ABC Electric v. NE Beef ( 2001 )


Menu:
  •                       United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 00-2021
    No. 00-2022
    ___________
    ABC Electric, Inc.,                      *
    *
    Plaintiff - Appellee/              *
    Cross Appellant,                   *
    * Appeals from the United States
    v.                                 * District Court for the
    * District of Nebraska.
    Nebraska Beef, Ltd.,                     *
    *
    Defendant - Appellant/             *
    Cross Appellee,                    *
    ___________
    Submitted: December 14, 2000
    Filed: May 7, 2001
    ___________
    Before LOKEN and MAGILL, Circuit Judges, and BATTEY,* District Judge.
    ___________
    LOKEN, Circuit Judge.
    Nebraska Beef, Ltd. (“Nebraska Beef”), decided to renovate and expand a
    slaughtering and beef processing facility. It hired JB Contracting, Inc. (“JB”), as
    general contractor. JB subcontracted with ABC Electric, Inc. (“ABC”), to provide
    electrical work on the project. As work progressed, problems developed, and ABC
    *
    The HONORABLE RICHARD H. BATTEY, United States District Judge for
    the District of South Dakota, sitting by designation.
    submitted substantial invoices for the costs of excessive overtime and extra work.
    Nebraska Beef refused to pay these additional amounts and eventually ordered ABC
    off the project. ABC filed this diversity suit against Nebraska Beef and JB, seeking
    damages for unpaid work. Nebraska Beef and JB counterclaimed to recover expenses
    incurred in completing the project’s electrical work.
    After ABC dismissed JB from the case, the district court1 concluded there was
    no express or implied-in-fact contract between Nebraska Beef and ABC and dismissed
    all remaining breach-of-contract claims. After a jury trial, the court submitted ABC’s
    quantum meruit and promissory estoppel claims. The jury returned a verdict in favor
    of ABC, awarding damages of $335,190 on the quantum meruit claim and $356,280
    on the promissory estoppel claim. Nebraska Beef appeals, arguing the district court
    erred in construing the subcontract and instructing the jury, in admitting parol evidence,
    in dismissing Nebraska Beef’s breach-of-contract counterclaim, and in awarding
    prejudgment interest. ABC filed a protective cross-appeal. We affirm.
    I. ABC’s Quantum Meruit Claim.
    Under the Nebraska law of quantum meruit, ABC is entitled to recover the
    reasonable value of electrical services that it performed for Nebraska Beef’s benefit in
    circumstances that would make it inequitable for Nebraska Beef not to pay. See, e.g.,
    Hoffman v. Reinke Mfg. Co., 
    416 N.W.2d 216
    , 219 (Neb. 1987). Nebraska Beef
    contends that ABC, an unpaid subcontractor, may not recover from Nebraska Beef, the
    project owner, because the two were not in privity of contract. We disagree. Recovery
    under quantum meruit does not require privity of contract. See Siebler Heating & Air
    Conditioning, Inc. v. Jenson, 
    326 N.W.2d 182
    , 184 (Neb. 1982). The evidence,
    viewed most favorably to the jury’s verdict, established that Nebraska Beef directly
    1
    The HONORABLE WILLIAM G. CAMBRIDGE, United States District Judge
    for the District of Nebraska.
    -2-
    supervised the part of the project that renovated the existing facility. Nebraska Beef,
    not JB the general contractor, controlled the entire project, finally approved change
    orders, and directly paid ABC for work performed. ABC’s quantum meruit claim did
    not include work for which Nebraska Beef had paid JB. In these circumstances, we
    conclude the Supreme Court of Nebraska would apply the principles of quantum meruit
    to permit an unpaid subcontractor to recover from the project owner. See generally
    Annot., Building and Construction Contracts: Right of Subcontractor Who Has Dealt
    with Primary Contractor to Recover Against Property Owner in Quasi Contract, 
    62 A.L.R. 3d 288
     (1975).
    A party may not recover under quantum meruit for work it was obligated to
    perform under an express contract. See Siebler, 326 N.W.2d at 184-85. However, a
    quantum meruit claim may supplement an express contract by seeking reasonable
    compensation for work not covered by the contract. See Associated Wrecking &
    Salvage Co. v. Wiekhorst Bros. Excavating & Equip. Co., 
    424 N.W.2d 343
    , 348-49
    (Neb. 1988). Here, ABC’s subcontract with JB required ABC to perform electrical
    work for an $880,000 “Contract Price.” ABC’s quantum meruit claim is not precluded
    by the subcontract, but it may not recover for the work it promised to perform for
    $880,000. Construing the proper scope of the $880,000 price term in the subcontract
    is the most difficult and critical issue in this case.
    The parties agree that two provisions in the subcontract defined what work was
    covered by the contract price -- the scope-of-work paragraph, in which ABC agreed to:
    Furnish and install, complete all electrical work per plans and specs
