challenge to the
    validity of the contract.
    Winforge also argues that the defendants have waived
    their challenge to the validity of the contract because
    the defendants’ Motion to Compel Arbitration, brought
    before the district court, asserted entitlement to relief that
    arose exclusively out of the Agreement. We disagree. The
    defendants’ attempt to compel arbitration was not an
    admission that the Agreement was valid and enforceable.
    Further, disputes concerning the validity of a contract may
    properly be the subject of arbitration when the parties
    so intend. See Matterhorn, Inc. v. NCR Corp., 
    763 F.2d 866
    , 868, 872 (7th Cir. 1985). We also disagree with
    Winforge’s position that the defendants’ Motion for
    Attorneys Fees, also before the district court, constituted
    an acknowledgment of the validity of the Agree-
    ment. That Motion sought relief under the separate
    Loan Agreement between the parties and did not
    mention the Development Agreement.
    Additionally, Winforge claims that the defendants
    are precluded from challenging the validity of the
    contract because the district court, in its Order on Sum-
    32                                              No. 10-3178
    mary Judgment, found that the parties entered into the
    Agreement. Winforge raised the same argument before
    the district court. The district court, in its Findings of
    Fact and Conclusions of Law, responded that the defen-
    dants were not precluded from raising their defense
    to formation because the court’s previous “finding” in
    the summary judgment order that the parties had entered
    into the Agreement “was not based on any specific
    factual or legal findings as to validity or enforceability,
    which issues manifested fully at trial.” Winforge, 
    2010 WL 3326856
    , at *8 n.11 (citing Occidental Fire & Cas. Co. v.
    Cont’l Bank N.A., 
    918 F.2d 1312
    , 1230 (7th Cir. 1990)).
    We agree with the district court and conclude that the
    defendants are not precluded from arguing that no
    contract existed.
    In sum, we find that the district court did not err in
    concluding that the Agreement is not a valid contract
    because it lacked mutuality of assent, and we find that
    the defendants never waived their claim that the Agree-
    ment is not a valid contract.
    III. The District Court Did Not Err in Finding that
    the Defendants Did Not Breach the Contract.
    The district court also found that, even if the Agreement
    were a valid contract, the defendants had not breached it.7
    The district court found that Mod-U-Kraf had completed
    7
    For convenience, we refer to the Agreement and Preliminary
    Scope of Work, together, as the “contract” in this section of
    the opinion.
    No. 10-3178                                              33
    all of its obligations to produce building plans and
    obtain approvals for those plans as defined by the clear
    language of the contract and modified by a June 2004 oral
    modification. Any failure to obtain the approvals on time,
    the district court concluded, was due to Winforge’s—not
    Mod-U-Kraf’s—failure to timely perform its obligations
    under the contract. The district court also concluded that,
    even though the defendants were obligated under the
    contract to construct the modular units, their failure to
    do so was not a breach because that failure was due to
    Winforge’s deficient performance of Winforge’s duties
    under the contract.
    On appeal, Winforge challenges the district court’s
    conclusion that the defendants did not breach the
    contract and argues: (1) the district court incorrectly
    interpreted the plain language of the contract to find
    that Mod-U-Kraf’s obligation to prepare plans and
    obtain approvals for those plans was limited to its respon-
    sibility to provide modular units and did not extend to
    the building as a whole; (2) the district court erred in
    concluding that the parties had orally modified the con-
    tract in June 2004 to assign a number of Mod-U-Kraf’s
    responsibilities under the contract to Winforge; and (3) the
    district court erred by excusing Mod-U-Kraf’s obligation
    to construct the modular units. Underlying all three
    arguments is Winforge’s main contention that, under the
    plain language of the contract, Mod-U-Kraf and All-
    American were required to prepare all drawings, designs,
    and plans for the entire hotel building—not just for the
    modular units—and obtain all necessary approval for
    34                                              No. 10-3178
    those plans, including all building permits, by Decem-
    ber 31, 2004. Winforge maintains that the defendants’
    failure to timely do so constituted breach of the contract,
    as did their failure to construct any of the modular units.
    Although we have already concluded that the Agree-
    ment is not an enforceable contract, we nonetheless
    have considered Winforge’s arguments on appeal and
