Weitz Co. LLC v. MacKenzie House, LLC ( 2011 )


Menu:
  •                     United States Court of Appeals
    FOR THE EIGHTH CIRCUIT
    ___________
    No. 10-3713
    ___________
    The Weitz Company LLC,                *
    *
    Appellant,                 *
    *
    v.                               * Appeal from the United States
    * District Court for the
    MacKenzie House, LLC;                 * Western District of Missouri.
    MH Metropolitan, LLC;                 *
    Arrowhead Contracting, Inc.;          *
    Concorde Construction Co., Inc.,      *
    *
    Appellees.                 *
    ___________
    Submitted: September 20, 2011
    Filed: December 8, 2011
    ___________
    Before MELLOY, SMITH, and BENTON, Circuit Judges.
    ___________
    BENTON, Circuit Judge.
    The Weitz Company, LLC sued MacKenzie House, LLC and MH Metropolitan,
    LLC for breach of a construction contract. Arrowhead Contracting, Inc. and Concorde
    Co., Inc. are third-party defendants. MH Metropolitan counterclaimed for breach of
    the same contract, seeking liquidated damages and the cost to complete the project.
    Arrowhead also counterclaimed. The jury returned a verdict of $4,991,970.87 for MH
    Metropolitan, of $556,110 for Arrowhead, and for Concorde on Weitz’s claim. The
    district court1 denied post-judgment motions. Weitz appeals. Jurisdiction being
    proper under 28 U.S.C. § 1291, this court affirms.
    I.
    MacKenzie House was the developer of a multi-building apartment project
    known as the Metropolitan Apartments. MacKenzie was also the managing member
    of MH Metropolitan, the owner of the Apartments. MH Metropolitan hired Weitz as
    the general contractor. Weitz initially agreed to complete the project within 458 days
    for a maximum price of $13,498,006. The time for completion was ultimately
    extended to 507 days, with the maximum price increased to $14,401,609. Weitz
    subcontracted with Arrowhead and Concorde, among others.
    Work on the Apartments was delayed. Weitz attributes the delays to its
    subcontractors. MH Metropolitan blames Weitz, asserting several material breaches,
    including failing to provide required lien waivers, allowing liens to be filed against
    the project, providing poor quality construction, and falsifying a pay application. MH
    Metropolitan contends it exercised its contractual right to withhold payment on two
    of Weitz’s applications. Weitz stopped work on December 26, 2006. By then, the
    first Building of the project was four months late, and the entire project two months
    late. On January 18, 2007, MH Metropolitan terminated Weitz for cause, finishing
    the project without Weitz.
    The next month, Weitz sued MacKenzie House and MH Metropolitan for the
    unpaid contract balances. MH Metropolitan counterclaimed for breach of contract,
    seeking liquidated damages and the cost to complete. According to MH Metropolitan,
    Weitz’s mismanagement was cause to stop payment and cancel the contract. Weitz
    1
    The Honorable Ortrie D. Smith, United States District Judge for the Western
    District of Missouri.
    -2-
    made third-party claims against Arrowhead and Concorde for their allegedly defective
    work, the cost to complete their work, and the delays they allegedly caused.
    Arrowhead counterclaimed for amounts due under its subcontract, arguing Weitz
    terminated it improperly.
    The jury awarded MH Metropolitan liquidated damages of $3,022,520 due to
    project delay, and $1,969,450.87 for the cost of completion. The jury also awarded
    Arrowhead $556,110, and found for Concorde. The district court denied post-
    judgment motions, entering judgment on the jury’s verdict. Weitz appeals.
    II.
    Weitz contends that the district court erred as a matter of law in six ways by:
    not granting judgment as a matter of law against MH Metropolitan; excluding
    evidence of two other construction projects involving the parties; miscalculating the
    liquidated damages and completion costs; declining to enter judgment on Weitz’s
    breach-of-contract claims against Arrowhead; not entering a default judgment against
    Concorde for failing to appear at trial; and ruling that MacKenzie House could not be
    vicariously liable for the acts of MH Metropolitan.
    A.
    Weitz argues that the district court erred in failing to grant it judgment as a
    matter of law on MH Metropolitan’s breach-of-contract claim.
    This court reviews de novo a denial of a motion for judgment as a matter of law.
    Chalfant v. Titan Distrib., Inc., 
    475 F.3d 982
    , 988 (8th Cir. 2007). Judgment as a
    matter of law is granted if “a party has been fully heard on an issue and there is no
    legally sufficient evidentiary basis for a reasonable jury to find for that party on that
    issue.” Fed. R. Civ. P. 50(a)(1). This court makes all reasonable inferences in favor
    -3-
    of the nonmoving party and views the facts most favorably to that party. 
    Chalfant, 475 F.3d at 988
    .
    During the twelve-day trial, MH Metropolitan presented evidence that Weitz
    committed several material breaches — failing to provide the required lien waivers,
    allowing liens to be filed against the project, causing substantial delays in the project,
    completing poor quality construction, and falsifying a pay application. MH
    Metropolitan submitted testimony and videos showing Weitz’s poor quality
