Perficient v. Thomas Munley ( 2022 )


Menu:
  •               United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 21-2121
    ___________________________
    Perficient, Inc.
    Plaintiff - Appellee
    v.
    Thomas Munley
    Defendant - Appellant
    Spaulding Ridge, LLC
    Defendant
    ____________
    Appeal from United States District Court
    for the Eastern District of Missouri - St. Louis
    ____________
    Submitted: January 13, 2022
    Filed: August 9, 2022
    ____________
    Before LOKEN, GRUENDER, and GRASZ, Circuit Judges.
    ____________
    GRUENDER, Circuit Judge.
    The district court 1 granted Perficient, Inc.’s motion for summary judgment
    against Thomas Munley and Spaulding Ridge, LLC. It awarded nominal damages
    and attorney’s fees to Perficient, but its orders did not quantify the amount of the
    award. Munley appealed. Perficient filed a motion to dismiss for lack of appellate
    jurisdiction, arguing that the orders from which Munley appealed are not final. We
    grant the motion and dismiss for lack of jurisdiction.
    I.
    Perficient moved for summary judgment against its former employee Munley
    and Munley’s new employer Spaulding Ridge in a lawsuit involving non-
    competition and confidentiality agreements that Munley signed when he worked for
    Perficient. Munley also filed a motion for summary judgment. On April 15, 2021,
    the district court entered two orders granting Perficient’s motion and denying
    Munley’s. In these orders, the district court observed that Munley was liable to
    Perficient on its breach-of-contract claim. The district court determined, however,
    that no actual damages resulted from Munley’s breach. It instead found that
    Perficient was entitled to nominal damages. It also concluded that the attorney’s
    fees sustained by Perficient as a result of Munley’s breach were consequential
    damages of the breach, which were compensable as part of the damages element of
    the breach-of-contract claim. The district court did not specify any amount of either
    nominal damages or attorney’s fees; rather, it ordered that Perficient file a motion in
    support of its request for damages and attorney’s fees and that Munley file a
    response. The second order states that “[f]ollowing this briefing, the Court will enter
    a final judgment.” On May 14, 2021, before any judgment was entered, Munley
    filed a notice of appeal as to the April 15, 2021 orders. On June 2, 2021, Perficient
    filed a motion to dismiss for lack of jurisdiction.
    1
    The Honorable John A. Ross, United States District Judge for the Eastern
    District of Missouri.
    -2-
    II.
    Generally, a party in a civil case who desires to appeal must file a notice of
    appeal “within 30 days after entry of the judgment or order appealed from.” Fed. R.
    App. P. 4(a)(1)(A). The requirement of a timely notice of appeal is mandatory and
    jurisdictional. Arnold v. Wood, 
    238 F.3d 992
    , 995 (8th Cir. 2001). Federal courts
    of appeal have jurisdiction over appeals from “final decisions” of United States
    district courts. 
    28 U.S.C. § 1291
    .
    Munley argues that the April 15, 2021 orders constituted a final judgment
    from which he timely appealed. Perficient contends that Munley’s notice of appeal
    was premature because the district court had not entered a final judgment from which
    an appeal could be taken.
    We conclude that Munley’s notice of appeal was premature because the April
    15, 2021 orders were not final, appealable orders. See 
    28 U.S.C. § 1291
    . “A final
    decision within the meaning of § 1291 ‘ends the litigation on the merits and leaves
    nothing for the court to do but execute the judgment.’” Dieser v. Cont’l Cas. Co.,
    
