Environmental Law & Policy Center v. United States Nuclear Regulatory Commission , 470 F.3d 676 ( 2006 )


Menu:
  •                            In the
    United States Court of Appeals
    For the Seventh Circuit
    ____________
    No. 06-1442
    ENVIRONMENTAL LAW AND POLICY CENTER,
    BLUE RIDGE ENVIRONMENTAL DEFENSE LEAGUE,
    NUCLEAR ENERGY INFORMATION SERVICE,
    NUCLEAR INFORMATION AND RESOURCE SERVICE,
    and PUBLIC CITIZEN,
    Petitioners,
    v.
    UNITED STATES NUCLEAR REGULATORY
    COMMISSION and THE UNITED STATES OF AMERICA,
    Respondents,
    and
    EXELON GENERATION COMPANY, LLC,
    Intervening Respondent.
    ____________
    Appeal from the United States Nuclear Regulatory Commission.
    No. CLI-05-29
    ____________
    ARGUED SEPTEMBER 29, 2006—DECIDED DECEMBER 5, 2006
    ____________
    Before FLAUM, EVANS, and WILLIAMS, Circuit Judges.
    FLAUM, Circuit Judge. In January 2004, the Environ-
    mental Law and Policy Center, Blue Ridge Environmental
    Defense League, Nuclear Energy Information Service,
    Nuclear Information and Resource Service, and Public
    2                                             No. 06-1442
    Citizen (collectively “the Environmental Groups”) inter-
    vened in Nuclear Regulatory Commission (“NRC”) proceed-
    ings regarding an Early Site Permit (“ESP”) for new
    nuclear power facilities in Clinton, Illinois. The Environ-
    mental Groups contended, among other things, that the
    ESP applicant and the NRC failed to consider various
    alternative energy sources. After permitting one conten-
    tion to proceed for further adjudication, the NRC’s Atomic
    Safety Licensing Board (“Board”) determined that the
    applicant’s consideration of alternative energy sources
    satisfied the requirements of the National Environmental
    Policy Act (“NEPA”) and granted summary disposition in
    favor of the applicant. The NRC affirmed the Board’s
    ruling and issued a dismissal order against the Environ-
    mental Groups. For the reasons set forth below, we affirm
    the decision of the NRC.
    I. BACKGROUND
    Federal Guidelines require any entity commencing
    construction of a nuclear power plant to obtain a construc-
    tion permit and an operating license. Permit applicants
    must submit information related to the plant’s design, a
    safety assessment of the site, and a report that assesses
    the environmental impact of the plant’s construction and
    operation. After reviewing a permit application, the NRC
    prepares an Environmental Impact Statement (“EIS”) for
    the construction permit. If an entity is not yet ready to
    construct a nuclear power plant but desires to seek early
    approval for a potential construction site, NRC regulations
    permit the person to apply for an ESP. The ESP applica-
    tion process resolves key site-related safety, environmen-
    tal, and emergency preparedness issues before the NRC
    authorizes (or declines to authorize) construction on that
    site. If granted, the ESP allows an applicant to main-
    tain a site for possible future construction of new nuclear
    No. 06-1442                                                 3
    power facilities for up to twenty years. Moreover, an
    applicant may renew the ESP for an additional twenty
    year term. However, an ESP does not authorize the holder
    to construct a nuclear plant. NRC regulations require
    applicants to obtain additional permits before commenc-
    ing such construction. Under 
    10 C.F.R. § 52.17
     and § 52.18,
    an ESP applicant must submit a complete environmental
    report and the NRC must issue an EIS that addresses all
    issues NEPA identifies regarding the construction and
    operation of a nuclear power plant on the proposed site,
    but a project’s benefits need not be discussed at the ESP
    stage. If the benefits are not discussed, they must be
    evaluated at later permit or licensing stages before
    construction may begin.
    Persons whose interests may be affected by an NRC
    licensing proceeding may file a request for a hearing and
    a petition to intervene. The petition must demonstrate
    the petitioner’s standing and contain at least one ad-
    missible “contention.” An admissible contention is one that
    provides sufficient information to show that a genuine
    dispute exists on a material issue of fact or law. 
    10 C.F.R. § 2.309
    (f)(1)(vi). Once the Board chooses to admit a
    contention, however, 
    10 C.F.R. § 2.1205
     and § 2.710
    provide that any party may file a motion for summary
    disposition of a contention, and a contention may be
    dismissed if the Board finds that no genuine dispute of
    material fact remains.
