Nicholas Meyer v. McKenzie Electric Coop., Inc. ( 2020 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 18-3244
    ___________________________
    Nicholas Meyer
    lllllllllllllllllllllPlaintiff - Appellee
    v.
    McKenzie Electric Cooperative, Inc.,
    lllllllllllllllllllllDefendant - Appellant
    ____________
    Appeal from United States District Court
    for the Northwestern District of North Dakota
    ____________
    Submitted: November 12, 2019
    Filed: January 17, 2020
    ____________
    Before COLLOTON, WOLLMAN, and BENTON, Circuit Judges.
    ____________
    WOLLMAN, Circuit Judge.
    Nicholas Meyer, an employee of 4T Construction (4T), sued McKenzie Electric
    Cooperative, Inc. (McKenzie) under both negligence-based and strict liability law
    principles after he was seriously injured while replacing a high voltage transmission
    line for the Bear Ben Road Reconductor Project (Project). The district court1 granted
    1
    The Honorable Daniel L. Hovland, then Chief Judge of the United States
    District Court for the District of North Dakota.
    summary judgment in favor of McKenzie, holding that McKenzie was not liable
    because 4T was an independent contractor and because North Dakota has not
    recognized the maintenance of high-voltage power lines as an ultra hazardous
    activity. We affirm.
    McKenzie hired 4T in March 2014 to install, replace, and repair high voltage
    transmission lines for the Project, which involved three energized phase conductors
    and one neutral conductor. The contract between McKenzie and 4T stated that 4T is
    “an independent contractor performing its work to the requirements as set out by
    [McKenzie] but without supervision of [McKenzie] or its employees, [4T] agrees to
    hold harmless, indemnify, and defend [McKenzie].”
    In assigning work to 4T, McKenzie followed its practice of issuing work
    orders, which identified the work that the contractor was hired to perform, and
    “staking sheets,” which indicated where the work was to be performed and what
    electrical equipment was already installed. The work order and staking sheets for the
    Project explained that the four conductors were sized at 1/0. The three energized
    phase conductors were to be upsized to 4/0, while the neutral conductor was to
    remain at 1/0. Steve Lautenschlager, McKenzie’s contractor manager and
    journeyman lineman, made periodic inspections to the Project site. 4T’s president,
    John Gulley, testified that McKenzie was concerned with the finished product, but
    that it neither directed nor instructed 4T on how to complete the Project. 4T’s vice
    president, Lance Wood, testified that McKenzie did not supervise or give input to 4T
    beyond scheduling work start and completion dates. Jared DeHaven, the journeyman
    lineman and 4T’s crew foreman on site the day of Meyer’s accident testified that
    while 4T updated McKenzie on work progress, McKenzie did not oversee 4T’s work
    or safety program. McKenzie’s CEO, John Skurupey, testified that McKenzie did not
    supervise, monitor, or inspect 4T’s work and that it was concerned only with the
    finished product. Meyer himself, who was working as an apprentice lineman on the
    -2-
    Project, testified that he had never met any representative from McKenzie during the
    entire time that he was employed by 4T.
    While working on the Project, the 4T crew realized that the neutral conductor
    was not sized properly and had to be replaced. The crew, including Meyer, discussed
    procedures for safely installing a new neutral conductor given that one of the
    overhead conductors was energized at the time. Meyer climbed a pole to change out
    a neutral wire and suffered an electric shock, resulting in serious burns to his hands,
    forearms, and right leg, as well as brain damage. He subsequently underwent the
    amputation of his left hand and has experienced chronic pain and permanent
    disfigurement.
    We review de novo the district court’s grant of summary judgment, viewing the
    evidence in the light most favorable to the nonmoving party and drawing all
    reasonable inferences in that party’s favor. Bishop v. Glazier, 
    723 F.3d 957
    , 960-61
    (8th Cir. 2013). Summary judgment is appropriate if the moving party shows that
    there is no genuine dispute as to any material fact and the moving party is entitled to
    judgment as a matter of law. Fed. R. Civ. P. 56(a). The parties agree that North
    Dakota law governs this diversity action, and we are thus bound by the decisions of
    the North Dakota Supreme Court. See Captiva Lake Invs., LLC v. Fidelity Nat’l Title
    Ins. Co., 
    883 F.3d 1038
    , 1046 (8th Cir. 2018) (applying state law in a diversity
    action). If the state supreme court has not decided the issue, our role is to predict how
    that court would rule. 
    Id.
    Meyer argues that McKenzie owed him a duty of reasonable care and
    negligently caused his injuries. Meyer first contends that the contract between 4T and
    McKenzie was ambiguous and incomplete. He argues that the parties “entered into
    the Contract without any sincere intent to review, understand, negotiate, and/or
    actually abide by its terms.” R. Doc. 50, at 5 (quoting R. Doc. 40, at 6). “[T]he
    language of a contract governs its interpretation if the language is clear and explicit
    -3-
    and does not involve an absurdity.” Rogstad v. Dakota Gasification Co., 
    623 N.W.2d 382
    , 386 (N.D. 2001) (citing N.D. Cent. Code. § 9–07–02). The contract states that
    4T is an “independent contractor” that performs its work “without supervision” by
    McKenzie, which we conclude constitutes a clear and unambiguous statement that 4T
    was retained as an independent contractor.
    Meyer next argues that McKenzie is liable for his injuries because it retained
    actual control over 4T’s work. The North Dakota Supreme Court “has recognized the
    general rule that an employer is not liable for acts or omissions of its independent
    contractor.” Schlenk v. Nw. Bell Tel. Co., Inc., 
    329 N.W.2d 605
    , 608 (N.D. 1983).
    It has also recognized the exception to the general rule that “an employer is liable for
    an independent contractor’s acts on a job over which it has retained control.” Id. at
    612. That is, an employer “who entrusts work to an independent contractor, but who
    retains the control of any part of the work.” Id. (quoting Restatement (Second) of
    Torts § 414). An employer does not retain control over a project when it “is
    concerned primarily only with the finished product.” Id. (citing Lumpkin v. Streifel,
    