    440 F.3d 920
    , 923 (8th Cir. 2006) (quoting Borntrager v. Cent. States, Se. & Sw.
    Areas Pension Fund, 
    425 F.3d 1087
    , 1091 (8th Cir. 2005)). “A judgment awarding
    damages but not deciding the amount of the damages or finding liability but not
    fixing the extent of the liability is not a final decision within the meaning of § 1291.”
    Id.; see also St. Mary’s Health Ctr. of Jefferson City v. Bowen, 
    821 F.2d 493
    , 498
    (8th Cir. 1987) (citing Parks v. Pavkovic, 
    753 F.2d 1397
    , 1404 (7th Cir.), cert.
    denied, 
    473 U.S. 906
     (1985) (“Normally an order that merely decides liability and
    leaves the determination of damages to future proceedings does not finally dispose
    of any claim; it is just a preliminary ruling on the plaintiff’s damage claim.”));
    Albright v. UNUM Life Ins. Co. of Am., 
    59 F.3d 1089
    , 1092 (10th Cir. 1995)
    ((brackets omitted) (quoting 16 Charles A. Wright & Arthur R. Miller, Federal
    Practice and Procedure § 4009 (3d ed.)) (“[A]n order that determines liability but
    leaves damages to be calculated is not final.”).
    -3-
    However, a judgment awarding damages but not specifying the amount may
    still be considered final “if only ministerial tasks in determining damages remain.”
    Goodwin v. United States, 
    67 F.3d 149
    , 151 (8th Cir. 1995); see also Kohlbeck v.
    Wyndham Vacation Resorts, Inc., 
    7 F.4th 729
    , 736 (8th Cir. 2021) (concluding that
    the district court’s task was more than ministerial where it had yet to determine the
    amount of damages); Minn., Dep’t. of Revenue v. United States, 
    184 F.3d 725
    , 726
    n.1 (8th Cir. 1999). The determination of damages is “ministerial” where it
    “requir[es] no independent legal judgment.” Cappuccio v. Prime Cap. Funding
    LLC, 
    649 F.3d 180
    , 187 (3d Cir. 2011); see also Woosley v. Avco Corp., 
    944 F.2d 313
    , 316-317 (6th Cir. 1991) (concluding that the determination of damages is
    “ministerial” where it consists merely of the calculation of a predetermined amount;
    that is, it is a mechanical or computational task).
    Here, the district court awarded nominal damages but did not determine the
    amount of those damages. See Dieser, 
    440 F.3d at 923
    . Perficient did not request a
    specific amount of nominal damages, nor did the district court quantify the amount
    of nominal damages it intended to award in its orders. Cf. Green v. Study, 
    250 S.W.3d 799
    , 801-02 (Mo. Ct. App. 2008) (holding that the judgment was not final
    where it “state[d] no amount of punitive or nominal damages”). In fact, the district
    court explicitly left the nominal damage amount unresolved; it ordered that
    Perficient “may file any motion in support of its request for damages” and that
    Munley could respond. See Kohlbeck, 7 F.4th at 736 (stating that the district court’s
    order granting summary judgment was not final where it determined liability and
    ordered the parties to file a motion to determine the damages amount). Without a
    quantification of the amount of nominal damages, we cannot say that there was
    “nothing for the court to do but execute the judgment.” See Dieser, 
    440 F.3d at 923
    .
    Had the district court awarded an unspecified amount of compensatory
    damages in addition to attorney’s fees, its order would unquestionably have been
    nonfinal. See Kohlbeck, 7 F.4th at 736. And nominal damages are no less “concrete”
    than compensatory damages. See Uzuegbunam v. Preczewski, 592 U.S. ---, 
    141 S. Ct. 792
    , 801 (2021) (“Despite being small, nominal damages are certainly
    -4-
    concrete.”). In the standing context, the Supreme Court has treated nominal
    damages as equivalent to compensatory damages, rejecting the view that “nominal
    damages are purely symbolic” and the contention that they do not “change a
    plaintiff’s status or condition.” 
    Id. at 800-01
     (brackets omitted) (“[W]e have already
    held that a person who is awarded nominal damages . . . may demand payment for
    nominal damages no less than he may demand payment for millions of dollars in
    compensatory damages” (internal quotation marks omitted)). This cautions against
    treating nominal damages differently from compensatory damages here.
    The district court here left a task that is more than “ministerial.” See DeJohn
    v. Temple Univ., 
    537 F.3d 301
    , 306-08 (3d Cir. 2008) (describing the quantification
    of damages as “more than a ministerial act to be performed by the clerk of the court
    and routinely executed by the judge” where the district court’s damage award
    included only nominal damages); Uzuegbunam, 141 S. Ct. at 800 (rejecting the view
    that “courts awarded nominal damages merely as a technical matter”). Although
    nominal damages are “trifling” in value, see “Damages,” Black’s Law Dictionary
    (11th ed. 2019), there is no standard amount awarded to parties under Missouri law.2
    See, e.g., Heifetz v. Apex Clayton, Inc., 
    2015 WL 6737772
    , at *1 (Mo. Cir. Ct. Oct.
    26, 2015) (awarding nominal damages of $1,000), aff’d, 
    554 S.W.3d 389
    , 392 (Mo.
    2018); Green v. Study, 
    286 S.W.3d 236
    , 242 (Mo. Ct. App. 2009) (reversing the trial
    court’s nominal damages award of $1,000 in the replevin context but acknowledging
    trial courts’ authority to exercise discretion in choosing the amount of a nominal
    damages award); Evans v. Werle, 
    31 S.W.3d 489
    , 493 (Mo. Ct. App. 2000)
    (awarding nominal damages of $1); Morgan Publ’ns, Inc. v. Squire Publishers, Inc.,
    
