Northeastern Rural Electric Membership Corp. v. Wabash Valley Power Ass'n , 707 F.3d 883 ( 2013 )


Menu:
  •                              In the
    United States Court of Appeals
    For the Seventh Circuit
    No. 12-2037
    N ORTHEASTERN R URAL E LECTRIC
    M EMBERSHIP C ORPORATION,
    Plaintiff-Appellant,
    v.
    W ABASH V ALLEY P OWER A SSOCIATION, INC.,
    Defendant-Appellee.
    Appeal from the United States District Court
    for the Southern District of Indiana, Indianapolis Division.
    No. 1:12-cv-00144-SEB-DML—Sarah Evans Barker, Judge.
    A RGUED S EPTEMBER 25, 2012—D ECIDED F EBRUARY 22, 2013
    Before K ANNE, T INDER, and H AMILTON, Circuit Judges.
    H AMILTON, Circuit Judge. This appeal tests the
    boundaries of federal-question subject matter jurisdic-
    tion. The issue is whether a claim for breach of a long-
    term requirements contract for wholesale electricity
    arises under federal law or state law. We conclude that
    the claim arises under state law, that the district court
    2                                             No. 12-2037
    therefore lacked jurisdiction to enter its preliminary
    injunction, and that the case should be remanded to
    state court.
    Defendant Wabash Valley Power Association, Inc.
    (Wabash Valley) is a not-for-profit power generation
    cooperative. Plaintiff Northeastern Rural Electric Mem-
    bership Corporation (Northeastern) is a member of
    Wabash Valley that purchases electricity from Wabash
    Valley and resells it to consumers. In 1977, Northeastern
    and Wabash Valley entered into a wholesale power supply
    contract under which Northeastern agreed to purchase
    all of its electric power from Wabash Valley for the
    next forty years. The contract provided that Northeastern
    would pay for the electricity at rates to be set by the
    Wabash Valley board of directors “[s]ubject to the
    approval of the Public Service Commission of Indiana,”
    though the key contractual provision also stated that
    revised rates would not be effective unless approved
    by the ambiguously phrased “applicable regulatory
    authorities,” as well as the administrator of the fed-
    eral Rural Electrification Administration.
    On January 5, 2012, Northeastern filed this suit in
    Indiana state court seeking a declaratory judgment
    that Wabash Valley materially breached the 1977
    contract by taking action in 2004 that had the effect of
    transferring regulation of its rates from the Indiana Com-
    mission to the Federal Energy Regulatory Commission
    No. 12-2037                                                  3
    (FERC).1 Northeastern contends that the “applicable
    regulatory authorities” in the 1977 contract are limited to
    the Indiana Commission, while Wabash Valley believes
    that the contract language is flexible enough to permit
    rate regulation by either regulatory body.
    Wabash Valley removed the case to federal court
    under 
    28 U.S.C. § 1441
    (a) on the theory that the claim
    for breach of contract necessarily arises under the
    Federal Power Act (FPA), 16 U.S.C. §§ 791a et seq. North-
    eastern moved to remand to state court while Wabash
    Valley moved for a preliminary injunction to prevent
    Northeastern from ceasing performance under the con-
    tract. The district court denied Northeastern’s motion
    for remand and granted Wabash Valley’s motion for a
    preliminary injunction, agreeing with Wabash Valley
    that federal jurisdiction exists because Northeastern’s
    suit is “a collateral attack on the FERC-filed rate,” and
    thus raises a question of federal law. Northeastern has
    appealed both rulings, arguing that the suit does not
    attack a filed rate.
    We have appellate jurisdiction to consider the prelimi-
    nary injunction under 
    28 U.S.C. § 1292
    (a)(1). The appeal of
    the district court’s denial of remand also fits within
    the narrow doctrine of pendent appellate jurisdiction
    because the preliminary injunction appeal presents pre-
    1
    In 1987, the Public Service Commission of Indiana was
    renamed the Indiana Utility Regulatory Commission. We
    refer to this continuing regulatory body as simply “the Indiana
    Commission.”
    4                                               No. 12-2037
    cisely the same question of subject matter jurisdiction as
    the motion to remand. The denial of a motion to remand
    ordinarily cannot be appealed, see 
    28 U.S.C. § 1447
    (d),
    but here the denial of remand is “inextricably inter-
    twined” with the appealable preliminary injunction. See,
    e.g., Research Automation, Inc. v. Schrader-Bridgeport Int’l,
    Inc., 
    626 F.3d 973
    , 977 (7th Cir. 2010) (exercising pendent
    appellate jurisdiction over non-appealable transfer
    order that presented same issue as appealable denial of
    injunction to block litigation in transferee district); cf.
    Abelesz v. Magyar Nemzeti Bank, 
    692 F.3d 661
    , 669 (7th
    Cir. 2012) (holding that appellate jurisdiction over denial
    of motion to dismiss based on foreign sovereign im-
    munity defense did not support pendent appellate juris-
    diction over rejection of separate statute of limitations
    defense).
    Turning to the merits of the appeal, we agree with
    Northeastern and conclude that the federal courts lack
    subject matter jurisdiction over this case. North-
    eastern’s claim is limited to a construction of the parties’
    rights under the 1977 contract and does not necessarily
    raise a question of federal law. To prove its claim, North-
    eastern needs to show only that it had a valid contract
    and that Wabash Valley’s voluntary action to transfer
    regulatory jurisdiction from the Indiana Commission
    to FERC breached the contract. Neither of these elements
    necessarily raises a question of federal law. While North-
    eastern may eventually attempt to use a favorable state
    court judgment to seek FERC’s permission to terminate
    its obligations under the tariff filed with FERC, North-
    eastern agrees that such relief cannot be achieved in
    No. 12-2037                                                  5
    this suit. If Northeastern prevails on the merits of its
    claim, it will then need to seek that relief directly
    from FERC. Northeastern has therefore pled a claim
    that does not arise under federal law. We vacate the pre-
    liminary injunction and order remand of this action
    to state court.
    I. Regulatory, Factual, and Procedural Background
    A. Wholesale Electrical Power Regulation
    Regulation of the electricity market is divided between
    federal and state regulators. In general, the federal gov-
    ernment through FERC regulates the interstate whole-
    sale electricity market, while the states regulate the
    retail sale of this power to consumers.
    FERC regulates the sale of wholesale electricity
    through rate regulation. Under the Federal Power Act,
    public utilities under FERC jurisdiction may charge
    only “just and reasonable” rates. 16 U.S.C. § 824d(a). The
    Act grants FERC the exclusive authority to enforce
    this provision by regulating the rates, terms, and condi-
    tions governing the interstate transmission and sale of
    wholesale energy in interstate commerce. See Mississippi
    Power & Light Co. v. Mississippi ex rel. Moore, 
    487 U.S. 354
    , 371 (1988). In practice, FERC enforces this statutory
    provision through tariff filing. Public utilities regulated
    by FERC are required to file tariffs that detail rates
    and terms of service. 16 U.S.C. § 824d(c); 
    18 C.F.R. § 35.1
    (a).
    The basis for the filed tariff is often a contract negoti-
    ated privately between wholesaler and distributor that
    6                                                 No. 12-2037
    is then submitted to FERC. FERC will then accept the
    contract as the basis for the rate as long as the terms are
    “just and reasonable” and not discriminatory. Once a
    rate is filed, the rate takes effect unless FERC initiates a
    hearing to inquire into the reasonableness of the rate.
    16 U.S.C. § 824d(e). If a utility or customer is unhappy
    with a proposed term, it may protest the rate filing with
    FERC or seek to intervene in any proceedings. 
    18 C.F.R. § 385.211
    (a) (establishing general rule that “[a]ny
    person may file a protest to object to . . . [a] tariff or rate
    filing”); 18 C.F.R § 385.214 (requirements for interven-
    tion). An aggrieved party may seek judicial review
    before a federal court of appeals within 60 days. 16 U.S.C.
    § 825l(b). Once a rate is accepted, however, the parties
    to the rate filing are bound to the terms of the filed rate
    and may not change them without giving notice and
    making a new filing with FERC. 16 U.S.C. § 824d(d);
    
