Midwest Medical Solutions, LLC v. Exactech U.S., Inc. ( 2021 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 21-1621
    ___________________________
    Midwest Medical Solutions, LLC; Hugh Bradley
    Plaintiffs - Appellants
    v.
    Exactech U.S., Inc.
    Defendant - Appellee
    ____________
    Appeal from United States District Court
    for the District of Minnesota
    ____________
    Submitted: October 21, 2021
    Filed: December 29, 2021
    ____________
    Before COLLOTON, SHEPHERD, and KELLY, Circuit Judges.
    ____________
    KELLY, Circuit Judge.
    Exactech U.S., Inc. terminated its Sales Agency Agreement (the Agreement)
    with Midwest Medical Solutions, LLC and Hugh Bradley (collectively, Midwest),
    after Midwest failed to meet its sales quota for two or more consecutive quarters.
    Under the Agreement’s non-compete provision, Midwest was entitled to Restricted
    Period Compensation (RPC) after termination. The parties dispute the amount of
    RPC owed, and Midwest initiated an action in the District of Minnesota seeking,
    among other things, a declaratory judgment as to the amount of RPC. Upon
    Midwest’s motion for summary judgment, the district court concluded that the
    Agreement limited RPC to a total of 7.5 percent of sales during the previous 12
    months, divided into six monthly payments. Midwest appeals, arguing the district
    court misconstrued the Agreement.
    I.
    Exactech, a manufacturer of orthopedic implants and surgical instruments for
    hip, knee, and shoulder surgery, entered into an Agreement with Midwest, under
    which Midwest was the exclusive sales representative for Exactech’s products in
    Minnesota, North Dakota, South Dakota, and LaCrosse County, Wisconsin.
    Exactech paid Midwest commission between 15 and 22 percent of invoiced sales,
    depending on the product sold. Exactech could terminate the Agreement by
    providing 30 days’ written notice if Midwest failed to meet the average quarterly
    total of its quota plan for two consecutive quarters. After termination, Midwest
    would be subject to a non-compete covenant for 12 months, during which time
    Midwest could not solicit Exactech customers or employees. The Agreement
    included an RPC provision, Paragraph 5.D.ii, that would apply during the non-
    compete period:
    In the event this Agreement is terminated or not renewed by Exactech,
    then during each calendar month of the first six (6) months after such
    termination, Exactech will pay [Midwest] an amount equal to seven and
    one half percent (7.5%) of the total sales in the Territory during the
    trailing twelve (12) months ending on such termination date (the
    “Restricted Period Compensation”).
    The Agreement contained an integration clause, specifying that it represented the
    entire understanding between the parties and superseded all prior agreements or
    understandings and that the Agreement could be modified only by written
    agreement.
    -2-
    By December 31, 2018, Midwest had missed its sales quota for two or more
    consecutive quarters, and on February 5, 2019, Exactech notified Midwest that it
    would terminate the Agreement, effective March 7, 2019. Through counsel,
    Midwest and Exactech disputed the amount Midwest would be entitled to in RPC
    per the Agreement terms. Both agreed that the total sales for the previous 12 months
    were approximately $4 million. However, Midwest maintained it was entitled to 7.5
    percent of that $4 million to be paid each month for six months, for a total RPC of
    approximately $1.8 million. Exactech disagreed, contending Midwest was entitled
    to 7.5 percent of the roughly $4 million in sales to be paid out in six monthly
    installments, for a total RPC of approximately $300,000.
    On March 15, 2019, Midwest brought claims against Exactech in the District
    of Minnesota. 1 Relevant on appeal, Midwest sought a declaratory judgment that,
    pursuant to Paragraph 5.D.ii of the Agreement, it was entitled to approximately $1.8
    million in RPC. On June 13, 2019, the district court, applying Minnesota law as
    agreed to by the parties, denied Midwest’s motion for summary judgment on the
    declaratory judgment claim. The district court rejected Midwest’s proposed
    interpretation of Paragraph 5.D.ii and agreed with Exactech’s. The district court did
    not analyze the text of Paragraph 5.D.ii itself but considered other factors to
    conclude:
    There is no dispute that the purpose of the RPC is to compensate
    Plaintiffs for a twelve-month non-compete covenant after termination.
    Reading the sales agreement in this light, the Court finds that the
    1
    Exactech filed counterclaims against Midwest, including for reformation
    based on mutual mistake and rescission based on mutual or unilateral mistake, both
    with respect to Paragraph 5.D.ii. After the district court denied Midwest’s motion
    for summary judgment on Midwest’s claim for declaratory judgment, Exactech
    amended its answer and counterclaims, retaining only a counterclaim for breach of
    confidentiality. At oral argument, however, counsel for Exactech expressed the view
    that the reformation and rescission counterclaims are still in the case. We leave it to
    the district court to determine the status of any remaining counterclaims upon
    remand.
    -3-