    find that the district court did not clearly err in finding
    that, even if the Agreement were a valid contract, the
    defendants had not breached it.
    In Virginia, “ ‘[t]he elements of a breach of contract
    action are (1) a legally enforceable obligation of a defen-
    dant to a plaintiff; (2) the defendant’s violation or breach
    of that obligation; and (3) injury or damage to the
    plaintiff caused by the breach of obligation.’ ” Sunrise
    Continuing Care, LLC v. Wright, 
    277 Va. 148
    , 154, 
    671 S.E.2d 132
    , 135 (2009) (quoting Filak v. George, 
    267 Va. 612
    , 619, 
    594 S.E.2d 610
    , 614 (2004)). A plaintiff bears the
    burden of proving a breach by the defendant. Sunrise
    Continuing Care, LLC, 277 Va. at 154, 
    671 S.E.2d at 135
    .
    It is undisputed that Mod-U-Kraf was responsible
    for providing the modular units under the contract and
    that Mod-U-Kraf ultimately did not construct any
    modular units. However, Mod-U-Kraf could not com-
    mence construction of the modular units until the neces-
    sary plans were prepared and then approved by the
    appropriate entities. Therefore, as the district court
    noted, the parties’ dispute over who breached the
    contract centers on who was responsible for the failure
    to obtain timely approval of the Project plans from the
    No. 10-3178                                              35
    State and the City of Pigeon Forge. That question, in
    turn, depends on who was responsible for preparing the
    plans and securing the approvals. Winforge argues that
    the failure to obtain timely approval was the defendants’
    fault because the contract assigned to the defendants
    the responsibility of completing all plans related to the
    hotel building and securing all franchiser, third-party,
    state, and local approvals for those plans by December 31,
    2004. The defendants argue, and the district court found,
    that the failure to obtain timely approval was the fault
    of Winforge. The district court found that, under the
    contract, the defendants’ design and approval duties
    were limited to the modular unit design and those
    other duties specifically enumerated, and the defendants
    successfully fulfilled those obligations. The district court
    found that, under the terms of the contract, as orally
    modified in June 2004, Winforge was responsible for a
    number of other designs that had to be incorporated
    into the Project plans before the plans could be approved.
    The district court concluded that Winforge’s delay in
    providing those designs caused the defendants’ delay
    in obtaining State approval. Additionally, the district
    court found that Winforge was responsible for obtaining
    the final building permit from the City of Pigeon Forge
    and that Winforge’s failure to timely apply for that
    permit resulted in the permanent stagnation of the Project.
    On appeal, Winforge first argues that the district court
    incorrectly interpreted the plain language of the Agree-
    ment and Scope of Work with respect to the parties’
    responsibilities to complete the plans for the building
    and obtain approval of those plans. Winforge contends
    36                                             No. 10-3178
    that the plain language of the Scope of Work makes
    clear that Mod-U-Kraf was solely responsible for pro-
    viding “all architectural drawings needed in order to
    obtain approval involving the building itself from the
    ground up” by December 31, 2004. Therefore, Winforge
    contends, Mod-U-Kraf’s failure to obtain timely approval
    constituted breach of the contract. Winforge argues that
    the district court incorrectly interpreted Sections 1.2 and
    1.3 of the Scope of Work to mean that Mod-U-Kraf’s
    obligation to prepare “drawings” and obtain approval
    for those drawings was “clearly limited to its responsi-
    bility for providing modular units, not to the building
    project as a whole.” According to Winforge, there is no
    distinction between “modular units” and “the building
    project as a whole” because the building consisted only
    of modular units. Winforge contends that it was only
    responsible for the design and approval of plans related
    to the area outside of the building.
    In the absence of ambiguity, a court interprets the
    agreement by examining solely the language of the con-
    tract. School Bd. of City of Newport News v. Commonwealth
    of Virginia, 
    279 Va. 460
    , 467-68, 
    689 S.E.2d 731
    , 735
    (2010). “ ‘The primary goal in the construction of written
    contracts is to determine the intent of the contracting
    parties, and intent is to be determined from the
    language employed, surrounding circumstances, the
    occasion, and apparent object of the parties.’ ” Flippo v.
    CSC Assocs. III, LLC, 
    262 Va. 48
    , 64, 
    547 S.E.2d 216
    , 226
    (Va. 2001) (quoting Christian v. Bullock, 
    215 Va. 98
    , 102,
    
