Save Greers Ferry Lake, Inc. v. Department of Defense , 255 F.3d 498 ( 2001 )


Menu:
  •                     United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    Nos. 00-3320/3321
    ___________
    Save Greers Ferry Lake, Inc., an         *
    Arkansas Not-For-Profit Corporation,     *
    *
    Appellant/cross-appellee,         *
    *
    John E. Allen, Richard E. Atkins,        *
    Clement Valys, Paul E. Barley,           *
    Jim Wallis, John Gillenwater, Jim        *
    Hale, Bill Hebert, Gene Rudd,            *
    Charles Purtle, Joe Coe, Neil            *
    Beisenstein, Samual Boellner, James      *
    Bolhuis, Wesley Harris, Chuck Case,      *
    S.C. Cooke, Carol Fick, Jim Gowen,       *
    William Avrett, Timothy Henwood,         *
    Gene Cutrell, Stacy Schmidt, Bob         *   Appeal from the United States
    Pittman, John Reaves, Shelby Moore,      *   District Court for the
    Edmund Massey, Kenneth Nadeau,           *   Eastern District of Arkansas
    Cecil Roberts, Michael Stuart, Larry     *
    Jolley, John C. Olsen, Bill Julian,      *
    *
    Intervenor Plaintiffs-Appellees. *
    *
    v.                                *
    *
    Department of Defense, United States *
    Army Corps of Engineers, Thomas A. *
    Holden, Jr., Colonel, District Engineer, *
    Little Rock District Corps of Engineers, *
    Edwin J. Arnold, Brigadier General,      *
    Division Commander, Southwest            *
    Division, U.S. Army Corps of             *
    Engineers, Joseph N. Ballard, Lt. Gen.,*
    Chief of Engineers, U.S. Army Corps    *
    of Engineers; Joseph Westphal,         *
    Assistant Secretary, Civil Works,      *
    U.S. Department of the Army, Louis     *
    Caldera, Secretary of the United       *
    States Department of the Army,         *
    *
    Appellees/cross-appellants.      *
    *
    Lance Phillips, William C. Adkisson,   *
    Don St. Pierre, Gerald Schenebeck,     *
    Albert Vajda, Thomas Kennedy,          *
    Charles Doty, Jenette Hebert,          *
    Donald Faughn, Mike Hoffman,           *
    *
    Movants.                  *
    ___________
    Submitted: May 16, 2001
    Filed: July 3, 2001
    ___________
    Before McMILLIAN and BEAM, Circuit Judges, and KYLE,1 District Judge.
    ___________
    McMILLIAN, Circuit Judge.
    Greers Ferry Lake (the Lake) is located in the Ozark Mountains, within the State
    of Arkansas, and its shoreline is under the management of the United States Corps of
    Engineers, Little Rock District (the Corps). On April 12, 2000, a not-for-profit
    1
    The Honorable Richard H. Kyle, United States District Judge for the District
    of Minnesota, sitting by designation.
    -2-
    organization, Save Greers Ferry Lake, Inc. (SGFL), filed the present action in the
    United States District Court for the Eastern District of Arkansas2 under the judicial
    review provisions of the Administrative Procedure Act (APA), 
    5 U.S.C. §§ 702-706
    ,
    seeking injunctive and declaratory relief based upon certain actions taken by the Corps
    in its management of the Lake's shoreline. Jurisdiction was asserted under 
    28 U.S.C. § 1331
    . Specifically, SGFL alleged that the Corps had violated the National
    Environmental Policy Act (NEPA), 
    42 U.S.C. § 4332
    , by issuing a Finding of No
    Significant Impact (FONSI) in relation to its so-called 2000 Shoreline Management
    Plan (2000 SMP), thereby determining it did not have to prepare an Environmental
    Impact Statement (EIS) before adopting the 2000 SMP. NEPA requires all federal
    government agencies to prepare an EIS for all “major Federal actions significantly
    affecting the quality of the human environment.” 
    42 U.S.C. § 4332
    (2)(C). SGFL
    alleged that the 2000 SMP significantly affected the quality of the human environment
    because: (1) it rezoned numerous areas along the Lake, thus authorizing the Corps to
    issue permits for the construction of new boat docks in those rezoned areas; (2) it
    increased by 300% the area around habitable structures that could be cleared of
    vegetation; and (3) it instituted a "Wildlife Enhancement Permit" which allowed
    limited, but unspecified, modifications of the Lake's shoreline. See Appellants'
    Appendix at 28-30 (Complaint for Declaratory and Injunctive Relief, ¶ 38). In its