    18 C.F.R. § 35.15
     (requiring notice and filing with FERC
    to cancel or terminate a rate schedule). This process
    provides the exclusive method for reviewing the rea-
    sonableness of the terms of filed rates.
    FERC’s exclusive jurisdiction over the reason-
    ableness of rates under its jurisdiction is protected by
    the “filed-rate doctrine.” The filed-rate doctrine prohibits
    courts — both state and federal — from questioning a
    rate that has been filed with a federal regulator, except
    through the review process just noted. See Montana-Dakota
    Utilities Co. v. Northwestern Public Service Co., 
    341 U.S. 246
    , 251-52 (1951). The doctrine has been expanded to
    include the terms of the tariff that affect the rate and
    state regulations that might indirectly achieve the same
    No. 12-2037                                                 7
    result. See Natural Gas Co. v. State Corporation Comm’n
    of Kan., 
    372 U.S. 84
    , 91 (1963) (applying doctrine to bar
    state order allocating purchases among numerous wells
    in same gas field). By this reasoning, if Northeastern
    had brought this action as a suit for damages or to
    enjoin the rate it pays under the filed tariff, the action
    would be barred by the filed-rate doctrine. An award of
    damages would require a court to determine that the
    rate paid was unreasonable, and any damages paid in
    such a suit would effectively alter the rate Northeastern
    paid for electricity under the FERC tariff during the
    period in question.
    FERC would have had regulatory authority over the
    original 1977 Northeastern-Wabash Valley contract but
    for a relevant exception to FERC’s jurisdiction. While
    the Federal Power Act generally grants FERC exclusive
    jurisdiction over the regulation of wholesale power,
    FERC lacks jurisdiction over utilities that are regulated
    by the Rural Electrification Administration (REA), an
    agency that has promoted rural electrification by
    providing loans for infrastructure development. See
    Dairyland Power Cooperative, 37 F.P.C. 12 (1967) (inter-
    preting 
    16 U.S.C. § 824
    (f) to hold that FERC predecessor,
    the Federal Power Commission, lacked jurisdiction
    over wholesale rates charged by power cooperatives
    financed by REA); Salt River Project Agricultural Improve-
    ment & Power District v. FPC, 
    391 F.2d 470
    , 474-77 (D.C. Cir.
    1968) (agreeing with FPC’s holding in Dairyland Power);
    see also Wabash Valley Power Ass’n, Inc. v. Rural Electrifica-
    tion Admin., 
    903 F.2d 445
    , 448 (7th Cir. 1990) (noting
    the Dairyland Power rule). Unlike FERC, the REA does
    8                                                  No. 12-2037
    not have exclusive jurisdiction over the regulation of
    wholesale electric rates. This means that state reg-
    ulators may have jurisdiction to regulate wholesale
    power companies that are financed by the REA.
    B. The 1977 Contract
    In 1977, Northeastern and Wabash Valley entered into
    a wholesale power supply contract. Wabash Valley
    was within the REA’s jurisdiction at that time due
    to outstanding REA debt, so state rate regulation was
    permissible. See generally Wabash Valley Power Ass’n, Inc.
    v. Rural Electrification Admin., 
    988 F.2d 1480
     (7th Cir.
    1993). The contract provided that Northeastern would
    purchase all of its electric power and energy from
    Wabash Valley for the next forty years.2 Since future
    price is uncertain, such long-term contracts typically
    specify a procedure for changing the rate over time.
    The 1977 contract provided for the rate to be changed in
    the following manner:
    2
    The original contract has been amended a number of times
    to alter the duration of the contract term and to provide alter-
    native avenues for Northeastern to terminate its dealings
    with Wabash Valley. Because Northeastern is alleging a breach
    of the 1977 contract, and because we conclude that this claim
    is not subject to federal court jurisdiction, we do not address
    the significance of these amendments. Whether such amend-
    ments ratified the alleged breach or superseded the 1977
    contract would not affect the jurisdictional question. These
    are questions for the state courts to consider.
    No. 12-2037                                                 9
    4. Rate. Subject to the approval of the Public Service
    Commission of Indiana:
    ...
    (b) . . . The Member agrees that the rate, from time
    to time, established by the Board of Directors of
    [Wabash Valley] shall be deemed to be substituted
    for the rate herein provided and agrees to pay
    for electric power and energy furnished by
    [Wabash Valley] to it hereunder after the effective
    date of any such revision at such revised rates;
    provided, however, that no such revision shall
    be effective unless approved by applicable regulatory
    authorities and the Administrator [of the Rural
    Electrification Administration].
    S.A. 72-73 (emphasis added).
    The parties disagree over the scope of the phrase
    “applicable regulatory authorities.” Northeastern be-
    lieves that “Subject to the approval of the Public Service
    Commission of Indiana” at the beginning of subsection 4
    limits the applicable regulatory authority to the Indiana
    Commission. Wabash Valley believes that the term was
    intentionally left undefined to allow for a change in
    the regulator. Nevertheless, the parties agree that
    the Indiana Commission was the applicable regulatory
    authority when the contract was signed in 1977. As
    noted, state regulation was permissible because
    Wabash Valley still had REA debt.
    In 2004, however, Wabash Valley decided to repay its
    REA debt early. Repaying the REA debt meant that
    10                                                  No. 12-2037
    Wabash Valley would become subject to the exclusive
    regulatory jurisdiction of FERC. While Wabash Valley
    was considering the move to FERC regulation, North-
    eastern sent a letter to Wabash Valley to object, con-
    tending that a move to FERC would breach the 1977
    contract. Wabash Valley disagreed and filed a rate sched-
    ule with FERC consisting of a formula rate tariff and the
    1977 contract on April 30, 2004.3 FERC then assumed
    exclusive jurisdiction over the rates, terms, and conditions
    of the wholesale electricity services provide by Wabash
    Valley. Federal law barred the Indiana Commission from
    3
    Midwest ISO, another member of Wabash Valley, challenged
    this initial rate-filing in front of FERC. Midwest argued that
    the filing should not be accepted by FERC because the
    Michigan Commission (the alleged applicable regulatory
    authority under the Midwest-Wabash Valley contract) had not
    approved the filing. FERC rejected this objection on June 29,
    2004. Wabash Valley Power Ass’n, Inc., 
    107 FERC ¶ 61327
     (June 29,
    2004). In a decision that is not entirely clear, FERC concluded
    that the language of the 1977 Midwest-Wabash Valley contract
    conditioning rate changes on approval by the applicable
    regulatory authorities did not “preclude application of the
    proposed Formula Rate Tariff to Midwest under that con-
    tract.” 
    Id. at *3
    . It is unclear whether FERC concluded that this
    would not be a breach of the 1977 contract, or whether
    the contract was not a bar to regulation due to FERC’s statu-
    tory authority. Any uncertainty about the grounds of FERC’s
    decision does not matter for our jurisdictional inquiry
    because collateral estoppel and res judicata are affirmative
    defenses and do not provide a basis for federal jurisdiction.
    Rivet v. Regions Bank of Louisiana, 
    522 U.S. 470
    , 478 (1998).
    No. 12-2037                                                 11
    continuing to regulate the rates charged. See United
    States v. Public Utilities Comm’n of Cal., 
    345 U.S. 295
    , 308
    (1953) (observing that the Federal Power Act prohibits
    state regulation of wholesale electric rates within Federal
    Power Commission — now FERC — jurisdiction).
    C. The Dispute and Prior Proceedings
    Northeastern proceeded to purchase power from
    Wabash Valley until December 2010. On December 27,
    Northeastern sent Wabash Valley a notice of material
    breach based on the change in regulatory authority
    that took place in 2004 and demanded that Wabash
    Valley cure by restoring rate regulation by the Indiana
    Commission.4
    Following failed negotiations, Wabash Valley filed a
    declaratory action with FERC seeking an order
    that: (1) FERC “has exclusive jurisdiction over the
    Commission-approved Formula Rate Tariff;” (2) any
    “changes to the rates paid by [Northeastern] under the
    Tariff . . . are subject to approval of the applicable regula-
    tory authorities; and (3) the Commission is the applicable
    regulatory authority with jurisdiction over the rates
    [Northeastern] pays under the Tariff . . . .” Wabash Valley
    Power Ass’n, Inc., 
    137 FERC ¶ 61148
    , at *1 (Nov. 21,
    2011). In response, Northeastern agreed with the well-
    4
    In its brief Northeastern also details several disputes it had
    with Wabash Valley from 2004 through 2010, but these are not
    material to the jurisdictional issue.
    12                                            No. 12-2037
    established law that FERC had jurisdiction over a filed
    tariff and argued that the only dispute was over whether
    Wabash Valley was in material breach of contract.
    FERC granted Wabash Valley’s petition and concluded
    that “since 2004, the Commission has had exclusive
    jurisdiction over the Tariff” and that any changes to the
    rates are subject to FERC approval. 
    Id. at *5
    . Because
    Wabash Valley sought only a “jurisdictional declara-
    tion,” FERC considered Northeastern’s claim for breach
    of contract to be “beyond the scope” of the proceeding.
    
