Dennis Loehrer v. McDonnell Douglas , 98 F.3d 1056 ( 1996 )


Menu:
  •                                          No. 95-3964
    Dennis W. Loehrer; Stephen D.                  *
    Brandt,                                        *
    *
    Plaintiffs - Appellants,              *
    *
    James L. Loretta; Elmer W.                     *
    Yordt; Richard L. Darling, on                  *
    their own behalf and on behalf                 *   Appeal from the United States
    of all others similarly                        *   District Court for the Eastern
    situated,                                      *   District of Missouri.
    *
    Plaintiffs,                           *
    *
    v.                                             *
    *
    McDonnell Douglas Corporation,                 *
    *
    Defendant - Appellee.                 *
    Submitted:       June 12, 1996
    Filed:    October 22, 1996
    Before RICHARD S. ARNOLD, Chief Judge, FLOYD R. GIBSON, Circuit                   Judge,
    and KORNMANN,1 District Judge.
    FLOYD R. GIBSON, Circuit Judge.
    This     appeal    represents       yet   another   chapter   in   the   litigation
    surrounding    the     United    States    Navy's    turbulent,    controversial,    and
    ultimately unsuccessful attempt to design and manufacture the A-12 Avenger
    II fighter-bomber, extolled for years as the Service's "number one aviation
    priority."     Appellants Dennis Loehrer and Stephen Brandt are former
    employees of appellee McDonnell Douglas Corporation ("McDonnell Douglas"),
    which along with the General
    1
    The HONORABLE CHARLES B. KORNMANN, United States District
    Judge for the District of South Dakota, sitting by designation.
    Dynamics Corporation ("General Dynamics") served as contractor for the A-12
    program.   Following months of communications between the Government and the
    contractors which varied from contentious to conciliatory, the Secretary
    of Defense, Dick Cheney, withdrew support for the A-12 on January 7, 1991,
    and the Navy canceled the contract on that same day.       As a consequence,
    McDonnell Douglas found it necessary to terminate the employment of
    thousands of workers in the St. Louis area.        Loehrer received written
    notice on January 15, 1991 that he was to be laid off effective January 29,
    1991; Brandt's notice of January 14, 1991 indicated that his last day of
    employment with the company would be January 25.         Loehrer and Brandt
    subsequently initiated this suit in the United States District Court for
    the Eastern District of Missouri, claiming that McDonnell Douglas violated
    the Worker Adjustment and Retraining Notification Act, 29 U.S.C. §§ 2101-
    2109 (1994)(the "WARN Act"), by failing to give 60 days notice before the
    company implemented a mass layoff.   McDonnell Douglas concedes that it did
    not comply with the time period customarily prescribed by the WARN Act, but
    it maintains that the statute's exception for "unforeseeable business
    circumstances" applies to excuse the shortened notice in this case.    After
    2
    a two day bench trial, the district court       entered judgment in favor of
    McDonnell Douglas.   Loehrer and Brandt appeal, and we affirm.
    I.   BACKGROUND
    On January 13, 1988, the Navy contracted with McDonnell Douglas and
    General Dynamics for the full scale engineering development of the A-12.
    On April 26, 1990, Secretary Cheney presented to the House Armed Services
    Committee the results of a Major Aircraft Review ("MAR") of four ongoing
    development programs, including the A-12.   Based on the MAR, the Secretary
    believed that
    2
    The HONORABLE EDWARD L. FILIPPINE, Senior United States
    District Judge for the Eastern District of Missouri.
    2
    there were no major impediments to the timely completion of the A-12
    program.      In his testimony before the Committee, the Secretary recommended
    a   reduction in the number of A-12 Avengers to be produced, but he
    underscored         that    the    aircraft      remained        "one   of    our      most    urgent
    requirements."
    Soon after the Secretary uttered these optimistic remarks, the A-12
    program, and the relationship between the contractors and the Government,
    plunged into a downward spiral.                    By mid-1990, it was apparent that
    McDonnell Douglas and General Dynamics were experiencing considerable
    difficulties with the program and were unlikely to complete the project on
    time and within budget.            The contractors discovered that production of the
    jet would be more troublesome than expected due to unanticipated problems
    with    the    manufacture         of   the    aircraft's    "big       ribs."         Due    to   this
    realization, McDonnell Douglas generated a contingency plan describing the
    options it would consider if the Navy refused to restructure the A-12
    contract.           One     of     these      options     included      claiming        "commercial
    impracticability to perform."
