J.B. Hunt Transport, Inc. v. BNSF Railway Company ( 2021 )


Menu:
  •                  United States Court of Appeals
    For the Eighth Circuit
    ___________________________
    No. 20-2679
    ___________________________
    J.B. Hunt Transport, Inc.
    Plaintiff - Appellant
    v.
    BNSF Railway Company
    Defendant - Appellee
    ____________
    Appeal from United States District Court
    for the Western District of Arkansas - Fayetteville
    ____________
    Submitted: April 14, 2021
    Filed: August 13, 2021
    ____________
    Before GRUENDER, BENTON, and SHEPHERD, Circuit Judges.
    ____________
    GRUENDER, Circuit Judge.
    On October 24, 2019, an arbitration panel (the “Panel”) issued its award (the
    “Award”) in a dispute between J.B. Hunt Transport, Inc. and BNSF Railway Co.
    Hunt moved the district court to confirm the Award and to provide additional relief,
    which Hunt described as “enforcement” of the Award. The district court confirmed
    the Award but denied Hunt’s request for additional relief. Hunt appeals. We affirm
    in part and reverse in part.
    I.
    BNSF, a railroad company, and Hunt, a trucking company, entered into a Joint
    Service Agreement (the “JSA”) in 1996. Under the terms of the JSA, either BNSF
    or Hunt may offer a customer a quote for door-to-door shipping service. If the
    customer accepts the offer, then Hunt trucks the load from the customer’s origin
    point to a nearby BNSF ramp, BNSF ships the load by rail to a ramp near the
    customer’s destination point, and Hunt trucks the load from the ramp to the
    destination point. Section 1 of the JSA requires each party to “provide the other with
    all shipping and billing information for all movements in joint service.” Although
    the JSA permits either party to offer quotes to potential customers, in practice, it has
    been Hunt that has solicited business under the JSA.
    The JSA provides two methods for allocating the revenue from a joint-service
    shipment. The default method is for BNSF and Hunt to split the revenue according
    to a fixed formula (the “Revenue Split”). At Hunt’s option, however, the parties
    may use the method described in section 3(a) of the JSA instead. Section 3(a)
    provides that “any rates for movement of dry vans, refrigerated or protective service
    trailers or containers or flatbed trailers [BNSF] makes available to any truckload
    motor carrier for movement over [BNSF’s] lines, will also be made available on an
    equivalent or at least as favorable basis to [Hunt] for comparable service.” We use
    the term “Rate Offer” to refer to an offer package composed of a rate and the terms
    and conditions that constitute the “basis” on which the rate is being provided. Thus,
    under section 3(a), Hunt may select a Rate Offer that BNSF has extended to another
    truckload carrier for comparable service and apply it to the rail portion of a joint-
    service shipment in lieu of paying BNSF its share of the Revenue Split.
    In 2017, the parties brought several JSA-related disputes to the Panel pursuant
    to the JSA’s arbitration provision. Some of these disputes concerned sections 1
    and 3(a). In 2019, the Panel issued the Award, which took the form of a final
    decision (the “Final Ruling”) that incorporated multiple interim decisions, including
    one issued in 2018 (the “Interim Ruling”). The Panel explicitly “decline[d] to award
    -2-
    damages or other penalty, order, etc., as to section 3(a).” It did, however, attempt to
    clarify the parties’ obligations under sections 1 and 3(a), in part by specifying the
    factors that determine “what constitutes an ‘equivalent or at least as favorable basis’
    and ‘comparable service’ for purposes of JSA Section 3(a).”
    Immediately, Hunt and BNSF disagreed about how to interpret the Award.
    First, Hunt claimed, and BNSF denied, that the Panel’s lists of equivalent-basis and
    comparable-service factors are exclusive. Second, the parties disagreed about which
    Rate Offers the Panel held BNSF must disclose and permit Hunt to use in lieu of the
    Revenue Split.
    Hunt moved the district court to confirm the Award. It also moved for
    additional relief, which it labeled “enforcement” relief, consisting of “an order
    specifically setting forth BNSF’s obligations [under section 3(a) as interpreted by
    the Award] and requiring BNSF to comply with them.” BNSF agreed that the Award
    should be confirmed but opposed Hunt’s request for additional relief. According to
    BNSF, Hunt’s request for additional relief rested on a misinterpretation of the
    Award, and even it if did not, the district court had no authority to grant the relief.
