AgGrow Oils v. National Union Fire ( 2005 )


Menu:
  •                     United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 03-3345
    No. 03-3346
    ___________
    AgGrow Oils, L.L.C.,                      *
    *
    Plaintiff - Appellee,               *
    *
    v.                                  *   Appeals from the United States
    *   District Court for the
    National Union Fire Insurance             *   District of North Dakota.
    Company of Pittsburgh, PA;                *
    Anderson International Corporation,       *
    *
    Defendants - Appellants.            *
    ___________
    Submitted: February 16, 2005
    Filed: August 23, 2005
    ___________
    Before LOKEN, Chief Judge, RILEY and SMITH, Circuit Judges.
    ___________
    LOKEN, Chief Judge.
    AgGrow Oils L.L.C. (AgGrow) hired T.E. Ibberson Company (Ibberson) to
    design and build an oilseed processing plant in Carrington, North Dakota. Ibberson’s
    performance as general contractor was secured by a bond issued by National Union
    Fire Insurance Company of Pittsburgh (National Union). Anderson International
    Corporation (Anderson) supplied critical seed processing equipment. Despite lengthy
    efforts to solve numerous problems, the completed plant was unable to meet promised
    performance levels and closed. This complex litigation followed.
    Following an interlocutory appeal to resolve arbitration issues, AgGrow Oils
    L.L.C. v. Nat’l Union Fire Ins. Co. of Pittsburgh, PA, 
    242 F.3d 777
    (8th Cir. 2001),
    the parties agreed that all disputes would be heard initially by a panel of special
    masters, whose findings of fact would be final. After nine days of testimony, the
    masters issued their Report, and all parties filed objections. In a thorough opinion,
    the district court1 modified some conclusions of law, adopted the masters’ ultimate
    recommendations, and ordered that Ibberson and National Union are jointly and
    severally liable to AgGrow in the amount of $2,578,840.53 and Anderson is jointly
    and severally liable to AgGrow for $900,794.20 of Ibberson’s and National Union’s
    total liability. AgGrow Oils L.L.C. v. Nat’l Union Fire Ins. Co. of Pittsburgh, PA,
    