    Id. at *6
    . Northeastern then filed the present case in
    state court arguing that the change in regulatory
    authority was a material breach of the 1977 contract.
    Wabash Valley then removed to the federal district
    court, which issued its preliminary injunction and
    denied remand to state court.
    II. Subject Matter Jurisdiction
    The federal courts are courts of limited jurisdiction,
    and we have an obligation at each stage of the pro-
    ceedings to ensure that we have subject matter jurisdic-
    tion over the dispute. Where, as here, a party challenges
    the removal of a case to federal court, we review de novo
    a district court’s denial of a motion for remand, at least
    in the absence of disputed factual issues. Chase v. Shop
    ‘N Save Warehouse Foods, Inc., 
    110 F.3d 424
    , 427 (7th
    Cir. 1997).
    A case filed in state court may be removed to federal
    court only when the case originally could have been
    No. 12-2037                                                13
    filed in federal court. 
    28 U.S.C. § 1441
    (a). Because the
    parties here are both citizens of Indiana, diversity of
    citizenship is not present, and the propriety of removal
    depends on the existence of a federal question that
    could confer jurisdiction under 
    28 U.S.C. § 1331
     or
    another statutory grant of jurisdiction. See Caterpillar Inc.
    v. Williams, 
    482 U.S. 386
    , 392 (1987). It is well established
    that such a federal question must be apparent on the
    face of the plaintiff’s well-pleaded complaint. Louisville &
    Nashville R.R. Co. v. Mottley, 
    211 U.S. 149
    , 152 (1908); Gully
    v. First Nat’l Bank, 
    299 U.S. 109
    , 112-13 (1936). Federal
    defenses to a well-pleaded complaint, such as preemption
    or preclusion, do not provide a basis for removal. See
    Rivet v. Regions Bank of Louisiana, 
    522 U.S. 470
    , 478 (1998).
    Plaintiffs, however, may not avoid removal to federal
    court by omitting necessary federal questions from
    their complaints through artful pleading. While plain-
    tiffs are entitled to omit federal claims from their com-
    plaints so as to avoid federal jurisdiction, they may not
    omit necessary federal elements of an included claim.
    See Franchise Tax Bd. of State of Cal. v. Constr. Laborers
    Vacation Trust for Southern Cal., 
    463 U.S. 1
    , 22 (1983). Put
    another way, a “plaintiff cannot frustrate a defendant’s
    right to remove by pleading a case without reference to
    any federal law when the plaintiff’s claim is necessarily
    federal.” 14B Charles Alan Wright & Arthur R. Miller,
    Federal Practice and Procedure § 3722 (4th ed.). When a
    plaintiff omits from its pleadings federal questions that
    are necessary elements of a claim, courts will read the
    necessary federal elements into the complaint. See Hays
    v. Cave, 
    446 F.3d 712
    , 713 (7th Cir. 2006) (“What is true
    14                                             No. 12-2037
    is that if federal law creates the claim on which the
    plaintiff is suing, the fact that he has omitted from his
    complaint any reference to federal law will not defeat
    removal.”). Similarly if federal law preempts all state
    causes of action in an area of law, under the complete
    preemption doctrine, we treat any state law claim as
    necessarily arising under federal law. See Beneficial
    Nat’l Bank v. Anderson, 
    539 U.S. 1
    , 8 (2003) (“When the
    federal statute completely pre-empts the state-law cause
    of action, a claim which comes within the scope of that
    cause of action, even if pleaded in terms of state law,
    is in reality based on federal law.”)
    With this background in mind, we now examine
    whether Northeastern’s complaint arises under federal
    law to confer federal subject matter jurisdiction. First,
    we consider whether a substantial federal question
    exists to confer jurisdiction under 
    28 U.S.C. § 1331
     or the
    grant of jurisdiction in the Federal Power Act, 16 U.S.C.
    § 825p. Second, we examine whether the Federal Power
    Act completely preempts state causes of action in the
    field of wholesale power regulation, bringing the com-
    plaint within the complete preemption doctrine.
    A. Jurisdiction under 
    28 U.S.C. § 1331
     or 16 U.S.C. § 825p
    Wabash Valley argues that there is federal jurisdic-
    tion because the complaint is based on a rate filed
    with FERC. This could confer “arising under” jurisdic-
    tion under 
    28 U.S.C. § 1331
    , or bring the case within
    the Federal Power Act’s jurisdiction provision that pro-
    vides for original and exclusive federal court jurisdiction
    No. 12-2037                                                15
    over “all suits in equity and actions at law brought to
    enforce any liability or duty created by, or to enjoin any
    violation of, [the Federal Power Act] or any rule, regula-
    tion, or order thereunder.” 16 U.S.C. § 825p; California
    ex rel. Lockyer v. Dynegy, Inc., 
    375 F.3d 831
    , 843, amended
    on denial of reh’g, 
    387 F.3d 966
     (9th Cir. 2004) (finding
    § 825p provides a basis for federal court jurisdiction
    when federal question jurisdiction under § 1331 may
    be absent). We conclude that these two avenues do not
    confer jurisdiction because Northeastern’s suit is not
    based on a filed rate or a direct challenge to a filed rate.
    No federal issues are necessary elements of North-
    eastern’s claim.
    Northeastern’s complaint presents a claim for a dec-
    laratory judgment based on state contract law. The com-
    plaint thus presents a state law cause of action. We recog-
    nize that the nature of the cause of action does not
    always determine the existence of federal jurisdiction.
    See, e.g., Smith v. Kansas City Title & Trust Co., 
    255 U.S. 180
     (1921) (finding jurisdiction where decisive question
    of federal law was embedded in state law cause of ac-
    tion). Thus, we might still have federal question jurisdic-
    tion under section 1331 if the state law claims in the
    complaint “necessarily raise a stated federal issue,
    actually disputed and substantial, which a federal forum
    may entertain without disturbing any congressionally
    approved balance of federal and state judicial responsi-
    bilities.” Grable & Sons Metal Products, Inc. v. Darue Eng’g &
    Mfg., 
    545 U.S. 308
    , 314 (2005) (disavowing a “single,
    precise, all-embracing” test for federal question jurisdic-
    tion when federal issues are embedded in state law
    16                                              No. 12-2037
    causes of action, and finding federal question jurisdic-
    tion in quiet title action that depended on interpretation
    of federal tax law). We may also have jurisdiction if the
    state law cause of action falls within the scope of the
    Federal Power Act’s grant of jurisdiction. 16 U.S.C. § 825p.
    Wabash Valley contends that a substantial federal
    question necessarily exists because the suit is a chal-
    lenge to a federally-filed tariff. Wabash Valley rests
    this argument on our previous decision holding that a
    state law action seeking to enforce or challenge terms of
    a federally-filed tariff arises under federal law. See
    Cahnmann v. Sprint Corp., 
    133 F.3d 484
    , 488-89 (7th Cir.
    1998). The reason behind this is straightforward. Tariffs
    filed with federal agencies are the equivalent of federal
    regulations issued by the agency. Any liability the plain-
    tiff seeks to enforce necessarily arises under federal law
    because federal law created the liability. Id.; see also
    Marcus v. AT&T Corp., 
    138 F.3d 46
    , 56 (2d Cir. 1998). If
    Northeastern’s suit sought to challenge a filed tariff,
    the same reasoning would support jurisdiction under
    section 825p because it would be seeking to challenge
    the tariff — a regulation issued under the Federal
    Power Act. See California ex rel. Lockyer, 
    375 F.3d at 843
    .
    Federal question jurisdiction does not exist, however,
    where there is a federally-filed tariff, but the complaint
    alleges a contract and breach of that contract that both
    predate the federal tariff. In the cases defendant
    Wabash Valley cites, the alleged wrongdoing was based
    on conduct that occurred after a federal tariff was sub-
    mitted for regulation. See Bastien v. AT&T Wireless Serv.,
    No. 12-2037                                                 17
    
