International Paper Co. v. United Paperworkers International Union , 215 F.3d 815 ( 2000 )


Menu:
  •                      United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 99-1890
    ___________
    International Paper Company,           *
    *
    Appellee,                *
    * Appeal from the United States
    v.                              * District Court for the Eastern
    * District of Arkansas.
    United Paperworkers International      *
    Union; United Paperworkers             *        [PUBLISHED]
    International Union, Local 735;        *
    International Brotherhood of           *
    Electrical Workers,                    *
    *
    Appellants.              *
    ___________
    Submitted: December 15, 1999
    Filed: June 12, 2000
    ___________
    Before BEAM, HEANEY, and HANSEN, Circuit Judges.
    ___________
    BEAM, Circuit Judge
    The United Paperworkers International Union, its Local, and the International
    Brotherhood of Electrical Workers (collectively, "the Union") appeal the district court's
    order vacating an arbitration award. We affirm the district court.
    -2-
    I.    BACKGROUND
    International Paper Company ("the Company") owns and operates a paper mill
    in Pine Bluff, Arkansas. The production and maintenance workers at the mill are
    members of the Union. The workers are covered by a collective bargaining agreement
    (CBA) with the Company. The 1993 to 1998 CBA was in force at the time of the
    dispute at issue in this case.
    The CBA provides that "maintenance employees are generally expected to
    perform operating maintenance, preventive maintenance and day-to-day equipment
    repairs." CBA Article XVII § (B)(1)(b). Another provision in the agreement requires
    the Company to employ a "crew sufficient to do the work required in each department,"
    including maintenance. CBA Article XVII § (A)(1). The CBA also recognizes,
    however, that "situations may arise which will necessitate the use of outside forces to
    perform such work." CBA Article XVII § (B)(1)(b). In such cases, "when outside
    forces are in the Mill to perform such work," the agreement provides for a "matching
    hour penalty," that requires employees to be offered overtime to the same extent as the
    outside forces. CBA Article XVII § (B)(1)(b).
    The parties' bargaining history shows that over time the parties have agreed to
    accept more work by outside contractors. Before 1983, the agreement generally
    prohibited subcontracting of maintenance work except in very limited circumstances.
    Both the 1983 and 1990 agreements relaxed the maintenance subcontracting
    restrictions.
    The "crew sufficient" language was first proposed by the Union and added to the
    CBA in 1970 in response to concerns that crews were often understaffed and it was
    unfair, for example, to require three employees to do the work of four. The language
    appeared in two places in the 1983 and 1990 agreements: in Article XVII, paragraph
    (A)(1) (referring to all departments) and again in paragraph (C)(1)(a), the paragraph
    -3-
    that refers to subcontracting of maintenance work. Although the first reference to
    "crew sufficient" still appeared in the 1993-98 CBA, the second reference to the "crew
    sufficient" language was deleted from the agreement.
    On February 15, 1994, the Company shut down a large piece of equipment for
    eight hours of routine preventive maintenance work and hired an outside contractor to
    perform the work. The Union filed a grievance asserting that the Company had
    violated the terms of the contract by hiring outside contractors to perform routine
    maintenance. The Union contended that the "crew sufficient" language required the
    Company to maintain a maintenance work force of 186 general maintenance (GM)
    engineers and that the Company had failed to maintain that work force level. Its
    desired settlement was that the Company "hire enough GM's to replace retired GM's
    and future GM's as they retire." The Company was also asked to "[s]top this practice
    of using [outside workers] on [preventive maintenance] for shut-downs." The
    Company denied the grievance asserting that the shutdown was a situation that
    necessitated "the use of outside forces to perform such work" under the contract.
    The matter proceeded to arbitration. After a hearing, the arbitrator found that,
    although the "crew sufficient" language of the contract did not require the Company to
    maintain any particular number of maintenance employees, it obligated the Company
    to hire enough employees to accomplish the work of the maintenance department. The
    arbitrator thus found that the "employees of the Maintenance Department [had] the
    right to perform operating maintenance work, preventive maintenance work, and day-
    to-day equipment repairs" and ordered the Company to "cease and desist from the
    practice of using contractors or any outside forces to perform that work."
    The Company appealed the decision to the district court. On cross-motions for
    summary judgment, the district court found that the arbitrator's award "fails to draw its
    essence from the contract" and vacated the award. The Union appeals.
    -4-
    II.   DISCUSSION
    The scope of judicial review of an arbitrator's decision is narrow. See Alvey,
    Inc. v. Teamsters Local Union No. 688, 
    132 F.3d 1209
    , 1211 (8th Cir.1997). A court
    may not reconsider the merits of an award even if the award rests on errors of fact or
    on a misinterpretation of the contract. See 
    id. As long
    as an arbitrator's award draws
    its essence from the collective bargaining agreement, the award is legitimate. See 
    id. A court
    cannot interfere with the arbitrator's award unless the contract is not susceptible
    of the arbitrator's interpretation. See Kewanee Machinery Div. v. Local Union No. 21,
    
    593 F.2d 314
    , 318 (8th Cir.1979).