    308 N.W.2d 878
    , 883 (N.D.1981)). The employer is liable for the actions of the
    independent contractor “only when the employer retains the right to control the
    method, manner, and operative detail of the work.” Iverson v. Bronco Drilling Co.,
    
    667 F. Supp. 2d 1089
    , 1094-95 (D. N.D. 2009). The North Dakota Supreme Court
    has explained that
    [I]t is not enough for an employer to retain a general right to inspect the
    work progress or receive reports, to make suggestions or
    recommendations, or to prescribe alterations or deviations because those
    general rights are usually reserved to employers of independent
    contractors. Instead, the employer must retain a right of supervision so
    the independent contractor is not entirely free to do the work in its own
    way.
    Pechtl v. Conoco, Inc., 
    567 N.W.2d 813
    , 817 (N.D. 1997).
    -4-
    We conclude that McKenzie did not retain control over 4T’s and Meyer’s
    actions. The statements of those with leadership positions within 4T and McKenzie
    make clear that McKenzie was concerned only with the final product. Moreover, the
    staking sheets and work orders set forth only the location and final outcome of 4T’s
    work, rather than prescribing the specific method in which the work was to be done
    or further details regarding the manner. Finally, even though Lautenschlager
    performed periodic inspections, North Dakota law states that inspecting work does
    not create enough supervision to manifest actual control. See id. at 817.
    Leaving aside McKenzie’s argument that Meyer failed to preserve the claim
    on appeal, Meyer also contends that McKenzie is strictly liable for his injuries, as he
    was engaged in an ultra hazardous activity. The North Dakota Supreme Court has
    declined to hold a utility company strictly liable for “injuries and damages from
    contact with high tension power lines.” Wirth v. Mayrath Indus., Inc., 
    278 N.W.2d 789
    , 791 (N.D. 1979). In rejecting the plaintiff’s argument for imposing strict
    liability for abnormally dangerous activities as set forth in the Restatement (Second)
    of Torts §§ 519 and 520, the Wirth court concluded that the Restatement provisions
    were inapplicable because electrical power is necessary and important and does not
    present an “abnormal danger[].” Id. at 794. Meyer argues that Wirth is
    distinguishable because his case involved the replacement of transmission lines
    energized with high-voltage electricity, rather than the mere transmission of high-
    voltage electricity as was the case in Wirth. Both maintenance and ownership of
    power lines were addressed in Wirth, id. at 791-92, and so we see no reason to read
    its holding as inapplicable to the facts of this case.
    The judgment is affirmed.
    ______________________________________
    -5-
    

Document Info

Docket Number: 18-3244

Filed Date: 1/17/2020

Precedential Status: Precedential

Modified Date: 1/17/2020