    The district court confirmed the Award but denied Hunt’s request for
    additional relief on the ground that it rested on a misinterpretation of the Award.
    Hunt appeals. As it did before the district court, BNSF both contests Hunt’s
    interpretation of the Award and maintains that, even assuming Hunt’s interpretation
    is correct, Hunt was not entitled to the additional relief it requested.
    II.
    We begin with BNSF’s arguments that we need not reach the parties’ dispute
    about the interpretation of the Award because even assuming Hunt’s interpretation
    is correct, the district court properly denied Hunt’s request for additional relief. See
    Duffner v. City of St. Peters, 
    930 F.3d 973
    , 976 (8th Cir. 2019) (“We may affirm on
    any ground supported by the record.”). We review legal determinations de novo and
    -3-
    factual findings for clear error. See RGA Reins. Co. v. Ulico Cas. Co., 
    355 F.3d 1136
    , 1138 (8th Cir. 2004).
    A.
    BNSF’s first argument is that Hunt’s request for additional relief was
    premature. As BNSF notes, Hunt captioned its request for additional relief as a
    request for “enforcement” of the Award. According to BNSF, this request was
    premature because “an arbitration award is . . . converted to a judgment” only when
    it is confirmed, and “until there is a judgment, there is nothing for federal courts to
    ‘enforce.’”
    BNSF would be correct if Hunt had been using “enforcement” in the standard
    sense of the term, to refer to the imposition of sanctions on a party for violation of a
    court order. See, e.g., Int’l Union, United Mine Workers of Am. v. Bagwell, 
    512 U.S. 821
    , 835 (1994) (using “enforcement” in this sense). As BNSF points out, an
    arbitration award acquires the force of a court judgment only when it is confirmed.
    See Domino Grp., Inc. v. Charlie Parker Mem’l Found., 
    985 F.2d 417
    , 420 (8th Cir.
    1993) (explaining that confirmation is what “convert[s an award] into a court
    judgment”). Therefore, if Hunt had been asking the district court to sanction BNSF
    for its alleged failure to comply with the terms of the as-of-then-unconfirmed Award,
    then Hunt’s request would have been premature.
    But Hunt’s filings make clear that it was not asking for “enforcement” in this
    sense. Instead, the substance of Hunt’s request for additional relief was twofold.
    First, Hunt explained that it sought “an order specifically setting forth BNSF’s
    [section 3(a)] obligations” under the Award because BNSF had refused to recognize
    the Panel’s holdings. In other words, Hunt was asking for a declaratory judgment
    adopting its interpretation of the Award’s interpretation of section 3(a). Second,
    Hunt explained that it was seeking a court order “requiring BNSF to comply” with
    its section 3(a) obligations because Hunt feared that BNSF would not perform its
    section 3(a) obligations unless under threat of sanctions for contempt of court. In
    -4-
    other words, in addition to a declaratory judgment adopting Hunt’s interpretation of
    the Award’s interpretation of BNSF’s section 3(a) obligations, Hunt was asking for
    an order of specific performance directing BNSF to discharge those obligations. Cf.
    Koolvent Metal Awning Corp. of Am. v. Bottom, 
    205 F.2d 209
    , 215 (8th Cir. 1953)
    (describing “a suit for specific performance” as a request for “enforcement of the
    contract[]”).
    Neither of these two forms of relief presupposes that BNSF’s alleged failure
    to comply with the terms of the Award prior to its confirmation constitutes a breach
    of a court order. Therefore, focusing on the substance of Hunt’s request for
    additional relief rather than how Hunt captioned it, see BBCA, Inc. v. United States,
    
    954 F.2d 1429
    , 1431-32 (8th Cir. 1992), we conclude that the request was not
    premature.
    B.
    BNSF’s second argument, in essence, is that Hunt’s request for additional
    relief is either moot or statutorily precluded. On the one hand, confirmation of an
    award “convert[s it] into a court judgment.” Domino Grp., 
    985 F.2d at 420
    .