    205 F.3d 983
     (7th Cir. 2000); Cahnmann, 
    133 F.3d at
    486-
    87; City of Chanute v. Kansas Gas and Electric Co.,
    No. 06-4096-JAR-JPO, 
    2007 WL 1041763
     (D. Kan. 2007).
    In Cahnmann we relied on precisely this point of timing
    to distinguish the iconic example of the well-pleaded
    complaint rule, Louisville & Nashville R.R. v. Mottley, 
    211 U.S. 149
     (1908). In Mottley, the Mottleys sued the
    railroad to enforce a contract to give them free passes
    on the railroad for the rest of their lives (as partial settle-
    ment of an injury claim). The railroad’s defense was
    that honoring its contract would violate a federal law
    and tariff prohibiting free transportation for anyone.
    The Supreme Court held that the federal courts lacked
    jurisdiction over the suit because the federal issues were
    all defenses to the Mottleys’ contract claim. We reasoned
    in Cahnmann that because the contract in Mottley had
    been made before the federal tariff, the complaint in
    Mottley did not state a question of federal law. The “crucial
    difference” between Cahnmann and Mottley was that:
    The requirement that the carrier provide the service
    in question in accordance with tariffed terms didn’t
    come into the law until after the contract between
    the railroad and the plaintiffs was made and went
    into effect, so the plaintiffs’ claim couldn’t have been
    thought an effort to enforce a tariff or an appeal to
    the regulatory commission’s power to invalidate
    one. It was a state-law claim whether or not subse-
    quently extinguished by the passage of the federal
    law putting the subject matter of the contract under
    tariff regulation.
    
