Pat Costner v. URS Consultants ( 2003 )


Menu:
  •                    United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 01-3764
    ___________
    United States of America ex rel. Pat     *
    Costner; Sharon Golgan; Carolyn          *
    Lance; Debra Litchfield; Becky           *
    Summers; Kenny Brown; Edward             *
    Campbell; Don Daniel; Jeffrey Foot;      *
    David Hermanson; Arkansas Peace          *
    Center; Vietnam Veterans of America,     *
    Arkansas State Council, Inc.,            * Appeal from the United States
    * District Court for the
    Plaintiffs/Appellants,      * Eastern District of Arkansas.
    *
    v.                                 *
    *
    United States of America,                *
    *
    Movant,                     *
    *
    URS Consultants, Inc.; Morrison          *
    Knudsen Corporation; MRK                 *
    Incineration, Inc.; Vertac Site          *
    Contractors,                             *
    *
    Defendants/Appellees.       *
    ___________
    Submitted: November 4, 2002
    Filed: January 28, 2003
    ___________
    Before WOLLMAN, FAGG, and LOKEN, Circuit Judges.
    ___________
    WOLLMAN, Circuit Judge.
    This is a qui tam action brought on behalf of the United States by the plaintiffs
    as relators pursuant to the False Claims Act (FCA), 
    31 U.S.C. §§ 3729-3733
    . The
    complaint alleges that URS Consultants, Inc. (URS), Morrison Knudsen Corporation
    (MK), MRK Incineration, Inc. (MRK), and Vertac Site Contractors (VSC) conspired
    to submit false claims for payment under a government contract for the treatment and
    disposal of hazardous waste at the Vertac Chemical Plant site in Jacksonville,
    Arkansas. The plaintiffs appeal the district court’s1 judgment in favor of the
    defendants. We affirm.
    I.
    The plaintiffs filed this False Claims Act suit in 1995. The suit arises out of
    the defendants’ contract with the Environmental Protection Agency to clean up a
    contaminated industrial site known as the Vertac site. We set out the history of the
    site and this litigation in a prior appeal:
    From 1948 to 1987, the Vertac site was home to various chemical,
    herbicide, and pesticide production facilities. Throughout the years,
    chemical waste from such activity was deposited in landfills and stored
    in drums or barrels above ground with little or no attention to human
    health or environmental consequences. As a result, the site became
    extremely contaminated with dioxin and other highly toxic chemicals.
    The United States Environmental Protection Agency (EPA) has placed
    the site on the Superfund National Priorities List.
    ...
    1
    The Honorable James M. Moody, United States District Judge for the Eastern
    District of Arkansas.
    -2-
    Substantial cleanup began in 1987, following Vertac Chemical's
    abandonment of the site. After learning that approximately 28,000
    corroding and leaking drums of toxic waste had been left on the
    premises, the EPA initiated an emergency removal action pursuant to
    section 9604 of the Comprehensive Environmental Response,
    Compensation, and Liability Act (CERCLA), 42 U.S.C. § § 9601-9675
    (1995 & Supp. 1998). The state then negotiated a contract for on-site
    incineration of the waste with MRK Incineration, Inc., which
    subsequently assigned the contract to Vertac Site Contractors, a joint
    venture composed of MRK and MK Environmental Services, a division
    of Morrison Knudsen Corp.
    ...
    Pursuant to the agreement, the state imposed various conditions
    regarding the operation of the incinerator constructed by the contractors,
    but certified that the contractors had demonstrated the ability to satisfy
    state and federal regulations. In 1991, the district court approved and
    entered an additional consent decree. The EPA remained involved in
    the cleanup by monitoring air quality, handling and transporting the
    drums of waste to be incinerated by the contractors, and disposing of
    incinerator ash.
    In 1992, after it became clear that the trust fund would not be
    sufficient to complete the cleanup, the EPA assumed primary
    responsibility for the site and approved a federal removal action using
    federal funds. When the trust fund was depleted, the state terminated its
    contract with Vertac Site Contractors. Soon after, the EPA assigned
    general oversight authority of the site to URS Consultants, Inc. URS
    then entered into a contract with Vertac Site Contractors to continue
    incineration activities. In 1995, the EPA transported the remaining
    drums of toxic waste to a site in Kansas for incineration.
    Costner v. URS Consultants, Inc., 
    153 F.3d 667
    , 671-72 (8th Cir. 1998) (citations
    omitted) (Costner I).
    The EPA assumed responsibility for the project on June 8, 1993. The EPA
    executed an agreement with URS, giving URS general oversight authority over the
    -3-
    incinerator and authorizing it to contract with VSC to continue VSC’s incineration
    operations. From the start of the cleanup, the EPA had a Remedial Project Manager,
    a team of engineers, a risk assessment specialist, and other scientists assigned to the
    site. URS and VSC produced daily, weekly, and monthly reports concerning site
    operations, as well as air monitoring reports, quality assurance reports, and other
    regulatory compliance reports. In response to allegations made by the plaintiffs and
    others during the course of operations, the EPA conducted investigations into
    intentional tampering and regulatory violations. The investigators suggested
    improvements, improvements were made, and the EPA continued to make payments
    under the contract.
    The plaintiffs allege that before and during the course of the contract the
    defendants concealed operational problems and numerous regulatory violations from