    On June 13, 1990, McDonnell Douglas and General Dynamics informed
    Lawrence Garrett, Secretary of the Navy, that the full scale development
    costs       would   overrun       the   contract       ceiling    price3     by   an    amount     the
    contractors could not absorb, and the companies requested that the Navy
    consent to restructure the agreement.                   Approximately one month later, the
    Navy formally notified the contractors that they had failed to deliver the
    first aircraft as required by the contract and that the entire A-12 program
    was in jeopardy.           Subsequently, on August 17, 1990, the Navy approved a
    3
    The A-12 contract was a fixed-price agreement with a target
    price of approximately $4.4 billion. The Government committed to
    pay all costs up to that amount. Costs between the target price
    of $4.4 billion and the ceiling price of approximately $4.8
    billion were shared by the Government and the contractors: the
    Government paid sixty percent of the costs and the contractors
    paid forty percent. The contractors assumed all costs above the
    ceiling.
    3
    modification of the contract which unilaterally reestablished the delivery
    schedule, but it specifically reserved the right to an equitable adjustment
    in price as consideration for revising the time-line.
    By letter dated September 5, 1990, McDonnell Douglas and General
    Dynamics asserted that the Government had obligated insufficient funds to
    the A-12 project to cover the corporations' costs.            The contractors asked
    for additional funds to be provided at a more rapid rate "to preclude the
    possibility that the contractors may have to stop work under the contract."
    On October 3, 1990, the Navy refused this plea for an accelerated delivery
    of supplemental funds, but the Government continued to make regular
    progress payments to the companies through December of 1990.
    As it happened, these troubling events coincided with a review of the
    A-12 by the Defense Acquisition Board ("DAB").         The DAB was responsible for
    making a final recommendation regarding the continuation of the A-12
    program.     Before evaluation by the DAB, which was scheduled for December
    7,   1990,   the   A-12   had   to   successfully   undergo   several    intermediate
    assessments.    One of the most important of these was a phased examination
    of the A-12 design known as the Critical Design Review ("CDR").              Problems
    identified during the CDR were discussed at three design review boards.
    At the last design review board, the chief Navy procurement officer
    indicated that the parties had fixed the jet's structural problems and that
    the resulting design would produce an effective aircraft.
    Secretary Cheney, who was ultimately responsible for deciding the
    fate of the fighter-bomber, was also monitoring the progress of the A-12
    program.     Following his rosy remarks to Congress he, of course, became
    aware of the complications experienced by the contractors.              The Secretary
    responded by pursuing a positive, yet cautious, approach to ongoing
    development of the plane.       On June 19, 1990, he reiterated his belief that
    the Avenger was a high
    4
    priority Navy program.    In October, though, he ordered the Navy to create
    a new aviation plan that could be activated in the event that the A-12
    project failed or was significantly reduced or delayed.              Still, in an
    interview printed in the December 17, 1990 issue of Defense Week, the
    Secretary refused to speculate on the possible cancellation of the A-12
    program.    The article reflected the Secretary's understanding that defense
    contractors often exceed their budgets and fall behind schedule.         In fact,
    the district court determined that "the [G]overnment has rarely ever
    cancelled a contract for a program for which the [G]overnment had stated
    a need.     In the past, when a contractor encountered difficulty with a
    contract,    either   additional   funding   was   provided,   the   schedule   of
    production was altered, or the output requirement was modified."
    In hindsight, it is apparent that the death knell for the A-12
    program began to sound in December of 1990.          On December 14, Secretary
    Cheney directed the Navy to "show cause" by January 4, 1991 why the
    Government should not terminate the contract.      By letter dated December 17,
    1990, the Navy notified McDonnell Douglas and General Dynamics that the
    corporations' performance was "unsatisfactory" and that unless specified
    "conditions are cured by 2 January 1991 the Government may terminate for
    default."     These events prompted McDonnell Douglas to issue advisory
    memoranda to its workers.    On December 20, the company distributed a letter
    to all its employees explaining that the A-12 program was in danger.            The
    letter further indicated that cancellation of the contract could require
    the corporation to layoff 4,000 persons, and it stated that employees at
    immediate risk would receive a follow-up communication.          The memorandum
    concluded, "If you do not receive such a letter you will not be laid off
    in connection with our near-term actions in response to the possible
    cancellation of this program."         On the next day, December 21, the
    contractor, as promised, notified roughly 2,500 employees that they would
    lose
    5
    their jobs if the A-12 project were terminated.4         Neither Loehrer nor
    Brandt received the December 21 letter.