    133 F.3d at 489
    .
    18                                               No. 12-2037
    Like the breach of contract in Mottley, the alleged
    breach here is not based on a federally-filed tariff.
    Wabash Valley’s alleged breach took place before the
    filing of a federal tariff, so the rights at issue cannot be
    said to arise out of the federal tariff. This means the
    complaint does not necessarily raise a federal question.
    For Northeastern to obtain its requested declaratory
    judgment it must show only that it has a valid contract
    and that Wabash Valley’s submission to the regulatory
    jurisdiction of FERC breached the contract. Federal
    law is not at issue in either of these questions. The
    duty Northeastern claims Wabash Valley breached was
    not created by federal law or a filed tariff. And North-
    eastern does not seek to directly alter any duty or
    liability created by a filed tariff. We recognize that
    Wabash Valley will likely raise a number of federal issues
    in defense, but potential federal defenses are not neces-
    sary elements of the plaintiff’s claim and do not provide
    a basis for jurisdiction under the well-pleaded com-
    plaint rule.
    Wabash Valley contends that Northeastern’s com-
    plaint asks the state court to invalidate a federal filed
    rate because Northeastern seeks a declaration that it
    has “no further obligation to purchase power from
    Wabash Valley under the FERC filed [1977 contract],
    the termination of which is a matter within FERC’s ex-
    clusive jurisdiction.” We disagree. We must resolve
    genuine doubts about removal in favor of state court
    jurisdiction, see Schur v. L.A. Weight Loss Centers, Inc., 
    577 F.3d 752
    , 758 (7th Cir. 2009), and Wabash Valley, as the
    party asserting federal jurisdiction, bears the burden of
    establishing it, see Boyd v. Phoenix Funding Corp., 366 F.3d
    No. 12-2037                                               19
    524, 529 (7th Cir. 2004). With these standards in mind,
    we read the complaint as seeking only a declaration of
    rights and obligations under the 1977 contract. Such a
    judgment may provide an important stepping stone
    toward modifying Northeastern’s obligations under
    the federally-filed tariff in a separate filing with FERC,
    but the requested declaratory relief under the 1977
    contract does not ask the state court to resolve the
    separate and federal question of the effect of this breach
    on Northeastern’s obligations under the federally-filed
    tariff. If Northeastern prevails on the merits of its state
    law claim, it will need to make a subsequent filing with
    FERC to alter its obligations under the federal tariff, as
    its counsel acknowledged in oral argument. The com-
    plaint filed in state court, though, does not raise a federal
    question or challenge a federally-filed tariff, so there is
    no jurisdiction under section 1331 or under section 825p.
    B. Complete Preemption
    Wabash Valley’s next argument to support federal
    jurisdiction appears to rely on the complete preemption
    doctrine. Although it does not explicitly invoke the doc-
    trine, Wabash Valley cites our decision in Bastien v. AT&T
    Wireless Services — in which we found jurisdiction over
    a contract claim based on complete preemption under a
    section of the Federal Communications Act — for the
    proposition that federal filed-rate questions support
    removal when the effect of granting relief would alter
    the regulation of the rates. 
    205 F.3d 983
    , 989 (7th Cir.
    2000). This argument misreads Bastien and the filed-rate
    20                                                        No. 12-2037
    doctrine. In Bastien we found jurisdiction based on com-
    plete preemption under the Federal Communications
    Act, not simply on the existence of a filed rate. This is
    critical because the filed-rate doctrine does not provide
    an independent basis for removal absent a statute with
    complete preemptive force.5 We agree with nearly all of
    the other courts that have considered the question and
    conclude that the Federal Power Act does not com-
    pletely preempt state law.6 The complete preemption
    5
    In most cases challenging filed rates, a federal court will have
    jurisdiction under the theory of Cahnmann — that is, that a
    federal regulation forms the basis of the contractual relation-
    ship, so any claim necessarily arises under federal law.
    6
    See, e.g., Jeffrey Lake Dev., Inc. v. Cent. Nebraska Pub. Power & Irr.
    Dist., 4:11CV3112, 
    2011 WL 7122188
    , *6 n.4 (D. Neb. Nov. 23,
    2011), report and recommendation adopted, 
    2012 WL 296144
    (D. Neb. Feb. 1, 2012) (“there is no complete preemption under
    the FPA”); Cent. Iowa Power Coop. v. Midwest Indep. Transmission
    Sys. Operator, 06-CV-0053-LRR, 
    2007 WL 1058561
    , *23 (N.D. Iowa
    Mar. 30, 2007), rev’d and remanded on other grounds, 
    561 F.3d 904
     (8th Cir. 2009) (“neither in section 317 of the FPA, 16
    U.S.C. § 825p, nor any other provision of the FPA does
    Congress manifest an intent to completely preempt state law
    in the field of electrical power regulation”); Consol. Edison Co.
    of New York, Inc. v. Entergy Nuclear Indian Point 2, 05-CV-0222
    (RO), 
    2006 WL 929208
    , *2 (S.D.N.Y. Apr. 7, 2006) (“there is no
    evidence in the Federal Power Act of a congressional intent to
    create complete preemption”); In re California Retail Natural
    Gas & Elec. Antitrust Litig., 
    170 F. Supp. 2d 1052
    , 1057-58 (D. Nev.
    2001) (no complete preemption under Federal Power Act or
    (continued...)
    No. 12-2037                                                  21
    doctrine does not provide a basis for jurisdiction in
    this case.
    1. The Complete Preemption Doctrine
    The complete preemption doctrine refers to a limited
    set of cases in which a properly pled state law claim may
    6
    (...continued)
    Natural Gas Act); Hendricks v. Dynegy Power Mktg., 
    160 F. Supp. 2d 1155
    , 1159 (S.D. Cal. 2001) (“fact that the Federal Power Act
    includes an exclusive jurisdiction provision does not mean
    that the entire field is preempted”); Indeck Maine Energy, LLC
    v. ISO New England, 
    167 F. Supp. 2d 675
    , 687 (D. Del. 2001)
    (“Federal Power Act does not completely preempt state law
    in the field of electrical power regulation because Congress
    has not manifested an intent to do so in the statute”).
    The only cases arguably to the contrary are Franklin v. City
    of Alexandria, CIV.A. 07-1011, 
    2007 WL 3023941
     (W.D. La. Sept.
    17, 2007), and AES Sparrows Point LNG, LLC v. Smith, 
    470 F. Supp. 2d 586
     (D. Md. 2007). Smith, however, concerned a
    plaintiff pleading an affirmative claim of preemption that
    sought injunctive relief, bringing the claim within the purview
    of Shaw v. Delta Air Lines, 
    463 U.S. 85
     (1983). This basis for
    jurisdiction is distinct from the complete preemption doctrine
    and not applicable in this case. In Franklin, the court referred
    to the existence of complete preemption in passing; how-
    ever, jurisdiction existed under section 825p, so the court’s
    reference to complete preemption was an alternative holding
    without supportive reasoning. Moreover, the court did not
    attempt to reconcile the finding of complete preemption with
    the Supreme Court’s decision in Pan American Petroleum Corp.
    v. Superior Court of Del., 
    366 U.S. 656
     (1961), discussed below.
    22                                              No. 12-2037
    be said to arise under federal law because Congress
    has effectively eliminated state law causes of action in
    the entire field. See Beneficial Nat’l Bank v. Anderson, 
    539 U.S. 1
    , 8 (2003) (“When the federal statute completely pre-
    empts the state-law cause of action, a claim which
    comes within the scope of that cause of action, even
    if pleaded in terms of state law, is in reality based on
    federal law.”) The Supreme Court has recognized
    complete preemption under sections of the Employee
    Retirement Income Security Act, Metropolitan Life Ins. Co.
    v. Taylor, 
    481 U.S. 58
     (1987), the Labor Management
    Relations Act, Avco Corp. v. Machinists, 
    390 U.S. 557
    (1968), and the National Bank Act, Anderson, 
    539 U.S. 1
    .
    We have recognized complete preemption under a por-
    tion of the Federal Communications Act in Bastien
    v. AT&T Wireless Services, 
    205 F.3d 983
     (7th Cir. 2000)
    (finding § 332(c)(3) of the Federal Communications Act
    completely preempts state law causes of action). Cf. City
    of Chicago v. Comcast Cable Holdings, 
    384 F.3d 901
     (7th
    Cir. 2004) (holding § 542(b) of the Federal Communica-
    tions Act does not create federal jurisdiction under com-
    plete preemption doctrine).
    Complete preemption exists when federal law
    provides “the exclusive cause of action” for claims in a
    regulated area. Anderson, 
    539 U.S. at 9
    . Thus stated, the
    standard sounds admittedly circular, but there is no
    doubt that any further expansion of the doctrine beyond
    its origins with the Labor Management Relations Act
    requires a clear showing of Congressional intent to elimi-
    nate state law entirely. See In re Repository Technologies,
    