    construction. The jury also heard that Weitz could not properly prepare, update, or
    follow its schedules, which contributed to delaying the project. The project architect
    concluded that Weitz breached the contract in at least these respects. The evidence
    at trial also established other breaches. As a result, MH Metropolitan exercised the
    contractual right to withhold payment and terminate Weitz for cause. As the jury
    instructions noted, to recover for breach of contract, a party must show its own
    substantial compliance with the contract. Brockman v. Soltysiak, 
    49 S.W.3d 740
    , 745
    (Mo. App. 2001). Weitz alleges that it complied with the contract, but whether a
    contract has been substantially performed depends on the facts and circumstances of
    the particular case. In re Estate of English, 
    691 S.W.2d 485
    , 489 (Mo. App. 1985).
    The jury as fact finder resolved this issue against Weitz. See Browning v. President
    River Boat Casino-Missouri, Inc., 
    139 F.3d 631
    , 634 (8th Cir. 1998) (“Appellate
    review of a jury verdict is extremely deferential”). There was a legally sufficient
    evidentiary basis for the jury’s verdict. See 8th Cir. R. 47B.
    B.
    Weitz maintains that the district court incorrectly excluded evidence of two
    other construction projects — one ending in litigation2 — involving the parties.
    2
    Weitz Co. v. MH Washington, 
    631 F.3d 510
    (8th Cir. 2011).
    -4-
    This court respects the district court’s “‘wide discretion in admitting and
    excluding evidence, and its decision will not be disturbed unless there is a clear and
    prejudicial abuse of discretion.’” McPheeters v. Black & Veatch Corp., 
    427 F.3d 1095
    , 1101 (8th Cir. 2005) (citation omitted). To warrant reversal, such a prejudicial
    abuse of discretion must also affect the substantial rights of a party. 
    Id. Likewise, the
    denial of a motion for a new trial is reviewed for an abuse of discretion. 
    Chalfant, 475 F.3d at 992
    . “The crucial determination ‘is whether a new trial should have been
    granted to avoid a miscarriage of justice.’” PFS Distrib. Co. v. Raduechel, 
    574 F.3d 580
    , 589 (8th Cir. 2009) (citation omitted).
    MacKenzie House was the developer on the two other projects Weitz references
    (other corporate entities MacKenzie House managed owned the projects). Even
    assuming that MH Metropolitan and MacKenzie House are one entity, however,
    evidence of prior or other acts “is not admissible to prove the character of a person
    in order to show conformity therewith.” Fed. R. Evid. 404(b). “[P]rior acts include
    prior lawsuits.” Batiste-Davis v. Lincare, Inc., 
    526 F.3d 377
    , 380 (8th Cir. 2008).
    Evidence of prior or other acts “may, however, be admissible for other purposes, such
    as proof of motive, opportunity, intent, preparation, plan, knowledge, identity, or
    absence of mistake or accident.” Fed. R. Evid. 404(b). This type of evidence is
    admitted only when one of these legitimate purposes is at issue in the case. King v.
    Arens, 
    16 F.3d 265
    , 268 (8th Cir. 1994); Donald v. Rast, 
    927 F.2d 379
    , 381 (8th Cir.
    1991).
    The only claims in this case are for breach of contract. The issue at trial was
    whether the parties complied with the contract. Proving a breach here does not put
    motive, intent, plan, or knowledge at issue. See Unit Drilling Co. v. Enron Oil &
    Gas Co., 
    108 F.3d 1186
    , 1194 (10th Cir. 1997). Weitz argues that MH Metropolitan
    “opened the door” to the evidence, but points to no instance where MH Metropolitan
    focused on the other projects. In addition, the district court instructed the jury not to
    speculate about the previous projects and to decide the case solely on the law and the
    -5-
    evidence in this trial. In light of the instruction, the few instances where MH
    Metropolitan alluded to another project do not affect Weitz’s substantial rights. The
    district court properly exercised its discretion in excluding the evidence of other
    projects.
    C.
    According to Weitz, the district court erred in miscalculating the liquidated
    damages and completion costs.
    Weitz asserts that the liquidated damages clause is a penalty. The interpretation
    of a contract is a question of law, reviewed de novo. Simeone v. First Bank N.A., 
    971 F.2d 103
    (8th Cir. 1992). Here, the liquidated damages clause was a reasonable
    forecast of delay damages — as the parties agreed at the time of contracting — and
    is thus enforceable. See Diffley v. Royal Papers, Inc., 
    948 S.W.2d 244
    , 246 (Mo.
    App. 1997); Information Sys. & Networks Corp. v. City of Kansas City, 
    147 F.3d 711
    , 714 (8th Cir. 1998) (applying Missouri law).
    Weitz argues that the liquidated damages are overstated because they were
    measured based on the wrong number of buildings. The district court properly ruled
    that the parties’ agreement is unclear about how many buildings should be used.
    Because of this ambiguity, the issue was properly submitted to the jury, and this court
    will not overturn their reasoned verdict. See Graham v. Goodman, 
    850 S.W.2d 351
    ,
    354 (Mo. banc 1993) (“The trial court must then determine from the evidence whether
    the surrounding circumstances are such that a fact issue exists for the jury to