    In this case, Exelon Generation Company (“Exelon”)
    applied for an ESP, seeking approval for the construc-
    tion of one or two new nuclear reactors on an existing
    Clinton nuclear power station site. Exelon is a merchant
    generator, which means that it sells power on the open
    wholesale market. Unlike a traditional regulated utility,
    Exelon is not required to supply the energy needs of any
    particular area. In its ESP application, Exelon stated that
    it sought to reserve the proposed site for future large-scale,
    4                                               No. 06-1442
    baseload nuclear energy generation; that is, the creation of
    new energy intended to continuously produce electricity
    at or near full capacity, with high availability. Exelon
    intended to sell any new energy it generated on the open
    wholesale market.
    As part of its ESP application, Exelon submitted an
    environmental report. Although the report did not address
    the general need for power, it examined a number of
    alternative energy sources that could generate baseload
    power. Exelon evaluated alternative sources in terms of
    their ability to produce a baseload power equivalent to the
    amount of electricity that the proposed nuclear facility
    would produce. In its initial report, Exelon evaluated
    wind power coupled with energy storage mechanisms, solar
    power coupled with energy storage mechanisms, fuel cells,
    geothermal power, hydropower, burning wood water or
    other biomass, burning municipal solid water, burning
    energy crops, oil-fired plants, coal-fired plants, and natural
    gas-fired plants. The report concluded that several of the
    alternatives were not viable baseload energy alterna-
    tives because, for example, they involved insufficiently
    matured technology (fuel cells) or the state lacked suffi-
    cient available fuel supplies (geothermal power, hydro-
    power, woodwaste, and biomass). The report stated that
    wind and solar power, by themselves, were not reasonable
    baseload alternatives because they are intermittent
    energy sources and therefore cannot maintain contin-
    uous full rated capacity (the sun is not always shining, and
    the wind is not always blowing). In addition, the report
    concluded that power generated from natural gas and
    coal had greater environmental impacts on air quality
    than a nuclear plant.
    After Exelon submitted its environmental report, the
    Environmental Groups filed a contention alleging several
    shortcomings in Exelon’s evaluation of energy alternatives.
    In particular, the Environmental Groups alleged that
    No. 06-1442                                                 5
    Exelon had failed to adequately consider energy efficiency1
    or combinations of wind or solar power with fossil fueled
    plants. The Environmental Groups also claimed that
    Exelon used flawed information in its evaluation of wind
    and solar power. The Board rejected the energy efficiency
    claim, reasoning that energy efficiency is not an alter-
    native generation method that independent power genera-
    tors like Exelon typically employ. In addition, the Board
    reasoned, an energy efficiency analysis would essentially
    consider the need for power, an analysis that may be
    postponed until Exelon requests an actual construction
    permit. The Board acknowledged the Environmental
    Groups’ contention that Exelon had failed to consider
    combining wind or solar power with fossil fueled facilities
    and had used potentially flawed and outdated informa-
    tion regarding wind and solar power generation methods
    (“Contention 3.1”).
    After the Board recognized Contention 3.1, Exelon
    provided a report evaluating facilities that combined wind
    or solar power with fossil fuel. Exelon’s revised evaluation
    concluded that coal-fired facilities, gas-fired facilities, or
    facilities using a combination of these alternatives were
    not environmentally preferable to the proposed nuclear
    facility, because the combination would produce environ-
    mental impacts greater than or equal to a new nuclear
    facility.
    After reviewing the submitted information, the NRC
    issued a draft EIS, which evaluated a wide range of
    reasonable alternatives to nuclear baseload energy. The
    draft EIS reached conclusions similar to those reached
    1
    Energy efficiency was characterized by the Board as “demand
    side management,” i.e., measures aimed at reducing energy
    consumption. Exelon Generation Co., LLC, No. 52-007-ESP at
    21 (Atomic Safety and Licensing Bd. Jul. 28, 2005).
    6                                              No. 06-1442
    by Exelon. Specifically, the draft EIS found that
    individual wind and solar facilities were not sufficient on
    their own to generate baseload power. The draft EIS also
    concluded that, from an environmental standpoint, the
    nuclear facility would be preferable or equivalent to a
    combination facility using wind or solar power and fossil
    fuel. The draft also concluded that a new nuclear unit
    was preferable in terms of air resources, ecological re-
    sources, water resources, and aesthetics.