    On January 2, 1991, the contractors submitted a written response to
    the Navy's December 17 cure demand, noting that many previously existing
    problems had been corrected and explaining the current status of the A-12
    program.      In addition, the companies offered a proposal for continuation
    of the project.     On January 2-3, 1991, representatives from the contractors
    met with Assistant Secretary of the Navy Gerald Cohn; Rear Admiral Morris,
    the senior A-12 contracting officer; Eleanor Spector, Director of Defense
    Procurement, Department of Defense; Under-Secretary of Defense Yockey; and
    several attorneys from the Department of Defense.       After presentation of
    the contractors' proposal and two days of negotiations, McDonnell Douglas
    and General Dynamics agreed to absorb a $1.5 billion loss in exchange for
    a restructuring of the contract, $500 million of which was an up front
    loss.       Admiral Morris gave McDonnell Douglas a draft of a Memorandum of
    Understanding outlining terms under which the Navy was willing to rework
    the A-12 project.        The memorandum evidences that the Navy planned to
    support the contractors in their application for "extraordinary relief" in
    the form of an additional appropriation from Congress.        Under-Secretary
    Yockey told McDonnell Douglas that there was "no[] intent to terminate."
    Despite this encouraging meeting, and although Congress had recently
    expressed continued conditional support for the A-12
    4
    General Dynamics, McDonnell Douglas's cocontractor,
    transmitted comparable communications to its employees on the
    same days. In a substantially similar suit against General
    Dynamics, the district court characterized the December 21
    letters as "conditional WARN notices." International Ass'n of
    Machinists, AFL-CIO v. General Dynamics Corp., 
    821 F. Supp. 1306
    ,
    1310 (E.D. Mo. 1993). The court proceeded to conclude that
    General Dynamics had not violated the WARN Act, and the
    plaintiffs in that case did not file an appeal.
    6
    program, Secretary Cheney on January 7, 1991 instructed the Navy to
    terminate the A-12 contract.           Accordingly, the Navy immediately canceled
    the contract for default.       As mentioned above, Loehrer and Brandt received
    notice early in 1991 that their positions would be eliminated on January
    29 and January 25, respectively.             The two employees thereafter instituted
    this suit against McDonnell Douglas and alleged that the company had
    violated the WARN Act.5
    After contemplating the evidence, the district court found, and the
    parties evidently agree, that the layoff in question falls within the WARN
    Act's general parameters.          Therefore, under normal conditions, McDonnell
    Douglas would have been obliged to give all "affected employees," including
    Loehrer     and    Brandt,   sixty    days     notice   preceding   the   terminations.
    Nonetheless, the district court decided that McDonnell Douglas was excused
    from the Act's sixty day standard under the exception for mass layoffs
    caused by "business circumstances that were not reasonably foreseeable as
    of    the   time   that   notice     would    have   been   required."    29   U.S.C.   §
    2102(b)(2)(A) (1994).        The court determined that, throughout the latter
    half of 1990, the corporation had "exercised reasonable business judgment
    in continuing to believe that termination [of the contract] would not
    occur."     Because the events precipitating the mass layoff did not become
    reasonably foreseeable until January 7, 1991, the very date of the
    contract's cancellation, the court concluded that the company satisfied the
    WARN Act by giving Loehrer and Brandt as much notice as was practicable.
    The   court recognized that relevant regulations might have permitted
    McDonnell Douglas to transmit earlier conditional notice to affected
    employees, but it held that the circulation of such notice is permissive
    rather than mandatory.          On appeal, Loehrer and Brandt challenge the
    district court's interpretation and application of the "unforeseeable
    business
    5
    Though this case originally involved five named plaintiffs,
    Loehrer and Brandt were the only plaintiffs whose claims
    proceeded to trial.
    7
    circumstances" exception.
    II.   DISCUSSION
    Under the WARN Act, certain large employers who order a plant closing
    or mass layoff must provide sixty days advance written notice to, among
    others, affected employees or their union representatives.                  See 29 U.S.C.
    § 2102(a) (1994).      The purpose of the Act is to extend
    protection to workers, their families and communities by
    requiring employers to provide notification 60 calendar days in
    advance of plant closings and mass layoffs. Advance notice
    provides workers and their families some transition time to
    adjust to the prospective loss of employment, to seek and
    obtain alternative jobs and, if necessary, to enter skill
    training or retraining that will allow these workers to
    successfully compete in the job market.