    described on Schemmer Associates, Inc. drawings . . . [plus] temporary
    wiring/lighting as required in existing and new plant. Sub-Contractor is
    aware that Nebraska Beef will add equipment requiring electrical services
    to its existing plant and new addition, not shown on plan or specified.
    Sub-Contractor agrees to provide electrical service as required. Electrical
    is deemed to mean all inclusive electrical wiring, outlets, breakers, panels,
    -3-
    etc. as required such that when this contract is complete, the plant is
    operational electrically for production equipment.
    and the contract price provision, in which JB agreed:
    To pay [ABC] for the full, faithful and prompt performance of this
    contract agreement, subject to all of the terms and conditions hereof, the
    sum of Eight hundred and eighty thousand Dollars ($880,000.00)
    hereinafter called the “Contract Price” plus all additions and less all
    deductions herein provided for . . . .
    A major difficulty in construing and integrating these provisions is that the Schemmer
    Associates drawings referred to in the scope of work covered only the proposed
    addition to the facility, whereas the entire project also included a major renovation of
    the existing facility. The parties hotly disputed, at trial and on appeal, whether the
    $880,000 contract price covered only, in the words of the scope-of-work provision, “all
    electrical work per plans and specs described on Schemmer Associates, Inc. drawings.”
    Under Nebraska law, construing an unambiguous contract is a question of law
    for the trial court. “However, if the contract is ambiguous -- that is, if it may
    objectively be understood in more than one sense -- then extrinsic evidence is
    admissible, and the parties’ intent is a question of fact for the jury.” Rayman v.
    American Charter Fed. Sav. & Loan Ass’n, 
    75 F.3d 349
    , 354 (8th Cir. 1996). Here,
    in the Order on Final Pretrial Conference, both parties listed as a disputed issue
    whether the scope of work described in the subcontract was ambiguous. But neither
    party asked the district court to resolve this issue prior to trial, and substantial extrinsic
    evidence on the question of the parties’ intent was admitted without objection at trial.
    At the close of evidence, just prior to the instruction conference, the district court
    ruled that the subcontract unambiguously limited the $880,000 price term to the work
    described in the Schemmer Associates drawings. Although Nebraska Beef objected
    -4-
    to this construction, it did not argue that the subcontract is ambiguous and therefore
    the scope-of-work issue should be submitted to the jury. Accordingly, the district court
    instructed the jury, consistent with its construction of the subcontract, that ABC may
    only recover in quantum meruit for “construction work on the premises of [Nebraska
    Beef] over and above that required under the plans and specs described on Schemmer
    Associates, Inc. drawings.”
    Consistent with its position at trial, Nebraska Beef argues on appeal that the
    subcontract unambiguously committed ABC to perform for $880,000 all electrical work
    within the scope of the entire project (excluding change orders and other extra work
    that were the subject of ABC’s separate promissory estoppel claim). Therefore, the
    question whether the subcontract is ambiguous has been waived, and the only issue
    before us is whether the unambiguous contract has been properly interpreted by the
    district court, or by Nebraska Beef. We review the district court’s interpretation of an
    unambiguous contract de novo. See Case Int’l Co. v. T.L. James & Co., 
    907 F.2d 65
    ,
    66 (8th Cir. 1990).
    The district court construed the subcontract as requiring ABC to perform the
    work detailed in the Schemmer drawings for $880,000, and additional electrical work
    for additional compensation. The court relied on the language in the scope-of-work
    provision that “Nebraska Beef will add equipment requiring electrical services,”
    reading that language in conjunction with the language in the price provision that JB
    would pay $880,000 “plus all additions.” On the other hand, Nebraska Beef argues
    that ABC’s promise “to provide electrical service as required,” including work not
    shown on the Schemmer drawings, means that all such work was included in the
    $880,000 contract price.
    The subcontract was signed after ABC and JB had begun work on the project,
    but before Nebraska Beef had defined the scope of the work to be performed in
    addition to that shown on the Schemmer Associates drawings. Viewing the issue of the
    -5-
    contracting parties’ unambiguous intent at that point in time, JB would not reasonably
    have demanded, and ABC would not reasonably have made, an open-ended
    commitment to perform whatever work Nebraska Beef might decide in the future to
    require for a fixed price of $880,000. Thus, ignoring the extrinsic evidence of intent