    complaint, SGFL requested, among other things: a declaration that the 2000 SMP was
    null and void; an order compelling the Corps' compliance with NEPA, including the
    preparation of an EIS, before the adoption of a new shoreline management plan;
    preliminary and permanent injunctions prohibiting the issuance of permits pursuant to
    the 2000 SMP, including permits for the construction of new boat docks; and an order
    requiring the Corps to revoke any permits previously issued pursuant to the 2000 SMP.
    See 
    id. at 39-40
     (request for relief).
    2
    The Honorable William R. Wilson, Jr., United States District Judge for the
    Eastern District of Arkansas.
    -3-
    SGFL moved for a preliminary injunction on April 20, 2000. After holding
    hearings on May 25 and May 30, 2000, the district court granted SGFL's motion.3 See
    Save Greers Ferry Lake, Inc. v. United States Army Corps of Engineers, No. 1:00-CV-
    051 (E.D. Ark. June 1, 2000) (order). In a written order filed on August 24, 2000, the
    district court explained that the record as a whole, including the Corps' own
    environmental assessment, “did not support the Corps’ conclusion that the 2000 SMP
    would have no significant adverse impacts on the environment.” See 
    id.,
     slip op. at 1-2
    (Aug. 24, 2000) (final order). The district court also declared that any boat dock
    permits issued pursuant to the 2000 SMP were "inoperative," except that, where a
    permit had already been implemented – i.e., where a dock had already been constructed
    – those docks could remain in place but were not to be used, pending certain binding
    adjudications or events.4 See 
    id. at 3-4
    .
    In the interim, however, on June 9, 2000, the Corps publicly announced that it
    was canceling and withdrawing the 2000 SMP retroactively to May 30, 2000, and that
    the Corps’ pre-existing shoreline management plan, adopted in 1994, would remain in
    effect pending the adoption of a new shoreline management plan “‘issued pursuant to
    applicable laws and regulations.’” 
    Id. at 2
    . Furthermore, at a hearing before the district
    court held on June 13, 2000, the Corps specifically stated on the record that it would
    prepare an EIS. 
    Id.
    3
    At the same time, the district court denied a motion for summary judgment filed
    by the Corps, but that ruling is not on appeal. See Save Greers Ferry Lake, Inc. v.
    United States Army Corps of Engineers, No. 1:00-CV-051 (E.D. Ark. June 1, 2000)
    (order).
    4
    The Corps had issued 32 boat dock construction permits between April 11 and
    May 23, 2000, pursuant to the 2000 SMP. See 
    id.,
     slip op. at 2 (Aug. 24, 2000) (final
    order).
    -4-
    Meanwhile, a petition for leave to intervene was filed with the district court by
    a group of property owners who had been issued boat dock construction permits prior
    to May 30, 2000, pursuant to the 2000 SMP. The district court granted them leave to
    intervene, for the limited purpose of appealing the district court’s order granting SGFL's
    motion for a preliminary injunction. See 
    id.
     (July 31, 2000) (amended and substitute
    order granting motion to intervene). The intervening property owners (hereinafter
    appellants) timely appealed from the district court's final order enjoining further
    construction or use of boat docks permitted under the 2000 SMP, pending certain
    developments. SGFL cross-appealed the district court's ruling that the handful of boat
    docks already constructed pursuant to 2000 SMP permits could remain on the Lake
    pending certain developments. By letter submitted to this court on November 3, 2000,
    the Corps declined to participate in the appeal.
    We have jurisdiction over the appeal and cross-appeal under 
    28 U.S.C. §§ 1291
    ,
    1292(a).
    For reversal, appellants argue that the district court erred in holding that the
    Corps acted arbitrarily and capriciously in deciding that the 2000 SMP would have a
    significant adverse impact on the human environment and that an EIS was therefore
    required. In response, SGFL argues that there is no longer a live case or controversy
    within the meaning of Art. III, § 2, of the United States Constitution, and the appeal