    205 S.E.2d 635
    , 638 (1974)).
    No. 10-3178                                                   37
    We agree with the district court that the plain language
    of Section 1.2 and 1.3 of the Preliminary Scope of Work
    does not support Winforge’s argument that Mod-U-
    Kraf was responsible for all the drawings and approvals
    related to the entire building. Sections 1.2 and 1.3 of the
    Preliminary Scope of Work read as follows:
    1.2 Mod-U-Kraf shall manufacture modular units at
    the Mod-U-Kraf manufacturing facilities in ac-
    cordance with the approved Specifications and Draw-
    ings. Drawings to meet local, state, 3rd party and
    franchiser requirements. To include only materials
    and on-site services specified as supplied by MUK.
    1.3 MUK shall provide modular units and material
    noted on plans for installation and completion of
    a Wingate Inn. This will include all architectural
    drawings, structural calculations for modular unit
    construction, mechanical, electrical systems for
    modulars, and sprinkler system.
    These two provisions make clear that Mod-U-Kraf was
    responsible for preparing all architectural drawings for
    the modular units, securing local, state, third party, and
    franchiser approval for those drawings, and pro-
    viding the structural calculations, mechanical system, and
    electrical system for the modular units. The provision
    also states that Mod-U-Kraf was responsible for the
    sprinkler system.8 Nowhere in these provisions is there
    8
    The district court found that Winforge subsequently trans-
    ferred the responsibility for the sprinkler design from Mod-U-
    (continued...)
    38                                              No. 10-3178
    any indication that Mod-U-Kraf was responsible for
    preparing drawings for the entire building. Rather, all
    references to Mod-U-Kraf’s responsibility to prepare
    drawings or obtain approvals for those drawings are in
    reference to Mod-U-Kraf’s responsibility to provide
    modular units.
    The district court properly applied the principle of
    ejusdum generis to conclude that Sections 1.2 and 1.3 refer
    specifically to Mod-U-Kraf’s duty to manufacture and
    provide modular units for the Project. Under this rule,
    “ ‘when general and specific words are grouped, the
    general words are limited by the specific.’ ” Wood ex rel.
    Wood v. Henry County Pub. Schs., 
    255 Va. 85
    , 94-95, 
    495 S.E.2d 255
    , 260 (1998) (citation omitted). In Section 1.2,
    Mod-U-Kraf’s responsibility to prepare “[d]rawings to
    meet local, state, 3rd party and franchiser requirements”
    is clearly limited by the preceding sentence, which
    states that Mod-U-Kraf is responsible for manufac-
    turing modular units “in accordance with the approved
    Specifications and Drawings.” Similarly, Section 1.3 is
    limited by its first sentence, which states that Mod-U-Kraf
    “shall provide modular units and material noted on
    plans for installation and completion of a Wingate Inn.”
    Section 1.3 then states, “This will include all architectural
    drawings.” Mod-U-Kraf’s responsibility to complete “all
    architectural drawings” is limited by the preceding sen-
    8
    (...continued)
    Kraf to Winforge in June 2004 through oral modification of
    the Agreement.
    No. 10-3178                                             39
    tence, which refers to Mod-U-Kraf’s responsibility to
    produce modular units. In sum, the plain language of
    Sections 1.2 and 1.3 of the Scope of Work indicates that
    Mod-U-Kraf’s responsibilities to prepare drawings and
    obtain approvals were limited to Mod-U-Kraf’s responsi-
    bility to manufacture modular units. Sections 1.2 and 1.3
    clearly do not assign Mod-U-Kraf responsibility for
    designing plans and obtaining approvals for the entire
    building, from the ground up, as Winforge claims.
    Winforge further argues that the building consisted
    “only of modular units.” Therefore, Winforge argues, Mod-
    U-Kraf’s responsibility to provide “all architectural draw-
    ings,” even if interpreted to mean all drawings for the
    modular units, must refer to all drawings for the entire
    building. We are not convinced by this argument. The
    Scope of Work explicitly refers to building components,
    to be completed on-site, that are distinct from the
    modular units. Section 1.4 of the Scope of Work assigns
    the task of “overseeing the completion of” a number
    of those components to Winforge:
    1.4 WINFORGE will be responsible for overseeing the
    completion of the modular units tie-in and com-
    ponents such as the following to complete the
    Wingate Inn on-site:
    • Plumbing connections between levels
    • Plumbing connections to city sewer & water
    • Electrical connections and equipment as noted on
    plans
    40                                               No. 10-3178
    • Elevator
    • Roof Facade (Completion of Parapet Wall)
    • Finish decor at all common areas, drop ceiling,