    resolve.”); Fitch v. Doke, 
    532 F.2d 115
    , 117 (8th Cir. 1976) (“Where, however, the
    contract is ambiguous, the meaning of its terms is to be determined by the jury in the
    light of the evidence of the surrounding circumstances and the practical construction
    of the parties.”). See generally 
    Browning, 139 F.3d at 634
    (“Appellate review of a
    jury verdict is extremely deferential”).
    -6-
    Weitz seeks to apply a Missouri Supreme Court decision limiting liquidated
    damages for construction delay to the time before the owner removes the contractor
    from the project. Moore v. Board of Regents, 
    115 S.W. 6
    , 12-13 (Mo. 1908). The
    facts in Moore were different from those here: there, the project was not yet late when
    the owner terminated the contract. 
    Id. at 12-13.
    More importantly, if faced with this
    case, the Missouri Supreme Court would not follow Moore. Moore relied on a New
    York case for the principle that liquidated damages are not the correct measure of
    damages when the contractor does not complete the project. Gallagher v. Baird, 
    66 N.Y.S. 759
    , 763 (App. Div. 1900). Gallagher actually stands for the proposition that
    the cost to complete is a better measure of damages when a contractor abandons the
    project before the contracted completion date. 
    Id. at 762-63
    (“There was no
    completion or attempt to complete, but an utter abandonment, and such [liquidated
    damages] clause was not intended to cover such a case, nor was provision made in the
    contract for such a contingency.”).3 That conclusion does not resolve the calculation
    of liquidated damages in this case where the project is late when the owner terminates
    the contract.
    Weitz also invokes a Missouri intermediate appellate case that acknowledges
    the divided authorities, but follows Moore. Twin River Const. Co. v. Public Water
    Dist. No. 6, 
    653 S.W.2d 682
    , 693-94 (Mo. App. 1983). Intermediate court decisions,
    however, are not dispositive as to how a state’s highest court would resolve a matter.
    E.g., Bogan v. General Motors Corp., 
    500 F.3d 828
    , 831 (8th Cir. 2007); cf. Six
    Companies of California v. Joint Highway Dist. No. 13, 
    311 U.S. 180
    , 188 (1940)
    3
    At any rate, other cases in New York allow liquidated damages against a
    contractor who abandons a project. See generally Jay M. Zitter, Annotation, Liability
    of Contractor who Abandons Building Project Before Completion for Liquidated
    Damages for Delay, 
    15 A.L.R. 5th 376
    , §§ 4-5 (1993) (compiling two contrary lines
    of New York cases about whether the abandoning contractor can or cannot be held
    liable for liquidated damages for period of time reasonably necessary to complete
    project).
    -7-
    (instructing federal appellate courts to follow intermediate state appellate court
    decisions when “there is no convincing evidence that the law of the State is
    otherwise.”); Washington v. Countrywide Home Loans, Inc., 
    2011 WL 3962831
    , *3
    (8th Cir. 2011) (noting intermediate appellate court decisions must be followed if they
    are the best evidence of the law). In the absence of guidance from the highest state
    court (or a statute on point), the federal court’s task is to predict how the Missouri
    Supreme Court would rule if confronted with the issue today. E.g., Pennsylvania
    Nat’l Mut. Cas. Ins. Co. v. City of Pine Bluff, 
    354 F.3d 945
    , 952 (8th Cir. 2004);
    Maschka v. Genuine Parts Co., 
    122 F.3d 566
    , 573 (8th Cir. 1997). If the Missouri
    Supreme Court were to address the issue today, it would allow liquidated damages for
    a reasonable time after abandonment by the contractor or termination by the owner.
    Weitz contends that the contract precluded MH Metropolitan from claiming
    certain damages as part of the completion costs. “When a breach [in a construction
    contract] results from a combination of defective construction and a failure to
    complete the work, the owners’ damages are calculated using the reasonable cost of
    reconstruction, repair, and completion in accordance with the contract.” Ernery v.
    Freeman, 
    84 S.W.3d 529
    , 536 (Mo. App. 2002); see also Information 
    Systems, 147 F.3d at 713
    (applying Missouri law). Weitz would categorize some of MH
    Metropolitan’s damages as “delay damages” and “theft and property damages” that
    the contract bars MH Metropolitan from recovering. MH Metropolitan responds that
    the damages are in fact costs to complete incurred when it became the contractor on
    the project. The district court correctly decided that these are issues of fact for the
    jury. The jury rejected Weitz’s damages arguments, and this court will not overturn
    its reasoned verdict. See 
    Browning, 139 F.3d at 634
    (“Appellate review of a jury
    verdict is extremely deferential”).
    -8-
    D.
    Weitz claims that the district court should have entered judgment as a matter
    of law for it on the breach-of-contract claims against Arrowhead.
    This court reviews de novo a denial of a motion for judgment as a matter of law
    and grants it if “a party has been fully heard on an issue and there is no legally
    sufficient evidentiary basis for a reasonable jury to find for that party on that issue.”
    
