Sierra Club v. City of Little Rock ( 2003 )


Menu:
  •                        United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ________________
    No. 03-1160
    ________________
    Sierra Club,                               *
    *
    Appellee,                   *
    *       Appeal from the United States
    v.                                   *       District Court for the
    *       Eastern District of Arkansas.
    City of Little Rock,                       *
    *           [PUBLISHED]
    Appellant.                  *
    ________________
    Submitted: June 11, 2003
    Filed: December 12, 2003
    ________________
    Before MELLOY, HANSEN, and SMITH, Circuit Judges.
    ________________
    HANSEN, Circuit Judge.
    The City of Little Rock appeals the district court's award of attorney fees to the
    Sierra Club in Sierra Club's action against the City and against the Little Rock
    Sanitary Sewer Committee1 under the Clean Water Act, 33 U.S.C. §§ 1251-1387.
    The City also appeals the district court's denial of its request for expert fees. We
    reverse the grant of attorney fees and affirm the denial of expert fees.
    1
    The district court ordered that both the City and the Little Rock Sanitary
    Sewer Committee pay attorney fees to Sierra Club. The Little Rock Sanitary Sewer
    Committee does not appeal its order.
    I.
    The City of Little Rock ("the City") operates a Municipal Separate Storm
    Sewer System in the city of Little Rock, Arkansas, pursuant to a National Pollutant
    Discharge Elimination System (NPDES) permit issued by the Arkansas Department
    of Environmental Quality (ADEQ).2 The permit authorizes the City to discharge
    storm water runoff into the Arkansas River. The permit requires the City to
    effectively prohibit non-storm water discharges (i.e., sewage) into the Storm Sewer
    System. The storm water permit also requires the City to operate a Storm Water
    Quality Management Program, which includes controls necessary to reduce the
    discharge of pollutants to the maximum extent practicable, a defined term under the
    permit. The permit further requires the City to utilize "a comprehensive master
    planning process" related to reducing the discharge of pollutants from areas of new
    development. (Appellant's App. at 394.)
    The City has delegated the operation of the Little Rock Sanitary Sewer
    Collection System to the Little Rock Sanitary Sewer Committee (hereinafter "Sewer
    Committee") pursuant to Arkansas statute. See Ark. Code Ann. § 14-235-
    206(a)(1)(A) ("The construction, acquisition, improvement, equipment, custody,
    operation, and maintenance of any works for the collection, treatment, or disposal of
    sewage and the collection of revenue from it for the service rendered by it, shall be
    effected and supervised by a committee to be designated for that purpose by the
    municipal council."). The Sewer Committee has control over the operation and
    maintenance of the Sanitary Sewer Collection System and control over revenues
    collected from the use of the system. To the extent funds in excess of the revenues
    generated from use of the system are needed to operate and maintain the Sanitary
    2
    The permit was issued to the City and the State Highway Department as co-
    permittees, but we refer only to the City throughout our opinion, as the State Highway
    Department is not a party to this suit.
    2
    Sewer Collection System, the City retains authority to issue bonds or authorize rate
    increases. The Sewer Committee likewise operates pursuant to a NPDES permit.
    The Sierra Club, a national non-profit public interest organization, brought a
    citizens' complaint against the City and the Sewer Committee, alleging that the
    defendants violated the Clean Water Act and their respective permits by allowing
    untreated sewage from the Sanitary Sewer Collection System to overflow (referred
    to throughout the litigation as sanitary sewer overflows) on numerous occasions and
    enter Arkansas rivers and streams. The Sierra Club's second cause of action alleged
    that the City failed to follow the comprehensive master planning process mandated
    by the City's NPDES permit. The Sierra Club alleged in its third cause of action that
    the sanitary sewer overflows also violated the Resource Conservation and Recovery
    Act, 42 U.S.C. § 6901 et seq. ("RCRA"), by creating imminent and substantial
    endangerment to the environment. The district court granted partial summary
    judgment to Sierra Club against the Sewer Committee, finding that it had violated the
    Clean Water Act, a strict liability statute, by allowing the sanitary sewer overflows.
    See 33 U.S.C. § 1311(a). The Sewer Committee and Sierra Club entered into a
    Settlement Agreement to address the sanitary sewer overflows. Sierra Club dismissed
    the other counts against the Sewer Committee pursuant to the Settlement Agreement.
