Winthrop Resources v. Eaton Hydraulics ( 2004 )


Menu:
  •                   United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 03-1790
    ___________
    Winthrop Resources Corporation,       *
    a Minnesota corporation,              *
    *
    Appellee,                  * Appeal from the United States
    * District Court for the
    v.                              * District of Minnesota.
    *
    Eaton Hydraulics, Inc., formerly      *
    known as Vickers, Inc., a             *
    Delaware corporation,                 *
    *
    Appellant.                 *
    ___________
    Submitted: October 23, 2003
    Filed: March 11, 2004
    ___________
    Before RILEY, HEANEY, and SMITH, Circuit Judges.
    ___________
    SMITH, Circuit Judge.
    Eaton Hydraulics, Inc. ("Eaton"),1 appeals the district court's2 summary
    judgment issued in favor of Winthrop Resources Corporation ("Winthrop") in
    Winthrop's breach-of-contract claim. The district court determined that Eaton
    breached the contract and owes $4,365,437.64 in damages, costs, disbursements, and
    attorney's fees. We affirm.
    I. Background
    Winthrop leases computer systems and other technology equipment to
    corporate customers. After Winthrop's customers select their equipment, Winthrop
    then purchases and leases the equipment to the customers. In June 1997, Eaton and
    Winthrop entered into a master lease agreement.3 The agreement provided that
    Winthrop would purchase almost $9 million of computer equipment that Eaton
    selected. The parties also signed nine lease schedules (001R, 002R, A01, A02, A03,
    B01, B02, C01 and C02) issued pursuant to the master lease agreement.4 Each lease
    schedule identified particular pieces of equipment leased by Eaton, and each
    incorporated the terms of the master lease by reference. Each lease schedule listed the
    monthly amount Eaton agreed to pay for the use of Winthrop's equipment. By
    1
    Vickers, Inc. originally entered into the lease agreements with Winthrop.
    Eaton subsequently acquired Vickers. Eaton acknowledges that it is bound by the
    lease agreements with Winthrop. For ease of discussion, we refer only to Eaton in this
    appeal.
    2
    The Honorable David S. Doty, United States District Judge for the District of
    Minnesota.
    3
    The lease provided that Minnesota law would govern all disputes.
    4
    The master lease agreement and the lease schedules are collectively referred
    to as the "Lease" unless otherwise noted.
    -2-
    executing the Lease, both Winthrop and Eaton expressly agreed that each provision
    was binding and enforceable.5
    Winthrop sued Eaton on April 13, 2001, alleging that Eaton breached the
    Lease. Specifically, Winthrop claimed that Eaton failed to meet numerous payment
    obligations, failed to properly maintain the equipment during possession, failed to
    properly package the equipment upon return, and impermissibly sold pieces of
    equipment in violation of the Lease terms. Eaton counterclaimed that Winthrop
    breached the implied covenant of good faith and fair dealing, committed fraud,
    breached the contract, and violated various provisions of Minnesota law.
    Winthrop moved for summary judgment on its claims and moved to dismiss
    Eaton's counterclaims. In its motion, Winthrop requested damages in the amount of
    $4,222,024.67, plus costs, disbursements, and attorney's fees. Winthrop provided
    affidavits and supporting documents detailing Eaton's various Lease breaches.
    Winthrop submitted its damage calculation pursuant to section 18 of the Lease setting
    forth past-due Lease charges, past-due taxes and late fees, and the greater of: (i) the
    accelerated rent remaining due, or (ii) the Casualty Loss Value ("CLV") for each
    lease schedule.6
    5
    When Eaton acquired Vickers, Eaton sent its standard lease agreement to
    Winthrop and asked Winthrop to substitute Eaton's standard form for the Lease that
    Vickers and Winthrop negotiated and signed. Winthrop declined the proposed
    substitution; however, Winthrop included Eaton's proposed substitution lease in its
    brief and appendix to compare the language of the proposed lease to the language of
    the controlling Lease.
    6
    The "past due" component of Winthrop's damages calculation was the sum
    of: (i) past-due Lease charges incurred during the initial terms of lease schedules
    002R, A02, A03, B01, B02, C01 and C02; (ii) past due Lease charges incurred during
    the extension terms of lease schedules 001R and A01; (iii) past-due taxes and late
    fees. The "greater of accelerated rent or Casualty Loss Value" component of