    Chalfant, 475 F.3d at 988
    ; Fed. R. Civ. P. 50(a)(1). This court makes all reasonable
    inferences in favor of the nonmoving party and views the facts most favorably to that
    party. 
    Chalfant, 475 F.3d at 988
    .
    Weitz largely reargues its version of the facts. On each point, there was
    sufficient evidence to reject Weitz’s position. The jury was entitled to credit
    Arrowhead’s evidence that Weitz committed the first material breach and did not
    substantially perform its agreement with Arrowhead, excusing Arrowhead from
    performance. After receiving the evidence, the jury chose — as it was entitled to do
    — to reject Weitz’s evidence. This court finds a legally sufficient evidentiary basis
    for that choice. See 8th Cir. R. 47B.
    E.
    Weitz asserts that the district court erred in refusing to enter a default judgment
    against Concorde when it failed to appear at trial, or in the alternative, refusing to
    grant Weitz judgment as a matter of law on its claims against Concorde. This court
    reviews decisions on default judgments for abuse of discretion. Forsythe v. Hales,
    
    255 F.3d 487
    , 490 (8th Cir. 2001).
    Concorde was represented by counsel for much of the litigation — filing an
    answer, complying with all pretrial orders, and responding to all discovery requests
    -9-
    and dispositive motions. By these acts, particularly by filing an answer, Concorde did
    defend, and the district court was not required to enter a default judgment against it.
    See United States v. Harre, 
    983 F.2d 128
    , 130 (8th Cir. 1993) (“Because [the party]
    filed an answer . . . he indicated a desire to defend against the action.”); cf. Ackra
    Direct Marketing Corp. v. Fingerhut Corp., 
    86 F.3d 852
    , 857 (8th Cir. 1996) (stating
    it is within the district court’s discretion to enter default judgment even after filing of
    answer if party’s later conduct includes ‘willful violations of court rules,
    contumacious conduct, or intentional delays.’ (citation omitted)). About two and a
    half weeks before trial, Concorde’s attorneys moved to withdraw; the court granted
    the motion on January 13, 2010. On the morning of January 25, when trial began,
    Concorde was not represented by counsel. The district court denied Weitz’s motion
    for a default judgment, and Weitz — unopposed — submitted its claims against
    Concorde to the jury. Choosing not to appear for trial — especially after defeating
    motions to dismiss a counterclaim — does not necessarily constitute the “willful
    violation” of court rules that places a defendant in default. See 
    Harre, 983 F.2d at 130
    . (Default judgment for failure to defend is appropriate when the party's conduct
    includes “willful violations of court rules, contumacious conduct, or intentional
    delays.”). The jury rejected Weitz’s claims, and the district court properly allowed
    that decision to stand. Cf. Pfanensteil Architects, Inc. v. Chouteau Petroleum Co.,
    