    HVAC System, Lights, Finish Floor, Drywall & Finish
    as shown, Entry Doors, FF&E materials, etc.
    • For additional material and task, reference to plans[.]
    The plumbing connections between levels of the building,
    electrical connections, elevator, roof facade, parapet
    wall, and HVAC system are all components of the
    building itself, to be completed on-site, that are distinct
    from the modular units.
    Winforge argues that Section 1.4 refers only to
    Winforge’s responsibilities “to provide labor and
    material after the design, approval and construction of
    the modular units in connection with assembly of
    modular units on site.” Winforge insists that the design
    and approval of these components were exclusively the
    responsibility of Mod-U-Kraf, while Winforge was only
    tasked with construction-related activities. We disagree
    with Winforge’s reading of this provision. Section 1.4
    clearly assigns to Winforge the responsibility of com-
    pleting these crucial building components, and nowhere
    else in the Agreement or Scope of Work—certainly not
    in Section 1.2, 1.3, or 1.4—is the design or approval of
    these components separately identified as the responsi-
    bility of Mod-U-Kraf.
    Winforge also argues that the district court incorrectly
    concluded that Winforge was responsible for obtaining
    No. 10-3178                                             41
    the necessary and crucial building permit from the City
    of Pigeon Forge. According to Winforge, Mod-U-Kraf
    was responsible for obtaining all building approvals,
    including the permit from the City. However, Section 9
    of the Agreement makes clear that Mod-U-Kraf was not
    responsible for all building approvals. Section 9 pro-
    vides that Winforge was responsible for other “licenses,
    permits, approvals” for which Mod-U-Kraf would not
    be responsible, “including the building permits”:
    9. BUILDING PERMIT, FEES AND APPROVALS.
    Except for those licenses, permits and fees related to
    the Work which are the responsibility of MUK pursu-
    ant to this Agreement, Winforge and the General
    Contractor or the Project Manager shall secure and
    pay for all other licenses, permits, approvals . . .
    required for the development, construction, use or
    occupancy of permanent structures or for permanent
    changes in existing facilities, including the building
    permits.
    Based on this provision, we agree with the district court
    that Winforge was responsible for obtaining the building
    permit from the City of Pigeon Forge. Additionally, the
    parties’ actions show that the parties understood that
    responsibility to be Winforge’s. The district court found
    that Winforge had prepared an incomplete application
    for the building permit from the City of Pigeon Forge. It
    was only after Winforge had delayed submitting the
    application that Mod-U-Kraf, on its own initiative, hired
    a general contractor, who completed and submitted the
    application.
    42                                            No. 10-3178
    We conclude that the plain language of the contract
    provides that Mod-U-Kraf’s responsibilities to complete
    designs and obtain approval were limited to its responsi-
    bilities to provide the modular units and certain other
    specifically noted responsibilities, such as the sprinkler
    design (which was later transferred to Winforge through
    oral modification). Winforge was responsible for ob-
    taining the building permit from the City. Moreover,
    we note that undisputed facts cited by the district court
    clearly show that the parties understood Mod-U-Kraf’s
    design and approval responsibilities to be generally
    limited to the modular units and that the parties under-
    stood Winforge to be responsible for the design of a
    number of building components distinct from the
    modular units. Mod-U-Kraf was repeatedly delayed in
    securing State approval of its plans because it was
    waiting for Winforge to provide code-compliant designs
    necessary for State approval, including designs for the
    HVAC, plumbing, mechanical, and sprinkler systems.
    Winforge ultimately completed those tasks in sum-
    mer of 2005.
    Winforge’s next argument is that the district court
    erred in its finding that Mod-U-Kraf’s obligations to
    complete certain designs had been transferred to
    Winforge due to a June 2004 oral modification to the
    Agreement. Winforge argues that because the Agreement
    provided that all modifications had to be in writing, the
    fact that there was no written modification establishes
    that no modification ever occurred.
    Modification of a contract may be established with
    evidence of the parties’ course of dealing. Cardinal Dev.
    No. 10-3178                                               43
    Co. v. Stanley Constr. Co., 
    255 Va. 300
    , 305, 
    497 S.E.2d 847
    ,
    851 (1998). This is true even where the contract required
    all modifications to be in writing. Reid, 
    259 Va. at 369-70
    ,
    