    26 S.W.3d 164
    , 176 (Mo. Ct. App. 2000) (affirming a nominal damages award of
    $2); Alexander v. Link’s Landing, Inc., 
    814 S.W.2d 614
    , 621 (Mo. Ct. App. 1991)
    (affirming a damage award where the nominal damages were $10); see also 24
    Samuel Williston & Richard A. Lord, A Treatise on the Law of Contracts § 64:10
    (4th ed. 1993 & Supp. 2022) (recognizing that “nominal damages have been awarded
    2
    The non-competition agreement signed by Munley when he was employed
    by Perficient specifies that Missouri law would govern the agreement and all aspects
    of Munley’s employment.
    -5-
    in greater amounts [than $1]”). The district court thus has yet to determine the value
    of the nominal damages and “personalize[] the remedy.” See Welch v. Spangler, 
    939 F.2d 570
    , 573 (8th Cir. 1991). So, the district court’s quantification of nominal
    damages requires “independent legal judgment.” See Cappuccio, 
    649 F.3d at 187
    ;
    see also Corpus v. Bennett, 
    430 F.3d 912
    , 915 (8th Cir. 2005) (describing the district
    court’s evaluation of a nominal damages award as an exercise of discretion).
    Compare State of Minn. v. Kalman W. Abrams Metals, Inc., 
    155 F.3d 1019
    , 1023
    (8th Cir. 1998) (describing “final approval of the settlement” as a “‘ministerial task’
    that does not defeat finality”), and Bath Junkie Branson, L.L.C. v. Bath Junkie, Inc.,
    
    528 F.3d 556
    , 560 n.2 (8th Cir. 2008) (noting that the district court’s remaining task
    of “entering the judgment” was “ministerial”), with SBC Advanced Sols., Inc. v.
    Comms. Workers of Am., Dist. 6, 
    794 F.3d 1020
    , 1032 (8th Cir. 2015) (describing
    the initial determination of a damages award amount as more than ministerial).
    Further, Federal Rule of Appellate Procedure 4(a)(2) cannot save the
    prematurely filed notice of appeal here. See Dieser, 
    440 F.3d at 925
    . The rule states
    that “[a] notice of appeal filed after the court announces a decision or order—but
    before the entry of the judgment or order—is treated as filed on the date of and after
    the entry.” “Rule 4(a)(2) permits a notice of appeal filed from certain nonfinal
    decisions to serve as an effective notice from a subsequently entered final
    judgment.” FirsTier Mortg. Co. v. Invs. Mortg. Ins., 
    498 U.S. 269
    , 274 (1991).
    However, the rule applies “only when a district court announces a decision that
    would be appealable if immediately followed by the entry of judgment” and does
    not save a premature appeal “from a clearly interlocutory decision—such as a
    discovery ruling or a sanction order under Rule 11.” 
    Id. at 276
     (emphasis omitted).
    A “belief that such a decision is a final judgment would not be reasonable.” 
    Id.
    (emphasis omitted). Rule 4(a)(2) is inapplicable here. The April 15, 2021 orders
    would not “be appealable if immediately followed by the entry of judgment.” See
    