    978 F.2d 430
    , 433 (8th Cir. 1992) (“When there are multiple defendants who may be
    jointly and severally liable for damages alleged by plaintiff, and some but less than
    all of those defendants default, the better practice is for the district court to stay its
    determination of damages against the defaulters until plaintiff's claim against the
    nondefaulters is resolved. . . . to avoid the problems of dealing with inconsistent
    damage determinations . . . .”)
    As the district court concluded, it would be unjust to grant judgment to Weitz
    after the jury rejected its contentions.
    -10-
    F.
    Weitz contends that the district court should have ruled that MacKenzie House
    — which did not sign the contract — could be vicariously liable for the acts of MH
    Metropolitan. Because the district court properly found against Weitz on all issues,
    there is no reason to consider the issue of vicarious liability.
    *******
    The judgment of the district court is affirmed.
    ______________________________
    -11-
    

Document Info

Docket Number: 10-3713

Judges: Melloy, Smith, Benton

Filed Date: 12/8/2011

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (24)

Ackra Direct Marketing Corp. And Michael Ackerman, ... ( 1996 )

Bogan v. General Motors Corp. ( 2007 )

United States of America, on Behalf of and for the Use of ... ( 1993 )

Batiste-Davis v. Lincare, Inc. ( 2008 )

Pfanenstiel Architects, Inc. v. Chouteau Petroleum Company ... ( 1992 )

eula-faye-king-eddie-dwayne-king-and-nancy-marie-king-as-the-heirs-at ( 1994 )

Twin River Construction Co. v. Public Water District No. 6 ( 1983 )

George Fitch v. Galen Doke, D/B/A Mid-America Stock Car ... ( 1976 )

Information Systems and Networks Corporation v. City of ... ( 1998 )

Michael E. McPheeters v. Black & Veatch Corporation ( 2005 )

Robert Wayne Chalfant v. Titan Distribution, Inc. Titan ... ( 2007 )

Gregory L. Donald v. Balfour J. Rast, Anthony D. Hogan, ... ( 1991 )

pennsylvania-national-mutual-casualty-insurance-company-a-pennsylvania ( 2004 )

Six Companies of Cal. v. Joint Highway Dist. No. 13 of Cal. ( 1940 )

74-fair-emplpraccas-bna-1035-74-empl-prac-dec-p-45623-aloysius-l ( 1997 )

Brockman v. Soltysiak ( 2001 )

Erney v. Freeman ( 2002 )

Diffley v. Royal Papers, Inc. ( 1997 )

Lee Browning v. President Riverboat Casino-Missouri, Inc., ... ( 1998 )

Weitz Co. v. MH WASHINGTON ( 2011 )

View All Authorities »