    the EPA. They contend that in light of this concealment the defendants’ requests for
    payment constituted false claims under the FCA. After extended discovery, the
    district court granted summary judgment to the defendants on all claims except those
    that alleged tampering with monitoring devices. The district court then dismissed
    certain of the tampering claims, finding they had been pled with insufficient
    particularity. After trial on the remaining two tampering claims, the district court
    entered judgment in favor of the defendants on all claims.
    II.
    We review the district court’s grant of summary judgment de novo, applying
    the same standards as the district court and viewing the evidence in a light favorable
    to the nonmoving party. Hammond v. Northland Counseling Ctr., Inc., 
    218 F.3d 886
    ,
    891 (8th Cir. 2000). Summary judgment is appropriate if there is no genuine issue
    of material fact and the moving party is entitled to judgment as a matter of law. Fed.
    R. Civ. P. 56(c). Once the party moving for summary judgment has demonstrated that
    the record contains no genuine issue on a material fact, the burden is on the
    -4-
    nonmoving party to present affirmative evidence raising a genuine issue as to that
    fact. Hammond, 
    218 F.3d at
    891 (citing Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323
    (1986)).
    A. Materiality
    The False Claims Act imposes liability on “[a]ny person who knowingly
    presents, or causes to be presented, to an officer or employee of the United States
    Government . . . a false or fraudulent claim for payment or approval.” 
    31 U.S.C. § 3279
    (a). In addition, several courts have required that the falsehood in the claim must
    be material to the payment decision. The district court dismissed all but two of the
    plaintiffs’ claims for failure to present affirmative evidence raising a genuine issue
    of material fact regarding the materiality of the defendants’ alleged misstatements and
    omissions. The existence of and appropriate standard for a materiality element is a
    matter of some disagreement in the courts. See, e.g., United States, ex rel. Cantekin
    v. Univ. of Pittsburgh, 
    192 F.3d 402
    , 415-16 (3d Cir. 1999) (declining to decide
    whether such an element exists because the claims at issue would easily qualify);
    United States v. Southland Mgmt. Corp., 
    288 F.3d 665
    , 674-78 (5th Cir.) (questioning
    existence of materiality element, but finding that false certification of compliance
    with condition required for payment satisfied even strict outcome materiality
    standard), reh’g en banc granted, 
    307 F.3d 352
     (5th Cir. 2002); Harrison v.
    Westinghouse Savannah River Co., 
    176 F.3d 776
    , 785 (4th Cir. 1999) (applying
    materiality requirement that depends on “whether the false statement has a natural
    tendency to influence agency action”).
    Although we have not heretofore directly considered whether a materiality
    element is implicit in the Act, we have stated that the Act provides recovery from one
    “who makes a material misrepresentation to avoid paying some obligation owed to
    the government.” United States v. Q Int’l Courier, Inc., 
    131 F.3d 770
    , 772 (8th Cir.
    1997). Moreover, our decision in Rabushka ex rel. United States v. Crane Co.
    -5-
    suggests that outcome materiality is the proper standard. 
    122 F.3d 559
    , 563 (8th Cir.
    1997) (“If Rabushka cannot show that the PBGC would have terminated CF&I’s
    pension plan [if it had known of the misrepresentations and nondisclosures], then
    there is no false claim because . . . liabilities would have occurred regardless of
    Crane’s actions.”). In our prior decision in this case we implied a materiality standard
    stricter than mere relevancy: “only those actions by the claimant which have the
    purpose and effect of causing the United States to pay out money it is not obligated
    to pay . . . are properly considered ‘claims’ within the meaning of the FCA.” Costner
    I, 
    153 F.3d at 677
    . We need not decide the precise contours of the materiality
    requirement, however, because we hold that the plaintiffs have failed to produce
    evidence raising a genuine issue of material fact as to whether the allegedly withheld
    information was even relevant to the EPA’s payment decision.
    In rejecting most of the plaintiffs’ claims, the district court found that although
    the EPA undisputably was informed of the operational problems from at least three
    sources, it nonetheless continued to approve monthly payments. The record contains
    extensive documentation revealing the inspections conducted by the EPA, the reports
    sent to the EPA by the defendant contractors and on-site EPA personnel, and the
    information obtained by the EPA through the plaintiffs’ previous lawsuits and other
    complaints. The EPA did not consider the operational difficulties encountered by the
    defendants to be contractual violations. The EPA worked with the defendants to
    resolve problems as they arose and to improve the efficiency of the process. The
    plaintiffs argue that the EPA was unaware of the extent of the problems and that
    complete knowledge would have been material to the payment decisions. Only with
    respect to the allegations of tampering with the PT-125 kiln draft monitor did the
    plaintiffs produce evidence that the EPA’s payment decision would have probably
    been affected if it had known of a particular omission. Accordingly, the district court
    did not err in granting summary judgment to the defendants on all but the PT-125 kiln
    draft monitor claims.
    -6-
    B. Government Knowledge
    The EPA’s knowledge of operational difficulties also bears on whether the
    defendants had the requisite intent under the Act. “[I]f the government knows and
    approves of the particulars of a claim for payment before that claim is presented, the