    601 F.3d 710
    , 723 (7th Cir. 2010). The doctrine does not
    No. 12-2037                                              23
    apply when the Supreme Court has held that federal
    law does not completely occupy the substantive field of
    law at issue. In such a case the Supreme Court
    has already found such intent not to exist. See Pollitt v.
    Health Care Serv. Corp., 
    558 F.3d 615
    , 616 (7th Cir. 2009)
    (finding complete preemption doctrine inapplicable
    because Supreme Court held federal law did not com-
    pletely occupy field of health insurance coverage for
    federal workers).
    2. Complete Preemption and the Federal Power Act
    Here, as in Pollitt, we find no complete preemption
    because, as the Supreme Court has recognized, federal
    law leaves a role for state law in wholesale power reg-
    ulation. Of particular significance, the Supreme Court
    has concluded that federal law does not completely
    occupy the field of wholesale natural gas regulation — a
    regulatory scheme that is closely analogous to wholesale
    power regulation. See Pan American Petroleum Corp.
    v. Superior Court of Del., 
    366 U.S. 656
     (1961).
    The case requires our close attention here. In Pan Ameri-
    can, Cities Service — an intermediate purchaser of
    natural gas — brought suit against several natural gas
    wholesalers in state court to seek a refund for an alleged
    overpayment. The relevant facts were as follows. Cities
    Service entered into contracts with the wholesalers for
    purchase of natural gas at a price of less than 11 cents per
    thousand cubic feet. After the contract took effect, the
    State of Kansas issued an order fixing a minimum price
    24                                               No. 12-2037
    of 11 cents per thousand cubic feet. Because the mini-
    mum price was higher than the contract price, Cities
    Service paid the higher state-mandated price but
    explicitly conditioned payment on its right to receive a
    refund if the state order were later found invalid. While
    this dispute was pending, the Supreme Court decided
    Phillips Petroleum v. State of Wisconsin, 
    347 U.S. 672
     (1954),
    which held that all wholesale sales of natural gas in
    interstate commerce — including the Cities Service con-
    tracts — fell within the jurisdiction of the Federal Power
    Commission. As a result of that decision, Cities Service
    and the wholesalers filed their contracts with the Federal
    Power Commission. Following the filing of the rate, the
    Supreme Court held the Kansas minimum rate order
    unconstitutional, and Cities Service brought a state law
    action seeking a refund for excess payments. The whole-
    salers contended that the Natural Gas Act — which in
    relevant part is the same as the Federal Power Act —
    stripped state courts of jurisdiction to hear such suits.
    The Supreme Court disagreed. Even though there was
    a filed rate that would likely need to be interpreted in
    the suit, the Court found that the case did not assert any
    right under the Natural Gas Act. Pan American, 
    366 U.S. at 663-64
    . The suit therefore arose under state law, and
    there was no federal question jurisdiction. Inconsistent
    with complete preemption, the Court noted that the
    existence of state court jurisdiction did not turn on “the
    extent to which the Natural Gas Act reinforces or
    abrogates the private contract rights” in controversy, but
    rather on the source of the right asserted. 
    Id. at 664
    . The
    rights at issue did “not lose their character because it
    No. 12-2037                                             25
    [was] common knowledge that there exist[ed] a scheme
    of federal regulation of interstate transmission of natural
    gas.” 
    Id. at 663
    . The Supreme Court’s recognition that
    state common law claims continued to exist alongside
    the federal regulatory scheme indicates that the Federal
    Power Act also does not completely preempt state
    law causes of action, for the relevant provisions of the
    Federal Power Act and the Natural Gas Act are “substan-
    tially identical.” See Arkansas Louisiana Gas Co. v. Hall,
    