    Winthrop's damages calculation was the sum of: (i) the CLVs of lease schedules
    -3-
    In its counterclaim, Eaton asserted that: (i) Winthrop failed to give notice and
    opportunity to cure the payment defaults; (ii) it had procured Manufacturer's
    Maintenance Agreements ("MSMAs") on the equipment and that Winthrop purchased
    the MSMAs; (iii) Winthrop breached first; (iv) the CLV was an unenforceable
    penalty; (v) the CLV did not apply to equipment on "terminated" lease schedules.
    Applying Minnesota law, the district court rejected Eaton's arguments as insufficient
    to avoid liability and damages under the plain terms of the Lease.
    On April 23, 2002, the district court granted Winthrop's motion for summary
    judgment. The district court found that Eaton breached the Lease and that the CLV
    damages provision was enforceable. The district court noted that Eaton did not
    dispute that it had breached the Lease. The court also noted that Eaton did not dispute
    Winthrop's damages calculation.
    Winthrop subsequently filed a motion pursuant to Federal Rules of Civil
    Procedure 58 and 59(e) requesting clarification of the damages award in the summary
    judgment and dismissal order. The district court awarded judgment on April 23, 2002,
    in the amount of $4,365,437.64, which included Winthrop's costs and attorney's fees,
    less mitigation, because Eaton failed to challenge Winthrop's calculation of damages.
    On May 8, 2002, Eaton moved pursuant to Federal Rule of Civil Procedure
    59(e) to alter or amend the judgment. Eaton argued that the expert reports it submitted
    after the summary-judgment hearing demonstrated the unreasonableness of the CLV
    provision. Eaton also argued–for the first time–that: (i) Winthrop failed to prove that
    its claimed damages were reasonable; (ii) it could not maintain MSMAs on the
    equipment because MSMAs did not exist for this equipment; (iii) Eaton properly
    terminated lease schedules A02 and C01.
    001R, 002R, A01, A03, B01, B02 and C02, and (ii) the accelerated rents due for lease
    schedules C01 and A02.
    -4-
    On December 10, 2002, the district court denied Eaton's Rule 59(e) motion.
    The district court determined that Eaton failed to submit any newly-discovered
    evidence, failed to show reversible error, and failed to present any facts or law
    overlooked by the court. Following this decision, Winthrop moved for entry of
    judgment on damages, and on February 21, 2003, the district court entered an
    amended judgment including damages in the amount of $4,365,437.64.
    Eaton timely filed a notice of appeal from all of the district court's orders.
    However, in this appeal, Eaton challenges only the grant of summary judgment and
    the order clarifying the damages award.
    II. Standard of Review
    Rule 56(c) provides that a motion for summary judgment shall be granted only
    if "there is no genuine issue as to any material fact and . . . the moving party is
    entitled to judgment as a matter of law." Fed. R. Civ. P. 56(c). We review de novo a
    grant of summary judgment, applying the same standard as the district court.
    Evergreen Inv., LLC v. FCL Graphics, Inc., 
    334 F.3d 750
    , 753 (8th Cir. 2003). When
    considering a motion for summary judgment, we must view the evidence and the
    inferences that may be reasonably drawn from the evidence in the light most
    favorable to the non-moving party. Enter. Bank v. Magna Bank, 
    92 F.3d 743
    , 747 (8th
    Cir. 1996). The burden of demonstrating that there are no genuine issues of material
    fact rests on the moving party. Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986);
    Medtronic, Inc. v. U.S. Xpress, Inc., 
    341 F.3d 798
    , 800 (8th Cir. 2003). If the moving
    party has carried its burden, the non-moving party must demonstrate the existence of
    specific facts in the record that create a genuine issue for trial. Anderson v. Liberty
    Lobby, Inc., 
    477 U.S. 242
    , 256 (1986); Krenik v. County of LeSueur, 
    47 F.3d 953
    , 957
    (8th Cir. 1995). In addition, where the district court's decision involved
    determinations of state law, we review those determinations de novo. Salve Regina
    Coll. v. Russell, 
    499 U.S. 225
    , 231 (1991).
    -5-
    III. Analysis
    Eaton challenged only the summary-judgment and damages orders.7 Despite
    the parties' extensive arguments in the briefs–including arguments raised in and in
    defense of Eaton's Rule 59(e) motion–we review de novo only the evidence and
    arguments that were before the district court when it made its determination in the
    orders challenged on appeal. See Hagerman v. Yukon Energy Corp., 