    presenter cannot be said to have knowingly presented a fraudulent or false claim.”
    United States ex rel. Becker v. Westinghouse Savannah River Co., 
    305 F.3d 284
    , 289
    (4th Cir. 2002) (quoting United States ex rel. Durcholz v. FKW, Inc., 
    189 F.3d 542
    ,
    543 (7th Cir. 1999)). A contractor that is open with the government regarding
    problems and limitations and engages in a cooperative effort with the government to
    find a solution lacks the intent required by the Act. United States ex rel. Butler v.
    Hughes Helicopters, Inc., 
    71 F.3d 321
    , 327 (9th Cir. 1995) (citing Wang ex rel.
    United States v. FMC Corp., 
    975 F.2d 1412
    , 1421 (9th Cir. 1992)). Similarly, we
    have held that “simple contract breaches . . . cannot provide evidence of a knowing
    violation of the [False Claims] Act.” United States ex rel. Norbeck v. Basin Elec.
    Power Coop., 
    248 F.3d 781
    , 795 (8th Cir. 2001).
    The plaintiffs contend that several of the alleged omissions raise a genuine
    issue of fact sufficient to preclude summary judgment. First, the plaintiffs cite dioxin
    levels recorded by on-site air monitors. The record reflects, however, that this data
    was available to the EPA, although it was not frequently examined because the EPA
    did not view production of the data as a required part of the contract. Second, the
    plaintiffs cite kiln puffs and kiln leaks and the causes thereof. Again, the record
    reflects that from the beginning the EPA knew of ongoing problems with kiln puffs
    and kiln leaks. The kiln puffs were cited as the reason the EPA took over cleanup
    operation from the state. Third, the plaintiffs cite tampering with the stack gas
    monitors by opening the incinerator rod ports. The EPA’s on-site Remedial Project
    Manager testified that the rod ports were regularly opened for maintenance purposes
    during incineration operations. The plaintiffs have directed us to no evidence that
    the rod ports were open for an improper purpose. Fourth, the plaintiffs cite the
    -7-
    defendants’ 1994 OSHA violations. The record shows that the EPA discussed these
    problems with the defendants and referred the matter to OSHA for investigation and
    possible sanctions. Although the record indicates that the defendants’ performance
    under the contract was not perfect, the extent of the government’s knowledge through
    its on-site personnel and other sources shows that, as in Durcholz, the “government
    knew what it wanted, and it got what it paid for.” Durcholz, 
    189 F.3d at 545
    . Thus,
    the district court did not err in finding that the defendants’ openness with the EPA
    about their problems and their close working relationship in solving the problems
    negated the required scienter regarding these issues.
    C. Rule 9(b) Particularity
    We review de novo the district court’s dismissal of a claim for failure to plead
    with particularity. Murr Plumbing, Inc. v. Scherer Bros. Fin. Servs. Co., 
    48 F.3d 1066
    , 1069 (8th Cir. 1995). A complaint alleging violations of the False Claims Act
    must be pled with particularity pursuant to Rule 9(b). United States ex rel. Russell
    v. Epic Healthcare Mgmt. Group, 
    193 F.3d 304
    , 308 (5th Cir. 1999). This
    particularity requirement demands a higher degree of notice than that required for
    other claims. The claim must identify who, what, where, when, and how. Parnes v.
    Gateway 2000, Inc., 
    122 F.3d 539
    , 550 (8th Cir. 1997) (applying Rule 9(b) to a
    securities fraud claim). Rule 9(b) is to be read in the context of the general principles
    of the Federal Rules, the purpose of which is to simplify pleading. Thus, the
    particularity required by Rule 9(b) is intended to enable the defendant to respond
    specifically and quickly to the potentially damaging allegations. Abels v. Farmers
    Commodities Corp., 
    259 F.3d 910
    , 920-21 (8th Cir. 2001).
    The only claims that survived the district court’s rulings on materiality and
    scienter were those relating to allegations of intentional tampering with the PT-125
    kiln draft monitor, a measuring device on the waste incinerator. After five years of
    discovery, the plaintiffs alleged that tampering occurred once on July 14, 1992, once
    -8-
    in mid-July 1993, and on other unspecified occasions. The alleged illegal act is the
    omission of a material fact in a claim for payment. To defend against the charge, the
    defendants must either dispute the occurrence of the alleged acts or attempt to prove
    that they adequately disclosed the acts to the government. Because the plaintiffs did
    not provide any information regarding the identity of those who allegedly tampered
    with the monitors or when such tampering occurred, the complaint is “not specific
    enough to give defendants notice of the particular misconduct which is alleged to
    constitute the fraud charged so that they can defend against the charge and not just
    deny that they have done anything wrong.” United States ex rel. Lee v. Smithkline
    Beecham Clinical Labs., 
    245 F.3d 1048
    , 1051-52 (9th Cir. 2001). Without
    information as to who tampered with the monitors and how and when the tampering
    occurred, the defendants would be largely unable to respond with contemporaneous
    witnesses and documents and expert witnesses to testify as to whether the monitoring
    data is consistent with tampering of the sort alleged to have occurred. Thus, the
    district court did not err in dismissing the claim of tampering on unspecified
    occasions and allowing the plaintiffs to proceed to trial only on the claims of
    tampering on July 14, 1992, and mid-July 1993.
    We find the plaintiffs’ remaining arguments to be without merit.
    The judgment is affirmed.
    A true copy.
    Attest:
    CLERK, U.S. COURT OF APPEALS, EIGHTH CIRCUIT.
    -9-
    