    453 U.S. 571
    , 577 n.7 (1981) (noting “established prac-
    tice of citing interchangeably decisions interpreting the
    pertinent sections of the two statutes”).
    The exclusive jurisdiction provision in the Federal
    Power Act, 16 U.S.C. § 825p, does not alter our conclu-
    sion. The provision provides the federal district courts
    with exclusive original jurisdiction only over suits to
    enforce liabilities or duties created under the FPA. If the
    liability or duty at issue is not created by the FPA, it
    does not fall within the exclusive jurisdiction provision.
    Absent a showing of Congressional intent to preempt all
    state law claims in the area of wholesale power regula-
    tion, there is no complete preemption. See Hendricks
    v. Dynegy Power Mktg., Inc., 
    160 F. Supp. 2d 1155
    , 1159
    (S.D. Cal. 2001) (“fact that the Federal Power Act
    includes an exclusive jurisdiction provision does not
    mean that the entire field is preempted”). To read
    the exclusive jurisdiction provision to cover more than
    the limits of its text would be to disregard Congress’s
    intent.
    26                                               No. 12-2037
    3. Complete Preemption and the Filed-Rate Doctrine
    We also reject the argument that the filed-rate doc-
    trine itself completely preempts state law. Citing Bastien
    v. AT&T Wireless Services, Wabash Valley appears to
    suggest that the filed-rate doctrine brings this case
    within the federal courts’ jurisdiction. Wabash Valley
    cites Bastien for the proposition that, “to determine the
    presence of a federal filed-rate question supporting
    removal,” we ask what the nature of the claim is and
    what the effect of granting the relief would be. The argu-
    ment misses the critical fact that in Bastien we found
    the Federal Communications Act to completely preempt
    state law. Our finding of complete preemption was
    a necessary prerequisite to our determination that
    federal jurisdiction existed.
    The filed-rate doctrine does not on its own eliminate
    state law causes of action. Plaintiffs, for example, may still
    bring breach of contract claims in state court seeking
    to enforce a contractually agreed wholesale rate that is
    within the bounds of the federal tariff, as in Pan American.
    The filed-rate doctrine prevents courts from second-
    guessing the reasonableness of terms in a federally-filed
    rate, but it does not divest state courts of jurisdiction
    to hear all cases involving wholesale power contracts.
    The confusion may arise from the faulty premise that
    the filed-rate doctrine is a jurisdictional doctrine as op-
    posed to a substantive one. This is understandable
    because many cases invoking the filed-rate doctrine
    concern challenges based on federal tariffs. As a result,
    decisions that find jurisdiction on the basis of a federal
    No. 12-2037                                               27
    tariff that creates the liability in the suit and that also
    find a suit preempted by the filed-rate doctrine may be
    over-read to suggest that the filed-rate doctrine creates
    the source of jurisdiction through complete preemption.
    In these cases, however, jurisdiction is based on rights
    created by a federal tariff itself, see, e.g., Cahnmann, 
    133 F.3d at 488-89
    , not by the fact that the suit pertains to
    the same subject matter as a filed rate. As discussed
    above, the necessary implication of the holding of Pan
    American that federal courts lack jurisdiction over state
    law contract claims seeking refunds for overpayments is
    that the filed-rate doctrine does not completely preempt
    state law. It is therefore properly treated as a federal
    defense rather than an affirmative basis for jurisdiction.
    4.   FERC Practice
    Finally, we find further support for our holding that
    the Federal Power Act does not completely preempt
    state law causes of action in FERC’s actual practices.
    FERC itself recognizes a role for state contract law in
    adjudicating contract disputes involving federal tariffs.
    See Portland General Electric Co., 
    72 FERC ¶ 61009
    , at *3
    (July 5, 1995) (“our jurisdiction to settle disputes over the
    meaning of rate schedules does not as a matter of law
    preclude state courts from entertaining contract litiga-
    tion . . . .”); Arkansas Louisiana Gas Co. v. Hall, 
    7 FERC ¶ 61175
    , at *3 (May 18, 1979) (discussing when FERC will
    exercise primary jurisdiction over contract disputes that
    would otherwise be subject to state court jurisdiction);
    see also PPL Montana, LLC, 
    96 FERC ¶ 61313
     (Sept. 14,
    28                                              No. 12-2037
    2001) (deferring to state courts to resolve power contract
    disputes). If the Federal Power Act completely pre-
    empted state law causes of action, we would not expect
    FERC — the agency that administers the statute — to
    recognize any role for state court adjudication of con-
    tract disputes involving filed tariffs.
    Portland General Electric Co. is particularly instructive.
    In that case, Edison filed a complaint against Portland
    General Electric in an Oregon state court alleging that
    under Oregon law, Portland General Electric was in
    default on a Power Agreement — which was also part of a
    filed rate — as a result of a nuclear plant closure. Portland
    General Electric then filed a complaint with FERC seeking
    a declaratory order that FERC was the only body with
    jurisdiction to resolve the contract dispute. FERC dis-
    agreed. Because the complaint in Oregon state court did
    not “challenge the reasonableness of any rate on file
    with FERC, or make claims based on the FPA,” the state
    court action was appropriate. Portland General Electric,
    