    After the NRC issued the draft EIS, Exelon submitted
    a motion for summary disposition of Contention 3.1. In its
    motion, Exelon asked the Board to find that Exelon’s
    response to the request for additional information cured
    its alleged failure to consider all reasonable alternatives.
    After the Board permitted the Environmental Groups to
    petition to amend Contention 3.1, it concluded that no
    genuine disputes of material fact remained. As a result,
    the board granted summary disposition of Contention 3.1
    in favor of Exelon and terminated the contested portion of
    the ESP proceeding. The Environmental Groups then
    appealed the Board’s decision to the NRC. The NRC
    affirmed the Board’s ruling, and the Environmental
    Groups appealed.
    II. DISCUSSION
    We consider three issues on appeal: whether the dis-
    missal of the Environmental Groups from NRC proceed-
    ings constitutes a final order under 
    28 U.S.C. § 2342
    ;
    whether the Board properly dismissed the Environ-
    mental Groups’ contention that Exelon failed to consider
    energy efficiency alternatives; and whether the Board
    properly granted summary disposition against the Envi-
    ronmental Groups on Contention 3.1.
    No. 06-1442                                                7
    A. Jurisdiction
    As a threshold matter, the NRC argues that this Court
    should not consider the Environmental Groups’ claims
    because the NRC’s decision to dismiss them from its
    proceedings is not a final order for purposes of 
    28 U.S.C. § 2342
    (4). Under the Hobbs Act, this Court’s jurisdiction
    is limited to review of final orders entered by the NRC in
    a proceeding to grant any license or construction permit.
    See id.; 
    42 U.S.C. § 2239
    . According to the NRC, it has not
    yet issued the ESP to Exelon, and, as such, there is no
    final order to appeal. In fact, the Board must independ-
    ently review the final EIS (which was published on July
    28, 2006), and the NRC must then consider it when
    deciding whether to issue an ESP. The NRC further
    states that the Environmental Groups will have addi-
    tional opportunities to raise NEPA-related contentions
    and obtain a hearing before the NRC’s final decision on
    whether to issue the ESP. Therefore, the NRC asserts, this
    lawsuit is premature.
    The Environmental Groups, on the other hand, maintain
    that the NRC’s ruling was final as it applies to them,
    because it terminated their participation in the ESP
    proceedings. The Environmental Groups liken the NRC’s
    order to a denial of a motion to intervene, which is immedi-
    ately appealable. See, e.g., Fla. Power & Light Co. v.
    Lorion, 
    470 U.S. 729
     (1985); In re UAL Corp., 
    408 F.3d 847
    , 849 (7th Cir. 2005) (holding that denial of motion to
    intervene is appealable immediately because it finally
    concludes the putative intervenor’s rights). The Environ-
    mental Groups argue that they are entitled to chal-
    lenge the NRC and Board orders now rather than at some
    later time, because those orders deprived them of the right
    to further participate in the proceedings. Additionally, they
    argue that the agency’s review of alternatives is essentially
    complete, because there is no reason to believe that the
    8                                             No. 06-1442
    NRC’s analysis will change between now and the issuance
    of the ESP.
    We agree with the Environmental Groups. Although the
    Board initially permitted the Environmental Groups to
    intervene, the order granting summary disposition in
    favor of Exelon concluded the intervention. This Court has
    noted that, in determining the finality of an order, the
    relevant considerations include “whether the process of
    administrative decisionmaking has reached a stage where
    judicial review will not disrupt the orderly process of
    adjudication and whether rights or obligations have
    been determined or legal consequences will flow from the
    agency action.” See Rosenthal & Co. v. Commodity Futures
    Trading Comm’n, 
    614 F.2d 1121
    , 1127 (7th Cir. 1980)
    (citing Port of Boston Marine Terminal Ass’n v.
    Rederiaktiebolaget Transatlantic, 
    400 U.S. 62
    , 71 (1970)).
    Although as of the date of oral arguments, the NRC had
    not yet granted the ESP, the Board’s order terminated the
    Environmental Groups’ involvement in the agency pro-
    ceeding. Therefore, it is clear that the Board’s order
    determined the Environmental Groups’ rights and legal
    consequences flowed from that determination. Moreover,
    since the final EIS already has been published, our re-
    view will not disrupt the process of adjudication. Conse-
    quently, the order is final and appealable under 
    28 U.S.C. § 2342
    .