    Therefore, BNSF reasons, if Hunt was asking the district court for an order that
    merely reiterated what the Award already held, then Hunt’s request for “additional
    relief” was redundant given its request for confirmation. In that case, having granted
    Hunt’s request for confirmation, the district court should have denied Hunt’s request
    for additional relief as moot. See DeFunis v. Odegaard, 
    416 U.S. 312
    , 316-17 (1974)
    (per curiam) (dismissing a claim as moot because the plaintiff had received
    everything he requested). On the other hand, BNSF reasons, if Hunt was asking the
    district court for an order that went beyond what the Award already held, then Hunt
    was asking the district court to modify the Award. In that case, the district court
    should have denied Hunt’s request for additional relief as precluded by 
    9 U.S.C. § 11
    , which enumerates the exclusive grounds for modifying an award, Hall St.
    Assocs., L.L.C. v. Mattel, Inc., 
    552 U.S. 576
    , 578 (2008), none of which either party
    maintains is present here.
    -5-
    We agree with BNSF in part, but we also disagree in part. Insofar as Hunt
    was requesting a declaratory judgment, we disagree. “In a case of actual controversy
    within its jurisdiction,” subject to exceptions inapplicable here, “any court of the
    United States, upon the filing of an appropriate pleading, may declare the rights and
    other legal relations of any interested party seeking such declaration, whether or not
    further relief is or could be sought.” 
    28 U.S.C. § 2201
    (a). A dispute about the scope
    of one party’s contractual obligations to another is an “actual controversy” that either
    party has the requisite interest to ask a federal court to resolve by a declaration
    pursuant to § 2201(a). See, e.g., Maytag Corp. v. Int’l Union, United Auto.,
    Aerospace & Agric. Implement Workers of Am., 
    687 F.3d 1076
    , 1081-82 (8th Cir.
    2012). And a dispute about what a confirmed arbitration award held to be a party’s
    contractual obligations is a dispute about what the party’s contractual obligations
    are as far as the law is concerned. See Am. Postal Workers Union v. U.S. Postal
    Serv., 
    550 F.3d 27
    , 30 (D.C. Cir. 2008) (explaining that a confirmed award’s
    interpretation of a contract “is to be treated as though it were a written stipulation by
    the parties setting forth their own definitive construction of the contract” (internal
    quotation marks omitted)). Therefore, a dispute about what an arbitration award
    held to be one party’s contractual obligations to another is a dispute that either party
    has the requisite interest to ask a federal court to resolve by a declaration pursuant
    to § 2201(a). Cf. RGA, 
    355 F.3d at 1138-39
     (affirming the district court’s resolution
    of a dispute about how much money an arbitration award required one party to pay
    the other, albeit without framing this remedy as a declaratory judgment);
    Brotherhood of Teamsters & Auto Truck Drivers Loc. No. 70 of Alameda Cnty. v.
    Celotex Corp., 
    708 F.2d 488
    , 491 (9th Cir. 1983) (affirming the district court’s
    resolution of a dispute about what an arbitration award held a contract required of
    one of the parties, albeit without framing this remedy as a declaratory judgment).
    Here, the parties disagree about what the Award held to be BNSF’s
    section 3(a) obligations to Hunt. For the reasons explained above, Hunt had the
    requisite interest to ask the district court to resolve this dispute by declaration after
    confirming the Award. And this dispute lay within the district court’s subject-matter
    jurisdiction because the parties are diverse and the amount in controversy exceeds
    -6-
    $75,000. See 
    28 U.S.C. § 1332
    (a). Therefore, assuming Hunt’s interpretation of the
    Award is correct, it was entitled to a declaratory judgment to that effect once the
    district court had confirmed the Award.
    BNSF’s argument to the contrary does not persuade us. By clarifying the
    meaning of the Award, a declaratory judgment would give Hunt something that
    confirmation of the Award did not. Therefore, the district court’s confirmation of
    the Award did not render Hunt’s request for a declaratory judgment moot. And by
    only clarifying the meaning of the Award, a declaratory judgment would leave the
    Award unmodified. See RGA, 
    355 F.3d at 1139
     (holding that clarification of an
    arbitration award does not constitute modification of the award). Therefore,
    
    9 U.S.C. § 11
     does not preclude granting Hunt’s request for a declaratory judgment.