    should be dismissed as moot. See Brief for Appellee at 14-17 (citing, e.g., Hickman
    v. Missouri, 
    144 F.3d 1141
     (8th Cir. 1998)). In any event, SGFL argues, the district
    court did not err in holding that the Corps acted arbitrarily and capriciously in issuing
    the FONSI and adopting the 2000 SMP.
    As indicated above, the present action was brought under the APA largely to
    challenge the validity of the 2000 SMP under NEPA, in the absence of a supporting
    EIS. Now, to the extent that the 2000 SMP is no longer in force, there is no longer a
    case or controversy for the courts to adjudicate regarding the present or future validity
    -5-
    of the 2000 SMP. In other words, while the district court’s preliminary injunction
    clearly had the salutary effect of prompting the Corps to reevaluate its issuance of the
    FONSI, withdraw the 2000 SMP, and decide to prepare an EIS, the injunction cannot
    continue in effect insofar as it purports to adjudicate the present or future legality of the
    withdrawn 2000 SMP and to order an EIS for the 2000 SMP. To that extent, the
    injunction lacks a jurisdictional basis in federal court.
    There is, however, a live controversy vis-a-vis the legality of the boat dock
    construction permits issued pursuant to the 2000 SMP prior to its revocation. The
    Corps has taken no definitive action with respect to those permits,5 and we recognize
    that appellants, many of whom are holders of such permits, have a real interest at stake
    in this litigation. Upon careful de novo review (for the limited purpose of addressing
    the legality of those existing boat dock construction permits), we agree with the district
    court that the Corps acted arbitrarily and capriciously in issuing the FONSI (a
    determination the Corps does not choose to dispute) and that the 2000 SMP was
    adopted in violation of NEPA. The reasons for these conclusions are thoroughly stated
    in the district court's order of July 31, 2000, and require no elaboration. See Save
    Greers Ferry Lake, Inc. v. United States Army Corps of Engineers, slip op. at 3-9 (July
    31, 2000) (order granting appellants leave to intervene for the limited purpose of
    bringing the present appeal). We therefore hold that any boat dock construction permit
    issued during the short life of the 2000 SMP may not be recognized or enforced as a
    matter of law.
    The boat docks that have already been constructed on the Lake under permits
    issued pursuant to the 2000 SMP may remain on the Lake, and they may be maintained
    5
    In the district court on June 23, 2000, the Corps stated: "[I]t was not the intent
    of the agency to revoke or invalidate boat dock permits issued prior to the preliminary
    injunction. That issue is pending before the Court and is for the Court, not the Corps
    of Engineers, to decide." See Addendum to Reply Brief for Appellants at 1-2.
    -6-
    to prevent movement or deterioration but may not be used for any recreational
    purposes, unless and until the Corps implements a new shoreline management plan in
    full accordance with NEPA and lawfully issues new permits for those docks or unless
    the docks can be authorized and permitted under the pre-existing (prior to the 2000
    SMP) shoreline plan in which event they may be both maintained and used like any
    other similar installations. If they may not be so authorized and permitted and if the
    Corps does not take such action within one year after the date of this order, then the
    subject boat docks shall be removed by whoever owns them as of that one-year
    anniversary date, subject to any order(s) permitting further maintenance or use issued
    by the district court or this court prior to that anniversary date.
    In conclusion, we remand the case to the district court with instructions to
    dissolve the preliminary injunction. The district court shall dismiss the case to the
    extent it is now moot and shall take any additional actions it deems necessary and
    appropriate to dispose of the case consistent with our opinion.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -7-
    

Document Info

Docket Number: 00-3320, 00-3321

Citation Numbers: 255 F.3d 498

Judges: McMillian, Beam, Kyle

Filed Date: 7/3/2001

Precedential Status: Precedential

Modified Date: 10/19/2024