    B. Failure to Consider Energy Efficiency
    Section 101 of NEPA declares a broad national commit-
    ment to protecting and promoting environmental quality.
    
    42 U.S.C. § 4331
    ; Robertson v. Methow Valley Citizens
    Council, 
    490 U.S. 332
    , 348 (1989). Section 102 of the act
    seeks to further those goals by prescribing procedures that
    federal agencies must follow when recommending or
    reporting on major federal actions “significantly affecting
    No. 06-1442                                                9
    the quality of the human environment.” See 
    42 U.S.C. § 4332
    ; Robertson, 
    490 U.S. at 348
    . The required report or
    recommendation, commonly called an Environmental
    Impact Statement (“EIP”), must address the following in
    detail:
    (i) the environmental impact of the proposed action,
    (ii) any adverse environmental effects which cannot
    be avoided should the proposal be implemented,
    (iii) alternatives to the proposed action,
    (iv) the relationship between local short-term uses of
    man’s environment and the maintenance and enhance-
    ment of long-term productivity, and
    (v) any irreversible and irretrievable commitments of
    resources which would be involved in the proposed
    action should it be implemented.
    See 
    42 U.S.C. § 4332
    ; Robertson, 
    490 U.S. at 348
    . Although
    NEPA requires detailed consideration of the environmental
    consequences of federal projects, it does not mandate
    particular results. Highway J Citizens Group v. Mineta,
    
    349 F.3d 938
    , 953 (7th Cir. 2003). It simply prescribes the
    necessary process. 
    Id.
    This Court’s review of agency action under NEPA is
    governed by the Administrative Procedure Act (“APA”).
    Mineta, 
    349 F.3d at 952
    . The APA instructs courts to set
    aside agency action only if it is “arbitrary, capricious, an
    abuse of discretion, or otherwise not in accordance with the
    law.” 
    5 U.S.C. § 706
    (2)(A). Under this standard, although
    a reviewing court’s inquiry is “searching and careful . . .
    the ultimate standard of review is a narrow one.” Mineta,
    
    349 F.3d at 952
     (citations and quotations omitted). A
    reviewing court must make two inquiries: 1) whether the
    agency’s decision was based on a consideration of the
    relevant factors; and 2) whether the agency has made a
    10                                             No. 06-1442
    clear error in judgment. 
    Id. at 952-53
    . If an agency has
    considered the proper factors and makes a factual determi-
    nation regarding the significance of environmental im-
    pacts, that determination implicates substantial agency
    expertise and is entitled to deference. 
    Id. at 953
    . This
    Court cannot substitute its own judgment for that of the
    agency as to the environmental consequences of its actions.
    
    Id.
     In fact, in applying the arbitrary and capricious
    standard, this Court’s only role is to ensure that the
    agency has taken a hard look at environmental conse-
    quences. 
    Id.
    The Environmental Groups challenge two aspects of the
    Board’s decision to decline consideration of energy effi-
    ciency alternatives. First, they contend that the Board
    unnecessarily excluded reasonable alternatives like
    energy efficiency measures by adopting Exelon’s goal of
    generating baseload energy. In any case, the Environmen-
    tal Groups argue that the Board should have considered
    energy efficiency alternatives in a “need for power”
    analysis—an analysis that the Board refused to conduct
    altogether.
    The Environmental Groups claim that the Board’s
    rejection of reasonable energy efficiency alternatives is
    contrary to the “searching inquiry into alternatives”
    required by NEPA. See Simmons v. U.S. Army Corps of
    Eng’rs, 
    120 F.3d 664
    , 666 (7th Cir. 1997). We have held
    that blindly adopting the applicant’s goals is “a losing
    proposition” because it does not allow for the full con-
    sideration of alternatives required by NEPA. 
    Id. at 669
    .
    NEPA requires an agency to “exercise a degree of skepti-
    cism in dealing with self-serving statements from a prime
    beneficiary of the project” and to look at the general goal
    of the project rather than only those alternatives by which
    a particular applicant can reach its own specific goals. 
    Id.
    In Simmons, the City of Marion, Illinois sought to build
    a new water reservoir to address its need for water. 120
    No. 06-1442                                              11
    F.3d at 666. Marion and the Army Corps of Engineers
    defined the project’s purpose as “supplying two users . . .
    from a single source—namely a new lake.” Id. at 667.
