Iowa Great Lakes Sanitary Dist. v. Travelers Cas. & Sur. Co. of Am. ( 2019 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 17-2732
    ___________________________
    Iowa Great Lakes Sanitary District
    lllllllllllllllllllllPlaintiff - Appellant
    v.
    Travelers Casualty and Surety Company of America; Evoqua Water Technologies
    lllllllllllllllllllllDefendants - Appellees
    ____________
    Appeal from United States District Court
    for the Northern District of Iowa - Sioux City
    ____________
    Submitted: October 16, 2018
    Filed: January 11, 2019
    ____________
    Before SMITH, Chief Judge, LOKEN and GRUENDER, Circuit Judges.
    ____________
    LOKEN, Circuit Judge.
    This is a diversity action removed from state court in December 2015. Iowa
    Great Lakes Sanitary District (IGLSD) alleges that an Ultraviolet Wastewater
    Disinfectant System (UV System) installed at IGLSD’s Dickinson County
    Wastewater Treatment Facility “has consistently failed to function in any working
    capacity.” IGLSD asserts a claim against Travelers Casualty and Surety Company
    of America (Travelers) under the Performance and Maintenance Bond issued to
    guarantee performance by the project’s contractor, and breach of warranty claims
    against the UV System vendor, Evoqua Water Technologies, f/k/a Siemens Water
    Technologies (Evoqua). IGLSD appeals the District Court’s1 grant of summary
    judgment dismissing these claims. Reviewing the grant of summary judgment de
    novo, we affirm. Bruce Martin Const., Inc. v. CTB, Inc., 
    735 F.3d 750
    , 753 (8th Cir.
    2013) (standard of review).
    I. Background.
    In 2007, IGLSD contracted with McHan Construction, Inc., to complete a
    $14,593,000 addition to the Wastewater Treatment Facility, including installation of
    a UV System. McHan procured a Performance and Maintenance Bond from
    Travelers fully guaranteeing McHan’s “faithful performance of the contract” with
    IGLSD. After the contract was in effect, McHan purchased a vertical open channel
    UV System from Evoqua for $132,000. The purchase agreement included an express
    two-year limited warranty “that the equipment or material . . . is free from defects in
    workmanship and materials.” The two-year warranty period would commence on the
    date the equipment successfully completed a required sixty-day performance test.
    After McHan defaulted in late 2009, Travelers and IGLSD entered into a “Take
    Over Agreement” whereby Travelers agreed “to complete the Project pursuant to the
    terms of the Contract,” with its Performance and Maintenance Bond “in full force and
    effect.” Start-up problems plagued installation of the UV System, causing further
    delays in completing the contract. When the installed UV equipment eventually
    completed the sixty-day performance testing, IGLSD’s project engineer, James
    Rasmussen, advised the parties on November 8, 2011: “With the latest Performance
    1
    The Honorable Leonard T. Strand, Chief Judge of the United States District
    Court for the Northern District of Iowa.
    -2-
    Test on Module No. 2 the UV disinfection equipment is now Substantially Completed
    and the project can be finally accepted. The Warranty Period for the equipment will
    be considered to be started on November 1, 2011.”
    Substantial Completion did not end the parties’ problems with the UV System,
    which IGLSD alleges was often nonoperational. In June 2012, an electrical fire
    damaged one of the modules; it was returned to Evoqua’s factory for repairs. In May
    2013, IGLSD complained there was soot in the system, it was malfunctioning, and
    warranty issues had not been addressed. In a July 2013 letter to Travelers, Engineer
    Rasmussen noted the equipment warranty would expire November 1, 2013, expressed
    concern that Siemens and Evoqua were not supporting the equipment, summarized
    numerous items needing repair, and asked Travelers to “develop a plan to
    repair/replace the equipment by the end of the Warranty date.”
    Alerted to these complaints, Evoqua sent a technician to assess the equipment
    in September 2013. Based on his report, in April 2014 Evoqua proposed that the two
    UV modules undergo a substantial rehab, with IGLSD and Evoqua splitting the
    $75,000.00 cost. In a May 12, 2014 letter, Engineer Rasmussen responded that
    IGLSD “does not wish to go any further to repair the failed equipment” and requested
    that the UV System “be removed from the project and the cost of the initial purchase
    of the equipment be refunded.” This lawsuit followed.
    In its summary judgment Order, the district court noted that Chief Magistrate
    Judge C.J. Williams had entered an order that “prohibited IGLSD from proffering
    expert testimony as a sanction for IGLSD’s failure to comply with the court’s
    deadlines.” The district court also ruled that IGLSD had violated Local Rule 56(b)
    by failing to respond to the Statements of Undisputed Material Facts submitted by
    Evoqua and Travelers in support of their summary judgment motions, and therefore
    those facts “are deemed to have been admitted by IGLSD.” IGLSD does not
    challenge these significant procedural rulings on appeal.
    -3-
    II. The Breach of Warranty Claim Against Evoqua.
    IGLSD claims that Evoqua breached its limited two-year express warranty that
    the UV System equipment “is free from defects in workmanship and materials.” A
    breach of express warranty claim under Iowa law “requires proof of a product defect
    as defined in Products Restatement section 2.” Cummings v. Deere & Co., 589 F.
    Supp. 2d 1108, 1118 n.22 (S.D. Iowa 2008), quoting Wright v. Brooke Group, Ltd.,
    