    72 FERC ¶ 61009
    , at *1. FERC made clear, however, that
    any decision to terminate the contract following state
    court adjudication of the contract law question would
    need to be filed with FERC itself. Id.; 
    18 C.F.R. § 35.15
    .
    In terms of the jurisdictional issue, the facts in Portland
    General Electric are virtually indistinguishable from
    the facts of this case. Northeastern has filed a complaint
    that does not assert any claims based on the FPA and
    does not challenge the reasonableness of a filed rate.
    Northeastern simply seeks the interpretation of a
    contract term to determine whether Wabash Valley
    No. 12-2037                                             29
    breached the contract by switching from state regula-
    tion to FERC regulation. And like Edison, Northeastern
    acknowledged at argument that if it prevails in state
    court, it will need to file a notice with FERC before
    terminating performance under the federally-filed
    rate schedule, providing FERC with an opportunity to
    address such remedial questions. See, e.g., Jersey Cent.
    Power & Light Co., 
    33 FERC ¶ 61071
     (Oct. 25, 1985) (de-
    clining to permit withdrawal of filed rate schedule). Since
    Northeastern is seeking only a declaration of state
    contract rights, a declaration that cannot obligate FERC
    to modify Northeastern’s obligations under the federal
    tariff, we recognize that it is not at all clear whether
    state courts could award meaningful relief to North-
    eastern. Nevertheless, FERC’s practice in cases like
    Portland General Electric suggests that FERC finds state
    court contract interpretation helpful in resolving such
    disputes when they eventually come before FERC.
    III. Conclusion
    Northeastern has pled a state law breach of contract
    claim that does not arise under federal law. The claim
    does not seek to enforce or challenge any duty or liability
    created by a federally-filed tariff, nor does the claim
    necessarily arise under federal law through complete
    preemption. In light of this conclusion, we also of course
    reject Wabash Valley’s request for sanctions on the
    theory that the appeal was frivolous. Because the dis-
    trict court lacked jurisdiction to issue its preliminary
    30                                         No. 12-2037
    injunction, we V ACATE the preliminary injunction and
    R EMAND the case so that the district court may remand
    it to state court.
    2-22-13
    

Document Info

Docket Number: 12-2037

Citation Numbers: 707 F.3d 883, 2013 U.S. App. LEXIS 3692, 2013 WL 646051

Judges: Eanne, Tinder, Hamilton

Filed Date: 2/22/2013

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (35)

Indeck Maine Energy, L.L.C. v. ISO New England Inc. , 167 F. Supp. 2d 675 ( 2001 )

In Re Cal. Ret. Nat. Gas & Electricity Anti. Lit. , 170 F. Supp. 2d 1052 ( 2001 )

Louisville & Nashville Railroad v. Mottley , 29 S. Ct. 42 ( 1908 )

Montana-Dakota Utilities Co. v. Northwestern Public Service ... , 71 S. Ct. 692 ( 1951 )

United States v. Public Utilities Commission , 73 S. Ct. 706 ( 1953 )

AES Sparrows Point LNG, LLC v. Smith , 470 F. Supp. 2d 586 ( 2007 )

Steven Bastien v. At&t Wireless Services, Inc. , 205 F.3d 983 ( 2000 )

people-of-the-state-of-california-ex-rel-bill-lockyer-attorney-general , 375 F.3d 831 ( 2004 )

Gully v. First Nat. Bank in Meridian , 57 S. Ct. 96 ( 1936 )

Caterpillar Inc. v. Williams , 107 S. Ct. 2425 ( 1987 )

Rivet v. Regions Bank of Louisiana , 118 S. Ct. 921 ( 1998 )

Grable & Sons Metal Products, Inc. v. Darue Engineering & ... , 125 S. Ct. 2363 ( 2005 )

Shaw v. Delta Air Lines, Inc. , 103 S. Ct. 2890 ( 1983 )

Hendricks v. Dynegy Power Marketing, Inc. , 160 F. Supp. 2d 1155 ( 2001 )

Pollitt v. Health Care Service Corp. , 558 F.3d 615 ( 2009 )

Research Automation, Inc. v. Schrader-Bridgeport ... , 626 F.3d 973 ( 2010 )

salt-river-project-agricultural-improvement-and-power-district-v-federal , 391 F.2d 470 ( 1968 )

Phillips Petroleum Co. v. Wisconsin , 74 S. Ct. 794 ( 1954 )

Avco Corp. v. Aero Lodge No. 735, International Ass'n of ... , 88 S. Ct. 1235 ( 1968 )

Franchise Tax Bd. of Cal. v. Construction Laborers Vacation ... , 103 S. Ct. 2841 ( 1983 )

View All Authorities »