    Accordingly, when the Corps prepared an EIS, it confined
    its analysis of reasonable alternatives under NEPA to
    single-source alternatives. Id. at 667-68. The Court
    determined that the Corps and Marion had defined the
    project’s purpose too narrowly. Id. The common problem
    faced by Marion and a neighboring district was “a thirst
    for water.” Id. at 667. As such, the goal of the project
    was to quench that thirst, and it was error for the Corps
    to look into only single -source alternatives. Id. Therefore,
    we held, the procedures undertaken by the Corps did not
    satisfy NEPA because the EIS did not examine the full
    range of reasonable alternatives, i.e., multiple-source
    alternatives. Id. The Environmental Groups argue that
    the instant case is analogous to Simmons because the
    Board “stacked the deck” against reasonable alterna-
    tives by adopting Exelon’s limited business purpose of
    generating baseload power. According to the Environmen-
    tal Groups, this purpose favors Exelon’s proposed new
    nuclear plant by rendering energy efficiency alternatives
    inconsistent with the project’s goal.
    Exelon and the NRC attempt to distinguish Simmons.
    They claim Simmons stands for the simple proposition
    that the purpose of a project cannot be so narrow as to
    define reasonable alternatives out of existence. In any
    case, they contend, Simmons does not require an agency
    to disregard a private applicant’s purpose for a project
    if that purpose is sufficiently broad to allow consideration
    of reasonable alternatives. In affirming the Board’s
    decision, the NRC held that it had not violated Simmons
    because Exelon considered numerous alternatives to
    meet the project’s general goals:
    It would be as if in Simmons the Seventh Circuit
    ordered the Army not only to consider alternate ways
    12                                             No. 06-1442
    to supply more water but also to examine whether
    Marion and the water district could reduce their need
    for water by prohibiting lawn-watering or requiring
    low-flow toilets. Nothing in Simmons requires a NEPA
    inquiry so far afield from the original proposal.
    Exelon Generation Co., LLC, Nuclear Reg. Rep. 31,493,
    
    2005 WL 4131570
     at *4 (Dec. 12, 2005). In other words,
    according to the NRC, just as Simmons did not require the
    Army Corps to reconsider the town’s “need for water,” it
    did not require the Board to consider alternatives to
    generating new energy. The NRC found such an inquiry
    particularly useless given that Exelon dealt only in the
    sale of wholesale power and had neither the authority nor
    the incentive to implement energy efficiency measures.
    The Board’s decision relied on case law supporting the
    proposition that a reviewing agency can take an applicant’s
    goals for a project into account. For example, in Citizens
    Against Burlington, Inc. v. Busey, the court noted that an
    agency’s evaluation of reasonable alternatives is “shaped
    by the application at issue.” 
    938 F.2d 190
    , 199 (D.C. Cir.
    1991). The Board also noted that where a federal agency is
    not the sponsor of a project, the “consideration of alterna-
    tives may accord substantial weight to the preferences of
    the applicant and/or sponsor in the siting and design of the
    project.” City of Grapevine v. Dep’t of Transp., 
    17 F.3d 1502
    , 1506 (D.C. Cir. 1994).
    We are persuaded by the Board’s analysis. Because
    Exelon was a private company engaged in generating
    energy for the wholesale market, the Board’s adoption of
    baseload energy generation as the purpose behind the
    ESP was not arbitrary, capricious, an abuse of discretion
    or otherwise not in accordance with law. See APA
    § 706(2)(A). The adopted purpose was broad enough to
    permit consideration of a host of energy generating
    alternatives. Moreover, it was reasonable for the Board
    No. 06-1442                                                13
    to conclude that NEPA did not require consideration of
    energy efficiency alternatives when Exelon was in no
    position to implement such measures. The Environmental
    Groups further contend that the Board should have
    independently analyzed energy efficiency alternatives,
    regardless of the project’s stated purpose because NEPA
    requires consideration of the need for power as part of
    any alternatives analysis. The NRC responds that the
    Board equated analysis of energy efficiency alternatives to
    a “need for power” analysis and that under NRC regula-
    tions 
    10 C.F.R. §§ 52.17
    (a)(2) and 52.18, Exelon and the
    NRC did not need to conduct a “need for power” analysis
    at the ESP stage. Instead, the Board reasoned, it could
    defer that analysis until a later combined licensing
    proceeding.