    Sierra Club pursued its claims against the City following the Settlement
    Agreement with the Sewer Committee. On cross-motions for summary judgment, the
    district court found that "the City [wa]s in violation of the portion of its permit which
    relates to sanitary sewer overflows into the municipal storm sewer system"
    (Appellant's App. at 265), but refused to enter an injunction or order any other
    remedy against the City. The court retained jurisdiction "to resolve any issues which
    may develop regarding remedies for permit violations." (Id.) The court subsequently
    held a bench trial, found for the City on Sierra Club's other claims, and ordered the
    case closed. (Id. at 400.)
    3
    Following the district court's disposition of the case, Sierra Club moved for an
    award of attorney fees against the Sewer Committee and the City. The City sought
    an award of expert witness fees against Sierra Club related to its successful defense
    of the comprehensive master planning process portion of the case. The district court
    denied the City's request, holding that as a prevailing defendant, the City had failed
    to establish that Sierra Club's action was frivolous, unreasonable, or without
    foundation. The court granted Sierra Club the full amount of attorney fees ($92,635)
    sought against the Sewer Committee, which award is not involved in this appeal, and
    granted 50% of the fees sought against the City to reflect the City's partially
    prevailing status. The City appeals the district court's denial of its motion for expert
    witness fees and its judgment ordering the City to pay $50,308.09 in attorney fees to
    Sierra Club.
    II.
    The Clean Water Act allows "any citizen to commence a civil action on his
    own behalf" against any governmental entity that has allegedly violated the Clean
    Water Act. 33 U.S.C. § 1365(a). The district court is authorized to enforce the
    violated standard or limitation and order civil penalties. 
    Id. The Clean
    Water Act
    also provides that "[t]he [district] court, in issuing any final order in any action
    brought pursuant to this section, may award costs of litigation (including reasonable
    attorney and expert witness fees) to any prevailing or substantially prevailing party,
    whenever the court determines such award is appropriate." § 1365(d). While we
    review the district court's decision regarding an award of costs and fees under the
    Clean Water Act for an abuse of discretion, the issue of whether a party is a
    "prevailing or substantially prevailing party" is an issue of law we review de novo.
    See Armstrong v. ASARCO, Inc., 
    138 F.3d 382
    , 388 (8th Cir. 1998).
    4
    A.    Sierra Club's Motion for Attorney Fees
    The City appeals the district court's award of $50,308.09 in attorney fees to
    Sierra Club, arguing that Sierra Club is not a substantially prevailing party. In
    granting partial summary judgment in favor of Sierra Club on the issue of whether the
    City violated its permit in allowing the sanitary sewer overflows to occur unabated,
    the court determined that the regulations under the Clean Water Act required the
    operator of a storm sewer system ultimately to either entirely eliminate non-storm
    water discharges into the storm sewers or seek a permit allowing a certain number of
    non-storm water discharges. The court found that the City was "technically in
    violation of its permit" (Appellant's App. at 333), given the length of time and the
    number of sanitary sewer overflows that had continued unabated. Despite the
    violation, the district court declined to award any of the relief Sierra Club sought,
    which included in relevant part: a declaration that the City was in violation of the
    Clean Water Act; an injunction ordering the City to comply with its permit, to cease
    all unlawful discharges, and to clean up prior unlawful discharges; and civil penalties
    up to $25,000 per day. (Id. at 33-35.) In denying Sierra Club's request for an
    injunction, the court noted that there was no evidence that the City would not
    cooperate with the Sewer Committee in carrying out the Sewer Committee's
    obligations under the Settlement Agreement, as the only record evidence showed that
    the City had always complied with the Sewer Committee's reasonable requests in the
    past. (Id. at 333-34.)
    Under the American Rule, parties to a lawsuit generally foot their own attorney
    fees "absent explicit statutory authority" to the contrary. Buckhannon Bd. & Care
    Home, Inc. v. W.V. Dep't of Health & Human Res., 
    532 U.S. 598
    , 602 (2001). The
    Clean Water Act explicitly allows an award of attorney fees to "a prevailing or
    substantially prevailing party." 33 U.S.C. § 1365(d). A party prevails either by
    "obtain[ing] an enforceable judgment . . . or comparable relief through a consent
    decree or settlement . . . [that] directly benefit[s the plaintiff] at the time of the
    judgment or settlement." Farrar v. Hobby, 
    506 U.S. 103
    , 111 (1992) (internal
    5
    citations omitted). The Supreme Court has made clear "'that a plaintiff [must] receive
    at least some relief on the merits of his claim before he can be said to prevail,'"
    
    Buckhannon, 532 U.S. at 603-04
    (quoting Hewitt v. Helms, 
    482 U.S. 755
    , 760
    (1987)), such that the relief "materially alters the legal relationship between the
    parties by modifying the defendant's behavior in a way that directly benefits the
    plaintiff." 