Document Info

Docket Number: 01-3764

Filed Date: 1/28/2003

Precedential Status: Precedential

Modified Date: 10/13/2015

Authorities (17)

murr-plumbing-inc-v-scherer-brothers-financial-services-co-a-minnesota , 48 F.3d 1066 ( 1995 )

ari-parnes-deborah-slyne-corey-emert-faye-martin-anderson-edward-r-pepper , 122 F.3d 539 ( 1997 )

Edwin P. Harrison, and United States of America, Party in ... , 176 F.3d 776 ( 1999 )

Stanley D. Rabushka, Ex Rel. United States of America ... , 122 F.3d 559 ( 1997 )

united-states-v-q-international-courier-inc-sued-as-quick-international , 162 A.L.R. Fed. 641 ( 1997 )

united-states-of-america-ex-rel-erdem-i-cantekin-an-individual-v , 192 F.3d 402 ( 1999 )

Marilynn K. Hammond, M.D. v. Northland Counseling Center, ... , 218 F.3d 886 ( 2000 )

United States of America, Ex Rel. Martin Becker v. ... , 305 F.3d 284 ( 2002 )

United States of America, Exrel., Insoon Lee v. Smithkline ... , 245 F.3d 1048 ( 2001 )

Russell v. EPIC Hlthcare Mgmt , 193 F.3d 304 ( 1999 )

united-states-of-america-united-states-of-america-ex-rel-robert-j-norbeck , 248 F.3d 781 ( 2001 )

dan-abels-les-a-beekman-steven-berschman-ronald-berschman-daryl-cushman , 259 F.3d 910 ( 2001 )

pat-costner-united-states-ex-rel-sharon-golgan-carolyn-lance-debra , 153 F.3d 667 ( 1998 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Chen-Cheng Wang, AKA C.C. Wang, an Individual and Ex Rel. ... , 975 F.2d 1412 ( 1992 )

United States of America Ex Rel. Robert A. Durcholz, and ... , 189 F.3d 542 ( 1999 )

United States of America Ex Rel., and Jerome F. Butler v. ... , 71 F.3d 321 ( 1995 )

View All Authorities »