    839 F.2d 407
    ,
    413 (8th Cir. 1988) (failure to raise an argument when contesting motion for summary
    judgment, and raising it only in a post-judgment Rule 59(e) motion does not preserve
    issue for de novo review on appeal). As such, this appeal turns on two core issues–
    (1) whether Eaton defaulted under the contract, and (2) whether the damages award
    was proper.
    A. Default Under the Lease
    The district court determined that Eaton defaulted under section 17(a) of the
    Lease by failing to make required Lease, late-charge, and property-tax payments for
    the equipment in 2001, failing to properly pack, ship, and return all of the equipment
    as required in section 7, and failing to properly maintain the equipment under the
    MSMAs required in section 8.8
    7
    Eaton's notice of appeal includes the district court's orders on summary
    judgment, damages, and Rule 59(e). However, Eaton stated in its initial brief and in
    oral argument that it appeals only from the district court's orders on summary
    judgment and damages.
    8
    Because we affirm the district court's decision regarding Eaton's default under
    section 17 of the Lease, we need not address whether Eaton also defaulted–or whether
    Winthrop complied with the cure provisions–under sections 7, 8, and 17(b) of the
    Lease.
    -6-
    Eaton argues that it did not default under section 17(a) of the Lease because,
    although it now concedes that it made late payments of "Lease Charges,"9 10 it argues
    for the first time here that section 17(a) required Winthrop to give Eaton notice and
    twenty days to cure any potential default. Section 17(a) of the Lease provides in
    pertinent part:
    The occurrence of any of the following events shall constitute an
    event of default under this Lease Agreement or any Lease Schedule:
    9
    Section 3 of the Lease provides that the aggregate Lease charges are due no
    later than the first day of each month, and late charges accrue if payments are not
    timely:
    The Monthly Lease Charge shall be paid by Lessee monthly in advance
    (first day of the month) with the first full month’s payment due on the
    Commencement Date.
    ***
    Lessee agrees that if payment as specified above is not received by
    Lessor on the due date, Lessee shall . . . pay on demand, as a late charge,
    an amount equal to one and one-half percent (1½%) or the maximum
    percentage allowed by law, whichever is less, of the amount past due.
    10
    Winthrop submitted documentation detailing which payments were late and
    by how many days, and summaries of unpaid charges and late charges due as of
    December 31, 2001. Eaton, on the other hand, submitted affidavits from two of its
    employees denying that it made any payments late. Eaton argues that these affidavits
    created a question of fact sufficient to defeat summary judgment. These affidavits are
    unsupported by any documentation. A party resisting a properly supported summary-
    judgment motion may not rest upon the mere allegations or denials of the pleadings,
    but by affidavit or otherwise as provided by Rule 56 must set forth specific facts
    showing the existence of a genuine issue for trial. Allen v. Entergy Corp., 
    181 F.3d 902
    , 904 (8th Cir. 1999) (citing Dancy v. Hyster Co., 
    127 F.3d 649
    , 653 (8th Cir.
    1997), cert. denied, 
    523 U.S. 1004
     (1998); Fed. R. Civ. P. 56(e)).
    -7-
    (a) The nonpayment by Lessee of any Lease Charges when due, or the
    nonpayment by Lessee of any other sum required hereunder to be paid
    by Lessee which nonpayment continues for a period of twenty (20) days
    after written notice thereof from Lessor.
    The district court determined that this section unambiguously provides that default
    occurs if Eaton failed to pay Lease charges when due. Eaton argues that the district
    court incorrectly interpreted the plain, unambiguous language of section 17(a).
    To interpret the terms of a contract under Minnesota law, we must initially
    determine whether a contract term is ambiguous. Porous Media Corp. v. Midland
    Brake, Inc., 
    220 F.3d 954
    , 959–960 (8th Cir. 2000) (citing Green Tree Acceptance,
    Inc., v. Wheeler, 
    832 F.2d 116
    , 117 (8th Cir. 1987) (applying Minnesota law)). The
    determination that a contract is or is not ambiguous is a legal determination, and no
    deference is paid to the trial court's decision on this issue. Maurice Sunderland
    Architecture, Inc. v. Simon, 
    5 F.3d 334
    , 337 (8th Cir. 1993); Blattner v. Forster, 
    322 N.W.2d 319
    , 321 (Minn. 1982). If the contract is unambiguous, the interpretation is