    agreement clearly and unambiguously limits RPC to 7.5% of the
    preceding twelve-months sales. This amount bears a reasonable and
    rational relationship to Plaintiffs’ actual fees and commissions under
    the agreement . . . and the purpose of the compensation.
    The parties later stipulated to entry of judgment against Exactech on
    Midwest’s declaratory judgment claim pursuant to the district court’s interpretation
    of Paragraph 5.D.ii. The district court entered judgment on March 1, 2021, ordering
    Exactech to pay RPC to Midwest in the amount of $287,077.23, plus pre-judgment
    interest in the amount of $47,128.51.
    With a final judgment in hand, Midwest timely appealed, challenging the
    district court’s interpretation of Paragraph 5.D.ii set forth in the summary judgment
    order.
    II.
    A party is entitled to “summary judgment if the movant shows that there is no
    genuine dispute as to any material fact and the movant is entitled to judgment as a
    matter of law.” Fed. R. Civ. P. 56(a). In a case of contract interpretation,
    construction of an unambiguous contract is a question of law that we review de novo,
    but if the contract is ambiguous, its meaning is a question of fact, and summary
    judgment is inappropriate unless evidence of the parties’ intent is conclusive.
    Qwinstar Corp. v. Anthony, 
    882 F.3d 748
    , 752 (8th Cir. 2018) (quoting Swift & Co.
    v. Elias Farms, Inc., 
    539 F.3d 849
    , 851 (8th Cir. 2008)).
    For a contract to be deemed unambiguous, Minnesota law requires a court to
    construe the contract as a whole to determine whether it is subject to only one
    reasonable interpretation. See id. at 754. Where the parties to a contract “express
    their intent in unambiguous words, those words are to be given their plain and
    ordinary meaning.” Motorsports Racing Plus, Inc. v. Arctic Cat Sales, Inc., 
    666 N.W.2d 320
    , 323 (Minn. 2003). And “when a contractual provision is clear and
    unambiguous, courts should not rewrite, modify, or limit its effect by a strained
    -4-
    construction.” Travertine Corp. v. Lexington-Silverwood, 
    683 N.W.2d 267
    , 271
    (Minn. 2004). Accordingly, we must first examine the text of Paragraph 5.D.ii to
    determine whether that provision is unambiguous and, if so, assess the plain and
    ordinary meaning of the words therein.
    Although the parties advocate different interpretations of Paragraph 5.D.ii,
    both argue on appeal that the provision is unambiguous. In relevant part, Paragraph
    5.D.ii provides, “during each calendar month of the first six (6) months after such
    termination, Exactech will pay [Midwest] an amount equal to seven and one half
    percent (7.5%) of the total sales in the Territory during the trailing twelve (12)
    months ending on such termination date.”
    We agree with the parties and the district court that this provision is
    unambiguous. The first phrase, “during each calendar month of the first six (6)
    months after such termination,” sets the frequency and number of payments. The
    second phrase, “Exactech will pay Agency an amount equal to seven and one half
    percent (7.5%) of the total sales in the Territory during the trailing twelve (12)
    months ending on such termination date,” sets the amount of each payment. Thus,
    Exactech must make a payment of 7.5 percent of the total sales from the trailing 12-
    month period to Midwest each month for six months. The plain and ordinary
    meaning of Paragraph 5.D.ii aligns with Midwest’s, rather than Exactech’s,
    interpretation.
    To endorse Exactech’s contrary position—that RPC is limited to 7.5 percent
    of sales during the preceding 12 months to be paid out in six monthly installments—
    we would have to eliminate or read-in language. Either we would need to ignore the
    first phrase—“during each calendar month of the first six (6) months after such
    termination”—or we would need to insert or infer language about the total payment
    being made through equal monthly installments. In other words, to read Paragraph
    5.D.ii as Exactech advocates, we would have to rewrite or modify unambiguous
    contract language, which Minnesota law prohibits, and which we decline to do.
    Travertine Corp., 683 N.W.2d at 271; see also Am. Com. Ins. Brokers, Inc. v. Minn.
    -5-
    Mut. Fire & Cas. Co., 
    551 N.W.2d 224
    , 227–228 (Minn. 1996) (“If no ambiguity
    exists, there is no reason for construction, and the court is bound to attribute the usual
    and accepted meaning to the phrase.”).
    Nevertheless, Exactech argues that the court must construe Paragraph 5.D.ii
    in light of the rest of the contract and should thus reject Midwest’s position because
    it would lead to an unreasonable, harsh result for Exactech and a windfall for
    Midwest. Exactech is correct that under Minnesota law, courts consider a relevant
    contractual provision in the context of the entire contract and the parties’ positions
    at the time of contract formation to determine “what they reasonably meant to
    accomplish in view of the contract as a whole, its plain language, and the
    surrounding circumstances.” Qwinstar, 882 F.3d at 754 (quoting Ecolab, Inc. v.
    Gartland, 
    537 N.W.2d 291
    , 295 (Minn. Ct. App. 1995)). This includes reading a
    contract so as to harmonize all clauses and avoid rendering a portion meaningless.
    