    Insofar as Hunt was requesting an order of specific performance, however, we
    agree with BNSF. If the Award had ordered specific performance, then the district
    court’s confirmation of the Award would have rendered Hunt’s request for another
    order of specific performance moot. See DeFunis, 
    416 U.S. at 316-17
    . In fact, the
    Panel explicitly “decline[d] to award damages or other penalty, order, etc., as to
    section 3(a).” Therefore, Hunt’s request for an order of specific performance was
    not moot. But, for the same reason, it was statutorily precluded. Unlike merely
    clarifying the Award, granting a remedy that the Award did not grant would
    constitute modifying the Award. See, e.g., In re Petrie v. Clark Moving & Storage,
    Inc., No. 09-CV-06495, 
    2010 WL 1965801
    , at *5 (W.D.N.Y. May 17, 2010) (noting
    that if an arbitration award is silent on interest, then to add interest would be to
    modify the award). And Hunt does not claim that the conditions for modifying an
    award under 
    9 U.S.C. § 11
     are present. Therefore, because the Award did not order
    specific performance, 
    9 U.S.C. § 11
     precluded the district court from doing so.
    In sum, we agree with BNSF that we need not reach the merits of the parties’
    dispute about the interpretation of the Award to conclude that the district court
    properly denied Hunt’s request for “enforcement” insofar as it was a request for an
    -7-
    order of specific performance.1 But we do need to reach the merits of the parties’
    dispute about the interpretation of the Award to determine whether the district court
    properly denied Hunt’s request for “enforcement” insofar as it was a request for a
    declaratory judgment. Accordingly, we turn to the merits of the parties’ interpretive
    dispute.
    III.
    We review a district court’s interpretation of an arbitration award de novo.
    Turner v. United Steelworkers of Am., Loc. 812, 
    581 F.3d 672
    , 673 (8th Cir. 2009).
    Here, the parties disagree about (1) whether the Award’s comparable-service and
    equivalent-basis factors are exclusive and (2) which Rate Offers the Award obligates
    BNSF to disclose and permit Hunt to use in lieu of the Revenue Split. We resolve
    these disagreements in Sections B and C, respectively. In Section A, we address the
    threshold question how to proceed in the event that the Award is ambiguous.
    A.
    Generally, “[a]n ambiguous award should be remanded to the arbitrators.”
    Domino Grp., 
    985 F.2d at 420
    . As discussed below, the Award was less than clear
    on several points. Arguably, then, the district court should have vacated the Award
    and remanded to the arbitrator for clarification. But see Teamsters Loc. No. 579 v.
    B & M Transit, Inc., 
    882 F.2d 274
    , 278 (7th Cir. 1989) (“When possible, . . . a court
    should avoid remanding a decision to the arbitrator because of the interest in prompt
    1
    As the district court noted, if in the future Hunt suspects that BNSF is in
    breach of what the Award declared to be BNSF’s section 3(a) obligations, then Hunt
    should bring its claim to arbitration per the JSA’s arbitration provision. Assuming
    the arbitrator agreed that BNSF had breached its contractual obligations, it would be
    up to Hunt to convince the arbitrator to award specific performance rather than or in
    addition to damages. Only if and when an arbitrator awards specific performance, a
    court confirms that award, and BNSF still refuses to perform would it be proper for
    Hunt to initiate contempt proceedings. Until then, BNSF would be in breach of, at
    most, its contractual obligations, not a court order.
    -8-
    and final arbitration.”); Matrix Serv., Inc. v. Int’l Union of Operating Eng’rs, Loc.
    150, No. 05 CV 3618, 
    2005 WL 8179249
    , at *1 (N.D. Ill. Nov. 22, 2005) (“[C]ourts
    may vacate arbitration awards only ‘upon the application of any party to the
    arbitration.’” (emphasis omitted) (quoting 
    9 U.S.C. § 10
    (a))); Van Erkis & Co. v.
    Solo Worldwide Enter., No. 98 CIV. 1385 (DLC), 
    2000 WL 423523
    , at *2-3
    (S.D.N.Y. Apr. 18, 2000) (same).
    Even assuming the district court erred in confirming the Award, however, it
    would be inappropriate for us to vacate the confirmation because neither party
    appealed the issue. See United States v. Sineneng-Smith, 590 U.S. ---, 
    140 S. Ct. 1575
    , 1579 (2020) (explaining that courts should not “sally forth . . . looking for
    wrongs to right” but should instead “normally decide only questions presented by
    the parties”); El Paso Nat. Gas Co. v. Neztsosie, 
    526 U.S. 473
    , 478-79 (1999)
    (holding that the appellate court erred in addressing those parts of the district court’s
    orders that the parties did not appeal). Therefore, we do not disturb the confirmation
    of the Award.