    In deciding whether an award draws its essence from the agreement, we must
    decide whether the award is simply a mistaken interpretation of the contract that we
    must uphold, or whether it violates the fundamental principle that "an arbitrator is
    confined to interpretation and application of the collective bargaining agreement; he
    does not sit to dispense his own brand of industrial justice." United Steelworkers v.
    Enterprise Wheel and Car Corp., 
    363 U.S. 593
    , 597 (1960). Although an arbitrator
    may look to outside sources to aid in interpreting a collective bargaining agreement, he
    must construe the contract and he may not amend it. See Keebler Co. v. Milk Drivers
    and Dairy Employees Union, 
    80 F.3d 284
    , 288 (8th Cir.1996).
    We agree with the district court that the award does not draw its essence from
    the contract. The award effectively nullifies the contract language stating that
    "situations may arise which will necessitate the use of outside forces to perform such
    [preventive maintenance] work." The failure of the CBA to define those situations does
    not justify writing them out of the contract altogether. Moreover, the course of dealing,
    bargaining history, and industry custom supports the Company's contention that a
    shutdown may qualify as such a situation. In addition, an injunction banning the use
    of all maintenance subcontracting ignores the agreement's express provision of a
    "matching hour penalty" in the event of the use of such outside contractors. The Union
    -5-
    concedes that even if the Company were to employ a "crew sufficient" in the
    maintenance department, there would still be situations that required outside
    contractors to do maintenance work. Thus, we find that the arbitrator's broad
    injunction banning the use of outside contractors for all preventive maintenance
    contravenes the contract.1
    The Union's reliance on the "crew sufficient" language as essentially a condition
    precedent to the Company's use of outside contractors for maintenance is misplaced.
    We find no support in the record for the contention that the Company agreed to
    maintain any specific number of maintenance employees. The record supports the
    Company's contention that the "crew sufficient" language in the agreement is aimed at
    the problem of overworked employees and not the outside-contracting-of-maintenance-
    work issue. This is shown by the bargained-for deletion of the "crew sufficient"
    1
    The dissent contends that the court simply disagrees with the arbitrator's
    construction of the agreement and implies that the court engages in result-oriented
    jurisprudence. This is simply wrong.
    The arbitrator's decision does not draw its essence from the contract because it
    is expressly contrary to the terms of the agreement. The arbitrator framed the question
    thusly: "Did the Company violate the contract by its assignment of preventive
    maintenance work to outside contractors on February 15, 1994? If so, what shall be
    the remedy?" He never answered the framed question "yes" or "no." If he had done
    so, he would have been forced to decide if the eight-hour shutdown was a "situation"
    where the CBA permitted the Company to bring in outside contractors to do the work
    pursuant to the provisions of Article XVII § (B)(1)(b). Instead, he issued a blanket
    injunction against the Company ever hiring outside workers to do preventive
    maintenance work. That blanket prohibition eviscerates and writes out of the CBA the
    language that permits the Company to hire outside workers to do preventive
    maintenance work in certain "situations." The real issue, avoided by the arbitrator but
    clearly within and the object of his statement of the issue, was whether the eight-hour
    shutdown was one of those "situations" where the CBA gave the Company the right to
    bring in outside workers. The arbitrator did not interpret the contract, he rewrote it.
    -6-
    language in the portion of the contract dealing specifically with subcontracting
    maintenance work.
    III.   CONCLUSION
    For the above reasons, the judgment of the district court vacating the arbitrator's
    award is affirmed.
    HEANEY, Circuit Judge, dissenting.
    The majority overturns the arbitrator's award simply because it disagrees with
    the arbitrator's decision. The Supreme Court and our court have consistently
    disapproved such activism.
    I.     BACKGROUND
    The facts giving rise to this case are quite simple. On February 15, 1994, the
    Company shut down a paper machine to perform eight hours of routine maintenance
    work. It assigned that work to an outside contractor, rather than to its Union
    employees. The Union filed a timely grievance objecting to the assignment. The
    parties agreed to arbitrate the dispute. The CBA provides that the decision of the
    arbitrator shall be final and binding.
    At the outset of the hearing, the Union and the Company were unable to agree
    on the issue to be arbitrated, but stipulated that the arbitrator should frame the issue.
    The arbitrator framed the issue as follows: “Did the Company violate the Contract by
    its assignment of preventive maintenance work to outside contractors on February 15,
    1994? If so, what shall be the remedy?” (J.A. at 57.)
    -7-
    In defense of its position, the Company claimed that it was permitted by the
    CBA to use non-Union employees to perform routine maintenance work. Article XVII
    § (B)(1)(b) of the CBA states:
    The Company recognizes that maintenance employees are generally
    expected to perform operating maintenance, preventative maintenance and
    day-to-day equipment repairs. However, situations may arise which will
    necessitate the use of outside forces to perform such work.
    (J.A. at 108.)
    The arbitrator agreed that the governing provision was Article XVII(B)(1)(b).