    Farrar, 506 U.S. at 111-12
    . Further, the change in the relationship must
    be "judicially sanctioned;" a voluntary change in the relationship between the parties
    as a result of a lawsuit is insufficient to trigger a shift in the general rule that parties
    pay their own fees. 
    Buckhannon, 532 U.S. at 605
    (rejecting catalyst theory of
    awarding attorney fees under prevailing party fee-shifting statutes).
    Sierra Club can point to no "actual relief on the merits" as against the City.
    While the Sewer Committee entered a Settlement Agreement and agreed to address
    the sanitary sewer overflows, the City was not party to the agreement. Although the
    district court granted summary judgment in Sierra Club's favor, all Sierra Club
    received was a declaration that the City had violated its permit. The court declined
    to grant any of the relief that Sierra Club sought, not even a requested order enjoining
    the City from future violations of its permit. "A declaratory judgment . . . will
    constitute relief . . . if, and only if, it affects the behavior of the defendant toward the
    plaintiff." Rhodes v. Stewart, 
    488 U.S. 1
    , 4 (1988) (reversing attorney fee award in
    42 U.S.C. § 1988 case in which court found that prison officials violated prisoners'
    procedural rights in denying request for magazine subscription, where only relief was
    in form of changed prison policies that did not benefit either plaintiff as neither were
    in custody at time judgment was entered). "[A] judicial pronouncement that the
    defendant has violated the law, . . . without an enforceable judgment on the merits,
    cannot render [the plaintiff] a prevailing party." Pedigo v. P.A.M. Transp. Inc., 
    98 F.3d 396
    , 398 (8th Cir. 1996) (reversing attorney fee award where plaintiff received
    no damage award and no longer worked for the defendant, making any equitable
    relief unavailable). Sierra Club can point to no effect that the judicial declaration had
    6
    on the City's behavior toward Sierra Club. Further, without any relief to enforce,
    Sierra Club did not receive an "enforceable judgment" and was not a prevailing party.
    Sierra Club argues that the City's subsequent approval of a 42% sewer rate
    increase, in response to a request by the Sewer Committee for funding to fulfill the
    Sewer Committee's obligations under its Settlement Agreement with Sierra Club,
    constitutes the necessary relief to support an award of attorney fees. It argues that the
    district court's judgment declaring the City in violation of its permit was necessary
    to convince the City to approve the rate increase, inferring that "but for" the court's
    judgment that the City had violated its permit, the City would not have granted the
    rate increase, and the court's retention of jurisdiction supplies the requisite "judicial
    imprimatur" required by Buckhannon. 
    See 532 U.S. at 605
    . The facts of the case do
    not support Sierra Club's conclusion. The relief that Sierra Club sought against the
    City was an assurance that the City would cooperate with the Sewer Committee to
    ensure that the Settlement Agreement was implemented. (Appellant's App. at 312.)
    The district court found that the City had always cooperated with the Sewer
    Committee in the past and that there was no reason to believe it would not continue
    to do so. The district court explicitly refused to grant the requested injunction for this
    very reason. (Id.) Sierra Club cannot rely on the City's subsequent conduct in
    cooperating with the Sewer Committee as judicially sanctioned relief when the court
    specifically refused to require the City to take the subsequent action. The facts of this
    case demonstrate that the Sewer Committee's request was the source of the rate
    increase, not the district court's finding that the City had violated its permit. Cf. Peter
    v. Jax, 
    187 F.3d 829
    , 835-36 (8th Cir. 1999) (holding that plaintiff was not prevailing
    party where state defendant agreed to a stipulated injunction based on change in
    Supreme Court precedent rather than pending litigation), cert. denied, 
    529 U.S. 1098
    (2000).