    Consequently, we must decide how to resolve ambiguity in the Award. The
    Federal Arbitration Act provides that, once confirmed, an award “shall have the
    same force and effect, in all respects, as, and be subject to all the provisions of law
    relating to, a judgment in an action.” 
    9 U.S.C. § 13
    ; see also Domino Grp., 
    985 F.2d at 420
    . Therefore, having concluded that we may not disturb the Award’s
    confirmation, we must treat the Award as if it were a judgment issued by the district
    court. This means resolving any ambiguity in the Award by “constru[ing the Award]
    as a whole”; consulting the record if necessary; and, if the Award remains
    “susceptible of two interpretations,” adopting the interpretation that “renders it the
    more reasonable, effective and conclusive.” See Harjo v. Empire Gas & Fuel Co.,
    
    28 F.2d 596
    , 598-99 (8th Cir. 1928) (explaining how to resolve ambiguity in a court
    judgment).
    -9-
    B.
    The parties’ first interpretive dispute concerns whether the Award’s
    equivalent-basis and comparable-service factors are exclusive. The district court
    concluded that they are not. Based on the plain text of the Award, however, we
    agree with Hunt that they are. In the Interim Ruling, the Panel ordered the parties to
    attempt to settle their longstanding dispute about “the specific criteria that define
    ‘comparable service.’” “In the event that the parties are unable to agree,” the Panel
    continued, “[t]he Panel will resolve the matter in its final award.” The parties were
    unable to agree. Accordingly, after noting that the parties also continued to disagree
    about the meaning of the phrase “equivalent or at least as favorable basis,” the Panel
    declared in its Final Ruling that it “must determine [for the parties] what constitutes
    an ‘equivalent or at least as favorable basis’ and ‘comparable service’ for purposes
    of JSA Section 3(a).” The Panel’s use of “define” rather than “partially define” and
    “constitutes” rather than “partially constitutes” indicates that it intended the factors
    it enumerated to be exclusive.
    Moreover, even if the Award’s text were ambiguous, we would reach the same
    conclusion by considering “the entire record” and, if all else failed, adopting the
    interpretation that renders the Award more “reasonable, effective and conclusive.”
    See Harjo, 28 F.2d at 599. The record indicates that part of what drove the parties’
    dispute was Hunt’s concern that BNSF was narrowing what constitutes “comparable
    service” to avoid having to disclose favorable rates to Hunt. The Award could not
    have “resolve[d]” this dispute unless it enumerated an exclusive list of factors that
    precluded BNSF from adding more. Therefore, the record supports Hunt’s position
    that the Award’s lists of factors are exclusive. And even if the record were neutral,
    Hunt’s interpretation would still render the Award more “effective and conclusive”
    than BNSF’s interpretation. See id.
    -10-
    C.
    The parties’ second interpretive dispute concerns which Rate Offers the Panel
    held section 3(a) obligates BNSF to disclose and permit Hunt to use in lieu of the
    Revenue Split. Hunt argues that the Panel held that section 3(a) obligates BNSF to
    disclose to Hunt every Rate Offer that BNSF extends to another truckload carrier
    and to permit Hunt to use those which are for comparable service. BNSF argues,
    and the district court agreed, that the Panel held that section 3(a) obligates BNSF to
    disclose and permit Hunt to use only those Rate Offers that are for comparable
    service and that come with rates that are lower than BNSF’s share of the Revenue
    Split. In addition, BNSF appears to argue that its section 3(a) obligations are
    conditioned on Hunt providing BNSF with sufficient information to determine
    which Rate Offers meet these criteria. We adopt a middle-ground position.
    1.
    Hunt rests its position on the following passage in the Final Ruling:
    BNSF argued that, as a predicate to its compliance with its Section 3(a)
    obligations to provide rates to HUNT, HUNT must first provide to
    BNSF the rates that HUNT quotes or provides to JSA customers,
    including all of the information that BNSF claims is necessary for it to
    determine if the rates it quotes to other truckload motor carriers are
    lower than the revenue divisions it receives from HUNT for JSA
    movements or other agreed-upon rates applicable to JSA shipments.