    20 C.F.R. § 639.1(a) (1996).           Though the nearly two-month notice period
    mandated by the Act goes far to attain these laudable goals, Congress
    recognized, through the enactment of various exceptions in the statute,
    that supplying generous advance notice would not be possible, or desirable,
    in all cases.       See 29 U.S.C. § 2102(b) (1994).             One of these exceptions,
    pertaining to plant closings or mass layoffs caused by unforeseeable
    business circumstances, is the focal point of this appeal.                       See 
    id. § 2102(b)(2)(A).
    A.      The unforeseeable business circumstances exception
    The WARN Act expressly confirms that "[a]n employer may order a plant
    closing or mass layoff before the conclusion of the 60-day period if the
    closing or mass layoff is caused by business circumstances that were not
    reasonably    foreseeable    as   of    the       time   that   notice   would   have   been
    required."    
    Id. In formulating
    regulations interpreting this exemption,
    the Department of Labor ("DOL") was reluctant to list examples of events
    that would,
    8
    without deviation, qualify as unforeseeable business circumstances.                See
    Analysis of Final Rule and Comments, 54 Fed. Reg. 16,062 (1989).                Rather,
    the DOL indicated that the propriety of utilizing the exception in any
    particular scenario involves a highly factual inquiry to be assessed on a
    case by case basis.      
    Id. at 16,062-63.
              The regulations explain:
    An important indicator of a business circumstance that is
    not reasonably foreseeable is that the circumstance is caused
    by some sudden, dramatic, and unexpected action or condition
    outside the employer's control. A principal client's sudden
    and unexpected termination of a major contract with the
    employer . . . might . . . be considered a business
    circumstance that is not reasonably foreseeable.
    *   *   *
    The test for determining when business circumstances are
    not reasonably foreseeable focuses on an employer's business
    judgment.     The employer must exercise such commercially
    reasonable business judgment as would a similarly situated
    employer in predicting the demands of its particular market. .
    . .
    20 C.F.R. § 639.9(b)(1)-(2) (1996); see also 54 Fed. Reg. 16,063 (1996)
    ("What is important is that the circumstance be 'sudden, dramatic and
    unexpected.'").      Additionally, because unforeseeable business circumstances
    operate as an affirmative defense to WARN liability, the employer bears the
    burden of proving the existence of conditions giving rise to the exception.
    General 
    Dynamics, 821 F. Supp. at 1311
    ; 20 C.F.R. § 639.9 (1996).
    In     this   case,   the    district     court    acknowledged    the   extreme
    difficulties experienced by the A-12 cocontractors during the latter half
    of    1990,   culminating    in    the   Government's     December   17   communication
    indicating that the contract might be terminated for default.                   Despite
    these disquieting undercurrents, though, negotiations among the contracting
    parties were progressing favorably toward the end of the year; indeed, the
    court expressly found that, until the last possible minute, the Government
    and
    9
    McDonnell Douglas undertook extraordinary measures in an attempt to save
    the program.       Against this backdrop of events, the court held that
    "termination of the A-12 contract was not reasonably foreseeable until
    January 7, 1991."         Unlike Loehrer and Brandt, we find no fault in the
    district court's analysis.
    B.    Standard of Review
    As an initial matter, the parties dispute the amount of deference we
    should give to the district court's ultimate determination that the facts
    of   this   case   fall    within   the   exception    for    unforeseeable    business
    circumstances.     It goes without saying, of course, that we review for clear
    error the district court's findings of historical facts, see Fed. R. Civ.
    P. 52(a), and it is equally plain that we evaluate de novo the trial
    court's construction and interpretation of a statute, Rifkin v. McDonnell
    Douglas Corp, 
    78 F.3d 1277
    , 1280 (8th Cir. 1996).                 When, as here, the
    district court has applied an objective legal standard to established
    facts, we are confronted with a mixed question of law and fact.                     See
    Ornelas v. United States, 
    116 S. Ct. 1657
    , 1661-62 (1996).                    Though we
    normally exercise plenary review over mixed questions, we will afford
    deference to the district court's decision if "application of the rule of
    law to the facts requires an inquiry . . . that is founded 'on the
    application of the fact-finding tribunal's experience with the mainsprings
    of human conduct.'"       United States v. McConney, 
    728 F.2d 1195
    , 1202 (9th
    Cir.)(en banc), cert. denied, 
    469 U.S. 824
    (1984); see also Nodaway Valley
    Bank   v.   Continental     Casualty      Co.,   
    916 F.2d 1362
    ,   1366   (8th   Cir.