    a question of law and is reviewed de novo. Lakeland Tool & Eng'g, Inc. v.
    Thermo-Serv, Inc., 
    916 F.2d 476
    , 481 (8th Cir. 1990) (applying Minnesota law).
    However, if a contract is ambiguous, the meaning of the contract becomes a
    question of fact, City of Virginia v. Northland Office Properties Ltd. Partnership, 
    465 N.W.2d 424
    , 427 (Minn. Ct. App.1991), and summary judgment is inappropriate. In
    re Turners Crossroad Dev. Co., 
    277 N.W.2d 364
    , 368 (Minn. 1979). In interpreting
    the meaning of an unambiguous contract, the court cannot consider anything other
    than the contract. Carl Bolander & Sons, Inc. v. United Stockyards Corp., 
    215 N.W.2d 473
    , 476 (Minn. 1974). However, if a contract term is ambiguous, extrinsic
    evidence can be considered by the trier of fact to help it determine the parties' intent.
    Material Movers, Inc. v. Hill, 
    316 N.W.2d 13
    , 17 (Minn. 1982).
    -8-
    We believe the district court properly interpreted and applied the plain
    language of section 17(a). Section 17(a) provides two ways Eaton could default
    through nonpayment: 1) "nonpayment of any Lease Charges when due," or 2)
    "nonpayment of any other required sum which nonpayment continues for a period of
    twenty days after written notice." Grammatically, this language describes alternative
    nonpayment default triggers. It consists of two independent clauses, separated by a
    comma and the disjunctive "or," with no comma before the word "which" in the
    second clause. This clearly indicates that the sentence contains two separate
    provisions under which default may occur. Section 17(a) unambiguously provides
    that default occurred when Eaton failed to make timely payment of Lease charges. As
    such, we affirm the district court's determination that Eaton defaulted under section
    17(a) of the Lease.
    B. Damages
    Section 18 of the Lease provides various remedies that Winthrop may pursue
    in whole or in part upon Eaton's default. The relevant terms of section 18 provide:
    (a) Without retaking the Equipment
    (1) recover from Lessee all accrued and unpaid rents and other amounts
    then due and owing under the terms hereof,
    ***
    (3) accelerate and cause to become immediately due and payable all
    rents and other amounts due and/or likely to become due hereunder and
    recover from Lessee the then worth to Lessor of such amounts,
    (4) cause to become immediately due and payable and recover from
    Lessee the then applicable Unrecovered Investment in the Equipment;
    (b) Retake possession of the Equipment (by Lessor, independent
    contractor, or by requiring Lessee to assemble and surrender the
    -9-
    Equipment in accordance with the provisions of Section 7 hereinabove)
    without liability to Lessee therefor which is hereby expressly waived,
    and
    ***
    (2) recover from the Lessee all accrued and unpaid rents and other
    amounts owing under the terms hereof,
    (3) sell the Equipment at public or private sale, and recover from Lessee
    the difference, if any, by which the Net Proceeds of sale shall be less
    than the Lessor's then applicable Unrecovered Investment in the
    Equipment, . . . .
    Based on these recovery provisions, Winthrop claimed $4,222,024.67 in total
    damages. Eaton contested the claim by arguing that the CLV Lease provision was an
    unenforceable penalty rather than a liquidated-damages clause and that the CLV did
    not apply to equipment on terminated lease schedules.11 The district court determined
    that Winthrop was entitled to the entire amount–plus costs, disbursements, and
    attorney's fees–for an award totaling $4,365,437.64.12
    11
    The court noted in its February 21, 2003, order on Winthrop's motion for
    entry of judgment on damages that Eaton did not contest the calculation of damages,
    only whether damages were permissible. Eaton raised the calculation argument for
    the first time in its Rule 59(e) motion, arguing that Winthrop only provided the
    summary of damages in its reply brief on summary judgment. The record indicates,
    however, that Winthrop provided this summary in both the documents submitted in
    support of its motion for summary judgment and with an affidavit in its reply.
    Regardless, because this claim was raised in Eaton's Rule 59(e) motion, it is not
    cognizable on review of summary judgment.
    12
    The district court awarded the initial $4,222,024.67 in damages plus
    $221,132.97 in costs, disbursements, and attorney's fees, less $77,720 in mitigation,
    for a total judgment of $4,365,437.64.
    -10-
    We have reviewed the parties' summary-judgment arguments presented to the