    276 F. Supp. 2d 999
    (D.N.D. 2003). National Union and Anderson appeal. We
    affirm.
    I. National Union’s Appeal.
    The special masters found that National Union issued a bond guaranteeing
    Ibberson’s performance on the AgGrow project, that Ibberson breached its contract
    with AgGrow, that “[t]he performance bond issued by National Union was properly
    invoked by AgGrow,” and therefore that National Union is jointly and severally liable
    with Ibberson for project costs incurred by AgGrow as a result of the breach. The
    district court then ruled that National Union is also jointly and severally liable for
    AgGrow’s consequential damages (lost profits), making Ibberson and National Union
    jointly and severally liable for AgGrow’s entire $2,578,840.53 recovery.
    1
    The HONORABLE RODNEY S. WEBB, United States District Judge for the
    District of North Dakota.
    -2-
    On appeal, National Union argues it is not liable on the performance bond
    because the evidence establishes that AgGrow never properly invoked the bond,
    despite the special masters’ finding to the contrary. Specifically, National Union
    argues that the district court lacked “jurisdiction” to find that National Union waived
    compliance with certain bond conditions precedent -- that AgGrow as project owner
    must declare Ibberson’s default, formally terminate Ibberson’s right to complete the
    contract, and agree to pay the balance of the contract price to National Union or to a
    contractor selected to perform the contract. Alternatively, National Union argues that
    waiver is an issue of fact and the district court erred in summarily deciding the issue
    without notice to National Union and an evidentiary hearing.
    At the time the parties consented to appointment of the special masters, Rule
    53(e)(4) of the Federal Rules of Civil Procedure provided that, “when the parties
    stipulate that a master’s findings of fact shall be final, only questions of law arising
    upon the report shall thereafter be considered.”2 In a breach of contract action,
    whether a condition precedent to performance of the contract has been satisfied is an
    issue of fact, not an issue of law. See Glatt v. Bank of Kirkwood Plaza, 
    383 N.W.2d 473
    , 480 (N.D. 1986); Reynolds v. Ashabranner, 
    207 S.W.2d 304
    , 307 (Ark. 1948).
    Here, the special masters made the requisite ultimate finding -- “[t]he performance
    bond . . . was properly invoked.” The special masters were not required to make
    subsidiary findings explaining how each condition precedent to National Union’s
    obligations under the bond was satisfied. As this is entirely an issue of fact, Rule
    54(e)(4) makes it unreviewable by this court or by the district court. See Gilbane
    Bldg. Co. v. Fed. Reserve Bank of Richmond, 
    80 F.3d 895
    , 905 (4th Cir. 1996).
    Thus, we need not review the district court’s ruling as to waiver.
    2
    Rule 53 was substantially rewritten in 2003. Present Rule 53(g)(3)(B) also
    permits parties to agree that a master’s findings will be “final.”
    -3-
    Alternatively, we agree with the district court’s resolution of this issue. The
    special masters specifically found that, during the negotiations when AgGrow
    declared Ibberson in default, “National Union . . . advised AgGrow that Ibberson had
    ‘completed its work’” and that “National Union declined to complete performance
    under the Contract.” The district court reasoned that these findings were sufficient
    to support the ultimate finding that the bond was properly invoked because National
    Union’s unequivocal declarations rendered compliance with the additional bond
    conditions a “useless formality.” This analysis is consistent with the factual record
    and is in accord with North Dakota law. See Fargo Pub. Library v. City of Fargo
    Urban Renewal Agency, 
    185 N.W.2d 500
    , 505 (N.D. 1971). National Union’s
    suggestion that the district court’s decision was an unfair surprise is without merit.
    For these reasons, the district court’s judgment holding National Union liable
    on the bond must be affirmed.
    II. Anderson’s Appeal.
    The special masters found that the contract between general contractor
    Ibberson and supplier Anderson included a written guarantee by Anderson that, if its
    expander and expeller equipment received properly prepared oilseeds, the equipment
    would process 200 tons of seed per day and produce “expeller cake” containing only
    5-8% residual oil. Rejecting Anderson’s claim to the contrary, the special masters
    found that Anderson’s equipment “did not perform adequately to produce the
    guaranteed levels for these oilseeds even when the oilseeds provided to the Anderson
    equipment were in substantial conformity with stated specifications.” The special
    masters further found that Anderson breached a duty to cooperate and that Anderson
    agreed to indemnify Ibberson for losses arising from these breaches. Accordingly,
    the masters recommended that Anderson be jointly and severally liable for thirty
    percent of AgGrow’s costs to complete the plant and forty percent of AgGrow’s lost
    -4-
    profits. However, the special masters concluded that AgGrow was barred from
    recovering directly from Anderson by lack of privity and the economic loss doctrine.
    The district court concluded: (i) the contract between Ibberson and Anderson
    included production guarantees and a duty to cooperate; (ii) the special masters’
    findings that Anderson breached these provisions are unreviewable findings of fact;
    (iii) under § 2-207 of the Uniform Commercial Code as adopted in North Dakota,
    N.D. CENT. CODE § 41-02-14, the contract did not contain a promise by Anderson to
    indemnify Ibberson; but (iv) Anderson is directly liable to AgGrow as a third party
    beneficiary of the Ibberson - Anderson contract under N.D. CENT. CODE § 9-02-04.
    Accordingly, the court adopted the special masters’ recommendation that Anderson
    is jointly and severally liable for $900,794.20 of Ibberson’s total liability to AgGrow.
    On appeal, Anderson first argues that the special masters and the district court
    misread the Ibberson - Anderson contract by deriving production guarantees and a
    promise to cooperate from provisions in the sales contract that instead defined duties
    of Ibberson to Anderson. We disagree. As the district court noted, the terms of the
    contract must be determined in accordance with UCC § 2-207(3), N.D. CENT. CODE
    § 41-02-14(3), because it arose by reason of the parties’ performance, rather than by
    a written agreement. We agree with the district court that the contract proposals
    exchanged by the parties, though inconsistent in other respects, were consistent with
    regard to both the production guarantees, which were express warranties by Anderson
    under UCC § 2-313, N.D. CENT. CODE § 41-02-30, and Anderson’s duty to cooperate
    in achieving those guarantees. Thus, the district court correctly concluded that these
    terms were part of the contract as a matter of law. Alternatively, if defining the terms
    of a contract that is inherently ambiguous under UCC § 2-207 is an issue for the fact-