    Section 3(a) of the JSA does not expressly contain any such
    requirement, nor is BNSF’s obligation to make rates available to HUNT
    thereunder expressly predicated upon HUNT providing any such
    information or on whether such rates are lower than the revenue
    divisions BNSF receives . . . .
    According to Hunt, this passage holds that Hunt’s provision of information regarding
    JSA shipments is not a condition for BNSF’s section 3(a) obligation to permit Hunt
    to use Rate Offers extended to other truckload carriers for comparable service. As
    -11-
    Hunt points out, however, BNSF cannot know which Rate Offers are for comparable
    service unless Hunt supplies BNSF with information about the orders that Hunt is
    fulfilling. Therefore, Hunt argues, BNSF must be prepared to comply with its
    section 3(a) obligations despite not knowing which Rate Offers are for comparable
    service. And Hunt maintains that the only way for BNSF to do this is to disclose to
    Hunt every Rate Offer that BNSF extends to another truckload carrier. Thus, while
    conceding that it is entitled to use only those Rate Offers that are for comparable
    service, Hunt concludes that the Panel held that section 3(a) obligates BNSF to
    disclose to Hunt every Rate Offer.
    2.
    BNSF relies on the Interim Ruling to support its position. There, the Panel
    accepted the conclusions of a prior panel that had adjudicated a dispute between the
    parties in 2005. The 2005 panel found that, on at least one occasion, BNSF had
    failed to make available to Hunt a Rate Offer for comparable service that came with
    a rate that was lower than BNSF’s share of the Revenue Split. But the 2005 panel
    also noted that because Hunt “did not notify BNSF when it established [JSA] rates,”
    BNSF had no way of knowing which rates were lower than its share of the Revenue
    Split. The 2005 panel did not hold that BNSF was therefore obligated to disclose to
    Hunt every Rate Offer that BNSF extended to another truckload carrier to ensure
    that Hunt did not miss out on a Rate Offer to which it was entitled. On the contrary,
    the 2005 panel denied that the JSA imposed “duties to monitor, enforce or report the
    status of ongoing rate structures/offers made by either party to its customers.”
    Instead, the 2005 panel held that Hunt is “the party in the best position” to ensure
    that it does not miss out on a Rate Offer to which it is entitled by “advising BNSF
    of the J.B. Hunt-quoted JSA rates . . . or coordinating rate making and quoting with
    BNSF.” Accordingly, the 2005 panel declined to hold BNSF liable for its failure to
    make available to Hunt a Rate Offer for comparable service that came with a rate
    that was lower than BNSF’s share of the Revenue Split. Thus, the 2005 panel
    apparently interpreted section 3(a) to obligate BNSF to disclose and permit Hunt to
    use only those Rate Offers that are for comparable service and that come with rates
    -12-
    that are lower than BNSF’s share of the Revenue Split, and only on the condition
    that Hunt provides BNSF with sufficient information to determine which Rate Offers
    meet these criteria.
    In the Interim Ruling, the Panel not only stated that it accepted the 2005
    panel’s conclusions but also defended those conclusions on the merits. The Panel
    agreed with BNSF that section 1 of the JSA obligates Hunt to provide sufficient
    information “for BNSF to determine what is ‘comparable service’” and when it is
    “granting a lower rate” to another truckload carrier. The Panel explained that it is
    “[b]ecause Hunt . . . historically may not have complied fully with Section 1’s
    requirements” that “BNSF is left to guess at whether, when it makes a rate available
    to another truckload motor carrier, that rate might be lower than the JSA revenue
    division.” These remarks suggest that the Panel agreed with the 2005 panel that
    BNSF’s section 3(a) obligations are conditioned on Hunt providing sufficient
    information for BNSF to determine which Rate Offers are for comparable service
    and come with rates that are lower than BNSF’s share of the Revenue Split.
    3.
    The parties’ arguments expose a genuine ambiguity in the Award. The first
    step toward resolving this ambiguity is to read the passages cited by the parties
    together, harmonizing them where it is possible to do so and, where it is not, looking
    for indicators of which passage is controlling. See Harjo, 28 F.2d at 599 (explaining
    that ambiguity in a court judgment is to be resolved by construing the judgment as a
    whole).