    district court. Contrary to Eaton's much-expanded arguments on appeal, Eaton's
    summary-judgment response challenged Winthrop's motion on only two
    grounds–whether the CLV clause in the contract is an unenforceable penalty clause
    or a permissible liquidated-damages clause and whether the CLV applies to
    equipment on terminated lease schedules.
    1. Liquidated-Damages Clause
    Regarding whether the CLV is a liquidated-damages13 clause, Eaton argued in
    its response to summary judgment that the CLV clause, "independent of the other
    cumulative remedies set forth in the Lease, results in absurd and patently
    unreasonable penalty damages." Eaton based its proportionality argument upon the
    comparison of the fair-market value and the CLV. For example, Eaton argued that a
    computer with a fair-market value of $75 has a CLV of $500 to $700. Eaton argued
    that Winthrop's CLV is based, not on fair-market value upon return, but instead on
    the interest rate and "soft costs" associated with Winthrop's purchase of equipment.
    Finally, Eaton argued that Winthrop should not be permitted to recover both the
    accelerated Lease payments and the CLV.
    Under Minnesota law, a liquidated-damages clause is enforceable when 1) "the
    fixed amount is a reasonable forecast of just compensation for the harm caused by the
    13
    The term "liquidated damages" signifies the damages the amount of which the
    parties to a contract stipulate and agree, when the contract is entered into, shall be
    paid in case of breach. It is well settled that the parties to a contract may stipulate in
    advance as to the amount to be paid in compensation for loss or injury which may
    result in the event of a breach of the agreement. A stipulation of this kind is
    enforceable, at least in those cases where the damages which result from a breach of
    the contract are not fixed by law or are in their nature uncertain and where the amount
    stipulated does not manifestly exceed the injury which will be suffered. Dean Van
    Horn Consulting Assoc., Inc. v. Wold, 
    367 N.W.2d 556
    , 559–560 (Minn. App. 1985)
    (internal quotations omitted).
    -11-
    breach," and 2) "the harm is incapable or very difficult of accurate estimation."
    Bellboy Seafood Corp. v. Nathanson, 
    410 N.W.2d 349
    , 352 (Minn. Ct. App. 1987).
    The difficulty of proving damages is an important factor in determining whether the
    provision in the contract is a penalty. Meuwissen v. H.E. Westerman Lumber Co., 
    16 N.W.2d 546
    , 550 (Minn. 1944). Liquidated-damages clauses function best when
    damages include items such as goodwill and loss of profits, which can be difficult to
    evaluate. Id. at 550. "It is not of controlling importance, where the actual damages are
    doubtful, speculative, and difficult of proof, that the amount stipulated is much larger
    than the apparent actual injury and loss." Id. (quoting Taylor v. Times Newspaper,
    Co., 
    86 N.W. 760
    , 762 (Minn. 1901)). In addition, "[t]he rule is well settled that a
    contract provision for liquidated damages can be enforced without proving actual
    damages as long as the amount stated is reasonable." Willgohs v. Buerman, 
    115 N.W.2d 59
    , 62 (Minn. 1962).
    In determining the legality of the clause, we have to determine 1) whether the
    fixed amount is a reasonable forecast of just compensation for the harm caused by the
    breach, and 2) whether the harm is incapable or very difficult of accurate estimation.
    Bellboy Seafood Corp., 
    410 N.W.2d at 352
    . We find that the CLV clause in this
    contract is a proper liquidation clause because of the speculative nature of the value
    of the computers at termination of the lease schedules. Eaton's argument is that the
    percentages used in the CLV calculation are too high because the fair-market value
    of the equipment at lease-schedule termination will be much lower than the amount
    the percentages allow. However, the CLV provision is clearly not a fair-market value
    calculation. Instead, the CLV presumably includes Winthrop's liability for buying the
    computer equipment, any damage or loss of the equipment, and other reasonable
    considerations. That the CLV percentage at the end of a lease-schedule term or upon
    default may be four or five times the fair-market value of the equipment does not
    render this CLV clause a penalty clause. The parties negotiated these values prior to
    signing the contract, and the percentages were clearly set out in each of the lease
    schedules for each month of the lease-schedule term.
    -12-
    Winthrop and Eaton–two sophisticated international companies–negotiated this