    offered at trial -- evidence that may not be considered in construing an unambiguous
    contract -- the district court’s interpretation of the subcontract is clearly more
    reasonable than Nebraska Beef’s. As Nebraska Beef does not argue the subcontract
    is ambiguous in this regard, the district court’s construction must be affirmed.2
    II. A Parol Evidence Issue.
    Nebraska Beef argues the district court erred in admitting parol evidence that
    contradicted the unambiguous terms of the written subcontract. This contention
    borders on the frivolous. Parol evidence is admissible to aid in the interpretation of an
    ambiguous contract. Label Concepts v. Westendorf Plastics, Inc., 
    528 N.W.2d 335
    ,
    339-40 (Neb. 1995). Prior to trial, both parties listed as an issue for trial whether the
    subcontract was ambiguous, and neither party asked the district court to rule on that
    issue before trial. At trial, both parties offered extrinsic evidence on this issue without
    objection. Just prior to the instruction conference, the district court ruled that the
    subcontract was unambiguous, commenting that the court was “at a little bit of a loss
    why neither of the parties have objected to [the extrinsic evidence] on the basis of the
    parol evidence rule.” We decline to review the parol evidence question for plain error.
    It was affirmatively waived by both parties before and during trial.
    2
    Nebraska Beef’s challenge to the district court’s jury instruction on quantum
    meruit is without merit. The instruction accurately reflected the court’s construction
    of the subcontract, which is the proper way to instruct the jury when a contract is
    unambiguous. Nebraska Beef agrees the subcontract is unambiguous, so the only issue
    on appeal is whether the court properly construed that contract.
    -6-
    III. Nebraska Beef’s Counterclaim.
    Nebraska Beef filed a counterclaim for damages it incurred as a result of ABC’s
    alleged breaches of the subcontract. At the close of all the evidence, the district court
    granted ABC judgment as a matter of law on this counterclaim because there was no
    contract between ABC and Nebraska Beef. On appeal, Nebraska Beef does not
    challenge this ruling but argues that it should have been permitted to present its
    counterclaim evidence as an equitable offset to ABC’s quantum meruit and promissory
    estoppel claims. More specifically, Nebraska Beef objects to the district court’s
    exclusion of evidence reflecting amounts paid to other electrical subcontractors after
    ABC was removed from the project. This issue was not properly preserved.
    At trial, Nebraska Beef did not offer this evidence for the purpose of limiting the
    amount ABC should recover on its quantum meruit theory. It was only offered as
    evidence of Nebraska Beef’s damages on a breach-of-contract counterclaim that failed
    as a matter of law because no contract was proved. The district court charged the jury
    that ABC could recover under quantum meruit if it would be “inequitable and
    unconscionable to permit [Nebraska Beef] to avoid payment.” The court did not
    preclude Nebraska Beef from offering evidence and arguing to the jury regarding what
    “inequitable and unconscionable” should mean in this context. The court properly
    dismissed the breach-of-contract counterclaim and excluded as irrelevant evidence
    offered solely to quantify that counterclaim.
    IV. Prejudgment Interest.
    The district court awarded ABC $91,724.69 in prejudgment interest under NEB.
    REV. STAT. § 45-103.02, which provides that a prevailing plaintiff may recover
    prejudgment interest “on the unpaid balance of an unliquidated claim from the date of
    the plaintiff’s first offer of settlement which is exceeded by the judgment.” It is
    -7-
    undisputed that ABC’s settlement offer of April 7, 1998, satisfied the procedural
    requirements of this statute and that the judgment in favor of ABC exceeded that
    settlement offer. Nebraska Beef argues that prejudgment interest should not be
    assessed, however, because ABC’s settlement offer required acceptance by JB,
    Nebraska Beef’s co-defendant in the lawsuit at that time. We disagree. On November
    14, 1997, prior to ABC’s settlement offer, JB and Nebraska Beef entered into a
    separate agreement in which JB assigned all of its claims against ABC to Nebraska
    Beef and granted Nebraska Beef “sole authority and discretion” to settle or
    compromise claims made against JB arising out of this project. Thus, Nebraska Beef
    had the authority to settle the case on behalf of both itself and JB. In these
    circumstances, the district court properly awarded ABC prejudgment interest.
    The judgment of the district court is affirmed. ABC’s cross-appeal is dismissed
    as moot.
    A true copy.
    Attest:
    CLERK, U. S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -8-
    

Document Info

Docket Number: 00-2021

Filed Date: 5/7/2001

Precedential Status: Precedential

Modified Date: 10/13/2015