    Under NRC regulations, an applicant may defer an
    analysis of the need for power until a combined license
    application, when construction will be authorized. See 
    10 C.F.R. § 52.21
    . Because an ESP does not authorize con-
    struction, the evaluations conducted at the ESP stage
    are intended to provide early resolution to some—but not
    all—of the environmental issues. 
    10 C.F.R. §§ 52.79
    (a)(1)
    and 52.89 (stating that “any significant environmental
    issue not considered” at the ESP stage must be ad-
    dressed when the holder of an ESP applies to commence
    construction). Although the Environmental Groups contend
    that the NRC regulations violate NEPA, the agency
    regulations at issue are not inconsistent with the environ-
    mental law, because all relevant issues will eventually be
    considered. Courts have permitted agencies to defer
    certain issues in an EIS for a multistage project when
    detailed useful information on a given topic is not “mean-
    ingfully possible” to obtain, and the unavailable informa-
    tion is not essential to determination at the earlier stage.
    See, e.g., County of Suffolk v. Sec’y of the Interior, 
    562 F.2d 1368
    , 1378 (2d Cir. 1977). In this case, it is especially
    14                                             No. 06-1442
    reasonable to defer the “need for power” analysis to a later
    stage considering that construction on the nuclear reactor
    could begin as late as forty years from now. The need for
    power could vary considerably over that time period, so
    any analysis at this stage is speculative at best. The NRC,
    in its broad discretion to implement procedural rules under
    the APA, see, e.g., Vermont Yankee Nuclear Power Corps.
    v. Natural Res. Def. Council, Inc., 
    435 U.S. 519
    , 543-44
    (1978), deferred analysis that would be merely speculative
    at such an early stage. That decision was not arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance with the law. We therefore affirm the NRC’s
    dismissal of the Environmental Groups’ energy efficiency
    contention.
    C. Summary Disposition of Contention 3.1
    The final claim that the Environmental Groups advance
    is that the Board should not have granted summary
    disposition in favor of Exelon regarding Contention 3.1.
    The Environmental Groups argue that the NRC should
    have held a full evidentiary hearing in order to conduct
    a rigorous exploration and objective evaluation of clean
    energy alternatives and should have considered the
    comparative costs of the nuclear plant and the clean
    energy alternatives. They also claim that the NRC violated
    NEPA by distorting the combinations of clean energy
    alternatives.
    It is true that NEPA requires an agency to “rigorously
    explore and objectively evaluate all reasonable alterna-
    tives,” 
    40 C.F.R. § 1502.14
    (a), and to take a “hard look” at
    the environmental impacts of the proposed action and
    its alternatives. Robertson, 
    490 U.S. at 350
    . However, as
    this Court noted in Van Abbema v. Fornell, “it is not our
    role to second-guess. We merely consider whether the
    [agency] followed required procedures, evaluated relevant
    No. 06-1442                                            15
    factors and reached a reasoned decision.” 
    807 F.2d 633
    ,
    636 (7th Cir. 1986). The Environmental Groups’ claims
    regarding Contention 3.1 go to the substantive judg-
    ments made by the Board and the NRC—judgments this
    Court will defer to as long as they satisfy NEPA proce-
    dures and are not clearly wrong.
    The Board’s 57-page memorandum and order granting
    summary disposition in favor of Exelon demonstrates
    that the board rigorously explored all reasonable alterna-
    tives and took a hard look at the environmental impacts
    of the proposed action. See Exelon Generation Co., LLC,
    No. 52-007-ESP (Atomic Safety and Licensing Bd. Jul. 28,
    2005). The Board addressed the Environmental Groups’
    concerns point by point, carefully considering each issue
    and providing reasons for each decision it made. It is
    unnecessary to repeat the Board’s analysis here. Whether
    or not this court would have made the same substantive
    judgment is irrelevant so long as the decision is not
    arbitrary. It is clear that the Board satisfied NEPA’s
    procedural requirements and rendered a decision that
    thoughtfully considered all reasonable alternatives. We
    therefore affirm the decisions of the Board and the NRC.
    III. CONCLUSION
    For the foregoing reasons, we AFFIRM the NRC and its
    Board on all matters.
    A true Copy:
    Teste:
    ________________________________
    Clerk of the United States Court of
    Appeals for the Seventh Circuit
    USCA-02-C-0072—12-5-06