    contract and agreed upon the CLV and other damages provisions at signing. The CLV
    clause in section 18 specifically sets out the procedure to calculate CLV at any time
    during the initial term of the lease schedule and thereafter. As noted, the CLV of the
    equipment listed on any particular lease schedule is a percentage of the original cost
    of the equipment as set forth on the applicable casualty-loss table, which percentage
    decreases every month during the initial term. After the end of the initial term, the
    CLV remains constant. In essence, it is a depreciation schedule with the depreciation
    rate based on variable factors anticipated at the time of the signing of the agreement
    and based on the condition of the computer equipment, a very speculative
    consideration, at lease-schedule termination. See PacifiCorp Capital, Inc. v. Tano,
    Inc., 
    877 F.Supp. 180
    , 184 (S.D.N.Y. 1995). As Winthrop notes, Eaton's standard
    lease agreement also contains a CLV provision. This concept is not new to Eaton, and
    is one that it understood and agreed to in the Lease.
    Eaton also argued that Winthrop will be doubly compensated by recovering
    both the CLV and accelerated-rent payments. Eaton's argument is unfounded because
    the district court specifically ordered that Winthrop may collect the greater of the two,
    but not both.
    2. CLV and Terminated Lease Schedules
    Finally, Eaton asserted below that the CLV provision does not apply to
    equipment on properly-terminated lease schedules.14 Although the district court failed
    14
    Eaton argues on appeal that Winthrop could not recover the CLV for lease
    schedules A02 and C01 because a question of fact remains as to whether they were
    timely terminated. In addition, Eaton asserts that even if they were not timely
    terminated, Winthrop cannot extend those schedules for a year because Winthrop
    breached the contract prior to the extension of the lease-schedule term. Again, Eaton
    did not raise these specific arguments in the district court in opposition to summary
    judgment; Eaton instead raised these issues in its post-judgment Rule 59(e) motion.
    -13-
    to address this issue, we have thoroughly reviewed the record and conclude that the
    CLV provision possibly could, in particular situations, apply to lease schedules for
    which notice of termination has been timely provided. We do not reach the issue of
    whether the CLV provision applies in this particular instance, however, because
    Eaton failed to properly raise this issue below to allow us to address it on appeal.
    IV. Motion to Strike
    Winthrop filed a motion to strike two declarations Eaton submitted in its
    appendix and on which it relied in its brief to this court. These declarations from
    Leonid Kudishevich and Scott Deakin were not part of the pleadings and documents
    presented to the district court on summary judgment. In response to this motion,
    Eaton acknowledged its inadvertent inclusion of these declarations. As such, we grant
    Winthrop's motion to strike these declarations from Eaton's appendix and all
    references to them in Eaton's brief. It is well settled that "documents presented for the
    first time at the appellate stage of any proceeding are generally not considered part
    of the record for the review by the appellate court." Huelsman v. Civic Ctr. Corp., 
    873 F.2d 1171
    , 1175 (8th Cir. 1989). "[O]nly those papers and exhibits filed in the [trial]
    court can constitute the record on appeal." Huelsman, 
    873 F.2d at 1175
    . In Huelsman,
    we granted a motion to strike an affidavit presented by appellant for the first time on
    appeal. Id.; see also Shea v. Esensten, 
    208 F.3d 712
    , 720 (8th Cir. 2000) (granting
    motion to strike portions of appellant's appendix and references to those documents
    in appellant's brief where the documents were not before the trial court when it ruled
    on the matter below); Barry v. Barry, 
    78 F.3d 375
    , 379 (8th Cir. 1996) (granting
    motion to strike and stating that "only evidentiary materials that were before the trial
    court at the time the . . . ruling was made" would be considered).
    Because Eaton did not appeal that motion, we will not consider the arguments.
    -14-
    V. Conclusion
    We affirm the district court's decision in all respects. However, we remand to
    the district court for an accounting and adjustment to the damages calculation for
    mitigation amounts from any equipment resold by Winthrop, consistent with the
    holdings articulated in this opinion.
    ______________________________
    -15-
    