    To an extent, it is possible to harmonize the two passages. In the Final Ruling,
    the Panel noted BNSF’s argument that its section 3(a) obligations are conditioned
    on Hunt providing “the rates that HUNT quotes or provides to JSA customers,
    including all of the information that BNSF claims is necessary for it to determine if
    the rates it quotes to other truckload motor carriers are lower than the revenue
    divisions BNSF receives.” The Panel then held that “BNSF’s obligation to make
    -13-
    rates available to HUNT” under section 3(a) is not “expressly predicated upon
    HUNT providing any such information.” Hunt reads “any such information” to
    mean any information at all about the JSA shipments. But it is more plausible to
    read “any such information” to mean “the information . . . necessary for [BNSF] to
    determine if the rates it quotes to other truckload motor carriers are lower than the
    revenue divisions BNSF receives.” On this reading, the Final Ruling is consistent
    with the proposition—which the Interim Ruling appeared to endorse—that BNSF’s
    section 3(a) obligations are conditioned on Hunt providing the information
    necessary for BNSF to determine which Rate Offers are for comparable service.
    Although this reading minimizes the conflict between the passages, it does not
    eliminate it altogether. Two points of conflict remain. The first is whether BNSF
    must disclose and permit Hunt to use a given Rate Offer only if the Rate Offer comes
    with a rate that is lower than BNSF’s share of the Revenue Split. The second is
    whether BNSF must disclose and permit Hunt to use a given Rate Offer only if Hunt
    provides BNSF with sufficient information for BNSF to know whether the Rate
    Offer comes with a rate that is lower than BNSF’s share of the Revenue Split.
    Accordingly, we look for textual and structural indicators of which passage is
    controlling on these points. Comparison of the passages’ text supports treating the
    language in the Final Ruling as controlling. The Interim Ruling merely implied that
    BNSF must disclose and permit Hunt to use a given Rate Offer only if the Rate Offer
    comes with a rate that is lower than BNSF’s share of the Revenue Split and Hunt
    provides sufficient information for BNSF to know that this is the case. The Final
    Ruling’s indication to the contrary was much more explicit. In addition, the structure
    of the Award supports treating the language in the Final Ruling as controlling.
    Although the Final Ruling did incorporate the Interim Ruling, the Final Ruling was
    issued later and represents the Panel’s final word on the matter. Therefore, we treat
    the language in the Final Ruling as controlling on these points.
    Consequently, we can rule out BNSF’s position that section 3(a) obligates it
    to disclose and permit Hunt to use only those Rate Offers for comparable service
    -14-
    that come with rates that are lower than BNSF’s share of the Revenue Split. BNSF’s
    position is inconsistent with the Final Ruling’s statement, which we have decided is
    controlling, that BNSF’s section 3(a) obligations “to make rates available to HUNT”
    are not predicated upon “whether such rates are lower than the revenue divisions
    BNSF receives.”
    That said, nothing in the Final Ruling requires going so far as to adopt Hunt’s
    position that section 3(a) obligates BNSF to disclose every Rate Offer that BNSF
    extends to another truckload carrier and then permit Hunt to use any that is for
    comparable service. Hunt’s argument for this position rests on the premise that
    BNSF’s section 3(a) obligations are not conditioned on Hunt providing any
    information at all about the JSA shipments. But we have rejected this premise,
    concluding that it is plausible to interpret the Final Ruling in a way that is consistent
    with the Interim Ruling’s implicit endorsement of the proposition that BNSF’s
    section 3(a) obligations are conditioned on Hunt providing sufficient information for
    BNSF to determine which Rate Offers are for comparable service.
    Indeed, given that the Final Ruling does not say otherwise, the Interim Ruling
    allows us to rule out Hunt’s position too. According to the Interim Ruling, the JSA
    does not require either party to “report the status of ongoing rate structures/offers
    made by either party to its customers.” Hunt’s position that BNSF must disclose
    every Rate Offer that it extends to another truckload carrier is inconsistent with this
    statement.
    Having ruled out the parties’ positions on the extremes, we conclude that the
    Panel adopted a position somewhere in the middle. Unfortunately, the Panel failed
    to make clear precisely where in the middle this position was. Accordingly, because
    the Award remains “susceptible of [multiple] interpretations” even after
    “constru[ing it] as a whole,” we must resolve the residual ambiguity in whichever
    way renders the Award most “reasonable, effective and conclusive.” See Harjo, 28
    F.2d at 599.