    1990)(expressing approval for the Ninth Circuit's opinion in McConney).
    There is some force to the argument that a deferential standard of
    review should guide our analysis in this case.            Nevertheless, though this
    is undeniably an interesting quodlibet, we need not address the issue at
    present.    Because affirmance would
    10
    be appropriate regardless of the weight we give to the district court's
    relevant conclusions, we save the resolution of this question for another
    day.6
    C.      Reasonable Foreseeability
    We are mindful that an employer's commercially reasonable business
    judgment, rather than hindsight, dictates the scope of the unforeseeable
    business circumstances exception.            As such, a company will be excused from
    WARN        liability   if,     when     confronted   with   potentially   devastating
    occurrences, it reacts as would reasonable employers within its own market.
    See Chestnut v. Stone Forest Indus., Inc., 
    817 F. Supp. 932
    , 936 (N.D. Fla.
    1993)("[T]he statute imposes a standard of commercial reasonableness, based
    on what a similarly situated employer would do in predicting the demands
    of its particular market."); 20 C.F.R. § 639.9(b)(2) (1996).               The Act and
    its regulations necessarily recognize that even the most conscientious
    employers are not perfect, and they thus allow needed flexibility for
    predictions       about       ultimate    consequences   that,   though    objectively
    reasonable, proved wrong.          So long as it may still fairly be said that the
    eventual plant closing or mass layoff is caused by a sudden, dramatic, and
    unexpected event outside the employer's control, the exception applies.7
    6
    For analogous reasons, we need not decide whether to
    narrowly construe the exception for unforeseeable business
    circumstances. Compare Carpenters Dist. Council v. Dillard Dep't
    Stores, Inc., 
    15 F.3d 1275
    , 1282 (5th Cir. 1994)("[T]his
    exception to the general rule is to be narrowly construed."),
    cert. denied, 
    115 S. Ct. 933
    (1995) with 54 Fed. Reg. 16,061
    (1996)("The Department has reviewed the legislative history and
    agrees that it may not [be] appropriate to say that the
    unforeseeable business circumstances . . . exception[] should be
    narrowly construed.").
    7
    We join other courts in rejecting an interpretation of this
    exception which would require an employer to establish that it
    would not have been economically feasible to wait sixty days
    before instituting the plant closing or mass layoff. See Jurcev
    v. Central Community Hosp., 
    7 F.3d 618
    , 624-625 (7th Cir. 1993),
    cert. denied, 
    114 S. Ct. 1830
    (1994); Teamsters Nat'l Freight
    Indus.
    Negotiating Comm. v. Churchill Truck Lines, Inc., No. 94-1004-CV-
    11
    See Jurcev v. Central
    W-8, 
    1996 WL 480683
    , at *5 (W.D. Mo. Aug. 9, 1996)("The 'business
    circumstance exception' . . . does not impose upon an employer a
    requirement to provide sixty days notice or continue in business
    to its detriment for the sixty-day notice period, simply because
    it is economically feasible or possible to do so.").
    12
    Community Hosp., 
    7 F.3d 618
    , 625-27 (7th Cir. 1993)(analyzing facts to
    determine whether particular event was sudden, dramatic, and unexpected),
    cert. denied, 
    114 S. Ct. 1830
    (1994); 20 C.F.R. § 639.9(b)(1) (1996).
    After examining the record, we are convinced that the facts before
    us   fall   squarely    within   the   exception   for   unforeseeable   business
    circumstances.   In so deciding, we certainly realize that the A-12 program
    fell upon rocky times in 1990.     The scheduling delays and severe budgetary
    overruns, coupled with the Government's obvious unhappiness with the
    cocontractors' performance, would undoubtedly raise the eyebrows of any
    prudent businessperson.      In fact, these events did not go unnoticed at
    McDonnell Douglas, as that corporation sent advisory memoranda to its
    employees explaining the precarious situation.
    Despite this worrisome state of affairs, and under the totality of
    the circumstances, we think that the Government's cancellation of the A-12
    contract was not reasonably foreseeable to McDonnell Douglas prior to
    January 7, 1991.       To begin with, this case involves the rather unique,
    politically charged area of defense contracts.            In this setting, the
    commercial reasonableness of McDonnell Douglas's reluctance to issue WARN
    notices, even after the Government's December 17 cure letter, is manifest.