Document Info

Docket Number: 03-1790

Filed Date: 3/11/2004

Precedential Status: Precedential

Modified Date: 10/13/2015

Authorities (20)

Bellboy Seafood Corp. v. Nathanson , 1987 Minn. App. LEXIS 4659 ( 1987 )

Salve Regina College v. Russell , 111 S. Ct. 1217 ( 1991 )

cota-b-allen-leon-bee-rickey-billingsley-charles-doyle-mason-c-foster , 181 F.3d 902 ( 1999 )

sandra-barry-also-known-as-sandra-barry-lieberman-an-individual-v , 78 F.3d 375 ( 1996 )

maurice-sunderland-architecture-inc-maurice-sunderland-individually , 5 F.3d 334 ( 1993 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Donna Krenik v. County of Le Sueur , 47 F.3d 953 ( 1995 )

Lakeland Tool and Engineering, Inc. v. Thermo-Serv, Inc. , 916 F.2d 476 ( 1990 )

Porous Media Corporation v. Midland Brake, Inc., a Delaware ... , 220 F.3d 954 ( 2000 )

William F. Hagerman v. Yukon Energy Corporation, and David ... , 839 F.2d 407 ( 1988 )

Enterprise Bank v. Magna Bank of Missouri , 92 F.3d 743 ( 1996 )

dianne-l-shea-v-sidney-esensten-jeffrey-a-arenson-family-medical-clinic , 208 F.3d 712 ( 2000 )

Medtronic, Inc. v. U.S. Xpress, Inc. , 341 F.3d 798 ( 2003 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

Green Tree Acceptance, Inc. v. John W. Wheeler , 832 F.2d 116 ( 1987 )

Evergreen Investments, Llc, a Montana Limited Liability ... , 334 F.3d 750 ( 2003 )

Terril W. Huelsman Richard K. Yackey v. Civic Center ... , 873 F.2d 1171 ( 1989 )

City of Virginia v. Northland Office Properties Ltd. ... , 1991 Minn. App. LEXIS 81 ( 1991 )

Dean Van Horn Consulting Associates, Inc. v. Wold , 1985 Minn. App. LEXIS 4133 ( 1985 )

PacifiCorp Capital, Inc. v. Tano, Inc. , 877 F. Supp. 180 ( 1995 )

View All Authorities »