    7
    The district court's retention of jurisdiction over issues concerning permit
    violation remedies does not aid Sierra Club.3 If the City had declined to implement
    the requested rate increase, the court could not have held the City in contempt under
    its retained jurisdiction because the City would not have been in violation of any
    court order. The court order merely declared the City in violation of its permit and
    the court retained jurisdiction "to resolve any issues which may develop regarding
    remedies for permit violations." (Appellant's App. at 265 (emphasis added).) The
    court did not address what action, if any, the City was required to take in relation to
    the Sewer Committee's Settlement Agreement. In short, the judgment did not change
    the relationship between Sierra Club and the City. "[T]he district court's [retained]
    jurisdiction alone is not enough to establish a judicial 'imprimatur'" where the court's
    jurisdiction does not provide the court with contempt power. Christina A. ex rel.
    Jennifer A. v. Bloomberg, 
    315 F.3d 990
    , 993-94 (8th Cir. 2003) (holding that district
    court's retained jurisdiction over private settlement agreement did not elevate
    agreement to consent decree sufficient to establish prevailing party status; dismissal
    order approving of settlement agreement and retaining enforcement jurisdiction did
    not incorporate any settlement terms and at most provided avenue for parties to seek
    enforcement as a breach of contract, not as violation of a court order). At the end of
    the day, "the judgment . . . afforded [Sierra Club] no relief whatsoever," 
    Rhodes, 488 U.S. at 4
    , and the district court erred in ordering the City to pay attorney fees.
    B.    The City's Motion for Expert Witness Fees
    Where a statute allows an award of litigation fees to a prevailing party, the
    "district court may in its discretion award [litigation] fees to a prevailing defendant
    3
    The City argues that the district court's retained jurisdiction ended when it
    ordered the case closed with the entry of its judgment following the bench trial. The
    closing order does not mention its effect on the court's previously retained
    jurisdiction. Our disposition of this argument makes it unnecessary to resolve the
    extent of the district court's retained jurisdiction.
    8
    . . . upon a finding that the plaintiff's action was frivolous, unreasonable, or without
    foundation, even though not brought in subjective bad faith." Christiansburg
    Garment Co. v. E.E.O.C., 
    434 U.S. 412
    , 421 (1978) (emphasis added). There is no
    dispute that the City was the prevailing party on the comprehensive master planning
    process issue. The district court denied the City's request for expert fees, however,
    because it found that Sierra Club's claims on that issue were "not frivolous,
    unreasonable or without foundation." (Add. at 39.) Because the district court applied
    the proper standard, we review its denial of the City's request for expert fees for an
    abuse of discretion.
    Sierra Club claimed that the City violated its permit by failing to implement "a
    comprehensive master planning process to develop, implement, and enforce controls
    to reduce, to the [maximum extent practicable], the discharge of pollutants from areas
    of new development and significant redevelopment after construction is completed."
    (Appellant's App. at 32 (internal marks omitted).) In denying Sierra Club's motion
    for summary judgment on this issue, the district court noted "that there [wa]s going
    to be conflicting evidence by experts as to whether the City has or has not addressed
    the quality of the discharge into the . . . storm sewer system." (Appellant's App. at
    331.) During the bench trial, Sierra Club's expert testified that in his opinion the City
    had addressed only the quantity of discharge into the storm system but had failed to
    address whether any of the City's processes would reduce pollutants to the maximum
    extent practicable. Sierra Club forwarded its theory that the City, as a permittee, was
    required to perform a thorough review for the explicit purpose of determining
    whether and to what extent the City's procedures would reduce pollutants in areas of
    new development. It argued that a conglomeration of policies and ordinances that
    only tangentially affected water issues was not sufficient to meet the permit
    requirement.
    Although the district court ultimately concluded that "[t]he City has done
    exactly what the City stated would be done in its storm water application and storm
    9
    water permits" (Appellant's App. at 399), we cannot say that Sierra Club's action was
    frivolous, unreasonable, or without foundation. As noted by the district court, the
    EPA has provided tremendous flexibility to permittees "relative to the exact form the
    required comprehensive master planning process may take." (Id.) Nowhere does the
    EPA define what constitutes a comprehensive master planning process. The City's
    comprehensive master planning process has evolved over a period of several years
    and encompasses a variety of different ordinances, plans, codes, standards, and
    related processes. Although the permit does not require the comprehensive master
    planning process to be incorporated into a single document, the City's failure to do
    so made it difficult to determine the City's compliance when Sierra Club originally
    brought this suit. The district court did not abuse its discretion in denying the City's
    motion for litigation costs as the prevailing defendant.
    III.
    The district court's judgment ordering the City to pay attorney fees to Sierra
    Club is reversed, and its judgment denying litigation costs to the City is affirmed.
    ______________________________
    10