    Id.
     at 754–55. Further, courts “read contract terms in the context of the entire
    contract and will not construe the terms so as to lead to a harsh and absurd result.”
    Brookfield Trade Ctr., Inc. v. Cnty. of Ramsey, 
    584 N.W.2d 390
    , 394 (Minn. 1998);
    see also Am. Com. Ins. Brokers, 551 N.W.2d at 230 (interpreting insurance contract
    as a whole to avoid “potentially unlimited windfall of recovery”).
    Here, however, nothing in the remainder of the Agreement contradicts the
    plain meaning of Paragraph 5.D.ii. No one disputes that the purpose of RPC is to
    compensate Midwest during the non-compete period, but there is no evidence of the
    parties’ intent with respect to the amount of RPC owed other than the unambiguous
    language of the relevant provision itself. Indeed, there is no claim of unilateral or
    mutual mistake presently before the court that would permit consideration of the
    parties’ intent apart from the plain language of the Agreement. And though the plain
    language may result in a large sum paid to Midwest by Exactech as RPC, there is no
    evidence—other than the parties’ self-serving arguments—as to why this amount is
    or is not an absurd result. As such, we are bound to give Paragraph 5.D.ii its plain
    and ordinary meaning. See Motorsports Racing Plus, 666 N.W.2d at 323. To
    conclude otherwise would be to substitute our views of the contract or our inferences
    -6-
    about RPC for the parties’ intent as indicated by the clear and unambiguous language
    of Paragraph 5.D.ii, terms that the parties negotiated and to which they ultimately
    agreed.
    III.
    For the foregoing reasons, we conclude that the district court did not apply the
    plain and ordinary meaning of Paragraph 5.D.ii as required by Minnesota law, and
    we reverse and remand the case for further proceedings consistent with this opinion.
    ______________________________
    -7-
    

Document Info

Docket Number: 21-1621

Filed Date: 12/29/2021

Precedential Status: Precedential

Modified Date: 12/29/2021