    finder in North Dakota, then the special masters’ resolution of this issue was of
    course final and unreviewable under Rule 53(e)(4).
    -5-
    Anderson next argues it is not liable for breach of the production guarantees
    because the plant never delivered oilseeds to the Anderson equipment that met the
    required contract specifications. This is a question of fact under Rule 53(e)(4).
    Anderson argues we may nonetheless review the masters’ adverse findings because
    a finding of fact that lacks any evidentiary support is an error of law. We are
    skeptical of this blatant attempt to avoid the parties’ stipulation that the masters’ fact
    findings would be final. But in any event, as Anderson has not included in the record
    on appeal the entire fact record before the special masters, we cannot review the
    highly dubious assertion that there was no evidence to support the finding that
    Anderson’s equipment failed to meet its production guarantees even when the plant
    was able to deliver conforming oilseeds to that equipment. Therefore, even if the
    district court erred in failing to consider this purported issue of law, we decline to
    consider the alleged error because we cannot determine whether it was harmless.
    Finally, Anderson argues that, even if it did breach its contract with Ibberson,
    the district court erred in holding Anderson directly liable to AgGrow as a third party
    beneficiary of the contract because the special masters made no finding that AgGrow
    was an intended third party beneficiary. The special masters’ Report did not discuss
    the third-party beneficiary issue. But that is irrelevant. Though the inquiry is fact
    intensive, numerous Supreme Court of North Dakota decisions establish that the
    ultimate third party beneficiary determination is an issue of law. See First Fed. Sav.
    & Loan Ass’n of Bismarck v. Compass Inv., Inc., 
    342 N.W.2d 214
    , 219 (N.D. 1983)
    (“We conclude that as an incidental beneficiary . . . First Federal has no right to
    enforce”); Apache Corp. v. MDU Res. Group, Inc., 
    603 N.W.2d 891
    , 894 (N.D. 1999)
    (“we conclude the trial court did not err in concluding Apache was not a third-party
    beneficiary”); O’Connell v. Entm’t Enters., Inc., 
    317 N.W.2d 385
    , 388 (N.D. 1982)
    (we “conclude that O’Connell was merely an incidental beneficiary”). Thus, the
    district court properly considered and decided the third party beneficiary issue of law
    de novo, based upon the special masters’ findings and other relevant undisputed facts
    in the record.
    -6-
    Under North Dakota law, “[a] contract made expressly for the benefit of a third
    person may be enforced by him.” N.D. Cent. Code § 9-02-04. However, “a party
    only incidentally benefited by performance of a contract is not entitled to maintain an
    action to enforce it.” Hellman v. Thiele, 
    413 N.W.2d 321
    , 325 (N.D. 1987). In
    deciding whether a third party is only an incidental beneficiary, the Supreme Court
    of North Dakota looks to the intent of the contracting parties, which it determines
    from extrinsic evidence as well as from the four corners of the written contract when,
    as here, the contract is ambiguous. First 
    Federal, 342 N.W.2d at 217
    ; 
    O’Connell, 317 N.W.2d at 388
    . In this case, Anderson promised that its equipment would meet
    production guarantees that Ibberson had warranted to AgGrow. “In such cases, if the
    beneficiary [AgGrow] would be reasonable in relying on the promise [to Ibberson]
    as manifesting an intention to confer a right on him, he is an intended beneficiary.”
    Restatement (Second) of Contracts § 302 cmt. d (1979).
    Viewing the entire record, we agree with the district court that AgGrow was
    an intended third party beneficiary entitled to enforce Anderson’s express production
    guarantees in the Ibberson - Anderson contract. The special masters made the
    following findings relevant to this issue:
    • Prior to the formation of AgGrow, Anderson contracted with North
    Dakota State University (NDSU) to prepare an engineering package for a
    mechanical oilseed processing facility, working with John Gardner, a research
    agronomist at NDSU’s Experiment Station in Carrington who later became the
    general manager of AgGrow.
    • AgGrow was then formed and decided to enter into a design/build
    contract with a single firm. Before contracting with Ibberson, AgGrow told
    Ibberson that AgGrow had chosen Anderson to provide the essential plant
    equipment. Ibberson touted its familiarity with Anderson equipment.
    • Ibberson entered into a purchase agreement based on Anderson’s
    February 4, 1997 proposal, which included Anderson’s production guarantees.
    -7-
    AgGrow entered into the design/build contract with Ibberson on May 22, 1997.
    Anderson’s guarantees were “the critical elements in the viability of AgGrow’s
    plan for processing oilseeds” and were “instrumental” in the selection of
    Anderson as equipment provider.
    • Anderson’s proposal to Ibberson contained a flow chart of the plant
    containing the same elements as the flow chart Anderson previously submitted
    directly to AgGrow, demonstrating that Anderson “was not merely a seller of
    goods but provided extensive engineering requirements and parameters that
    were integral to the engineering for the entire process.”
    • Anderson’s engineering and performance commitments created a duty
    to cooperate in the effort to attain the production guarantees following the
    plant’s start-up.
    In addition, the district court noted that the front cover of Anderson’s formal proposal
    to Ibberson identified the AgGrow Oils Project, that Anderson’s letter accompanying
    that proposal referenced the AgGrow Oils Project, and that the proposal included a
    flow chart describing the planned operation of the AgGrow Oils plant.
    In many (perhaps most) construction contract situations, the project owner will
    not be an express third-party beneficiary who may directly enforce warranties made
    by subcontractors or suppliers to the general contractor. See Restatement (Second)
    of Contracts § 302 cmt. e, illus. 19. But this is not a typical situation. Anderson dealt
    directly with AgGrow before Ibberson was retained as general contractor, and both
    Anderson and Ibberson knew the production guarantees were critical to the economic
    success of the project. The guarantees related to the post-completion operation of the
    plant by AgGrow, and their attainment was likely to require both Anderson’s and
    Ibberson’s cooperation. In these circumstances, well documented in the special
    masters’ findings, the record supports the district court’s conclusion that AgGrow
    may directly enforce the production guarantees as an express third-party beneficiary
    -8-
    under § 9-02-04, whether the focus is the intent of the contracting parties, or the
    reasonable understanding of the third party, AgGrow.
    The judgment of the district court is affirmed.
    ______________________________
    -9-
    

Document Info

Docket Number: 03-3345

Filed Date: 8/23/2005

Precedential Status: Precedential

Modified Date: 10/13/2015