    652 N.W.2d 159
    , 182 (Iowa 2002). Summary judgment is mandated “against a party
    who fails to make a showing sufficient to establish the existence of an element
    essential to that party’s case, and on which that party will bear the burden of proof at
    trial.” Celotex Corp. v. Catret, 
    477 U.S. 317
    , 322 (1986). “Evidence of a defect is
    an indispensable element of any express or implied warranty claim.” Coop. Power
    Ass’n v. Westinghouse Elec. Corp., 
    60 F.3d 1336
    , 1344-45 (8th Cir. 1995).
    In cases involving “complicated technical and scientific issues . . . expert
    testimony is required to submit the issue of a product defect under Iowa law.”
    
    Cummings, 589 F. Supp. 2d at 1118
    . “Whether expert testimony is required
    ultimately depends on whether it is a fact issue upon which the jury needs assistance
    to reach an intelligent or correct decision.” Reed v. Chrysler Corp. 
    494 N.W.2d 224
    ,
    226 (Iowa 1992) (quotation omitted). Here, with IGLSD precluded from presenting
    expert testimony, the district court concluded that IGLSD could not prove that the UV
    system was defective, an essential element of its warranty claim, because the issue
    “involves sophisticated technology that kills bacteria in waste water through the use
    of light that is literally invisible to the naked eye. Such technology is far beyond the
    common knowledge and experience of the average layperson.” On appeal, IGLSD
    argues that the court erred in granting summary judgment because it can present a
    submissible case of equipment defect with lay witness testimony that “the UV
    equipment failed to function frequently and in so many ways that it clearly was
    defective and it wasn’t necessary for an expert to explain the obvious.”
    -4-
    Viewed in the light most favorable to IGLSD, the summary judgment record
    reflects that the UV System often malfunctioned.2 However, the question is whether,
    without expert testimony, IGLSD can establish that the UV System’s on-going
    operational issues, such as the 2012 fire in Module No. 2, were caused by equipment
    defects that breached the express warranty, rather than by improper operation and
    maintenance of the complex system, improper storage during the winter, or other
    possible causes.
    Even more significantly, the express warranty provided that IGLSD’s exclusive
    remedy “is the replacement f.o.b. shipping point of the defective part or parts of the
    material or equipment.” Evoqua’s Statement of Undisputed Material Facts, deemed
    admitted by the district court, recited that “Evoqua was ready and able to address the
    few remaining warranty issues on the punch list” but “IGLSD did not allow Evoqua
    to repair or replace the few remaining warranty items.” This is confirmed by
    Engineer Rasmussen’s May 2014 response to Evoqua’s rehab proposal in which he
    advised that IGLSD “does not wish to go any further to repair the failed equipment.”
    Buyer’s remorse, however justifiable, is not proof that the equipment had such serious
    “defects in workmanship and materials” that IGLSD was justified in refusing
    Evoqua’s offer to repair and replace, the exclusive remedy provided in the warranty,
    and bringing an action seeking refund of the entire purchase price. Only expert
    testimony could possibly justify IGLSD’s warranty claim for a remedy excluded by
    the warranty. We conclude the district court properly granted summary judgment
    dismissing IGLSD’s breach of warranty claim against Evoqua.
    2
    The Wastewater Treatment Facility only operated disinfection equipment
    during warm weather months, so IGLSD’s conclusory assertion that the UV System
    was nonoperational 57% of the time was not adequately explained and supported.
    -5-
    III. The Bond Claim Against Travelers.
    IGLSD also appeals the dismissal of its claim against Travelers under its
    Performance and Maintenance Bond. The bond guaranteed the contractor’s full
    performance of its obligations under its contract with IGLSD. Section 13.07 of the
    contract obligated the contractor to correct, at no cost to IGLSD, “any Work [that] is
    found to be defective” within one year after the date of Substantial Completion or any
    longer period prescribed “by the terms of any applicable special guarantee required
    by the Contract Documents.” If IGLSD had established that Evoqua’s UV System