    -15-
    The interpretation that we conclude renders the Award most reasonable is one
    that comports with its other holdings. When analyzing the meaning of “on an
    equivalent or at least as favorable basis,” the Panel identified eight factors, in
    addition to the rate itself, that determine how “favorable” a Rate Offer is. A Rate
    Offer that comes with a rate that is higher than BNSF’s share of the Revenue Split
    might be more favorable to Hunt than the Revenue Split on one of these factors. For
    example, that Rate Offer might come with free empty-repositioning services that
    would not otherwise be available to Hunt under the JSA. If Hunt could purchase
    empty-repositioning services from BNSF for less than the difference between
    BNSF’s share of the Revenue Split and the rate associated with the Rate Offer, then
    Hunt would be better off opting for the Revenue Split no matter how much it values
    empty repositioning. But if Hunt would have to pay BNSF more for empty-
    repositioning services than the difference between BNSF’s share of the Revenue
    Split and the rate associated with the Rate Offer, then whether Hunt is better off
    opting for the Revenue Split depends on how much it values empty repositioning.
    In that case, as Hunt points out, BNSF cannot know whether, from Hunt’s
    perspective, the Rate Offer is more favorable overall than the Revenue Split unless
    BNSF presents the Rate Offer to Hunt and lets Hunt decide. It would make little
    sense if the Panel nonetheless held that section 3(a) allows BNSF not to disclose or
    permit Hunt to use the Rate Offer.
    That said, the fact that BNSF must disclose some Rate Offers for comparable
    service that come with rates that are higher than BNSF’s share of the Revenue Split
    does not mean that BNSF must disclose all Rate Offers for comparable service.
    Presumably, the reason why the 2005 panel and the Interim Ruling limited BNSF’s
    section 3(a) obligations to disclosing and permitting Hunt to use Rate Offers that
    come with rates that are lower than BNSF’s share of the Revenue Split is that one
    way to discharge an obligation to make a rate available on an equivalent or at least
    as favorable basis is to make a rate available on even better terms. On this view, if
    BNSF can ascertain without consulting Hunt that the Revenue Split—the functional
    equivalent of a Rate Offer—is more favorable overall than every Rate Offer that
    BNSF extends to another truckload carrier for comparable service, then permitting
    -16-
    Hunt to use the Revenue Split discharges BNSF’s section 3(a) obligations. By
    permitting Hunt to use the Revenue Split, BNSF would effectively be making the
    rates offered to other truckload carriers available to Hunt on a more favorable basis.
    We find this view reasonable, and it comports with the Final Ruling, which merely
    clarified that being more favorable in one respect does not entail being more
    favorable overall.
    Thus, to determine whether it must disclose and permit Hunt to use a given
    Rate Offer for comparable service, BNSF must compare the Rate Offer with the
    Revenue Split. If the Revenue Split is at least as favorable overall as the Rate Offer
    no matter how Hunt values the equivalent-basis factors, then BNSF need not disclose
    or permit Hunt to use the Rate Offer. This will be the case if, by opting for the
    Revenue Split, Hunt can get at equal or less cost everything that it could get under
    the Rate Offer. Otherwise, BNSF must either disclose and permit Hunt to use the
    Rate Offer or make Hunt another Rate Offer that does give Hunt, at equal or less
    cost, everything that the former Rate Offer would give it.
    In sum, we hold that BNSF’s section 3(a) obligations under the Award are as
    follows. If Hunt fails to provide sufficient information for BNSF to determine which
    Rate Offers are for comparable service, then BNSF need not disclose or permit Hunt
    to use any Rate Offers in lieu of the Revenue Split. Otherwise, BNSF must disclose
    and permit Hunt to use a given Rate Offer if and only if (1) the Rate Offer is one that
    BNSF extended to another truckload carrier for comparable service; and (2) the Rate
    Offer would give Hunt something that Hunt could not get already, at equal or less
    cost, by opting for the Revenue Split or another Rate Offer that BNSF has extended
    to Hunt.
    IV.
    For the foregoing reasons, we affirm the district court’s denial of Hunt’s
    motion for “enforcement” insofar as it was a request for an order of specific
    performance, we affirm in part and reverse in part the district court’s denial of Hunt’s
    -17-
    motion for “enforcement” insofar as it was a request for a declaratory judgment, and
    we remand for entry of a declaratory judgment consistent with this opinion.
    ______________________________
    -18-