    As noted by the district court, "the [G]overnment has rarely ever cancelled
    a contract for a program for which the [G]overnment had stated a need."
    The Government had most definitely stated a need for the A-12 fighter-
    bomber, and high level defense officials continued to tout the program as
    imperative to national security.       Placing some
    13
    emphasis on this underlying context, we believe that McDonnell Douglas's
    conduct was in accord with what would be expected from a reasonable defense
    contractor.    Cf. General 
    Dynamics, 821 F. Supp. at 1312
    ("General Dynamics
    officials were exercising reasonable business judgment in the context of
    their particular market when they concluded that termination was not a
    likely outcome.").
    Moreover, other factors buttressed McDonnell Douglas's optimism.           In
    the months preceding the program's cancellation, Congress expressed ongoing
    conditional support for the A-12, and the Navy's chief procurement officer
    indicated that the contractors had remedied the jet's structural defects.
    Also, upbeat negotiations progressed through early 1991, resulting in a
    draft of a Memorandum of Understanding exhibiting the Navy's willingness
    to restructure the agreement, and on January 2, 1991 Under-Secretary Yockey
    declared that the Government had no intention to terminate the contract.
    Given these developments, we have little difficulty in concluding that the
    Government's January 7 announcement was sudden, dramatic, and unexpected.
    Furthermore,    while   McDonnell   Douglas   admittedly    was    aware    of   the
    Government's dissatisfaction with the cocontractors' performance, that
    knowledge alone cannot in this case suffice to prevent the operation of the
    exception for unforeseeable business circumstances.     See Wholesale & Retail
    Food Distribution Local 63 v. Santa Fe Terminal Servs., Inc., 
    826 F. Supp. 326
    ,    332    (C.D.    Cal.   1993)("This    information    [of     a     client's
    dissatisfaction], however, did not rise to the level of putting [the
    employer] on notice that the service agreement would be terminated.");
    Jones v. Kayser-Roth Hosiery, Inc., 
    748 F. Supp. 1276
    , 1286-88 (E.D. Tenn.
    1990) (finding loss of major account unforeseeable even though client had
    vocalized displeasure with product).
    In sum, McDonnell Douglas carried its burden of showing that the
    unforeseeable business circumstances exception applies in this
    14
    case.8   The termination of the A-12 program did not become reasonably
    foreseeable until January 7, 1991.      Because Loehrer and Brandt received
    notice as soon as practicable after that date, there was no violation of
    the WARN Act.9
    III. CONCLUSION
    The district court correctly determined that the exception for
    unforeseeable    business   circumstances   shields   McDonnell   Douglas   from
    liability under the WARN Act.    Consequently, we affirm the district court's
    entry of judgment in favor of the company.
    AFFIRMED.
    8
    This appeal is readily distinguishable from 
    Carpenters, 15 F.3d at 1282
    , in which the Court of Appeals for the Fifth Circuit
    reasoned that a merger of two companies was not unforeseeable to
    the very corporations promoting the merger. Here, in contrast to
    the situation in Carpenters, both the Government and McDonnell
    Douglas were working feverishly to prevent the occurrence of the
    event which caused the mass layoff.
    9
    The former employees have also argued that McDonnell
    Douglas, at some earlier time, should have given them conditional
    notice. The regulations permit conditional notice where the
    occurrence or nonoccurrence of some future event, which is
    certain to transpire, will necessarily lead within sixty days to
    a plant closing or mass layoff. 20 C.F.R. § 639.7(a)(3) (1996).
    To be sure, if the regulatory prerequisites to the issuance of
    conditional notice are satisfied, it seems that an employer would
    in most situations be well-advised to undertake notification in
    order to fend off the prospect of liability. It is clear,
    however, that a decision whether to give conditional notice is
    committed to an employer's discretion. See 
    id. ("Notice may
    be
    given conditional upon the occurrence or nonoccurrence of an
    event . . . ."). Therefore, even assuming that it would have
    been appropriate for McDonnell Douglas to distribute conditional
    notice in the instant case, cf. 54 Fed. Reg. 16,059
    (1989)("[C]onditional notice is permitted only if there is a
    definite event . . . ."), a failure to circulate conditional
    notice cannot, in itself, justify the imposition of WARN
    liability, see 
    id. ("[T]he regulations
    specify that conditional
    notice is optional to avoid the problem of imposing liability on
    employers for failing to give a conditional notice.").
    15
    16
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    17