    was “defective,” the contractor and its bonding company would be obligated by
    § 13.07 to correct or repair or replace the defective work. But we have affirmed the
    grant of summary judgment dismissing the claim of defective work.
    IGLSD argued an additional theory to the district court that became the focus
    of its appeal. As the district court explained, quoting IGLSD’s contention:
    IGLSD [argues] that recovery against Travelers is [not] dependent
    on and/or limited to a breach of warranty claim[] against a supplier of
    materials for the project. The [contract] provides that the project
    engineer and the owner have the authority to reject work that they
    believe to be defective or that the Engineer believes will not produce a
    completed project. On May 12, 2014 the engineer and the owner
    rejected the UV equipment and ordered that it be replaced or that the
    cost be reimbursed. The contractor hired by Travelers did not comply
    nor did Evoqua or Travelers which Plaintiff alleges is a breach of the
    terms of the contract and the Bond.
    The district court rejected this theory, concluding that Engineer Rasmussen’s
    authority to reject work applied during “the actual construction phase,” which ended
    when Rasmussen declared the project substantially completed on November 1, 2011.
    Although § 13.07 extended the contractor’s obligation to repair or replace defective
    work after Substantial Completion, the court reasoned that § 13.07 did not “extend
    -6-
    the project engineer’s ability to reject work indefinitely beyond completion.” Rather,
    the court concluded, “[t]o make a proper claim regarding completed work, IGLSD
    must establish a construction, installation or equipment defect.” We agree.
    Engineer Rasmussen’s authority to reject work he “believes to be defective, or
    . . . will not produce a completed project” is found in § 9.06 of the contract, part of
    Article 9 entitled “ENGINEER’S STATUS DURING CONSTRUCTION.”
    Rasmussen’s May 12, 2014 letter to Evoqua and Travelers was a response to
    Evoqua’s proposal to complete warranty repairs with a substantial rehab of the two
    UV modules. The letter did not state that the UV System was “rejected” and did not
    cite § 9.06 of the contract; rather, it requested that the system “be removed from the
    project and the cost of the initial purchase of the equipment be refunded to the
    District.” IGLSD argues on appeal that the letter was a proper exercise of the
    engineer’s power to reject work, a power limited only by his professional duty of care
    and reasonableness. But that characterization is contrary to the plain meaning of
    § 9.06 and the letter itself. And the argument ignores the fact that the letter was not
    sent until May 2014, months after expiration of Evoqua’s warranty and expiration of
    the contractor’s two-year “guarantee and maintenance period” that is referenced in
    IGLSD’s Notice To Bidders and the Travelers bond, but is not otherwise to be found
    in the Contract Documents IGLSD placed in the record on appeal.
    The summary judgment record established that IGLSD considered rejecting the
    UV system in 2010, well before the engineer certified Substantial Completion, but
    chose not to do so. On November 17, 2010, Travelers and IGLSD sent Evoqua an
    email warning that they were considering rejection due to installation delays. A July
    2011 internal Travelers email reported that IGLSD’s engineer was “mumbling about
    rejecting the system.” Instead, on November 1, 2011, Engineer Rasmussen certified
    that “the UV disinfection equipment is now Substantially Completed and the project
    can be finally accepted.” Under Iowa law, it is a “general rule that as to known
    defects, acceptance of the work in the absence of fraud or mistake is a complete bar
    -7-
    to recovery on the construction bond.” Elliott Consol. Sch. Dist. v. Busboom, 227 F.
    Supp. 858, 862 (S.D. Iowa 1964). In these circumstances, we agree with the district
    court that “IGLSD is unable to contort the contract/bond language to such an extent
    that it could unilaterally reject the UV unit in 2014, without showing (through expert
    testimony) some type of defect.”
    The judgment of the district court is affirmed.
    ______________________________
    -8-
    

Document Info

Docket Number: 17-2732

Judges: Smith, Loken, Gruender

Filed Date: 1/11/2019

Precedential Status: Precedential

Modified Date: 10/19/2024