    However, he found that the language in the second sentence of this Article was
    ambiguous in that it did not define what type of “situations” would arise that would
    permit the company to use outside contractors for work that Union employees are
    typically entitled to perform. He construed the ambiguity against the Company because
    it authored this provision.
    The arbitrator then stated:
    As described by the Company[,] the disputed work involved
    checking rotating equipment bearings that could only be checked while
    the equipment was not operating, and referred to that work as "preventive
    maintenance." The Company has conceded that such work is normally
    performed by General Mechanics in the Maintenance Department, but
    argues that the use of contractors in this instance was justified by (a) the
    necessity to complete it within the scheduled time frame of 8 hours, (b)
    not all the work could be performed by General Mechanics, (c) all
    available General Mechanics were being utilized, and (d) the decision to
    use a contractor was justified as opposed to interrupting work in other
    areas of the Mill, and was based on sound business practices.
    -8-
    Under other circumstances such reasons for the decision could be
    sound, but the problem with the Company's rationale in these
    circumstances is that it is based on exceptions which are not authorized
    by the Contract, such as Article XVII(B)(2). The Contract doesn't say
    routine maintenance work will be performed by General Mechanics
    "except" when there is a time scheduling problem, or "except" when all
    the General Mechanics are being utilized, or "except" when work in other
    areas would have to be interrupted, or "except" when the decision to use
    contractors is based on sound business practices.
    The Company has no absolute right to employ contractors at will.
    It must do so within the restrictions imposed by the Contract. The
    decision to use contractors can't be justified on the basis of enlightened
    management, labor costs, work efficiency, area priorities, available
    manpower, etc. The question is simply what is allowed by the Contract.
    (J.A. at 70-71 (emphasis added).)
    Because the Company's use of outside contractors to perform maintenance work
    was not specifically permitted by the CBA, he ruled that such use of outside contractors
    in this circumstance violated the CBA.
    II.   DISCUSSION
    It is well established that federal policy strongly favors arbitration as a means of
    resolving labor disputes. See United Paperworkers Int'l Union v. Misco, 
    484 U.S. 29
    ,
    37 (1987); Kewanee Mach. Div. v. Local Union No. 21, Int'l Bhd. of Teamsters, 
    593 F.2d 314
    , 316-17 (8th Cir. 1979). Accordingly, our review of an arbitrator's decision
    is “extremely limited.” United Food & Commercial Workers, Local No. 88 v. Shop
    'N Save Warehouse Foods, Inc., 
    113 F.3d 893
    , 894 (8th Cir. 1997). We must construe
    the arbitrator's award broadly, resolving all doubts in favor of its validity. See 
    id. at 895.
    “Because the parties have contracted to have disputes settled by an arbitrator
    -9-
    chosen by them rather than by a judge, it is the arbitrator's view of the facts and of the
    meaning of the contract that they have agreed to accept.” 
    Misco, 484 U.S. at 37-38
    .
    Contrary to the majority's assertion, the arbitrator did not nullify any contract
    language. He simply construed the CBA in a manner that was unacceptable to the
    Company and unacceptable to the majority. The arbitrator disregarded a portion of the
    CBA that he found too ambiguous to be given any meaning. Absent that portion of the
    CBA, he found no support for the Company's position.
    The arbitrator then ordered the Company to comply with the CBA. The majority
    asserts that this part of the award bans the use of all maintenance subcontracting,
    contravening the plain language of the CBA. I disagree. The arbitrator's award
    recognized that the Company may still use outside contractors, but required that the
    Union workforce be fully utilized before the Company used outside contractors to
    perform routine maintenance.
    Because the majority is not satisfied that the arbitrator's decision was the right
    one, it undertakes its own review and substitutes its own interpretation of the contract
    for that of the arbitrator. This conflicts directly with the Supreme Court's restriction on
    such practices. “[A]s long as the arbitrator is even arguably construing or applying the
    contract and acting within the scope of his authority, that a court is convinced he
    committed serious error does not suffice to overturn his decision.” 
    Misco, 484 U.S. at 38
    ; see also Shop 'N Save Warehouse 
    Foods, 113 F.3d at 895
    ; John Morrell & Co.
    v. Local Union 304 A of the United Food & Commercial Workers, 
    913 F.2d 544
    , 559
    (8th Cir. 1990). The arbitrator's result is fully supported by the record. Therefore, the
    decision should not have been disturbed by the district court, nor should it be disturbed
    by this court. Accordingly, I cannot join in the majority's affirming opinion.
    -10-
    III.   CONCLUSION
    When we review arbitration cases, whether or not this court would reach the
    same conclusion as the arbitrator is not the issue. Rather, we are obligated to broadly
    consider whether there is any support in the record for the arbitrator's award,
    irrespective of whether we believe the arbitrator reached the right conclusion. We are
    not permitted to micro-manage the business of arbitration. The arbitrator's award is
    what the parties bargained for, and the award is supported by the record. Under the
    well-settled precedent of the Supreme Court and this court, the award must stand. I
    respectfully dissent.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -11-