    527 S.E.2d at 145
    . We find that the district court did not
    clearly err in concluding that the parties accomplished
    an oral modification of the contract in June 2004
    whereby Winforge assumed responsibility for a number
    of duties that were originally assigned to Mod-U-Kraf
    under the Agreement. The district court cited evidence
    showing that in June 2004, Winforge communicated
    verbally to Mod-U-Kraf that Winforge would take
    over responsibility for providing the designs for the
    sprinkler system, PTAC units, and other mechanical and
    electrical components of the building, tasks that were
    originally assigned to Mod-U-Kraf under the Agreement.
    The court also found that before that time, Winforge
    had instructed Mod-U-Kraf not to work on the sprinkler
    system design. The district court also found that, in
    exchange for Winforge’s assumption of the duty to
    provide the designs for these components, Mod-U-Kraf
    would receive less money from Winforge. The court
    found that Mod-U-Kraf agreed to the changes and did not
    pursue designs of these components after that time. The
    district court concluded that these events constituted
    an oral modification of the Agreement, even though
    the Agreement stated that modifications were to be
    made in a written change order. The court also found
    that, consistent with the modification, Winforge later at-
    tempted to obtain designs and State approval for those
    components. In some cases, Winforge succeeded in
    completing those tasks. Based on these facts, the dis-
    44                                                 No. 10-3178
    trict court concluded that the parties had modified
    the Scope of Work through the oral modification in
    June 2004. We find that the evidence sufficiently sup-
    ports the conclusion that the parties had agreed to an
    oral modification of the contract.
    Finally, Winforge argues that the district court erred
    when it excused Mod-U-Kraf’s obligation to construct the
    modular sections. Winforge claims that Mod-U-Kraf’s
    failure to construct the modular units constituted
    breach because the Agreement unambiguously required
    Mod-U-Kraf to manufacture and deliver the modular
    units by December 31, 2004. Winforge argues that Mod-U-
    Kraf “is not entitled to relief from its obligation to con-
    struct the modular units based upon its own prior breach.”
    We agree that the Agreement assigned to Mod-U-Kraf
    the task of manufacturing and delivering the modular
    units.9 However, we find that the district court properly
    9
    Winforge repeatedly argues that the Agreement stated that
    Mod-U-Kraf was responsible for completing the design, ap-
    proval, and construction of the modular units by December 31,
    2004, citing to the Schedule of Work attached to the Agree-
    ment as Exhibit D. We have reviewed the text of the Agree-
    ment and Exhibit D, and the December 31, 2004 deadline
    is nowhere to be found. Exhibit D only states the following:
    “Modular rough set operations shall commence no later
    than ______, 2004 and shall be substantially complete by ______,
    2004. Siding shall be substantially complete by ______, 2004.”
    Moreover, Winforge, in its brief, incorrectly claims that the
    district court determined that the express language of the
    (continued...)
    No. 10-3178                                              45
    excused Mod-U-Kraf’s performance of this obligation
    based on a number of critical factors. First, the Project
    plans were rejected by the City of Pigeon Forge
    in August 2005, which meant that the Project was at a
    permanent standstill. At that time, it was reasonable
    for Mod-U-Kraf to decide that it would be futile to con-
    struct the modular units knowing that they could never
    be used for the Project. Second, we think the district
    court did not err in its determination that the failure
    to secure the building permit from the City was due
    to Winforge’s failures, not Mod-U-Kraf’s or All Amer-
    ican’s failures. Winforge never hired a general contractor
    and never paid Mod-U-Kraf, despite being required to
    do so under the Agreement. Additionally, the evidence
    shows that Winforge failed to timely complete the
    designs for a number of building components that were
    its responsibility under the Agreement, as orally modified
    in June 2004, including the elevator, plumbing, HVAC,
    electrical, and mechanical systems. These designs were
    crucial to the approval process because they were
    required to be incorporated into Mod-U-Kraf’s plans
    before those plans could receive State approval. Deviation
    reports issued by the State showed that the deviations
    related largely to those components for which Winforge
    was responsible. Winforge’s failure to timely provide
    9
    (...continued)
    Agreement obligated Mod-U-Kraf to construct and deliver the
    modular units by December 31, 2004. The district court never
    stated that December 31, 2004 was Mod-U-Kraf’s deadline for
    constructing and delivering the units.
    46                                              No. 10-3178
    those designs resulted in delay in the approval process.
    Finally, the district court found that Winforge failed
    to timely submit a completed building permit applica-
    tion to the City, even though securing that permit was
    Winforge’s responsibility under Section 9 of the Agree-
    ment. The evidence indicates that, if Winforge had sub-
    mitted the application on time, the City would have
    approved it. Based on our interpretation of the contract
    and our consideration of the district court’s findings
    of fact, we find that the district court did not err in con-
    cluding that the delays in getting approval by the State
    were the fault of Winforge and not Mod-U-Kraf.
    Therefore, we find that, based on its findings of fact,
    the district court reasonably concluded that the Mod-U-
    Kraf’s failure to construct any modular units did not
    constitute a breach of the contract because its failure to
    do so was due to Winforge’s deficient performance of
    its obligations under the contract, not Mod-U-Kraf’s or
    All American’s deficiencies.
    CONCLUSION
    For the foregoing reasons, we A FFIRM the district court’s
    judgment.
    A FFIRMED
    7-30-12
    