    id.
     (emphasis omitted). The district court ordered that Perficient “may file any
    motion in support of its request for damages and attorneys’ fees” and that Munley
    may file a response. Because the April 15, 2021 orders “expressly left unresolved”
    the amount of nominal damages, “these orders could not reasonably be believed to
    -6-
    be final within the meaning of § 1291.” See Dieser, 
    440 F.3d at 924
    ; Tweedle v.
    State Farm Fire & Cas. Co., 
    527 F.3d 664
    , 668 (8th Cir. 2008) (“[T]here must be
    some clear and unequivocal manifestation by the trial court of its belief that the
    decision made, so far as the court is concerned, is the end of the case.” (internal
    quotation marks and brackets omitted) (quoting Goodwin, 
    67 F.3d at 151
    )).3
    III.
    Because Munley’s appeal was not taken from a final, appealable order and
    was therefore ineffective to confer appellate jurisdiction upon this court, we grant
    Perficient’s motion to dismiss.
    ______________________________
    3
    In this appeal, Munley also challenges the district court’s September 5, 2019
    order granting a permanent injunction in favor of Perficient—an order he has already
    appealed once. See Perficient, Inc. v. Munley, 
    973 F.3d 914
     (8th Cir. 2020). This
    court determined in Munley’s first appeal that, even though the September 5 order
    was mooted by the expiration of the permanent injunction, the findings and
    conclusions in the order could still be subject to future appellate review “should they
    be challenged on appeal from the court’s final order.” 
    Id. at 918
     (emphasis added).
    But because there is no final judgment yet in this matter, the district court’s now-
    expired permanent injunction order is not presently reviewable.
    -7-
    

Document Info

Docket Number: 21-2121

Filed Date: 8/9/2022

Precedential Status: Precedential

Modified Date: 8/9/2022

Authorities (19)

state-of-minnesota-v-kalman-w-abrams-metals-inc-blum-holdings-inc-a , 155 F.3d 1019 ( 1998 )

Richard T. Arnold v. Gael D. Wood, Drema L. Grant, Daniel M.... , 238 F.3d 992 ( 2001 )

DeJohn v. Temple University , 537 F.3d 301 ( 2008 )

Reverend Lloyd L. Goodwin Martha J. Goodwin v. United States , 67 F.3d 149 ( 1995 )

L. Joseph Albright v. Unum Life Insurance Company of ... , 59 F.3d 1089 ( 1995 )

Cappuccio v. Prime Capital Funding LLC , 649 F.3d 180 ( 2011 )

st-marys-health-center-of-jefferson-city-v-otis-r-bowen-secretary-of , 821 F.2d 493 ( 1987 )

Sherman Woosley Edward Carmack Lester Blue, Jr. Stonnie ... , 944 F.2d 313 ( 1991 )

Evans v. Werle , 2000 Mo. App. LEXIS 1695 ( 2000 )

Tweedle v. State Farm Fire & Casualty Co. , 527 F.3d 664 ( 2008 )

Alexander v. Link's Landing, Inc. , 1991 Mo. App. LEXIS 1145 ( 1991 )

Green v. Study , 2009 Mo. App. LEXIS 369 ( 2009 )

Green v. Study , 2008 Mo. App. LEXIS 565 ( 2008 )

Morgan Publications, Inc. v. Squire Publishers, Inc. , 26 S.W.3d 164 ( 2000 )

John A. Welch v. Lt. Dean Spangler, Jack Ellefritz, ... , 939 F.2d 570 ( 1991 )

State of Minnesota, Department of Revenue v. United States , 184 F.3d 725 ( 1999 )

LEE BORNTRAGER, PLAINTIFFS—APPELLEES v. CENTRAL STATES, ... , 425 F.3d 1087 ( 2005 )

William Dieser v. Continental Casualty Company, Doing ... , 440 F.3d 920 ( 2006 )

Bath Junkie Branson, L.L.C. v. Bath Junkie, Inc. , 528 F.3d 556 ( 2008 )

View All Authorities »