Document Info

Docket Number: 10-3178

Citation Numbers: 691 F.3d 856, 2012 WL 3064726, 2012 U.S. App. LEXIS 15659

Judges: Easterbrook, Hamilton, Myerscough

Filed Date: 7/30/2012

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (30)

Browne v. Kline Tysons Imports, Inc. , 190 F. Supp. 2d 827 ( 2002 )

Grupo Dataflux v. Atlas Global Group, L. P. , 124 S. Ct. 1920 ( 2004 )

Steigleder v. McQuesten , 25 S. Ct. 616 ( 1905 )

Gilbert v. David , 35 S. Ct. 164 ( 1915 )

Denny v. Pironi , 11 S. Ct. 966 ( 1891 )

Frank Thomas v. General Motors Acceptance Corp. , 288 F.3d 305 ( 2002 )

Maryann J. Vershaw and Thomas Vershaw v. Northwestern ... , 979 F.2d 557 ( 1992 )

Lucy v. Zehmer , 196 Va. 493 ( 1954 )

Filak v. George , 267 Va. 612 ( 2004 )

Brown v. Brown , 53 Va. App. 723 ( 2009 )

Platinum Technology, Inc. v. Federal Insurance Co. , 282 F.3d 927 ( 2002 )

William Dilworth v. Underwood Dudley, Robert G. Bottoms, ... , 75 F.3d 307 ( 1996 )

Matterhorn, Inc. v. Ncr Corporation , 763 F.2d 866 ( 1985 )

Carnes Company v. Stone Creek Mechanical, Incorporated , 412 F.3d 845 ( 2005 )

Brunswick Leasing Corporation, a Pennsylvania Corporation v.... , 136 F.3d 521 ( 1998 )

SCHOOL BD. OF CITY OF NEWPORT NEWS v. Com. , 279 Va. 460 ( 2010 )

Occidental Fire & Casualty Company of North Carolina v. ... , 918 F.2d 1312 ( 1990 )

Christian v. Bullock , 215 Va. 98 ( 1974 )

Phillips v. Mazyck , 273 Va. 630 ( 2007 )

International Production Specialists, Inc. v. Schwing ... , 580 F.3d 587 ( 2009 )

View All Authorities »